• Shamel Hassanien
• Mohamed Habib.
• Sherif Ayman Kamal.
• Mai Elsayed.
Supervisor
Dr, Ahmed El-Sedawey
Table of contents
1. Introduction.
2. Technical Analysis.
3. Commercial, Marketing, and Sales Analysis.
4. Organizational, Administrative, and Legal Analysis.
5. Financial Analysis.
6. Conclusion.
1) Introduction
Ground floor
Wady Degla
club location
2) Technical study
2-2- Location analysis
• Location of the plot
Project plot No is 27 which is located in the cornier at the
intersection between 2 street there width is 20 m which is an
advantage in our project that the all apartments in all floors
have been design to see the roads
2) Technical study
2-2- Location analysis
Project location
2) Technical study
2-3- Accessibility.
• Accessibility to the project plot
We have 4 access points, to the
plot inside the District from the
north , south , east and west
• site hazards
No ( storm & Earthquakes ) hazards on
the location of this project
2) Technical study
2-4- Ecological conditions
• climate
Building & sun Direction regarding to the sun direction we have 2
elations should be treated to protect the building against heat, South
elevation (main elevation) by using a horizontal shading devices in the
architectural design of this elevation, and the west elevation using the
vertical shading devices as well
Farther more this we have to use the insolated Brick units for
constructing those 2 elevations which will make an energy saving
On the long run,
Building & wind Direction regarding to the preferred wind direction
(Northwest ) from the Neighbors sides @ north and the designer used an
internal court in Northwest direction to take the maximum Benefit from
the this wind
2) Technical study
2-5- Infrastructural conditions
There are a complete infrastructure network around the project and it will be extended in the
new extension area at the building location as the planed, this network contains to roads ( and
transportation ), water , pluming , electrical , low-currant , gas
Electrical works
Car parking area Full finished lighting fixture, Main Power control panels
Core areas: Full finished lighting fixture
Apartments : electrical conduit without wiring for lighting and power, Main Power control panels
for the apartment
Low currant works
Basement floor: Full finished smoke detectors system , fir alarm system , CCTV system , accesses
control system
Core areas: Full finished smoke detectors system , fir alarm system , CCTV system, accesses
control system
Apartments area : All conduits without wiring for audio visual , internet
2) Technical study
2-7- Engineering specification, systems & technology
IOT ( Internet Of Things ) systems works
Selected IOT systems in our project
Through IOT we can control and monitoring the below systems for our residential building:
Inside the apartments (monitored and controlled by the apartment owner):
• Hvac system , Lighting and energy saving, Water system, Gas system, Intrusions
detection, Fire protection, Sound
Strengths Weaknesses
Experienced sales team. The company has a small
number of employees.
Experienced technical team.
Opportunities Threats
The project's land payment on Stopping the construction
installment payments. permits & construction works for
6 months.
3) Marketing, Commercial, and Sales Analysis
3-7 The competitive profile.
Our project has a competitive advantage which is using the IOT system in the common areas
in the building, a swimming pool in the ground floor, and a recreation area and a gym in the
roof.
The competitors:
1- Maadi Company. (Leader)
2- Wadi Degla Company. (Challenger)
3- Al-Mansour Company. (Follower)
4- Egypt development Company. (Follower)
5- Future Homes Company. (Follower)
6- Degla Masr Company. (Follower)
7- Degla El-Maadi Company. (Follower)
3) Marketing, Commercial, and Sales Analysis
3-8 Market Share.
The estimated
advertising budget of the
project equals
approximately 5% of the
total capital.
4) Organizational, Administrative, and Legal Analysis.
4-1 Basic organization design and organization chart.
4-2 Indicate key persons skills required total employment
number and cost.
4-3 Customer relations policy
4-4 legal aspects:
4) Organizational, Administrative, and
Legal Analysis.
Staff Cost
Staff cost Duration Monthly Salary
Management
A Project Manager 1 24 25,000 600,000
Construction 25,000.00 600,000.00
B Senior Site Engineer 2 24 10,000 240,000
C Site Engineer 3 24 8,000 192,000
C Surveying 1 24 5,000 120,000
Technical Office 23,000.00 552,000.00
B Senior Tec. Office Eng.( Civil ) 1 12 8,000 96,000
Senior Tec. Office Eng.( ARCH ) 1 12 8,000 96,000
Contract, Planning & Cost 16,000.00 192,000.00
B Planning Eng. 1 12 5,000 60,000
MEP Team 5,000.00 60,000.00
C Elec Engineer 1 18 9,000 162,000
C Mech 1 18 8,000 144,000
Accounting & Admin Team 17,000.00 306,000.00
C Accountant 1 30 4,000 120,000
General Services Team 4,000.00 120,000.00
C Store Keeper 1 12 3,000 36,000
C IT Specialist 1 12 3,000 36,000
E Office Boy 2 30 3,000 90,000
TOTAL 17 252 9,000.00 162,000.00