Professional Documents
Culture Documents
Project
is well defined task which has a definable beginning and end
requires one or more resources for the completion of its
constituent activities (interrelated and accomplished)
can be broken down into a number of identifiable activities which
will consume time and other resources during their completion
is scheduled to be completed by a target date
is large and complex and has many interrelated activities
This material is only for classroom discussion. For limited circulation only.
Project
This material is only for classroom discussion. For limited circulation only.
Project
This material is only for classroom discussion. For limited circulation only.
Project
This material is only for classroom discussion. For limited circulation only.
Network
Graphical portrayal of activities and event
Shows dependency relationships between tasks/activities in a
project
Clearly shows tasks that must precede (precedence) or follow
(succeeding) other tasks in a logical manner
Clear representation of plan – a powerful tool for planning and
controlling project
Network techniques used are:
• CPM (Critical Path Method)
• PERT (Project Evaluation and Review Technique)
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
Activity-on-Node (AON):
• Uses nodes to represent the activity
• Uses arrows to represent precedence relationships
This material is only for classroom discussion. For limited circulation only.
technique.
• CPM is an activity oriented technique.
This material is only for classroom discussion. For limited circulation only.
PERT
(Project Evaluation and Review Technique) technique is used,
when activity time estimates are stochastic in nature.
• For each activity, three values of time (optimistic, most likely,
pessimistic) are estimated.
• Optimistic time (a or to) estimate is the shortest possible time
required for the completion of activity.
• Most likely time (m or tm) estimate is the time required for the
completion of activity under normal circumstances.
• Pessimistic time (b or tp) estimate is the longest possible time
required for the completion of activity.
• PERT activities are full of uncertainties, times estimates can
not easily be converted in to cost data.
• PERT
This material is only foris an event
classroom oriented
discussion. technique
For limited circulation only.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
This material is only for classroom discussion. For limited circulation only.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
This material is only for classroom discussion. For limited circulation only.
CPM
The critical path is the longest path through the network (thus
determines minimum time in which the network can be completed)
This material is only for classroom discussion. For limited circulation only.
CPM
CPM
CPM
• Earliest Start is earliest time an activity can start
ESij = Max (EFi)
• Earliest Finish is ESij plus the activity time
EFij = ESij + tij
This material is only for classroom discussion. For limited circulation only.
CPM
• Latest Start is latest time an activity can start
without delaying critical path time
LSij = LFij - tij
• Latest Finish is the latest finish time
LFij = Min (LSj)
This material is only for classroom discussion. For limited circulation only.
Slack
Slack is the amount of time an activity can be delayed without
delaying the project.
Slack Time exists for those activities not on the critical path
Slack, Sij, computed as follows:Sij = LSij - ESij or Sij = LFij - EFij
This material is only for classroom discussion. For limited circulation only.
Float
Amount of time by which completion of an activity can be delyed
beyond earliest expected completion time without affecting overall
project duration time.
Total Float (TFij ) = LFij - EFij
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
E D1
3 D 0
B
F G
A
3 5
C D2 4 3
4
2 0
This material is only for classroom discussion. For limited circulation only.
2
• variance: v b - a
6
This material is only for classroom discussion. For limited circulation only.
2
• variance: v b - a
6
discussion.
This material is only for classroom For limited circulation only.
PERT
t a 4m b
6
2
v b - a
6
This material is only for classroom discussion. For limited circulation only.
PERT
This material is only for classroom discussion. For limited circulation only.
PERT
• Find Critical path
• Find Total variance along the critical path
• Find probability that project can be completed in x time
Critical Path Activity Variance
13 1
35 1/9
57 16/9
79 4
total 62/9
This material is only for classroom discussion. For limited circulation only.
1-3-7-9-10
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
This material is only for classroom discussion. For limited circulation only.
Z= (41.5-42.8)/sqrt(6.13) = -0.52
30% approximate chances that the project will complete in 41.5 weeks or less
This material is only for classroom discussion. For limited circulation only.
THANKYOU
This material is only for classroom discussion. For limited circulation only.