Professional Documents
Culture Documents
14.01.2022
1 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Load capacity mentioned above will be used because 1*VT 20 was used as secondary grid.
Twice of load capacity mentioned above will be used beacuse 2*VT 20 were used as main ridge.
2 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Loads on PD8 Load Scaffolds will be compared with spindel lenght above the table and
load capacity equaled to to scaffold height.
3 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
4 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
5 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
6 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
2. FORM SETTLING
PLAN
TPYE SECTION
7 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
a. Concrete Load
b. Moving Loads:
Moving Loads are divided into 2 parts: Moving Loads by reason of concreting and Moving
Loads by reason of working on slab.
Q4 = 0.1 X Q2,b
0.75 kN/m² ≤ Q4 ≤ 1.75 kN/m²
c. Formwork Load:
For timber beam VT 20K and secondary grids which are supported by PD8 Scaffolds, under the
slab.
d. Total Load:
for d = 100 cm: Q = Q1 + Q2,b + Q2,p + Q4 = 0.40 + 24.50 + 0.75 + 1.75 = 27.40 kN/m²
8 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
9 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT/ ADANA
MAIN SUBSTATION
14.01.2022
Coming Load to Main Ridge (Q): Amax / e = 4.11 kN / 0.50 m = 8.22 kN/m
Section impacts for main ridge by using PERI Continuous Beam programme:
10 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Support reactions which is in calculation for ridge are regarded as coming load for each scaffold leg.
Amax = 9.68 kN
When coming load to scaffold leg is compared with the table and when spindel lenght is less than 30cm,
maximum load capacity for scaffold leg is calculated as 53.20 kN.
Amax = 9.68 kN < Aper = 53.20 kN so scaffold can carry the load safely.
11 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
a. Concrete Load
b. Live Loads:
Live Loads are divided into 2 parts: Live Loads by reason of concreting and Live Loads by
reason of working on slab.
Q4 = 0.1 X Q2,b
0.75 kN/m² ≤ Q4 ≤ 1.75 kN/m²
c. Formwork Load:
For timber beam VT 20K and secondary grids which are supported by PD8 Scaffolds, under the
slab.
d. Total Load:
for d = 100 cm: Q = Q1 + Q2,b + Q2,p + Q4 = 0.40 + 24.50 + 0.75 + 1.75 = 27.40 kN/m²
12 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
13 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Coming Load to Main Ridge (Q): Amax / e = 4.11 kN / 0.50 m = 8.22 kN/m
Section impacts for main ridge by using PERI Continuous Beam programme:
14 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Support reactions which is in calculation for ridge are regarded as coming load for each scaffold leg.
Amax = 13.38 kN
When coming load to scaffold leg is compared with the table and when spindel lenght is less than
30cm, maximum load capacity for scaffold leg is calculated as 53.20 kN.
Amax = 13.38 kN < Aper = 53.20 kN so scaffold can carry the load safely.
15 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
a. Concrete Load
b. Live Loads:
Live Loads are divided into 2 parts: Live Loads by reason of concreting and Live Loads by
reason of working on slab.
- Live Loads by Reason of Concreting
Q4 = 0.1 X Q2,b
0.75 kN/m² ≤ Q4 ≤ 1.75 kN/m²
c. Formwork Load:
For timber beam VT 20K and secondary grids which are supported by PD8 Scaffolds, under the
slab.
d. Total Load:
16 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
17 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Coming Load to Main Ridge (Q): Amax / e = 3.87 kN / 0.30 m = 12.90 kN/m
Section impacts for main ridge by using PERI Continuous Beam programme:
18 / 19
DEGIRMENCI YAPI INS.DAN.OTO. SAN.VE TIC.LTD.STI.
NEW PTA COMPLEX PROJECT / ADANA
MAIN SUBSTATION
14.01.2022
Amax = 14.18 kN
When coming load to scaffold leg is compared with the table and when spindel lenght is less than
30cm, maximum load capacity for scaffold leg is calculated as 53.20 kN.
Amax = 14.18 kN < Aper = 53.20 so scaffold can carry the laod safety.
19 / 19