BDC STOREROOM (Saudi Technical)

DOCUMENT NUMBERING SYSTEM


Submittal Number pattern to follow in submitting/uploading a new submittal in PROCORE.
CONTRACTOR NAME-PROJECT NAME-DOCUMENT TYPE-DISCIPLINE-SERIAL NUMBER-REVISION
Document Type Abbreviation/Revision Submittal Number Remarks

Not required to write R0, first


RFI RFI (Rev 0) ST-BDC Storeroom-RFI-E-001 submission is already understood
as Rev 0

ST-BDC Storeroom-RFI-E-001-R1
RFI (Rev 1, 2, 3 ….) ST-BDC Storeroom-RFI-E-001-R2
ST-BDC Storeroom-RFI-E-001-R3

Not required to write R0, first


MRI MRI (Rev 0) ST-BDC Storeroom-MFI-E-001 submission is already understood
as Rev 0

ST-BDC Storeroom-MRI-E-001-R1
MRI (Rev 1, 2, 3 ….) ST-BDC Storeroome-MRI-E-001-R2
ST-BDC Storeroom-MRI-E-001-R3

Not required to write R0, first


ST-BDC Storeroom-RFA-E-001
RFA RFA (Rev 0) submission is already understood
as Rev 0

ST-SCC Upgrade-RFA-E-001-R1
RFA (Rev 1, 2, 3 ….) ST-SCC Upgrade-RFA-E-001-R2
ST-SCC Upgrade-RFA-E-001-R3

Not required to write R0, first


ST-SCC Upgrade-SD-E-001
SHOP DRAWING SD (Rev 0) submission is already understood
as Rev 0

ST-SCC Upgrade-SD-E-001-R1
SD (Rev 1, 2, 3 ….) ST-SCC Upgrade-SD-E-001-R2
ST-SCC Upgrade-SD-E-001-R3

Not required to write R0, first


ST-SCC Upgrade-ABD-E-001
AS-BUILT DRAWING ABD (Rev 0) submission is already understood
as Rev 0

ST-SCC Upgrade-ABD-E-001-R1
ABD (Rev 1, 2, 3 ….) ST-SCC Upgrade-ABD-E-001-R2
ST-SCC Upgrade-ABD-E-001-R3

Not required to write R0, first


REDLINE DRAWING RLD (Rev 0) ST-SCC Upgrade-RLD-E-001 submission is already understood
as Rev 0

ST-SCC Upgrade-RLD-E-001-R1
RLD (Rev 1, 2, 3 ….) ST-SCC Upgrade-RLD-E-001-R2
ST-SCC Upgrade-RLD-E-001-R3

Not required to write R0, first


MATERIAL SUBMITTAL MSS (Rev 0) ST-SCC Upgrade-MSS-E-001 submission is already understood
as Rev 0

ST-SCC Upgrade-MSS-E-001-R1
MSS (Rev 1, 2, 3 ….) ST-SCC Upgrade-MSS-E-001-R2
ST-SCC Upgrade-MSS-E-001-R3

Not required to write R0, first


TECHNICAL QUERY TQ (Rev 0) ST-SCC Upgrade-TQ-E-001 submission is already understood
as Rev 0

ST-SCC Upgrade-TQ-E-001-R1
TQ (Rev 1, 2, 3 ….) ST-SCC Upgrade-TQ-E-001-R2
ST-SCC Upgrade-TQ-E-001-R3

Not required to write R0, first


METHOD STATEMENT MS (Rev 0) ST-SCC Upgrade-MS-E-001 submission is already understood
as Rev 0

ST-SCC Upgrade-MS-E-001-R1
MS (Rev 1, 2, 3 ….) ST-SCC Upgrade-MS-E-001-R2
ST-SCC Upgrade-MS-E-001-R3

ALL OTHER DOCUMENTS "WITHOUT DISCIPLINE CODE" WILL CATEGORIZE AS GENERAL SUBMITTAL (GS)

Not required to write R0, first


GENERAL SUBMITTAL (Other) GS (Rev 0) BT-SCC Upgrade-GS-001 submission is already understood
as Rev 0

BT-SCC Upgrade-GS-001-R1
GS (Rev 1, 2, 3 ….) BT-SCC Upgrade-GS-001-R2
BT-SCC Upgrade-GS-001-R3

CODE ACCORDING TO DISCIPLINE


E: Electrical MECH: Mechanical AR: Architectural PL: Plumbing
LC: Low Current HVAC: Heating Ventilation & Air Conditioning CI: Civil ST: Structural

DO NOT USE dash (—) (–) and the em dash


Use Only hyphen (-)

Should you need to submit/upload new document type in the system, and you aren't sure of the submittal number,
please do not hesitate to inquire us before submission.