Professional Documents
Culture Documents
Analysis
2 Network Analysis
Construction Management
Ahammed Aflah
Dept of Architecture, CET
What does a Network Look Like?
What does a Network Look Like?
Elements of a Network
Nodes
Li k
Linkages
Li k
Links = Relationships
R l ti hi
Activity 1
Finish‐Start
Activity 2
Construction
i j
Network
Relationships between nodes
Activity A
Activity A Activity B
Activity B Independent
Activity A
Activity A Activity B
Activity B
D
Dependent
d t
Activity A
Activity A
Activity C Merge
Activity B
Activity B
Activity B
Burst
Activity A
Activity C
Other classifications of relationships
Activity A Activity B
Predecessor‐
Successor
Activity B
Activity A Concurrent
Activity C
Types of Activities on a Network
Start
Dummy
Activities
Finish
Milestones
Activity 1
Activity 1 Tasks
Draw a Network
Joint
One Set of Wall and Footing Forms are Available
Construction Method
WBS
Task Description D ration
Duration
1 Footing 1 5 Days
2 Footing
g2 5 Days
y
3 Wall 1 3 Days
4 Wall 2 3 Days
The Network Diagram
2
Footing 2
4
Wall 2
1
Start Finish
Footing 1
3
Wall 1
Redundant Links
Activity A Activity B
Activity C
How to Build a Network or a
Precedence Diagram
1. Understand the Construction Methodology
Understand the Construction Methodology
2 Generate a WBS
2. Generate a WBS
3 Identify Dependencies between Activities
3. Id tif D d i b t A ti iti
4. Build the Network
Bridge Problem
2 3
4
5 6
7
9
8 10
11
12
14
15 16
13
17 18
Bridge Problem – Ball of Strings
2 3
4
5 6
7
9
8 10
11
12
14
15 16
13
17 18
Bridge – Precedence Diagram
1
4
5 7 9 13 11
Start 2
16
6 8 10 14 17
12
18
15
Finish
PD without constructing Ball of Strings
N
Network k
A Start 2 2
B A 3 3
C E,F ‐ 4
‐ 4
D E
E A 3 3
F S
Start 2 2
Finish B,C,D ‐ 5
Step 3 – The Network
1 2 3 4 5
A B D
Finish
Start E
F C
How Do you Estimate Activity Time?
• Intuition/Experience
• Random Guessing
d G i
• Historical Data and Statistical Methods
• Use Estimating Guides
Adding Contingencies
• Why do you add contingencies?
Why do you add contingencies?
– Weather
– Strikes
– Holidays
– Political/Economic issues
/
• How do you add contingencies?
– To all Activities
– To affected activities
– As a separate activity?
p y
Some thoughts to Keep in Mind
• The
The First Activity Starts at Time t= 0
First Activity Starts at Time t= 0
• Be consistent while representing time
elements E g a 12 hour activity is
elements. E.g. a 12 hour activity is
– 1 day?
– 2 days?
2d ?
– 0.5 days?
– 1.5 days?
– 3 days (including weekend)?
Summary – What you need to
construct a PD or an AoN diagram
1. Proper understanding of construction
methods
2. A good WBS
3. Relationships between Activities and
Duration
4. The techniques we have studied
Can we answer these questions with
the PD’s that we have produced?
• When is the earliest an activity can Start?
• When is the latest that it can finish?
• How much leeway does an activity have?
Thank You
Thank You