Will be discharge
to roadside drain
3
DI PIPE 450mm Ø
DISCHARGE TO
DRAINAGE SUMP
UDRAIN 1.8 x 1.9m
4
PROJECT : KAJANG ECO-VALLEY
EFFLUENT PUMPING DESIGN : 40700PE
1 DESIGN DATA
Page 1 of 3
* * HYDROLOGY * * * HYDRAULIC
AREA Intensity, Flow Rate, TOTAL DRAIN DETAILS, Velocity, Flow Rate,
LOCATION C ƩA i Q ƩQ W H P A R S V Q
MARKING (ha) (mm/hr) (m³/s) (m³/s) (m) (m) (m) (m²) (m) (m/s) (m³/s)
0.95 3.000 322.3 2.551 2.5514140 1.80 1.90 5.60 3.42 0.61 0.023 7.3 25.0126889
STP DISCHARGE 19.900 19.9000000
25 YEARS
DISCHARGE TO
22.4514140
SUMP
*refer MSMA N = 0.015
TOTAL AREA : ‐ acre STOR JPS KAJANG
ƩA 30,000.00
m2 ʎ K θ ɳ
3.00
ha 59.153 0.161 0.118 0.812
<Name>
Rectangular Highlighted
Bottom Width (m) = 1.9000 Depth (m) = 1.6215
Total Depth (m) = 1.9000 Q (cms) = 22.2000
Area (sqm) = 3.0809
Invert Elev (m) = 69.9000 Velocity (m/s) = 7.2056
Slope (%) = 2.3200 Wetted Perim (m) = 5.1431
N-Value = 0.015 Crit Depth, Yc (m) = 1.9000
Top Width (m) = 1.9000
Calculations EGL (m) = 4.2699
Compute by: Known Q
Known Q (cms) = 22.2000
71.8000 1.9000
71.5000 1.6000
71.2000 1.3000
70.9000 1.0000
70.6000 0.7000
70.3000 0.4000
70.0000 0.1000
69.7000 -0.2000
69.4000 -0.5000
0 .3 .6 .9 1.2 1.5 1.8 2.1 2.4 2.7 3
Reach (m)