TENDERING, BIDDING AND


CONTRACTING

Types of Contract
Submitted by: -
RP20018: - Nishant Pandit
RP20047: - Saloni Shah
RP20050: - Rohit Koppera
RP20057: - Kshitija Bhoir

Date of submission: - April 04, 2021

Submitted to: - Prahlad R.

1
2

1. Item Rate Contract

Sr. No. Description Quantity Rate Unit Amount

Carrying out total station survey of the


1 5800 1.5 sqm 8700
entire plot
Excavation in soil/ Soft Murrum by
2 3240 94 cum 304560
Mechanical means upto 1.0m depth

Excavation in soil/ Soft Murrum by


3 3240 113 cum 366120
Mechanical means upto 2.0m depth

Excavation in soil/ Soft Murrum by


4 3240 125 cum 405000
Mechanical means upto 3.0m depth

Excavation in soil/ Soft Murrum by


5 3240 438 cum 1419120
Mechanical means upto 4.0m depth

Excavation in soil/ Soft Murrum by


6 3240 575 cum 1863000
Mechanical means upto 5.0m depth
Excavation in soil/ Soft Murrum by
7 440 313 cum 137720
Manual means upto 1.0m depth
Excavation in soil/ Soft Murrum by
8 440 338 cum 148720
Manual means upto 2.0m depth
9 Excavation in Rock 4.0m to 5.0m depth 25 2524 cum 63100
Excavation in soil/ Soft Murrum by
10 Mechanical means upto 5.0m to 6.0m 3240 731 cum 2368440
depth
11 Excavation in Rock 5.0m to 6.0m depth 30 3149 cum 94470
Excavation in soil/ Soft Murrum by
12 Mechanical means upto 6.0m to 7.0m 3240 887 cum 2873880
depth
13 Excavation in Rock 6.0m to 7.0m depth 35 3774 cum 132090
Excavation in soil/ Soft Murrum by
14 Mechanical means upto 7.0m to 8.0m 3240 866 cum 2805840
depth
15 Excavation in Rock 7.0m to 8.0m depth 40 4399 cum 175960
Excavation in soil/ Soft Murrum by
16 Mechanical means upto 8.0m to 9.0m 3240 1022 cum 3311280
depth
17 Excavation in Rock 8.0m to 9.0m depth 45 5024 cum 226080

2
3

Excavation in soil/ Soft Murrum by


18 Mechanical means upto 9.0m to 10.0m 900 1178 cum 1060200
depth
Excavation in Rock 9.0m to 10.0m
19 15 5649 cum 84735
depth
Demolition of Stone or B. B. Masonry
20 5 1334 cum 6670
work in Excavation
Demolition of Concrete work in
21 5 563 cum 2815
Excavation
22 Demolition of RCC work in Excavation 5 938 cum 4690
Total 17863190

Total value of Item Rate Contract is Rs. 17,863,190/-.

3
4

2. Percentage Rate Contract

Sr. Percentage Modified


Description Quantity Rate Unit Amount
No. Variation Amount
Carrying out total station survey of the
1 5800 1.5 sqm 8700 0.30% 2610
entire plot
Excavation in soil/ Soft Murrum by
2 3240 94 cum 304560 0.50% 152280
Mechanical means upto 1.0m depth

Excavation in soil/ Soft Murrum by


3 3240 113 cum 366120 0.50% 183060
Mechanical means upto 2.0m depth

Excavation in soil/ Soft Murrum by


4 3240 125 cum 405000 0.50% 202500
Mechanical means upto 3.0m depth

Excavation in soil/ Soft Murrum by


5 3240 438 cum 1419120 0.50% 709560
Mechanical means upto 4.0m depth

Excavation in soil/ Soft Murrum by


6 3240 575 cum 1863000 1.00% 1863000
Mechanical means upto 5.0m depth
Excavation in soil/ Soft Murrum by
7 440 313 cum 137720 0.50% 68860
Manual means upto 1.0m depth
Excavation in soil/ Soft Murrum by
8 440 338 cum 148720 0.50% 74360
Manual means upto 2.0m depth
9 Excavation in Rock 4.0m to 5.0m depth 25 2524 cum 63100 0.80% 50480
Excavation in soil/ Soft Murrum by
10 Mechanical means upto 5.0m to 6.0m 3240 731 cum 2368440 0.80% 1894752
depth
11 Excavation in Rock 5.0m to 6.0m depth 30 3149 cum 94470 1.00% 94470
Excavation in soil/ Soft Murrum by
12 Mechanical means upto 6.0m to 7.0m 3240 887 cum 2873880 1.00% 2873880
depth
13 Excavation in Rock 6.0m to 7.0m depth 35 3774 cum 132090 1.50% 198135
Excavation in soil/ Soft Murrum by
14 Mechanical means upto 7.0m to 8.0m 3240 866 cum 2805840 1.50% 4208760
depth
15 Excavation in Rock 7.0m to 8.0m depth 40 4399 cum 175960 1.50% 263940
Excavation in soil/ Soft Murrum by
16 Mechanical means upto 8.0m to 9.0m 3240 1022 cum 3311280 2.00% 6622560
depth
17 Excavation in Rock 8.0m to 9.0m depth 45 5024 cum 226080 2.50% 565200

4
5

Excavation in soil/ Soft Murrum by


18 Mechanical means upto 9.0m to 10.0m 900 1178 cum 1060200 2.50% 2650500
depth
19 Excavation in Rock 9.0m to 10.0m depth 15 5649 cum 84735 2.00% 169470
Demolition of Stone or B. B. Masonry
20 5 1334 cum 6670 2.00% 13340
work in Excavation
Demolition of Concrete work in
21 5 563 cum 2815 2.00% 5630
Excavation
22 Demolition of RCC work in Excavation 5 938 cum 4690 2.50% 11725
Total 17863190 22879072

Total value of Percentage Rate Contract is Rs. 22,879,072/-.

3. Cost Plus Percentage Contract: -


Cost of the project = Rs. 17,863,190/-
Percentage fees = 12%
Contractor’s Profit = Rs. 17,863,190 X 12%
Total Cost Plus Percentage Fees = Rs. 20,006,772.8/-

4. Target Contract: -
Under Over
budget budget
Estimated cost 17863190 17863190
Actual cost 17000000 18500000
Rate 13.00% 13.00%
Difference 863190 -636810
13% Cost 221000000 240500000
Profit/ Loss incurred by
431595 -318405
each party
Total profit/loss incurred
221431595 240181595
by both parties