Professional Documents
Culture Documents
Advantages Disadvantages
It is very easy to disconnect and remove a The parallel redundant configuration
unit, with no need to switch off the supply clearly applies to critical loads, the
and hence no down time for the load; user must be cognisant of the fact
that initially such a system is more
expensive than a hot standby
configuration due to the complex
control required.
The reliability of a full active redundancy is greater than the reliability of its most
reliable component. Suppose that the components have reliabilities greater than
zero (ri > 0). Since 1 − ri < 1 for all i = 1,2, …, n, with increasing the number of
components, the probability of failure Pf tends to zero as a product of large
number of terms smaller than unity and the system reliability R in equation
2.17 can be made arbitrarily close to unity.
Standby redundancy
Where R1 is the reliability function of the power supplies. So, what is the reliability
expectation of this standby redundancy configuration?
A general formula
In the case with n standby units each with a perfect switch when the previous
elements have failed, the general formula is
Here’s a simple diagram of a system with n=3. Note the second standby units
doesn’t become active until the primary and first standby units fail. After the unit
brought online by the first switch fails, the second switch closes allowing the
system to operate with the second standby unit.
Standby Redundancy
You also need a third party to be the watchdog, which monitors the system to
decide when a switchover condition is met and command the system to switch
control to the standby unit and a voter, which is the component that decides
when to switch over and which unit is given control of the DUC. The system cost
increase for this type of redundancy is usually about 2X or less depending on your
software development costs. In Standby redundancy there are two basic
types, Cold Standby and Hot Standby.
Cold Standby
In cold standby, the secondary unit is powered off, thus preserving the reliability
of the unit. The drawback of this design is that the downtime is greater than in
hot standby, because you have to power up the standby unit and bring it online
into a known state. This makes it more challenging to reconcile synchronization
issues, but do to the length of the time it takes to bring the standby unit on line,
you will usually suffer a big bump on switchover.
Hot Standby
In hot standby, the secondary unit is powered up and can optionally monitor the
DUC. If you use the secondary unit as the watchdog and/or voter to decide when
to switch over, you can eliminate the need for a third party to this job. This design
does not preserve the reliability of the standby unit as well as the cold standby
design. However, it shortens the downtime, which in turn increases the
availability of the system.
Quezelco 1 Parallel-Series and Reliability Evaluation of
Distribution Systems
Descriptions and direct comments from the fault registers can be referred from
[35]. The key observations from the analysis are described next.
The case study data consists of fault registers for the selected MV grid with its
stations. The data is recorded in two registers for two consecutive sections of
time. The first register for January 2009 to December 2012 has 160 reported
failure events and the second register for January 2013 to September 2015 has
101 failure events. Note again that the cases in which a station or busbar breaker
operated unrelated to faults in the MV grid are excluded from the list of failures.
Contrasting observations and charts in the classification are presented in [35] on
various indices such as total number of registered faults, total number of
customers affected, Energy Not Delivered etc. The classification was followed by
an analysis of the observations.
The data sets were normalized considering yearly distribution of various faults
belonging to different modes. It is clear that the total number of failures per year
has declined with time. This can be the result of new investments and
maintenance practices in the system. However, while individually comparing the
faults reported under different failure modes, it is seen that an approximate 18%
reduction in active failures, which are the most frequent ones, is the main reason
for the decline in total number of failures per year. The faults with major
contingency escalations are seen to have increased over the years. The
correlation of reliability of control and protection equipment in overlapping
events with major contingency escalation is already established in [34]. This
strongly recommends focusing investments and maintenance on secondary
equipment further, so that more reduction in failures and customer interruptions
are possible.
A basic representation layout of a busbar with several lines feeding from it, as
shown in Figure 3.1, is considered as the basis of the RBD model. Both the busbar
and the individual feeder lines are assumed to have separate breakers for
protection and fault isolation. B0 denotes the busbar protection breaker and B1,
B2, .., Bn represents the feeder protection breakers for lines 1, 2, .., n. The
conductor components in each line and the total feeder section as a whole are
denoted by C and L respectively.
CCost(i,j) The construction cost of the potential line between nodes i and j (SEK)
λN(i) The failure rate of node i (f/yr)
LF(i,j) The amount of load flow in the potential line between nodes i and j
(MWh/h)
LC(i,j) The amount of line capacity for the potential line between nodes i and j
(MWh/h)
loss The amount of power losses in potential lines (%)
RELIABILITY FORMULA IN ELECTRICAL POWER SYSTEM WITH
EXAMPLES
EXAMPLE
Basic examples of series and parallel in circuits
Here, we have three resistors (labeled R1, R2, and R3), connected in a long chain from
one terminal of the battery to the other. (It should be noted that the subscript labeling
—those little numbers to the lower-right of the letter “R”—are unrelated to the resistor
values in ohms. They serve only to identify one resistor from another.) The defining
characteristic of a series circuit is that there is only one path for electrons to flow. In this
circuit the electrons flow in a counter-clockwise direction, from point 4 to point 3 to
point 2 to point 1 and back around to 4.
And, of course, the complexity doesn’t stop at simple series and parallel either!
We can have circuits that are a combination of series and parallel, too:
In this circuit, we have two loops for electrons to flow through: one from 6 to 5 to
2 to 1 and back to 6 again, and another from 6 to 5 to 4 to 3 to 2 to 1 and back to
6 again. Notice how both current paths go through R 1(from point 2 to point 1). In
this configuration, we’d say that R2 and R3 are in parallel with each other, while
R1 is in series with the parallel combination of R2 and R3.
This is just a preview of things to come. Don’t worry! We’ll explore all these circuit
configurations in detail, one at a time!
Learn the Basic Ideas of Series and Parallel Connection
The basic idea of a “series” connection is that components are connected end-to-
end in a line to form a single path for electrons to flow:
The basic idea of a “parallel” connection, on the other hand, is that all
components are connected across each other’s leads. In a purely parallel circuit,
there are never more than two sets of electrically common points, no matter how
many components are connected. There are many paths for electrons to flow, but
only one voltage across all components:
Series and parallel resistor configurations have very different electrical properties.
We’ll explore the properties of each configuration in the sections to come.
Series-Parallel Circuit Example 1
Calculate the current drawn from the supply in the circuit shown in figure
Req=R2||R3Req=R2||R3
To compute equivalent resistance:
Req=R2∗R3R2+R3=20∗3020+30=12ΩReq=R2∗R3R2+R3=20∗3020+30=12Ω
I=ER1+Req=2538+12=0.5A
EXAMPLE
Another example
Req=R2+R3=35+40=75ΩReq=R2+R3=35+40=75Ω
R1 and Req are in parallel:
R=R1||ReqR=R1||Req
To compute equivalent resistance:
R=R1∗ReqR1+Req=50∗7550+75=30ΩR=R1∗ReqR1+Req=50∗7550+75=30Ω
I=ER=7530=2.5A