Professional Documents
Culture Documents
a) Introduction
CE 1.1
This career episode discusses a project undertaken at the St. Joseph’s College of Engineering and
Technology named as “Low-Cost Generator Automation”. In this project, I worked as an
Undergraduate student in Electronic and Electrical Engineering. It was located in Palai, in the
state of Kerala in India. The total duration of this project was 6 months. It was started in Oct
2015 and completed in Mar 2016.
b) Background
CE 1.2
St. Joseph's College of Engineering and Technology-Palai, an esteemed institute in the field of
Engineering education and management studies was established in the year 2002. This college is
an ISO 9001:2008 certified institution which regularly conducts internal and external audits. The
project was based on a controller that was proposed to eliminate the manual operation in the
engagement of the user was required for turning the generator on and off and shifting the load
between the generator and the grid. The controller monitored the grid voltage and when there
was no voltage, the controller disconnected the load from the grid, started the generator, and
shifted the load to the generator and when the grid voltage came back on the system it turned off
the generator and transferred the load to the grid.
C.E 1.3
The objective of the project was to carry out the modeling of a cost effective generator
automation system consisting of an automatic transfer switch (ATS) for small buildings that
would automatically change the power supply between grid and generator. Temperature sensor,
fuel level sensor, and battery backup guarantee lifespan and protection to the equipment. GSM
technology was also provided which gave master control to the user.
C.E 1.4
The key roles and duties for which I was responsible are mentioned below:
Analyzed the working of existing power system and proposed the idea of implementing a
new technique for the advancement of the prevailing system
Identified the flaws in the present electrical system and proposed a rough idea to
overcome those problems
Designed the microcontroller program and flowchart based on the existing model to
easily identify the working principle
Planned, designed, and implemented the circuit diagrams and electric installations
Estimated the cost and scheduled timeline considering the timeline and financial budget
using a Gantt -Chart
Prepared reports and presentations by using latex software for report preparation and MS-
Power-point for presentations
Managed team and focused on productive working
C.E 1.5
The hierarchy of this project is shown below:
Head Of
Head The
Of The
Department
Department
Project
Project Co-
Co-
ordinator
ordinator
Project Guide
Team Leader
(Myself)
(Myself)
Technical
Technical
Team
Team
a) Introduction
CE 2.1
My second career episode is a detailed description of my project named as “Grid-Connected
Photovoltaic System with Energy Management Scheme”. I accomplished this project in the
institution ‘St. Joseph’s College of Engineering and Technology -Pala located in Pala, India. I
undertook this project as an Undergraduate student of Electrical and Electronics Engineering.
The project was started in June 2016 and accomplished in Oct 2017.
b) Background
CE 2.2
St. Joseph's College of Engineering and Technology-Pala, an esteemed institute in the field of
Engineering education and management studies was established in the year 2002. The College
was set up under the management of Syro-Malabar Catholic Diocese of Pala, located in Pala,
Kerala, India and is recognized by the All India Council for Technical Education (AICTE).
CE 2.3
A photovoltaic system connected to the utility grid with an energy management scheme was
accomplished in this project work. The energy management scheme was incorporated with the
grid-connected PV system to maintain the power balance in the system. Grid-connected PV
system consists of solar panel, inverter, and boost converter. The solar energy harvested from the
PV panel was utilized to power local loads. If the energy generated from the PV system was not
sufficient to meet the local load demand, additional power was taken from the grid. This system
allowed the bidirectional flow of power between the grid and PV system. The energy
management module helped to monitor the energy usage and controlled the inverter operation
and managed the energy demand of the loads.
CE 2.4
The objective of this project was to connect a photovoltaic system to the grid, incorporating the
idea to supply the excess energy generated from photovoltaic panel to the grid, and to take power
from grid whenever the energy generated from the photovoltaic system was not sufficient to
meet local needs and thereby allowing a bidirectional flow of power between grid and PV
system.
CE 2.5
Being the team leader, the major responsibilities I performed were:
Planned and designed basic working block diagram of the project
Planned, designed, and implemented the circuit diagrams (power supply, boost converter)
and electric installations
Carried out testing, evaluated the results, and modified the design according to the
requirement by using the Matlab Simulink and also tested the electrical connections to
analyze the desired output
Interpreted specifications, journals, standards, and regulations related to the components
used
Estimated the cost and scheduled timeline considering the timeline and financial budget
using a Gantt -Chart
Designed the PCB using eagle software for assembling the circuit components
Prepared reports and presentations by using used latex software for report preparation
CE 2.6
The organogram for the project which indicates my position is as follows;
Head Of The
Department
Project Co-
ordinator
Project Guide
Team Leader
(Myself)
Technical
Team
CE 2.10
During the process of the centralized solar project, I encountered a problem where I analyzed the
stand-alone PV system and pointed out its shortcomings. The problem was the lack of a
continuous power supply in all weather conditions and in cases of a blackout in the grid power.
After a detailed analysis and according to engineering perspective of the stand-alone system, I
proposed valuable solutions to the shortcomings of a stand-alone solar system for supplying
loads. I considered various parameters that included cost, size, and output power etcetera. I compared the
stand alone PV system with the new system and presented the idea using power point presentations. I
used MS PowerPoint to present various solutions, including; reduction in the preventive
maintenance by combining all the photovoltaic arrays at one place as a Solar Grid system,
construction of battery banks in series or parallel combination in specially designed cabins, and
supply of uninterrupted power to the loads through grid power during severe weather conditions.
CE 2.11
The effect of clouds shadow on a photovoltaic system was a significant problem as it caused grid
instability issues. I integrated Maximum Power Point Tracking technique in this system to make
sure that the photovoltaic panels produced the maximum output power working in a particular
point. However, it was a hectic procedure to maintain the panel at its maximum power yielding
point due to varying weather conditions In addition, an inverter operates at a particular DC
operating range and a simultaneous insolation causes the system to work outside the normal
voltage levels. This stopped the further operation of the inverter and thus the supply to the grid
was interrupted. Due to the simultaneous tripping of the inverter, there was a drastic change in
the output power of the photovoltaic cell. In order to solve this issue, I collected the various data
about generation of power and analyzed it to find out the largest rise and fall in power slopes
during different time period. Such variations in power slopes showed only a slight deviation of
larger and longer time delayed power fluctuations due to transients caused by solar irradiance. I
controlled the simultaneous hike in power by setting the arrangement in such a way, so as to
increase the power by certainly fixed increments using the inverter. By introducing extra
instrumentation devices such as storage batteries, I compensated the power loss in the system.
CE 2.12
I started preparing the budget after having a detailed analysis of the anticipated costs. I used
Gantt Chart for scheduling the work into different phases which helped me to complete the work
days before the deadline. Considering the amount that could be raised for the project, I planned
about the quality of the components that should be used. Observing the latest trends and changes
in the market, I procured the raw materials and equipment directly from the manufacturers at a
very low cost direct from the factory. The project was accomplished in a time period much less
than what was expected.
CE 2.13
I calculated the current through different elements in the equivalent circuit including shunt
resistance, diode and series resistance by using the equation given by, I= IL -ID -ISH, where I is
the output current given in ampere, whereas IL is the photo-generated current in ampere. ID is
the diode current (ampere), and ISH is shunted current (ampere). Another set of calculations that
I performed was to find the inductance (L) and a number of turns (n) of the inductor to be used in
the converter. I calculated the inductance and the number of turns if Bmax is the maximum flux
density (took as 0.2 T).
CE 2.14
I used MATLAB Simulink for the design as well as programming purpose. I used Creo sketch
software for the purpose of creating a rough sketch of the solar tracking electronic control unit. I
prepared the entire documents using Latex software sample report in MS Word and Excel and
presentations in PowerPoint. I used Eagle software for PCB designing and used Electrical
Estimating Software for the estimation purpose.
CE 2.15
I used appropriately insulated rubber gloves, goggles, and safety shoes while working on an
electrical circuit. Before starting the project, I gave a session on safety precautions and possible
hazards that could occur to my teammates. Whenever a fault occurred in the system, I insisted to
turn off the whole supply before correcting it to avoid electrical hazards. I took special care to
recover used goods and disposed of them safely.
CE 2.16
All my teachers, instructors, and colleagues were very helpful throughout the project work. I
referred to the internet as well as a lot of books like journals and technical magazines to enhance
my engineering knowledge. I read a monthly magazine provided by the Institute of Electrical and
Electronics Engineers (IEEE) to update my technical knowledge. Moreover, I attended a
seminar conducted by EL-SOL Power Solutions Pvt.Ltd, Changanacherry so as to understand the
basic assembly of solar panels. I also trained for one month with a solar panel installation
technician in EL-SOL Power Solutions Pvt.Ltd, Changanacherry so as to get a basic concept of
installation of PV systems in houses and industries. I attended a 1-week training in Latex
Programming. I also underwent an online training to learn Eagle software which I used for PCB
design in the project.
CE 2.17
In my design, I followed the IEEE Standard 315-1975, which consist of a listing of several Class
Designation codes to be considered while working on electrical and electronic assemblies and
Graphic Symbols to be used for Electrical and Electronic Diagrams. I also followed IEEE 388-
1992 Standard for Transformers and Inductors in Electronic Power Conversion Equipment. I also
followed RoHS (Restriction of Hazardous Substance).
CE 2.18
I arranged daily and weekly meetings throughout the period of a project with my colleagues and
divided the responsibilities among them. I conveyed the instructions from the project guide
towards my group members on these meetings. I consulted with them on various design
modifications and gave importance to their suggestions. I was responsible for management of the
team, which ensured continuous development of individuals and the team. With my technical
expertise and administrative skills, I managed my team very well. I ensured that all activities
were performed side by side and was accomplished in a time period less than expected.
CE 2.19
From the beginning, I presented power point presentations every week to highlight the
progression in front of teammates, project guide, faculty members, and head of the department. It
was like an open discussion where I got suggestions from my colleagues and teachers. It helped
me to improve my presentation skills and boosted my confidence level.
CE 2.20
Before implementing the hardware, I prepared an initial project report according to a basic
format including the literature survey and handover a soft copy to the project guide for
validation. Along with that, I prepared a power point presentation for getting approval from the
project guide and head of the department. During the project period, I presented the design and
implementation of boost converter and PV module in front of the project guides panel so as to
get approval for my design. The panel was impressed by the presentation and design details and
gave approval with some minor modifications.
d) Summary
CE 2.21
At all stages of the project, I was really satisfied about the progress. The project was
accomplished according to the planned timescale. I used my management and interpersonal skills
to manage the resultant outcomes of the projects. I was responsible for planning, scheduling, and
implementing the project. The successful completion of the project made me really elated and
felt accomplished. The project presented me a platform to showcase my engineering and
management skills to a great extent. I also learned how to refocus the direction of the project and
gained confidence in working with my teammates and improved my intellectual and subject
knowledge.
Career Episode 3
a) Introduction
CE 3.1
My third career episode describes my project named as “Scope of Energy Conservation at Bharat
Petroleum Corporation Limited (BPCL) 1t Ambalamukal, Kochi”. I worked on this project
during my undergraduate studies in St. Joseph’s College of Engineering and Technology located
in Palai, India. The project was accomplished by Bharat Petroleum Corporation Limited (BPCL)
at Ambalamukal, Kochi, India. It was started in Feb 2017 and completed in April 2017.
b) Background
CE 3.2
Cochin refinery is one of the units of Bharat Petrol Corporation Limited (BPCL) which was
established in the year 1996 with a production capacity of around 50000 barrels per day. This
firm was established in association with the Philips Petroleum Corporation in USA. The project
was related to different sectors in which energy wastage occurring in different sectors of BPCL
were identified and recommendations were given for energy conservation and improving the
overall efficiency of the system. The energy audit was done at BPCL at Ambalamukal near
Kochi. As there were no live metering devices to measure the actual power consumption at a
given time thus the load survey was on an assumption that the whole building was running near
to its connected load. The whole building consisted of only a single floor offering a great
opportunity to harness solar energy for internal lighting. The audit only sticks to the audit of
lighting and air conditioning loads and does not deal with any running motors in the building.
CE 3.3
The prime objective of the project was to perform pre-audit, audit, and post audit. The pre-audit
phase included planning and organizing the ideas about how to conduct the audit. Audit phase
included primary data gathering, conducting survey and monitoring, and conducting detailed
experiments and analysis of energy use. Post audit phase consisted of cost-benefit analysis,
reporting, presentation, and implementation.
CE 3.4
Being the team leader, the major responsibilities I performed were:
Planned and designed basic single line diagram of the electrical system
Prepared rough sketch of the area to be audited and all the electrical components were
marked
Interpreted specifications, journals, standards, and regulations related to energy auditing
Performed calculations related to the auditing such as payback period, total wattage, and
electrical installments
Compared old system and highlighted the improvements that could be brought into the
system by involving new techniques
Managed team and focused on productive working
CE 3.5
The hierarchy for the project is as follows;
Head Of The
Department
Project Co-
ordinator
Project Guide
Team Leader
(Myself)
Technical
Team
CE 3.10
During the project, I came across another problem related to the inefficiency of air conditioning
in the warehouse and how it was leading to more energy losses. Due to this, the energy bills were
at its peak and it caused many other power quality issues and the HVAC associated repairs. To
rectify this problem, I planned to conduct a blower door test to analyze the airtightness of the
warehouse. I used a calibrated blow door which was fitted in the doorway to draw the whole air
out of the room using the blower in the door while the higher outside air pressure then flowed in
through all unsealed cracks and openings. I attached the pressure gauges to calculate the pressure
of air leaving and entering the room. Then I fired a smoke pencil to smoke the house which
helped me to identify the spots through which air was infiltrating the building. I determined all
such spots in the warehouse and the air leakage was mainly through cracks. I used caulking to
seal most of the cracks as it dried faster and did not leave any trace of insulation. As a result of
this, the room was air tightened completely and the workers themselves told me that the air
conditioning was better and later the energy bills too got reduced.
CE 3.11
My primary aim in this project was to collect data and gather knowledge about those areas where
energy wastage was occurring. I prepared a presentation on energy conservation and gave many
suggestions such as replacement of metal halide and mercury vapor lamps with LED, use of
natural daylighting, methods to avoid harmonics, replacement of AC, ceiling fan, and rewound
motors with star rated units. I also prepared a comparison chart between the existed system and
the changes that could be made by introducing the new system clearly showing the payback
period and savings that could be made by following several energy conservation measures.
CE 3.12
I designed a heliostat which incorporated a mirror that kept on moving according to the motions
of the sun so as to track the sunlight and reflect those radiations towards a particular point which
was determined earlier. The major components that I used for the assembly were; a light
collector, a light pipe to pass on the light to different sections with very minute loss of light and
color dissipation, and a light diffuser to give away the light which effectively took the light
available during day time to the shadowy corners and improper roofing capped areas. It helped
me to prolong the sunny hours in the warehouse and maintenance shop of BPCL and distribute
constant brightness across the area all over the day.
CE 3.13
I mainly did two calculations which were total power consumption. I assumed the connected
loads to work only during day shift. The total connected load of the maintenance shop and
warehouse considering only the lighting and air-conditioning load equal to 136.656 kW.
Therefore, daily demand for energy if these components run for 9 hours a day would be equal to
1229.904 kWh. I performed payback period calculation and for this first, I noted a total number
of particular electrical equipment in warehouse and maintenance shop and the average usage
time of this equipment per day. Then I calculated wattage rating of the existing system and
identified the installation cost of single unit. I also found a total number of units and calculated
power consumed by this load and total cost on this unit.
CE 3.14
I utilized AutoCAD and PC Schematic for preparing the single line diagram. I used solid works
software for 3D designing purposes and FilterLab software for designing a filter circuit. I used
Electrical Estimating Software for the estimation purpose. I prepared documents using MS Word
and Excel and presentations using PowerPoint. I used adobe premiere pro for editing some
videos of my project and to present it more effectively in front of the project analyzing panel.
CE 3.15
I followed a set of safety precautions for in my project and before starting the project, I gave a
session on safety precautions and possible hazards that could occur to my teammates. I insisted
suppliers to use packaging which could be recycled. I followed the IEEE Standard 315-1975,
which consist of a listing of several Class Designation codes to be considered while working on
electrical and electronic assemblies and Graphic Symbols to be used for Electrical and Electronic
Diagrams. IEEE-519-2014 guidelines were also followed.
CE 3.16
I referred to the internet as well as lot of books to enhance my engineering knowledge. I attended
1-week training in AutoCAD software which helped me to design the single diagram of areas to
be audited during the course of my project. I also attended a 1-day seminar held by BPCL, Kochi
which discussed the topics of ‘Energy conservation and importance of using renewable energy
sources’. I attended the instruction class held by my Head of Department on the methodology to
be taken to complete the project and a 1-day class on different safety precautions.
CE 3.17
I held daily meetings throughout the project with my colleagues and divided different
responsibilities among them. I was responsible for management of the team, which ensured
continuous development of individuals and the team. During my project work in BPCL, I got the
chance to interact with the company manager, staff, and technical team which helped me to
improve my interpersonal skills. I arranged meeting with my project guide at regular interval of
1-week so as to update him with the progress of the project and present various design
calculation and received alterations and modifications.
CE 3.18
I prepared an initial project report including the literature survey and the methods I was going to
adopt for conducting energy audit. Along with that, I prepared a power point presentation in
which I presented that how I was going to replace the existing power system in the warehouse
and maintenance shop of BPCL so as to get approval for my design. The panel was impressed by
the presentation and design details and gave approval with some minor modifications.
d) Summary
CE 3.19
I was very satisfied with the progress of the project. Through proper literature survey, analysis,
and comparison of various aspects I was able to get into a conclusion easily. I managed the
project in such a way that it did not cost much and was accomplished in a time period less than
what was expected. Each phase of the project was progressive and went exactly like how it was
planned. The overall project was a success as I achieved my goals on time. The concept of
energy auditing helped me to gather ideas for energy conservation and implement it on this
particular site for improving overall efficiency and reducing energy cost. The project made me
professionally capable of facing all the technical challenges as well as gave me the confidence to
innovate and contribute new ideas.