General Fees:
Pursuant to City Ordinance No. 484, S-2011, the amount of fees per service
required are as follows:
C. PROCESSING FEE:
Twenty five (25%) of the corresponding prescribed Land Use Fee.
F. SURCHARGES
A surcharge of one hundred pecent (100%) of the total locational clearance fees
but not less than Two Thousand Pesos (P2,000.00) whichever is higher shall be
charged to any applicant, proponent, proprietor, owner or representative who
commences or undertakes any project without having first secured a Locational
Clearance and which shall be due upon securing of such clearance.
G. DEVELOPMENT CHARGES
COMPUTATION OF DEVELOPMENT CHARGES . Any proposed land improvement
or building expansion in excess of the allowable Floor Area Ratio or Building height as
provided in this Ordinance shall be subject to appropriate fees on top of the regulatory
fees prescribed under Section 40 of this Ordinance. The amount of the development
charge that shall be due from the proponent/owner shall be computed per 25% incre-
ment of the additional Building Area that may be allowed, and as follows:
Requirements:
• Duly accomplished Application Form and Pre- Compliance Checklist of Requirements
•At least seven (7) sets of Complete Plans (Architectural, Structural, Mechanical, Electrical,
Sanitary and Electronics and communications) signed by the owner or his duly authorized
representative and relevant professionals. Out of 7 sets of documents required,
One (1) set that provides details on the Green Building measures will be retained in the MCGBA.
• Architectural Plans
○ Site Development Plans
○ Floor Plan
○ Elevation and Section
○ Schedule Doors and Windows
○Spot Detailed Section (drawn into convenient scale)
- Doors and Windows
- Exterior and Interior Walls
- Roof Deck with water-proofing/roofing insulation
- Vertical and Horizontal Sun Shading
• Structural Plans
• Electrical Plans/Basis of Design/Design Calculation/Technical Specification
• Mechanical Plans & Fire Protection Plans/Basis of Design/Design Calculation/Technical Specification
• Sanitary Plans including details of Sewage Treatment Plan and Rain water harvesting/Basis of Design
/ Design Calculation/ Technical Specification
• Electronic and Communication Plans
The easiest way to avail the service:
STEPS HOW FAST? KEY PERSONS
1. Proceed to the CPDO: Dorina Dayon (RMP), Christian Angelo Solero (RMP)
Secure and Fill Out application form, 15 Minutes Engr. Vic Angel Belen, Mr.Robert Lagarto
and submit requirements.
2. Evaluates submitted documents: Engr. Ana Mae Hernandez
Pre-evaluates documents, Check all Archt. Abraham Raposon Jr.
requirements,prepares evaluation Engr. Vic Angel Belen
1-7 working
report,order of payment and GBPCC, Dorina Dayon, RMP
days
2.1 Site Inspection Christian Angelo Solero, RMP
Site inspection is conducted to Mr. Robert Lagarto
verify all existing condition.
3. Review of Documents Archt. Abraham L. Raposon Jr.
Review and Evaluates for correctness 1 working Engr. Gaspar F. Alcazar
and compliance of Green Building day
measures.
4.Approval
1 working
Review and sign certificate of com- Engr. Armando T. Comandao
day
pliance of green building measures
5. Releasing of GBPCC Dorina Dayon (RMP), Christian Angelo Solero (RMP)
1 working
The approved GBPCC is encoded into Engr. Vic Angel Belen, Mr.Robert Lagarto
day
the data bank prior to release. Ms. Susan S. Gasilao
MANDALUYONG CITY'S CITIZEN CHARTER 27
A Guidebook on City Government Services
CITY PLANNING AND DEVELOPMENT DEPARTMENT SERVICES "Pursuing Government Service Excellence"
Requirements:
• Duly accomplished Application Form and Pre- Compliance Checklist of Requirements
• Three(3) sets of As-Built Plan (Architectural, Structural, Mechanical, Electrical,
Sanitary and Electronics and communications) signed by the owner or his duly authorized
representative and relevant professionals.