Professional Documents
Culture Documents
net/publication/274246580
CITATIONS READS
2 1,700
3 authors:
Nebojša Petrović
JSC "Elektromreža Srbije" Belgrade - Serbian Transmission and Market Operator
5 PUBLICATIONS 2 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Dragoslav Perić on 23 December 2016.
SERBIA
dragoslav.peric@ems.rs
ABSTRACT
1 INTRODUCTION
The reliability of electricity supply to customers (e.g. the rate and duration of power outages)
depends on the reliability of HV/MV substations, namely on a single-pole diagram and on the
reliability of substation equipment. The reliability of HV/MV substations is determined by means of
the selective search method [1], in which coincidences (overlapping) of up-to-second-order events
leading to interruption of certain functions are taken into account. Reliability indices for equipment of
the HV/MV substations were taken over from [3], [4].
Reliability calculations for the single busbar "H" configurations (arrangements) were conducted to
analyse the cases: with one disconnector in a bus coupler; with two disconnections in a bus coupler; and
with two disconnectors and a circuit breaker in a bus coupler. Cases with or without longitudinal
sectioning of both busbar systems were analyzed for configurations with a double busbar system. The
calculations performed were aimed to determine the reliability indices for the transit of electric energy,
outage of an entire capacity or of a half of it. In dealing with double busbar configurations we also
considered the reliability of different switching states (normal state, busbar refurbishment). In addition,
sensitivity analysis of reliability results of studied functions was made for different equipment reliability
input data.
The performed analyses have shown that the active faults and durations of substation component
restoration have significant impact on their reliability indices so that it would be necessary to
adequately expand future questionnaires for equipment reliability surveys.
2
Fig.1 –HV/MV substation arrangements which are subject of analysis
Reliability indices for other blocks of the H2 arrangement (Table II) are calculated in the same
way. The letter "a" in the block failure designations active failures, or block faults which, due to
activation of the relay protection, cause, by rule, tripping of other blocks, which remain out of service
for the time s required to make necessary changes in topology and to restore facility functions .
Table II – Failure rate and duration for all blocks of H2 configurationt
Block fBk rBk Block fBk rBk Block fBk rBk
B1 0,0063 3,6030 B62 0,0154 4,1005 B32 0,0067 4,0503
B2 0,0063 3,6030 B63 0,0072 3,6500 B33 0,0029 4,0000
B4 0,0096 91,1642 B71 0,0207 3,5129 B34 0,0029 4,0000
B5 0,0096 91,1642 B72 0,0207 3,5129 B4aHV 0,0019 0,1
B61 0,0154 4,1005 B31 0,0067 4,0503 B5aHV 0,0019 0,1
Time for restoration is presented by value s = 0.1 h, and ratio of active failures in the total number
of failures by a value fa/f=0.25. Block B63 operates with a normally opened circuit breaker, and its
failures, therefore, do not affect the analyzed functions of the facility.
Events that should be analyzed are the following: interruption of entire load, interruption of a half
load and suspension of the transit on the HV side. Table III shows the lists of functional blocks the
outage of which leads to the interruption of analyzed functions.
Table III – Block failures that lead to interruption of certain functions for the case of H2 arrangement
Function Block failures that interrupt a function
Interruption of the entire load B1a, B2a, B31a, B32a, B33a, B34a, B4aHV, B5aHV
Interruption of half load B31, B32, B33, B34, B4, B4aMV, B5, B5aMV, B61, B62, B71a, B72a
Suspension of transit B1, B2, B31, B32, B33, B34, B4aHV, B5aHV
Reliability indices of analyzed facility functions are calculated using the relationships of the same
type as equations (1) and (2), by taking into account that the sum (∑) over k covers all failures that
interrupt the considered function. Hence, the failure rate of the transit suspensions is calculated by
adding the corresponding values for failure rates of blocks B1, B2, B31, B32, B33, B34, B4aHV,
B5aHV (Table II):
3
1
f = f Bk 0,0063 0,0063 0,0067 0,0067 0,0029 0,0029 0,0019 0,0019 0,0356 ,
Bk year
4
Table IV Unavailability – Annual interruption time of functions [min/year]
Suspension of Partial Transit Interruption of Entire Load Interruption of a half load Suspension of transit
H1 0,94 133,34 13,69
H2 0,08 135,08 14,56
H3 0,05 133,37 17,10
GH1 2,46 143,74 27,89
GH2 0,05 148,57 30,30
GH3 0,02 143,77 27,79
D11 0,10 128,78 0,10
D12 0,13 0,01 128,78 0,07
D13 0,08 128,78 0,05
D21 0,11 128,78 0,11
D22 0,10 0,01 128,89 0,05
D23 0,09 128,78 0,04
GD11 0,05 122,80 0,05
GD12 0,06 0,01 127,76 0,03
GD13 0,0 255,53 0,03
GD21 0,06 127,76 0,06
GD22 0,06 0,01 127,83 0,03
GD23 0,06 127,76 0,04
5
As can be seen, ratings of unavailability i among studied configurations and switching states are
maintained for all considered variations of the input data, though differences in the substation
unavailability in absolute terms become more obvious. From this we can draw an important
conclusion about the validity of the comparative reliability analysis of configurations from the
previous subsection, because the obtained ratings are also valid for significant variations of input data.
Fig. 3 - Sensitivity of the entire load outage function to the change of the equipment reliability
indices
4 QUESTIONNAIRES
In order to carry out a calculation of substation reliability it is necessary to have data on reliability
of substation components. Those data are collected from surveys, and the most relevant among them
are the CIGRE surveys [3], [4]. However, majority of the surveys deals mainly with component failure
rate, while the component restoration time and a share of active faults in the total number of failures
are analyzed in a much lesser extent.
6
4.1 Restoration Time
When a failure of substation component occurs, relay protection system triggers the opening of a
corresponding circuit breaker, and procedure for renovation of a faulty element starts thereafter. Steps
of element restoration are schematically shown in Fig. 4.
failure element (disconnection) t 1 t10 switching element (end of recovery)
restoration of power supplay of consumer (without faulty element) t2 t20 returning to the basic operation state
„open“ work permit t3 t30 „close“ work permit
start of work t4 t40 end of work
start effective work t5 t50 end of effective work
7
classified to active failures. The failure rate and schare of active failures is calculated as:
n fa na
f (4) (5)
NT f n
2. The values n and na are determined by means of forming a relevant list (list n and list na) and any
element failure is added to the list n, and if the failure is classified as active it adds to the list na.
The number of list items at the end of the period represents the value n and na.
3. If it is a complex fault with a higher number of outages, it is necessary to identify the element
affected by a failure which is to be added to its list n and na.
4. Failure duration time should be recorded for each active fault of element till putting the unaffected
elements back into operation. These times are by a rule, approximately the same for all elements,
because they primarily depend on the time required to make necessary changes in equipment
topology and can be categorized according to voltage level, of facility design, network
management organization, etc on.
5 CONCLUSION
The selective search method was used to carry out calculation of the HV/MV substation reliability
for different variants of a single busbar (H) configurations and configurations of double busbar on HV
side. Reliability indices were taken into consideration for electric power transit, outage of entire load
or of a half load. Also, reliability indices for double busbar configurations were taken into
consideration for different switching states (normal state, busbar refurbishment) which is a novelty in
the application of these methods. We conducted an analysis of sensitivity of results to changes of input
data on the reliability of equipment. The analysis confirmed the relative relations of unavailability of
different configurations and switching states. Basic practical conclusions of this analysis are:
1. H configurations should have two disconnectors in the bus section bay in HV busbars, and no
significant improvements to the substation reliability were achieved with a circuit breaker
added to the bus section.
2. Configurations with a double busbar installed on the HV (line) side of the substation are more
reliable than H configurations.
3. Configuration with a double busbar having complex bus section and bus coupler (circuit
breaker and six (6) disconnectors) is not significantly more reliable than the configuration
with a simple bus coupler (circuit breaker and two disconnectors).
4. The most reliable switching state out of all switching states for double busbar configurations
is the one where power lines and transformers are symmetrically (per half) arranged in two
busbar systems, and bus coupler is in position CLOSED.
5. Reliability of configurations performed in GIS technology proves to be significantly better for
the function of power transit for double busbar system configurations.
6. Time for renovation of elements and the share of active failures in the total number of failures
are not sufficiently covered by the surveys on substation component failures. This paper
highlights the need for collection and processing of these data in future surveys.
6 REFERENCES
[1] Jovan M. Nahman, Dependability of Engineering Systems, Springer-Verlag, Berlin, Heidelberg,
New York, 2002.
[2] J. Nahman, N. Mijušković, Reliability analysis of EHV substations, CIGRE Conference, Paris,
paper 23-05, 1980.
[3] Cigre TB 509, Final Report of the 2004 - 2007 International Enquiry on Reliability of High
Voltage Equipment Part 1 - Summary and General Matters Working Group A3.06,October 2012
[4] Cigre WG A2.37, Transformer Reliability Survey: Interim Report, Electra No 26, pp. 46-49,
April 2012
[5] C. R. Heising at al., Final report on high-voltage circuit breaker reliability data for use in
substation and system studies, CIGRE Conference, Paris, paper 13-201, 1994
[6] E. D. Tweed, C. E. Withers, D. J. Hughes, A distribution substation rating strategy based upon
reliability analysis, IEEE Trans. PAS, Vol. 102, No.9, pp. 2893-2897, Sept.1983.
[7] N. Mijušković, Calculation of reliability SF6 gas insulated plants and a proposal to amend the
"H" schemes in the SS 110/10 kV, 18. Conference JUKO CIGRE, R.23.02, 1987.