X. PAINTING
a. Flat wall latex paint (pails) 65 2200 143,000
b. Q.D. enamel (pails) 45 2500 112,500
c. Paint primer (gals) 40 500 20,000
d. Lacquer thinner (gals) 15 450 6,750
e. Conc. Neutralizer (gals) 15 300 4,500
f. Patching Compound (sacks) 10 1300 13,000
g. Sand Paper (#10, #150, #220) (meters) 30 130 3,900
h. Paint Thinner (gals) 10 300 3,000
i. Flat wall enamel (pails) 30 2300 69,000
j. Others Lumpsum 5,000
380,650
XI. ACCESSORIES
a. Door Knobs 36 700 25,200
b. Kitchen counter & hanging Cab. 9 7500 67,500
c. Others Lumpsum 5,000
97,700
XII. MISCELLANEOUS
a. Lighting use for construction Lumpsum 12,000
b. Water use for construction Lumpsum 15,000
d. Backfill for bldg. elevation Lumpsum 20,000
e. Others Lumpsum 10,000
57,000
SUMMARY
ITEM
I. MASONRY 1,561,100
II. HARDWARE 4,250,800
III. TILEWORKS 275,710
IV. LUMBER & BOARDS 153,450
V. TINSMITHRY 89,740
VI. PLUMBING FIXTURES 202,850
VII. PLUMBING SUPPLY 96,540
VIII. DOORS & WINDOWS 290,925
IX. ELECTRICAL 303,240
X. PAINTING 380,650
XI. ACCESSORIES 97,700
XII. MISCELLANEOUS 57,000
TOTAL 7,759,705
A. MATERIALS COST 7,759,705
B. LABOR COST Approx. 40% 3,103,882
C. SUPERVISION & OVERHEAD COST (APPROX.) Prof. Fee 5% 387,985
D. Bldg. & Occuppancy Permits (APPROX.) Govt. Fee 40,000
TOTAL PROJECT COST 11,291,572
PREPARED BY :
Dimension
Column Name
length
Number of Column
Ground Floor
Column 1 16.00 0.60
Column 2 3.00 0.30
2nd Floor
Column1 16.00 0.60
Column2 3.00 0.30
Planted Column 4.00 0.25
3rd floor
Column1 16.00 0.60
Column2 3.00 0.30
Planted Column 4.00 0.25
Parappet
Column1 16.00 0.60
Column2 3.00 0.30
Planted Column 4.00 0.25
CONCRETE FOUNDATION
Dimension
CONCRETE BEAM
Dimens
2F Framing
2-B1 1.00 174.00
2-B2 1.00 174.00
Beam
3F Framing
3-B1 1.00 145.00
Beam
3-B2 1.00 62.21
Roof Beam
RB 1 1.00 107.35
RB 2 1.00 62.21
Floor Beam
FTB 1.00 78.67
CONCRETE SUMMATION
CHB
ground floor
15.57 1 4.45 69.29
11.32 1 4.45 50.37
11.16 1 4.45 49.66
7.08 1 4.45 31.51
7.17 1 4.45 31.91
7.27 1 4.45 32.35
2.40 1 4.45 10.68
1.71 1 4.45 7.61
2.02 1 4.45 8.99
1.86 1 4.45 8.28
1.81 1 4.45 8.05
1.80 1 4.45 8.01
1.86 1 4.45 8.28
1.91 1 4.45 8.50
1.88 1 4.45 8.37
1.87 1 4.45 8.32
2.10 1 4.45 9.35
1.56 1 4.45 6.94
4.06 1 4.45 18.07
3.09 1 4.45 13.75
0.86 1 4.45 3.83
12.03 1 1.70 20.45
2nd floor
15.57 1 2.55 39.70
8.78 1 2.55 22.39
8.61 1 2.55 21.96
16.23 1 2.55 41.39
12.85 1 2.55 32.77
10.19 1 2.55 25.98
8.80 1 2.55 22.44
8.89 1 2.55 22.67
1.72 1 2.55 4.39
1.81 1 2.55 4.62
1.91 1 2.55 4.87
2.01 1 2.55 5.13
2.80 1 2.55 7.14
0.87 1 2.55 2.22
1.13 1 2.55 2.88
2.99 1 2.55 7.62
13.35 1 1.15 15.35
3rd floor
15.57 1 2.55 39.70
8.78 1 2.55 22.39
8.61 1 2.55 21.96
16.23 1 2.55 41.39
12.85 1 2.55 32.77
10.19 1 2.55 25.98
8.80 1 2.55 22.44
8.89 1 2.55 22.67
1.72 1 2.55 4.39
1.81 1 2.55 4.62
1.91 1 2.55 4.87
2.01 1 2.55 5.13
2.80 1 2.55 7.14
0.87 1 2.55 2.22
1.13 1 2.55 2.88
2.99 1 2.55 7.62
13.35 1 1.15 15.35
parapet wall
1.62 1 1.85 3.00
10.58 1 1.85 19.57
11.01 1 1.85 20.37
16.21 1 1.85 29.99
additional
4.00 1 0.80 3.20
Total 301.54
MORTAR
Total
PLASTERING
DIM. 1 DIM. 2
1.80 1.80
DIM. 1 DIM. 2
1.50
DIM. 1 DIM. 2
1.00 0.00
DIM. 1 DIM. 2
1.00
Beam LxW
DIM. 1 DIM. 2
column column
DIM. 1 DIM. 2
C1 0.35 0.60
C2 0.30 0.15
PC 0.25 0.20
MATT BARS
1 -0.075 0
LATERAL TIES
DIM. 1 DIM. 2
1
0.35 0.60
Size of column
2
DIM. 1 DIM. 2
2
0.50 0.40
Size of column
2
DIM. 1 DIM. 2
0.30 0.20
CHB Rebars
Number of
Length Height Area
Wall
TIE WIRES
Column Footing
Floor Slab
No. of matt bars every sides No. of slab No. of Cross section
Column
Column
Beam
FORMWORKS
Total Height of
Height of Column height of Beam
Column
LUMBER
ROOFING
commercial
@ length of 4.85 length 2.4m = lapping Pcs
8
2 pcs. Of 2.4m
g.i sheet @
4.85
7.00 2.00 2.00
@ length 15.80m one
side
Roof lapping
Length
@ 2.1/2=0.70
LATERAL TIES
Size of beam
rcb1
DIM. 1 DIM. 2
0.50 0.40
Size of beam
2
DIM. 1 DIM. 2
0.40 0.30
Size of beam
3
DIM. 1 DIM. 2
0.35 0.25
Size of beam
4
DIM. 1 DIM. 2
0.35 0.25
Size of beam
5
DIM. 1 DIM. 2
0.30 0.25
Size of beam
6
DIM. 1 DIM. 2
0.30 0.25
Size of beam
7
DIM. 1 DIM. 2
0.30 0.25
Size of beam
8
DIM. 1 DIM. 2
0.30 0.25
Size of beam
9
DIM. 1 DIM. 2
0.30 0.25
Size of beam
10
DIM. 1 DIM. 2
0.30 0.25
14.75 0.40
7.95 0.40
14.75 0.35
7.95 0.35
7.95 0.30
1.18 0.30
1.75 0.30
1.90 0.30
4.05 0.30
14.75 0.30
Mixed Type 40 kgs Cement
Gravel
2569.33
47.84
72.71
128.14
270.32
Total
Less Area of Window Less Area of Door Total Less Area CHB (sq/area) No. of CHB 5% Additional
0 0 0.00 69.29
0 0 0.00 50.37
0 0 0.00 49.66
0 0 0.00 31.51 393.825
0 0 0.00 31.91 398.83125
0 0 0.00 32.35 404.39375
1.875 1.47 3.35 7.34 91.6875
0.36 0 0.36 7.25 90.61875
0 1.47 1.47 7.52 93.9875
0 1.47 1.47 6.81 85.0875
0.36 0 0.36 7.69 96.18125
1.875 1.47 3.35 4.67 58.3125
0 1.47 1.47 6.81 85.0875
0.36 0 0.36 8.14 101.74375
1.875 1.47 3.35 5.02 62.7625
0.36 0 0.36 7.96 99.51875
1.875 1.47 3.35 6.00 75
1.875 1.47 3.35 3.60 44.9625
0 1.68 1.68 16.39 204.8375
1.68 1.68 3.36 10.39 129.88125
0 0 0.00 3.83 47.8375
0 0 0.00 20.45 255.6375
0 0 0.00 39.70
0 0 0.00 22.39
0 0 0.00 21.96
4.8 11.76 16.56 24.83 310.33125
6.75 2.1 8.85 23.92 298.96875
0 2.1 2.10 23.88 298.55625
0 0 0.00 22.44 280.5
0 0 0.00 22.67 283.36875
0.36 0 0.36 4.03 50.325
0.36 0 0.36 4.26 53.19375
0.36 0 0.36 4.51 56.38125
0.36 0 0.36 4.77 59.56875
0 0 0.00 7.14 89.25
0 0 0.00 2.22 27.73125
0 1.68 1.68 1.20 15.01875
2.25 0 2.25 5.37 67.18125
0 0 0.00 15.35 191.90625
0 0 0.00 39.70
0 0 0.00 22.39
0 0 0.00 21.96
4.8 11.76 16.56 24.83 310.33125
6.75 2.1 8.85 23.92 298.96875
0 2.1 2.10 23.88 298.55625
0 0 0.00 22.44 280.5
0 0 0.00 22.67 283.36875
0.36 0 0.36 4.03 50.325
0.36 0 0.36 4.26 53.19375
0.36 0 0.36 4.51 56.38125
0.36 0 0.36 4.77 59.56875
0 0 0.00 7.14 89.25
0 0 0.00 2.22 27.73125
0 1.68 1.68 1.20 15.01875
2.25 0 2.25 5.37 67.18125
0 0 0.00 15.35 191.90625
0 0 0.00 4.00 50
13.92 14.94 93.38 939.62 7527.50625 376.38
LESS CONCRETE COVER MULTIPLY BY 2 Length of Four
sides
Length of Four
LESS CONCRETE COVER MULTIPLY BY 2
sides
Length of Four
LESS CONCRETE COVER MULTIPLY BY 2
sides
Length of Four
LESS CONCRETE COVER MULTIPLY BY 2
sides
TOTAL
Less Area of Window Less Area of Door Total Less Area CHB (sq/area) Spacing Lapping
Divide by
Length of Tie Wire Total Length of
Length of tie wire No. of Footing length per
@ Single Footing Tie War
kilogram
Floor Slab
Divide by
Length of Tie Wire Total Length of
Length of tie wire Layers length per
@ Single Footing Tie War kilogram
mn
COLUMN
Beam
Area of
area of beam @ area of Beam No. of Plywood
3 sides of beam for plywood 2 sides (0.45) @ 1 side (0.30) Plywood per per Beam
beam
12.00 11.80 4.43 16.23 5.63
12.00 6.36 2.39 8.75 3.04
12.00 11.80 4.43 16.23 5.63
12.00 6.36 2.39 8.75 3.04
12.00 6.36 2.39 8.75 3.04
12.00 0.94 0.35 1.30 0.45
12.00 1.40 0.53 1.93 0.67
12.00 1.52 0.57 2.09 0.73
12.00 3.24 1.22 4.46 1.55
12.00 11.80 4.43 16.23 5.63
Column
Column 1
0.80 4.00 3.20 2.33 10.00 40.00
21.50 4.00 86.00 36.83 10.00 40.00
Column 1
0.80 4.00 3.20 2.33 5.00 20.00
12.50 4.00 50.00 21.83 5.00 20.00
Column 1
0.80 4.00 3.20 2.33 5.00 20.00
9.80 4.00 39.20 17.33 5.00 20.00
TOTAL
Beam
0.8
45.05 4 180.2 76.0833333333 2 8
0.8
24.65 4 98.6 42.0833333333 5 20
0.7
44.95 4 179.8 75.9166666667 4 16
0.7
24.55 4 98.2 41.9166666667 5 20
0.6
24.45 4 97.8 41.75 4 16
0.6
4.14 4 16.56 7.9 4 16
0.6
5.85 4 23.4 10.75 16 64
0.6
6.3 4 25.2 11.5 12 48
0.6
12.75 4 51 22.25 4 16
0.6
44.85 4 179.4 75.75 1 4
TOTAL
commercial
total roofing l w area
length 2.4m
0.00 0.00
0.00 0.00
PAINT SURFACE
PAINT SURFACE
0 0 0.00
21.75 87 0.125 1.00
13.92 69.6 0.08 1.00
0 0 0.00
0 0 0.00
10.88 43.5 0.075 1.00
8.40 27.9945 0.135 1.00
0 0 0.00
0 0 0.00
7.51 37.5725 0.07 1.00
4.35 21.7735 0.07 1.00
0 0 0.00
0 0 0.00
5.90 23.601 0.075 1.00
0 0 0.00
0 0 0.00
0 0 0.00
72.71 311.04 0.63 7.00
window door
Total CHB
l w l w
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
1.5 1.25 2.1 0.7
0.6 0.6 0 0
0 0 2.1 0.7
0 0 2.1 0.7
0.6 0.6 0 0
1.5 1.25 2.1 0.7
0 0 2.1 0.7
0.6 0.6 0 0
1.5 1.25 2.1 0.7
0.6 0.6 0 0
1.5 1.25 2.1 0.7
1.5 1.25 2.1 0.7
0 0 2.1 0.8
2.1 0.8 2.1 0.8
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
4 1.2 8 1.47
3 2.25 2.1 1
0 0 2.1 1
0 0 0 0
0 0 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0 0 0 0
0 0 0 0
0 0 2.1 0.8
1.5 1.5 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
4 1.2 8 1.47
3 2.25 2.1 1
0 0 2.1 1
0 0 0 0
0 0 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0.6 0.6 0 0
0 0 0 0
0 0 0 0
0 0 2.1 0.8
1.5 1.5 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
7903.88
additional bend (4 bends) additional bend ( free end) Total Length
Total Length of
Total Length of Total No. of Lat.
16 mm Dia. @ No. of Beam Total length
Continuous Bar Ties
single Beam
Total Length of
Total Length of No. of Total No. of Lat.
16 mm Dia. @ Total length
Continuous Bar Column Ties
single Beam
No. of 10mm.
LAPPING No. of SLAB TOTAL AREA
Needed
1205.55
window door
Total No. 10mm bars
l w l w
128.308 0 0 0 0
93.285 0 0 0 0
91.967 0 0 0 0
58.344 0 0 0 0
59.086 0 0 0 0
59.910 0 0 0 0
13.583 1.5 1.25 2.1 0.7
13.425 0.6 0.6 0 0
13.924 0 0 2.1 0.7
12.606 0 0 2.1 0.7
14.249 0.6 0.6 0 0
8.639 1.5 1.25 2.1 0.7
12.606 0 0 2.1 0.7
15.073 0.6 0.6 0 0
9.298 1.5 1.25 2.1 0.7
14.744 0.6 0.6 0 0
11.111 1.5 1.25 2.1 0.7
6.661 1.5 1.25 2.1 0.7
30.346 0 0 2.1 0.8
19.242 2.1 0.8 2.1 0.8
7.087 0 0 0 0
37.872 0 0 0 0
73.525 0 0 0 0
41.461 0 0 0 0
40.658 0 0 0 0
45.975 4 1.2 8 1.47
44.292 3 2.25 2.1 1
44.231 0 0 2.1 1
41.556 0 0 0 0
41.981 0 0 0 0
7.456 0.6 0.6 0 0
7.881 0.6 0.6 0 0
8.353 0.6 0.6 0 0
8.825 0.6 0.6 0 0
13.222 0 0 0 0
4.108 0 0 0 0
2.225 0 0 2.1 0.8
9.953 1.5 1.5 0 0
28.431 0 0 0 0
73.525 0 0 0 0
41.461 0 0 0 0
40.658 0 0 0 0
45.975 4 1.2 8 1.47
44.292 3 2.25 2.1 1
44.231 0 0 2.1 1
41.556 0 0 0 0
41.981 0 0 0 0
7.456 0.6 0.6 0 0
7.881 0.6 0.6 0 0
8.353 0.6 0.6 0 0
8.825 0.6 0.6 0 0
13.222 0 0 0 0
4.108 0 0 0 0
2.225 0 0 2.1 0.8
9.953 1.5 1.5 0 0
28.431 0 0 0 0
3.000 0 0 0 0
19.593 0 0 0 0
20.389 0 0 0 0
30.019 0 0 0 0
7.407 0 0 0 0
1740.04
No. of Bars Formula = area
/ spacing / lapping / bar
commercial length
Total No. of Plywood
47.40
17.01
5.52
Total 69.93
Total No. of
No. of beam Plywood
2.00 11.27
5.00 15.18
4.00 22.53
5.00 15.18
4.00 12.15
4.00 1.80
16.00 10.69
12.00 8.71
4.00 6.19
1.00 5.63
Total 109.34
880.00
440.00
440.00
1760.00
176
440
352
440
352
352
1408
1056
352
88
5016
lapping 0.7
18.01
0.00
5.52
0.00
2.30
25.83
72.96 42.56
4.005 2.0025
0 0
24.48 12.24
2.295 1.1475
2.55 2.04
0 0
24.48 12.24
2.295 1.1475
2.55 2.04
0 0
15.84 7.92
1.485 0.7425
1.65 1.32
154.59 85.40
NT SURFACE
11.52 11.52
0.9 0.9
12.42 12.42
NT SURFACE
0 0
87 0.125
69.6 0.08
0 0
0 0
43.5 0.075
27.9945 0.135
0 0
0 0
37.5725 0.07
21.7735 0.07
0 0
0 0
23.601 0.075
0 0
0 0
0 0
311.04 0.63
PAINT SURFACE
2543.54 1507.43
1996.80 83.20
406.80 16.95
153.60 38.40
0.00 138.55
No. of Lat. Ties No. of Beams Total length Total No. of Lat. No. of 10 mm
Ties dia.
No. of Lat. Ties No. of Beams Total length Total No. of Lat. No. of 10 mm
Ties dia.
TOTAL 0.00
total 16mm
375.00
337.50
89.46
20.74
143.13
62.21
78.67
1028.04
2535.47
2.00
5.00
4.00
5.00
4.00
4.00
16.00
12.00
4.00
1.00
PROJECT : PROPOSED 2 (TWO) STOREY RESIDENCE
LOCATION LOT 12 BLK 4 SACRED HEART SUBDIVISHION PHASE II, MANDURIAO, ILOILO CITY
OWNER : ARCHT. JOEL R. MERCURIO
SUBJECT : BILL OF MATERIALS AND ESTIMATES
DATE : ###
I. Masonry
a. Portland cement 742 bags 198 69,300
b. 4" hollow blocks 1,500 pcs. 10 15,000
c. screened sand 4 trucks 1,300 5,200
d. others lumpsum 3,000
P 92,500
II. Hardware
a. 10 mm ø def bars 270 pcs. 230 62,100
b. no. 16 G.I. tie wire2 rolls 2,500 5,000
c. assorted nails 20 kilo 70 1,400
d. others lumpsum 5,000
P 73,500
III. Lumber and Boards
a. False work forms
1. 2x3x12 cocolumb150 pcs. 66 9,900
2. 1/4" thk ordinary 25 pcs. 300 7,500
3. 3 ø bamboo 50 pcs. 50 2,500
b. 2x2x12 good lumb180 pcs 140 25,200
for ceiling joist
c. 1/4 " thk marine 43 pcs 350 15,050
d. others lumpsum 4,000
P 64,150
IV. Painting
a. latex paint 30 gal 480 14,400
b. Q.D. enamel 10 gal 550 5,500
c. others lumpsum 5,000
P 24,900
V. Electrical
a. Ceiling light recept47 pcs 20 1,316
b. 150 m roll no. 2. 5 rolls 3,000 15,000
c. 150 m roll no. 3. 4 rolls 3,700 14,800
d. 3/4" plastic mould45 pcs 90 4,050
e. circuit breaker 2 pcs 5,000 10,000
f. 40 watts fluouresc 47 pcs 400 18,800
g. switches 15 pcs 250 3,750
h. duplex conv. Outle28 pcs 250 7,000
i. others lumpsum 6,400
P 81,116
P 187,750
VII. Miscellaneous
a. electric const. exp lumpsum 7,000
b. water const expenlumpsum 7,000
c. plans & permit lumpsum 5,000
P 34,000
SUMMARY
ITEM AMOUNT
I. MASONRY P 92,500
II. HARDWARE 73,500
III. LUMBER & BOARD 64,150
IV. PAINTING 24,900
V. ELECTRICAL 81,116
VI. DOORS & ACCESSORIES 187,750
VII. MISCELLANEOUS 34,000
P 557,916
PREPARED BY :
I. MASONRY
a. Portland cement 742 bags 260 192,920
b. 6" Hollow blocks 2980 pcs. 14 41,720 4100
b. 4" hollow blocks 1130 pcs 12 13,560
c. gravel (4 cu.m) 15 truck 2,500 37,500
d. screened sand (4 cu.m) 18 truck 2,400 43,200
e. others Lumpsum 10,000
338,900
II. HARDWARE
a. 20 mm ø def bars 45pcs. 400 18,000
b. 16 mm ø def bars 330 pcs. 320 105,600
c. 12 mm ø def bars 800 pcs. 180 144,000
d. 10 mm ø def bars 550 pcs. 110 60,500
e. no. 16 G.I. tie wire 10 rolls 2,000 20,000
f. assorted nails 20 kilo 1000 20,000
g. hacksaw blade 55 pcs 55 3,025
h. 1/4"x 1 1/2" Angular 25pcs. 820 20,500
i. Welding Rod 15 kilos 100 1,500
j. Others Lumpsum 10,000
403,125
III. TILEWORKS
a. 12'x 12' Unglazed tiles (floor and toilet) 95pcs. 30 2,850
b. 12'x 12' Unglazed tiles (kitchen & toilet wall) 250pcs. 30 7,500
c. Grout Cement 5 kilos 20 100
d. Plastic Trims 8" long for tiles 20pcs. 30 600
e. Red Oxide (floor) 1 drum 1200 1,200
f. Decorative stones lumpsum 2,500
g. Others lumpsum 5,000
19,750
IV. LUMBER & BOARDS
a. work forms
1. 2x3x12 cocolumber 200 pcs. 78 15,600
2. 1/4" thk ordinary plywood 25 pcs. 340 8,500
3. 3" ø bamboo 50 pcs. 110 5,500
b. 2x2x12 ceiling joist wood 50 pcs. 112 5,600
c. 1/4 " thk marine plywood 30 pcs. 400 12,000
d. 1'' x 3'' x 12'' wood moulding 15 pcs. 200 3,000
e. others Lumpsum 5,000
55,200
V. TINSMITHRY
a. #26 Corr. G.I sheet 20' long (RIB type color) 45 pcs 5200 52,000
b.No. 26 ridge roll G.I (pre-painted) 5 pcs 750 3,750
c. Tex screw (roof fastener) 250 pcs. 2 500
e.Vulca seal/silicon glue 2 liters 400 800
f. Water proofing (flexi bond) 4 gal 780 3,120
e. others Lumpsum 5,000
65,170
X. PAINTING
a. Flat wall latex paint 25 pails 2200 55,000
b. Q.D. enamel 5 pails 2600 13,000
c. Paint primer 3 gal 500 1,500
d. Lacquer thinner 3 gal 450 1,350
e. Conc. Neutralizer 2 gal 300 600
f. Patching Compound 2 sacks 1300 2,600
g. Sand Paper (#10, #150, #220) 20 meters 130 2,600
h. Paint Thinner 5 gal 300 1,500
i. Flat wall enamel 3 pails 2400 7,200
j. Others Lumpsum 7,750
93,100
XI. ACCESSORIES
a. Door Knobs 13 pcs. 700 9,100
b. Kitchen counter & hanging Cab. 2 pcs 7500 15,000
c. Others Lumpsum 5,000
29,100
XII. MISCELLANEOUS
a. Lighting use for construction Lumpsum 10,000
b. Water use for construction Lumpsum 15,000
d. Backfill for bldg. elevation Lumpsum 20,000
e. Others Lumpsum 10,000
55,000
SUMMARY
ITEM
I. MASONRY 338,900
II. HARDWARE 403,125
III. TILEWORKS 19,750
IV. LUMBER & BOARDS 55,200
V. TINSMITHRY 65,170
VI. PLUMBING FIXTURES 39,450
VII. PLUMBING SUPPLY 67,590
VIII. DOORS & WINDOWS 140,384
IX. ELECTRICAL 174,405
X. PAINTING 93,100
XI. ACCESSORIES 29,100
XII. MISCELLANEOUS 55,000
TOTAL 1,481,174
PREPARED BY :
ARCHT. JOEL R. MERCURIO, UAP
PRC NO. 7812
1025 1121.35