INSPECTION AND TEST PLAN – CIVIL WORKS Ref: PL212533-SP-ETG-5230-0A

Rev:0A

Project Number: PL212533 Project Name: FLOATING ROOF ABOVE GROUND STORAGE TANK NUMBER #7
Vendor: HAROUGE OIL COMPANY CODE: API 650 Ed.2010
Sub Vendor: SOCOMENIN JOB N° / OF : PL212533

Prepared by: KAMMOUN Med Ali Date: 20/ 11/2013 Signature:


Review by QA/QC inspector: TLAHIG IMED Date: 20/ 11/2013 Signature:
Approved by Civil Work Manager: AZIZ HENTATI Date: 20/ 11/2013 Signature:

CIVIL INSPECTION AND TEST PLAN


Reference Acceptance Criteria/code and Verifying I n s p e c t e d by Remark
No Inspection and Test Plan
Documents standard documen Soco. sig. TPI Sig. HOO Sig.
t
Meeting Report
1 Construction Kick Off Meeting HOO Spec HOO Spec H
(MR)
2‐document review
2.1 Approval of civil works Drawings DWG, Spec. API 650, Spec. Drawing
H A

2.2 Certificate batching plant &emergency generator for Conformity


API 650, Spec Spec
batching plant Civil Work Procedure certificate H R

2.3 Excavator HOO Specifications for "Contractors Excavator


General HSE Requirements Certificate R A

2.4 Sand BS 812/ BS 1377/ ASTM C 88 / Specification


ASTM C 128 / ASTM C 29 / Sand & Test R R

2.5 Aggregate BS 882 / BS 812 / ASTM C 88 / BS Specification


1377 / ASTM C 142 / ASTM C 131 Aggregate & Test R R

2.6 Water BS 1377 Specification


Water & Test R R

2.7 Cement Specification


BS EN 196 R R
Cement & Test

2.8 Rebar BS 4449 Specification


R R
Rebar & Test

Page N°: 1/5


INSPECTION AND TEST PLAN – CIVIL WORKS Ref: PL212533-SP-ETG-5230-0A
Rev:0A

Reference Acceptance Criteria/code and Verifying I n s p e c t e d by Remark


No Inspection and Test Plan
Documents standard document Soco. sig. TPI Sig. HOO Sig.
3 – Civil work activities

3.1 Geotechnical Survey API 650, Spec. Spec Civil Work Procedure Inspection report W
H
3.2 Topographic Survey API 650, Spec. Spec Civil Work Procedure Inspection report H W
Contractual document Inspection report
3.3 Excavation ring beam- Checking Depth of Excavation Drawings, Engineering (checking depth of H W
Drawings excavation report)
Checking Elevation of Contractual document Inspection report
Structure Drawings, Engineering (checking level
Drawings H W
of structure)

3.4 Casting lean concrete Contractual document Test report


Slump Test
ASTM C143 / BS 1881 (slump test record) H W
Cube Test Record Contractual document Test report
BS 1881 (Cube test record) H R
Checking the top level of Contractual document Inspection report
Structure Drawing (checking level of H W
structure)
Checking concrete cover, Contractual document
position and verticality of Inspection Request H W
the formwork Drawing & BS 5975
Checking length, bend and Contractual document Inspection Request
3.5 Casting footing position of rebar, lap joint Drawing & BS 4466 H W
Concrete grade inspection Contractual document
(Mixing, Transportation, Drawing & BS 8110
timing, Placing, Compaction Inspection Request H W
with vibrator ,Curing)

Slump Test ASTM C143 / BS 1881 Test report


H W
(slump test record)
Cube Test Record Contractual document
Test report
BS 1881 H R
(Cube test record)
Acceptance Criteria/code and I n s p e c t e d by Remark
No Inspection and Test Plan Reference
Documents standard Verifying document Sig
Soco. TPI Sig. HOO Sig.

Page N°: 2/5


INSPECTION AND TEST PLAN – CIVIL WORKS Ref: PL212533-SP-ETG-5230-0A
Rev:0A

Submission of Design for Checking the formwork ACI specifications for formwork
3.6 Formwork including shuttering with the sketched details design ACI standard H R
and props
Rebar check dia, bending,
concrete cover, lap joint/ API 650
Inspection Request H W
Length, space quality ,
fixing status, top elevation
Contractual document Inspection report
Checking Level of
Drawing (Checking level of H W
Structure
structure).
Check cathodic protection
hole on ring wall is Inspection Request W
available.
Checking cover, position Contractual document
and verticality of the Drawing & BS 5975 Inspection Request H W
formwork and top
elevation
Concrete grade inspection Contractual document
(Mixing, Transportation, Drawing & BS 8110 Inspection Request H W
Placing, Compaction and
3.7 Casting Ring Beam Curing)
ASTM C143 / BS 1881 Test report
Slump Test Record H W
(slump test record)
Construction joint
between footing and ring
Inspection Request H W
beam, cleanliness and
sound connection
Contractual document Test report
Cube Test Record H W
BS 1881 (Cube test record)
Curing – covers by blanks Contractual document
and water sprayed Inspection Request H W

Visual surface inspection Contractual document Inspection Request H W


Contractual document Test report H
Compressive strength test BS 1881 W
(Cube test record) H
Reference Acceptance Criteria/code and I n s p e c t e d by Remark
Inspection and Test Plan
No Documents standard Verifying document Soco. sig. TPI Sig. HOO Sig.
Checking Depth of Contractual Inspection report
3.8 Leveling Under Tank Excavation Document Drawing (checking depth of H W
excavation report)
Page N°: 3/5
INSPECTION AND TEST PLAN – CIVIL WORKS Ref: PL212533-SP-ETG-5230-0A
Rev:0A

Contractual document Inspection report


Checking Level of Structure Drawing (checking level of H W
structure)
Protective coat( Integrade &
3.9
Interzone) for the whole Contractual Document
Backfilling Under Tank Ring beam internal and Drawing &Coat Inspection Request
external coating check Specifications
before backfilling
ASTM D 1557-78 Back filling Test
Result of test backfilling ASTM D 2049 ASTM D 1556 R
result H
Checking Depth of Contractual document Inspection report
Excavation Drawing (checking depth of H W
excavation report
Checking the Level of Contractual document Inspection report
Structure Drawing (checking level of H W
structure)
Checking concrete cover, Contractual document
H
Construction of pipe position and verticality of Drawing & BS 5975 Inspection Request W
supports, piping access the formwork
Checking length, bend , lap Contractual document
3.10 platforms, lighting poles H
and Manholes joint/ Length, and position Drawing & BS 4466 Inspection Request W
of rebar
Concrete grade
inspection(Mixing, timing Contractual document
H
Transportation, Placing, Drawing & BS 8110 Inspection Request W
Compaction with vibrators
and Curing)
Slump Test Record ASTM C143 / BS 1881 Test report R
H
(slump test record)
Cube Test Record Contractual document BS 1881 Test report R
H
(Cube test record)
Reference Acceptance Criteria/code and I n s p e c t e d by Remark
No Inspection and Test Plan Documents standard Verifying document Soco. sig. TPI sig. HOO sig.
Trench excavation for Checking Depth of Inspection report
3.11 Electrical cables, Earthing Excavation Contractual document (checking depth of
H W
cables and Underground Drawing excavation report
Pipe
Checking Depth of Contractual document Inspection report H W
Excavation Drawing (checking depth of
excavation report
Page N°: 4/5
INSPECTION AND TEST PLAN – CIVIL WORKS Ref: PL212533-SP-ETG-5230-0A
Rev:0A

Checking top level of Contractual document Inspection report


Structure Drawing (checking level of H W
structure)
Checking cover, position Contractual document
and verticality of the H
Drawing & BS 5975 Inspection Request W
formwork.
3.12 Construction of water run
Checking length, bend and Contractual document
position of rebar, lap Drawing & BS 4466 H
Inspection Request W
joint/length
Concrete grade
inspection(Mixing, Contractual document
Transportation, Placing, Inspection Request H W
Drawing & BS 8110
Compaction and Curing)
Slump Test Record ASTM C143 / BS 1881 Test report H
R
(slump test record)
Cube Test Record Contractual document BS 1881 Test report H R
(Cube test record)
Inspection report
3.13 Site grading Checking Level of Structure
Contractual document Drawing
(checking level of H W
structure)

H: Hold Point = Hold on the production till TPI /client Inspector performs inspection and supervise the required test
W: Witness Point = Manufacturer shall notify client and TPI Inspector but there is no hold on the production; Client can waive this inspection based on his discretion
A: Approval
R: Review of Contractors Documentati on
MR: Meeting Report

Page N°: 5/5