You are on page 1of 4

6TH INTERNATIONAL CONFERENCE ON MODERN POWER SYSTEMS MPS2015, 18-21 MAY 2015, CLUJ-NAPOCA, ROMANIA

The Reliability Evaluation of the Electrical


Substations with Various Connection Schemes

Pavel Atănăsoae, Radu Pentiuc, Eugen Hopulele


Faculty of Electrical Engineering and Computer Science
“Ştefan cel Mare” University of Suceava
Suceava, Romania
atanasoae@eed.usv.ro; radup@eed.usv.ro; eugenh@eed.usv.ro

Abstract— Under the conditions of promoting the production new energy sources: combined heat and power plants,
of electricity from medium and small power sources (distributed renewable energy sources.
generation), it is required that the connection of these groups to
the already existing electrical substations in the National Power The paper comparatively analyzed the most common types
System is functional. This paper presents an analysis of the of connections schemes of the electrical substations: single bus
reliability of existing electrical substations in order to connect system; single section bus system; double bus system; double
new sources for generating electricity. bus system and transfer bus. The reliability concepts can be
applied to virtually any engineering systems. In its broadest
Keywords—reliability; electrical substations; electricity market; sense, reliability is a measure of performance. This measure
distributed generation. can be used to help systems meet performance criteria, to help
quantify comparisons between various options, and to help
I. INTRODUCTION make economic decisions.
The reliability of an electricity supply system reflects its
ability to maintain service continuity. Transition to the market II. CALCULATION ASSUMPTIONS
economy changes dramatically relations between the To analyze the reliability of electrical installations,
participants in the electricity market. Electric power producers calculation models which involve independence of the state
began to compete in electricity sale, contradictions arose which goes through a particular entity compared with other
between the market subjects that led to heavy operational appropriate entities of the system are usually accepted. Because
regime of electric power systems and complicated their the component elements of electrical substations usually
managing. Now relationship between the participants in the consist of high reliability equipment (the ratio λ/µ ≤ 0.05),
electricity market is based on contractual obligations and these may be considered independent. This assumption allows
mutual financial settlements. In these conditions, the key approaching the reliability calculations for schemes of
objective is to eliminate decrease in reliability level that existed electrical substations whose initial configuration changes over
under the centralized management and adapt it to the time by deliberate actions of the operating personnel depending
requirements of each participant in the electricity market. on the needs of the system (manual or automatic maneuvers).
In the National Power System there are a variety of In order to avoid laborious calculations, in practice you can
connection schemes for electrical substations. The multitude of use equity methods which consist of transforming the
adopted solutions is due to the different criteria and the technological scheme of the system in the equivalent schemes
different share that was taken into consideration when the of reliability, which are dependent on the level of analyzed
electrical substation was built. Thus, the solution of building success. It is considered that the runtimes between two failures
such a substation was mainly influenced by their location and and the times to restore the component elements of the electric
the function that it was going to fulfill in the power system: substation are random variables, distributed according to an
outlet electrical substation, electrical transfer substation, exponential distribution function.
electrical distribution substation or electrical substation with
multiple functions. To evaluate the reliability, the system is often decomposed
into a number of individual subsystems or constituent
Under the conditions of promoting the production of components. The reliability for these can be calculated and
electricity from medium and small power sources (distributed then combined using various numerical techniques to estimate
generation), it is required that the connection of these groups to the reliability of the complete system. Then, we equate
the already existing electrical substations is functional. There is successively and in the calculation scheme we replace each set
a need to evaluate the reliability of the electrical substations in of elements that enters into an elementary connection (series,
which such groups are connected in order to achieve financial parallel) on each branch of the calculation scheme by a single
analysis calculations and justification of investment projects in equivalent element.

15
6TH INTERNATIONAL CONFERENCE ON MODERN POWER SYSTEMS MPS2015, 18-21 MAY 2015, CLUJ-NAPOCA, ROMANIA

Thus, for a system with n elements in series, the equivalent


indices are calculated using the following equations:
II
n
λ es = ∑ λi (1)
i=1
n III I
∑ λi B B A
i =1
µ es = n λ
(2) ……
i G
∑ n
i =1 µi
Fig. 1. Single section bus system
For a system with two elements in parallel, the equivalent
indices are calculated using the following equations:

λ1 ⋅ λ 2 ⋅ (µ1 + µ 2 )
λ ep = (3)
V II

µ1 ⋅ µ 2 + λ1 ⋅ µ 2 + λ 2 ⋅ µ1
µ ep = µ1 + µ 2 (4) IV
VI III I
For a system with n identical elements in parallel, the B B B B A
equivalent indices are calculated using the following equations: …… ……
G
a) for equivalent failure rate: n/2 n/2

  λ 
 2⋅λ ⋅ 
Fig. 2. Single section bus system

λ+µ
2
λ ep = 2 ⋅ λ = III

 2 2⋅λ + µ  λ 
 1+   II
 λ+µ
  λ 
2 IV

 3⋅ λ ⋅
λ + µ 
I
 
V

λ ep3 = 2 B B A
  λ   λ  ……
1+  +
 λ + µ   λ + µ 
G
  (5) n

M Fig. 3. Double bus system


 n −1
  λ  III
 n ⋅ λ ⋅ λ+µ
λ epn =  
n −1 II
  λ   λ 
 1+   + ... +  λ + µ 
λ+µ
IV
   VI
I
V
b) for equivalent repair rate:

µ ep2 = 2 ⋅ µ VII


µ ep3 = 3 ⋅ µ B B A
 ……

M (6) G

µ = n ⋅ µ n
 epn Fig. 4. Double bus system and transfer bus

16
6TH INTERNATIONAL CONFERENCE ON MODERN POWER SYSTEMS MPS2015, 18-21 MAY 2015, CLUJ-NAPOCA, ROMANIA

The reliability parameter values used as input data in our


calculations are taken from the NTE 005/06 standard [7]. The
1
diagrams shown in Figures 1-4 were compared in terms of
power transit between points A and B. The calculation 0.9
equations for reliability indicators are presented further. 0.8

Mean Time Between Failures: 0.7


n=2
0.6

Reliability
1
MTBF = (7)
0.5
n=6
λe 0.4
0.3
Mean Time To Repair:
0.2
n=12
1 0.1
MTTR = (8)
µe 0
0 2000 4000 6000 8000 10000
The system reliability is determined by the following relation: Time [hours]

R (t ) = e −λe ⋅t (9) Fig. 5. Reliability for single bus system

and the system availability:


1
MTBF
A= (10) 0.9
MTBF + MTTR 0.8

The probability of success of the electrical substation: 0.7


Reliability 0.6 n=2
µe
PS = (11)
0.5

λ e + µe 0.4
n=6
0.3
The probability of rejection of the electrical substation: n=12
0.2

λe 0.1
PR = (12)
λe + µe 0
0 2000 4000 6000 8000 10000
Mean Up Time in the analyzed period T: Time [hours]

µe
MUT = ⋅T (13) Fig. 6. Reliability for single section bus system
λe + µe
Mean Down Time in the analyzed period T: 1

λe
MDT = ⋅T (14) 0.9
n=2
λe + µe
0.8
The undelivered electricity:
Reliability

0.7
n=6
Wundelivered = MDT ⋅ Pinst (15) n=12
0.6
where Pinst is the installed power of the power unit connected at
the electrical substation.
0.5
III. RESULTS AND DISCUSSION
0.4
Figures 5-8 show how the configuration type and the
0 2000 4000 6000 8000 10000
number of circuits influence the reliability of the substation.
The single bus system is the simplest of the configurations, but Time [hours]
is also the least reliable. Failure of a circuit breaker or a bus
fault for single bus system causes loss of entire substation. Fig. 7. Reliability for double bus system

17
6TH INTERNATIONAL CONFERENCE ON MODERN POWER SYSTEMS MPS2015, 18-21 MAY 2015, CLUJ-NAPOCA, ROMANIA

1 TABLE II. MEAN DOWN TIME AND UNDELIVERED ELECTRICITY FOR


PINST=20 MW AND N=12
n=2
n=6 Electrical substation MDT The undelivered
0.95 configuration (hours/year) electricity for 10 years
n=12 (MWh)
Single bus system 19.50 3899.13
Reliability

0.9 Single section bus system 13.59 2717.25


Double bus system 5.95 1190.42
Double bus system and
0.16 32.11
0.85 transfer bus

The longitudinal and cross sectioning of the bars have


0.8 favorable consequences on the effects of incorrect operation of
0 2000 4000 6000 8000 10000 the switches. Frequency and duration of outages are relevant
measures for reliability in electricity supply systems.
Time [hours]
IV. CONCLUSIONS
Fig. 8. Reliability for double bus system and transfer bus The quantitative analysis of reliability aims to quantify
under the form of numerical indicators that show the level of
A sectionalized single bus bar configuration is flexible in reliability for the comparison of two or more solutions in terms
operation. It is higher in reliability than single bus bar of operational safety.
configuration. Isolation of bus sections for maintenance is
The economic efficiency of an investment can be
possible in this scheme. established based on a comparison of the economic effects in
In the case of the double bus system, if a bus fails, all the case of the non-evacuation in the power system of a certain
equipment connected to it can be placed on the other bar amount of electrical energy under the new conditions on the
system (the node is fully reserved). In practice, the double bus electricity market. The economic effect of reliability is finally
system schemes can be with one or both bars longitudinally quantified by the undelivered electricity caused by the failure.
sectioned, leading to a greater flexibility scheme. The amount of undelivered electricity can be used further in the
The double bus system and transfer bus scheme is the calculations for the financial analysis of investment projects.
safest but with the highest costs in terms of investments.
The probability of success and the number of interruptions The value of the undelivered electricity must consider the
cost of the penalty due to the imbalance from the approved
depending on the number of circuits and the configuration of
notification on the electricity market.
the electrical substation is presented in Table I.
REFERENCES
TABLE I. THE PROBABILITY OF SUCCESS DEPENDING ON THE NUMBER
OF CIRCUITS
[1] W. Li, R. Billinton and A. Tache, „ Reliability Evaluation of Multiple
Electrical substation Number of Number of The probability Substations with Distribution Networks”, in Proc. 2014 IEEE
configuration circuits interruptions per of success International Conference on Probabilistic Methods Applied to Power
year Systems, Durham, 7-10 July 2014, PMAPS 2014, pp. 1-6.
n=2 0.84 0.9988987 [2] C. C. Kuo and F. H. Chen, „Evaluation of substation bus schemes
Single bus system n=6 1.39 0.9984491 considering reliability”, in Proc. 2010 IEEE International Conference on
Machine Learning and Cybernetics, Qingdao, 11-14 July 2010, ICMLC
n=12 2.22 0.9977745 2010, pp. 2979-2984.
n=2 0.73 0.9889627 [3] Z. Dong, D. O. Koval and J. E. Propst, „Reliability of various industrial
Single section bus substations”, in IEEE Transactions on Industry Applications, vol.40,
n=6 0.97 0.9987867
system 2004, pp. 989-994.
n=12 1.39 0.9984491
[4] P. Jahangiri and M. Fotuhi-Firuzabad, „Reliability assessment of
n=2 0.32 0.9993362 distribution system with distributed generation”, in Proc. 2008 IEEE
Double bus system n=6 0.33 0.9993324 International Conference on Power and Energy, Johor Baharu, 1-3
December 2008, PECon 2008, pp. 1551-1556.
n=12 0.36 0.9993205
[5] I. Viziteu, „Fiabilitatea instalaţiilor electroenergetice (The reliability of
n=2 0.005 0.9999973 electric power plants)”, Editura PIM, Iaşi, 2010.
Double bus system and
n=6 0.01 0.9999936 [6] V.I. Nitu, C. Ionescu, „Fiabilitate în energetică (Reliability in power)”,
transfer bus
n=12 0.04 0.9999917 Editura Didactică şi Pedagogică, Bucureşti, 1980.
[7] ***NTE 005/06, ,,Normativ privind metodele şi elementele de calcul al
siguranţei în funcţionare a instalaţiilor energetice (Standard on
The mean down time and electricity undelivered for calculation methods and elements of safe operation of power plants)”,
Pinst=20 MW and n=12 circuits are presented in Table II. ANRE, 2006.

18

You might also like