METHOD STATEMENT FOR INSULATION WORKS
1. General
This work method covers the requirement for the preparation and application of thermal insulation for Evonik
to DuPont plant.
2.Purpose
The purpose of this method statement is to show the work scope and materials needed for the insulation job at
Evonik to DuPont Plant.
3. Scope
FERH scope is doing the insulation and jacketing works linking the 2 plants.
5. Responsibilities
Site Manager.
He will be the overall in charge of the operations.
Ensures that all workers follow the In house rules and Singapore Law
Ensure that all workers will be working on safe working conditions.
To enforce any corrective actions required by client
To also ensure proper housekeeping at all times.
To understand the whole work scope and requirements.
To participate in any HSE meetings and site walks required.
Project Coordinator.
He will be working closely with the site manager regards to operations.
He is the 2nd in command.
In any case, the site manager is unavailable for meetings, he will represent
He is to upkeep the requirements given by clients and site manager.
To do reporting and documentations for any submissions
He will be responsible to call for inspection once job completed, based on test packages
Supervisor/Foreman
He is mainly in charge on site supervision
He will work closely with the management and execution
He manages the workers with instructions given by managements
If required for site walk and inspection, he must be present on site
He must ensure all workers are equipped with proper PPE.
End of the day, he must ensure housekeeping to be done before going home.
Insulators
Workers are to report to supervisor every day for their job scope
They are check their tools before start of work.
Ensure proper PPE and if insufficient report to Supervisor.
They must be responsible of their own tools bags.
To follow all in house rules at all times.
To do housekeeping everyday
Page 2 of 7
METHOD STATEMENT FOR INSULATION WORKS
6. Materials
6.1Insulation Materials
Temperlite
Jacketing Materials
Fastening Materials
Silicone Sealant
SS Self Tapping Screw
7. Application Procedures
7.1 General
7.1.1 Surfaces shall be clean of dirt, loose rust, scale, loose paint, oil, grease and other foreign
matter.
7.1.2 All surfaces to be insulated shall be thoroughly dried before application of insulation.
7.1.3 Insulation material shall be protected from moisture and weather before and during
application. Applied insulation shall be free of moisture prior to application of insulation
finish.
7.1.4 Insulation shall be applied with all joints, butted to eliminate voids. Any opening through the
insulation finish shall be flashed moisture tight.
7.1.5 Insulation shall be discontinued at flanged connection to permit removal of the studs. The
distance from the end of insulation to back of flange on both sides of the connection shall be
equal to one stud length plus 25mm.The ends of insulation shall be straight.
7.1.6 On horizontal piping, the longitudinal lap shall be positioned to shed rainwater and minimize
dust collection.
8 Materials Attachments
8.1 Perlite Data Sheet
Page 4 of 7
METHOD STATEMENT FOR INSULATION WORKS
Thresho : 15
ld Limit mg/m3
Value
Reactivity Data
Material : Stable Chemical : Strong acids
Stability Incompatibil
ities
Hazardous : None Conditions : None in
Decompositi to Avoid design use
on
Hazardous Polymerization : Will not occur
Special Precautions
Precautions to be taken in handling and storage: Keep material dry and minimize the generation of dust.
Other Precautions: Use care in handling and storage of product to avoid crushing, breaking or undue wear
especially on product edges.
The information given in this document is believed to be accurate and is provided in good
faith.
DESCRIPTION / SPECIFICATIONS
Cherrit's Aluminium Roll Jacketing is manufactured from Alloy 3003 and 1060 and Temper H-14, conforming to ASTM B-
209. (Other alloys available on request).
Cherrit's Aluminium roll jacketing is available in a smooth finish or a stucco embossed pattern. Either finish can come
with 5mm (3 / 16") corrugations.
Thickness : 0.4 mm, 0.5 mm, 0.6 mm, 0.8 mm, 1.0 mm
(other thicknesses available).
Widths : 914mm and 1220mm (914mm for corrugated rolls)
Length : 30 meter (other lengths available on request)
9. HSE
Page 6 of 7
METHOD STATEMENT FOR INSULATION WORKS
WEC HSE Manager shall ensure that the work is performed accordance to the approved
Construction Safety Manual and precautions specified in the work permit. He shall
ensure that barricades, warning tapes, warning signs, firefighting equipments and first
aid kits are readily available at the working area.
Tool box talk shall be conducted on a daily basis to inform the workers of the recent
safety issues and incidents and to get feedback of any unreported unsafe acts. Feedback
will then be processed and resolved.
All Equipments and tools shall be checked for good conditions before commencing the
work.
Unauthorized persons shall be excluded from the area.
On completion of job, the area shall be cleared of any materials and keep clean and tidy.
Hazard analysis for hazardous operation shall be carried out prior to commencing the
works.