3. Fire Protection and Fire Supression Works 3. Fire Protection and Fire Supression Works
a.) Pipes and Fittings 2,557,000.00 a.) Pipes and Fittings 2,356,000.00
b.) Valves and Accessories 1,371,100.00 b.) Valves and Accessories 1,224,400.00
c.) Sprinkler Heads 185,900.00 c.) Sprinkler Heads 169,500.00
d.) Fire Hose Cabinet 228,000.00 d.) Fire Hose Cabinet 204,000.00
e.) Fire Department Connection 280,000.00 e.) Fire Department Connection 268,000.00
f.) Fire Pump 660,000.00 f.) Fire Pump 620,000.00
g.) Jockey Hump 220,000.00 g.) Jockey Hump 200,000.00
Fire Suppression System 950,000.00 Fire Suppression System 920,000.00
Testing and Commissioning 380,000.00 Testing and Commissioning 380,000.00
PHP 7,651,840.00 PHP 7,102,928.00
FINAL TOTAL COST Php 26,718,905.92 FINAL TOTAL COST Php 27,728,929.48
NOTES: NOTES:
3. Exclusion in the securement of Permits 3. As built plans excluded. Revision of plans WIHTOUT sign and sealed is included.
3. No discount given. 4. Total discount, included in the computation, is Php 1,850,000.
Remarks
a.)The only difference thay have is, in Sewerage Treatment Plant, Ardhee Builders will use an additional mateirals such as 30 CMD MBR System with chemical treatment
process, a Hollow fiber MBR module, Permeate Pumps, Roots Blower and Chemical Dosing Pump.