METHOD STATEMENT
1. PRELIMINARIES
Site logistic Plan for temporary site office, Stores, lab, Shuttering &
Rebar yards be prepared and established in consultation with the
Client.
3 Main Structures i.e. Data Hall, Gantry & FS building works shall be
started in parallel, 2 other structures i.e. Substation & fuel facility shall
be started 3 months later to decongest site from stacking excavated
stuff.
Batching Plant :
1 No 30 cum/hr capacity batching plant shall be sourced in nearby
area/ optional at site.
Concrete pump:
2 Nos concrete pump-35 cum/hr. capacity shall be placed at the site
Tower crane:
The initial location of the Tower crane is as shown in the logistic
plan.1 No 60 Mtr Jib length 1.5Mt tip load external type shall be
used for handing Rebar’s & Shuttering materials:
5 FORMWORK SYTEM
Columns: RMD Panels