VERSION NO 05
APPROVED BY
1.0 PURPOSE
To establish a system of equipment mobilization to sites and ensure that all the Plants &
equipment are duly checked, repaired and reconditioned before they are dispatched as
planned/required by the sites.
2.0 SCOPE
The scope of this procedure is limited to provide plants and equipment at project sites &
coordination for fitness compliance of plant & equipment, deployed by back to back contractors
will be covered. This covers those equipment, which are in usable condition at the time of
dispatch. All Plant & Machinery & Equipment, vehicles used in the site which are owned, hired
and brought by our subcontractors.
3.0 RESPONSIBILITY
3.1 Direct responsibility of this procedure shall be with Corporate Plant Head.
Responsibility of providing plants to project sites shall be with Divisional Plant Coordinator.
Responsibility of repair /maintenance of Plants at Depots shall lie with Depot Head/ Depot
Plant Head. Responsibility for carrying out necessary repair / maintenance at Project Site shall
be with Site Plant In Charge. Project In-Charge to provide resources for repair and
maintenance as required by Site-Plant- In-Charge and agreed by Divisional Plant Coordinator.
Responsibility of Site Plant In-charge & Site EHS In-charge is to conduct pre & periodical
inspection of all plant, machines, equipment & vehicles. The unfit plant, equipment, machinery,
vehicle will not be used at the site until it is maintained in safe working condition.
4.0 DEFINITION
4.1 Major Plant : Major Plants are as listed in the Data Sheet (DS-1/15) .These are the equipment
whose breakdown maintenance is expensive & time consuming .They are not easily available for
hire at local market.
4.2 CER : Capital Expenditure Report (Requisition)
4.3 HO : Head Office
4.4 FTS : Final Tendering Summary
4.5 DS : Data Sheet
4.6 OEM : Original Equipment Manufacturer
4.7 RTO : Road Transport Officer
4.8 CCO : Chief Commercial Officer
4.9 CTO : Chief Technical Officer
4.10 CPH : Corporate Plant Head
4.11 DPC : Division Plant Coordinator
4.12 SPIC : Site Plant In-Charge
4.13 PIC : Project In –Charge
4.14 DCR : De-commissioning Report
4.15 CR : Commissioning Report
4.16 PC No.: Plant Code Number (CCL No.)
4.17 PLTO : Plant Transfer Order
6.0 PROCEDURE
Tendering/ Estimation department forwards Plant Data Sheet. CPH gives input to
tendering/ estimation in Plant Data Sheets Pre-Tendering DS-2/15 within
prescribed time limit.
After award of the project, the project team prepares a Plant Deployment
Schedule (PDS) DS-4/15 and forwards it to CPH with a copy to DPC.
Based on the PDS received from project site, plant department at HO workouts a
Proposed Plant Allotment (PPA) R-12/15 which has the following provisions:
6.3.1.1 The entire surplus plants across projects/ depot are taken into consideration and
Plant Transfer Order (PTO) R-2/15 are issued by Plant Department HO based on
time schedule of actual requirement. For transfer of plant within division the
decision lies with DPC and for transfer of plant between division & depot, the
decision lies with CPH.
6.3.1.2 The sending Site Plant In-Charge assesses the plant. If the plant is found in
working condition then the plant is handed over to stores for initiating dispatch
procedure with Equipment Commissioning cum Decommissioning Report R-3/15.
6.3.1.3 If after assessment the plant requires repair, then R-11/15 is prepared. If the repair
estimate is below 1 (One) lakh INR then Site Plant In-charge can start repair with
intimation to Project In-charge and DPC. If repair estimate is below 3 (Three) lakh
INR then it is sent to DPC for approval and if the repair estimate exceeds 3
(Three) lakh INR then it is sent to CPH for approval. If the repair estimate is more
than 30 (Thirty) lakh INR then it sent to CTO for approval with justification from
CPH.
6.3.1.4 Once the repair plan in the form of R-11/15 is approved by DPC/ CPH/ CTO, then
spares and services shall be organised through stores/ procurement department -
responsibility of Site Plant In-charge in coordination with DPC and CPH.
6.3.1.5 After receipt of spares/ services, equipment shall be repaired, tested and handed
over to site stores for dispatch. Intimation of equipment repair Completion shall be
sent to Plant dept. HO - Responsibility of Site Plant In charge.
6.3.1.6 Final Commissioning of Equipment shall be done at the receiving site and
Equipment Commissioning cum Decommissioning Report R-3/15 shall be sent to
HO-Responsibility of Site Plant In charge.
6.3.1.7 The Site Plant In charge shall send Monthly Consolidated Plant Statement R-1/15
to the CPH with a copy to the DPC. The statement shall be duly approved by the
Project In-Charge.
6.3.1.8 Based on Monthly Consolidated Plant Statement R-1/15 received from Site Plant
In-charge, Plant accountant prepares Monthly Internal Plant Hire Statement R-
17/15 in consultation with DPC. The statement shall be forwarded to CPH & Site
Plant In-charge.
When plant is not available in house &/ or duration is for longer period &/ or the
equipment is not available generally in rental fleet then go for new plant purchase.
6.3.2.1 In case of any new purchase, CER shall be raised by the Plant Department HO
with proper justification as described above. The plant life cycle and internal plant
hire is ascertained at the time of raising CER. The duly approved CER copy shall
be forwarded to Purchase department for procurement. For procurement of capital
equipment Purchase procedure (P-8) shall be followed.
6.3.2.2 Plant Department at HO shall suggest the model & make based on the study or
performance data & information available with them. The new purchase is based
on two types.
6.3.2.3 The new equipment shall be commissioned at site and R-3/15 shall be prepared
and sent to HO. Equipment log sheet R-8/15 should be maintained at site.
6.3.2.4 After receipt of OEM/ dealer Commissioning Report from Site Plant In-Charge, the
plant department at HO allots every new plant with a unique equipment ID (CCL
number).
6.3.2.5 Internal Plant Hire rate is fixed while raising CER. Typical Internal Plant Hire Detail
– Datasheet DS-5/15 is enclosed as a typical format. Generally it is separately
circulated from time to time.
6.3.2.6 Typical Life Cycle of plant will be ascertained on procurement of new plant and will
be updated in the Typical Plant Life Cycle Datasheet DS-6/15 from time to time.
6.3.3.1 If the plant/ equipment is not available in-house &/or plant/ equipment is generally
for shorter period &/or plant/ equipment is far off from the place of deployment &/or
the new plant/ equipment delivery period is not within the acceptable limit then the
proposal for hiring of the plant & equipment shall be considered.
6.3.3.2 If the cost of plant/ equipment hire is exceeding the budget FTS, final approval
authority shall be Managing Director.
a) The project team to raise SPI to CPH, who in turn shall provide his
concurrence for outside hire.
b) The project team to raise “Justification & Approval of Plant Hire From Outside
– R-14/15” enclosing the SPI, duly commented by CPH for appropriate
approval, based on DS-3/15 and arrange issue of work order.
c) The work order shall follow relevant procedure of other functional department,
following authority level matrix as per DS-3/15.
6.3.3.3 Locating the suitable plant from external sources and Inspection of hiring plant
(major) shall be carried out by plant department representative and Okayed before
deployment to site. Inspection report of hire plant to be maintained at site.
6.3.3.4 Copy of Work Order issued to the party supplying plant/ equipment on hire shall
be sent to the CPH and DPC. OH&S guidelines shall be mentioned on work order
and will be duly signed & accepted by the agency.
6.3.3.5 The Site Plant In-Charge shall send a Hired Equipment Monitoring Summary R-
13/15 for hired plant/ equipment to the CPH with a copy to DPC by 15th of the
following month.
6.4.1.2 DPC will work out in coordination with Site Plant In-charge for plant manpower
requirement of plant staff, operator and maintenance crew.
6.4.1.3 First surplus/ idle manpower within division, DPC will initiate transfer.
6.4.2 Operations
6.4.2.2 OEM service engineer may be summoned for carrying out calibration/
commissioning of Major Stationary Plant (MSP) and Major Crawler Plant (MCP).
6.4.2.3 All transport vehicles, Tyre Mounted Road Plant, Tyre/ Wheel Mounted Plant for
which the registration is required as per the RTO rules, format R-6/15 Vehicle
RTO status should be maintained at project site and this report shall be sent on
monthly basis such that the report reaches HO by the 10th of the subsequent
month – responsibility of Site Plant In-Charge.
Site Plant In-Charge to alert Site Admin In-Charge to update and validate all the
statutory RTO documents.
6.4.2.4 Monthly Consolidated Plant Statement (MCPS) R-1/15, Daily Log Sheet R-8/15
needs to be maintained at site – Responsibility of Site Plant In-charge.
6.4.2.5 Daily Checks including tyre pressure, fan belt, reverse horn, swing horn, oil/
coolant level, over hoist limit switch, safe load indicator, wire rope, brake/ clutch
engagement/ disengagement, emergency stop switch, and all statutory safety
checks, etc. needs to be carried out by Site Plant Engineer before engaging any
plant/ equipment.
6.4.2.7 Site Plant In-Charge shall prepare preventive maintenance requirement for all the
equipment and forward them to stores for procurement in the form of Minimum
Stock Indent as prescribed by OEM. Site Plant In-Charge needs to intimate DPC
and CPH.
6.4.2.8 Plant Health Audit should be conducted as instructed by CPH as and when felt
necessary. Relevant Audit report should be sent to CPH.
6.4.3 Maintenance
For all Major Plant record of operation and periodic/ breakdown will be maintained
at project site - responsibility of Site Plant In-Charge.
6.4.3.1 Periodic maintenance will be ensured as per record R-9/15 – responsibility of Site
Plant In-Charge.
6.4.3.3 Any breakdown more than 3 days will be intimated to CPH and DPC.
6.4.3.4 Any repair though external agency shall be intimated to with written
communication CPH and DPC.
6.4.3.5 Any spares procured/ proposed to be procured from any source other than OEM
needs to be intimated with written communication to DPC & CPH for their consent.
6.4.3.6 If there is substantial delay in delivery of spares/ services (for major hydraulic
machine only) then, pool assembly is referred – responsibility of Site Plant In-
Charge in coordination with DPC and CPH.
6.4.3.7 A pool of all important assemblies like engine, hydraulic pump, hydraulic motor,
gearbox, etc. are maintained at depot which are recycled. Pool assembly
coordinator from HO organises replacement assembly in consultation with CPH to
reduce the downtime substantially.
6.4.3.8 Involve dealer/ OEM to the extent possible for repair of any modern day current
plant.
6.4.4 Demobilisation
6.4.4.1 After the completion of work, the project In-Charge declares the plant as surplus
with written communication to DPC. Expected release date of equipment should
be updated in MCPS. Then site plant In-Charge needs to certify and ensure the
working condition for next deployment.
6.4.4.2 For plant transfer within division, DPC will earmark transfer.
6.4.4.3 For plant transfer outside division &/ or from depot, CPH will identify site/ location.
6.4.4.5 If the plant requires major repair/ overhauling outside the site, same to be planned
and organized by DPC in consultation with CPH based on its next requirement.
6.4.4.6 If the repair estimate is costly &/ or un-economical &/ or plant is old and obsolete
&/ or the plant has completed its full life cycle, CPH will intervene to retire the plant
which is identified at project site for retirement evaluation so that the plant need
not be sent to depot and directly disposed off from site to the extent possible. The
retired plant has to be processed for disposal through GDA and handed over to
Inventory Department.
6.5.1 After the transfer of plant to depot based on the decision of CPH, Workshop In-
Charge will prepare inspection report and forward it to Depot Head for review.
Depot Head will circulate the inspection report to the concerned Site In-Charge,
DPC and CPH for information.
6.5.2 Plants which are lying for more than a year is listed in format - List of Non-Moving
Plant R-15/15, which is prepared on quarterly basis by Depot Head and forwarded
to CPH, who will evaluate the plant and explore its future prospect, alternative
usage and decide whether to retire the plant. The retired plant has to be
processed for disposal through GDA and is handed over to Inventory Department.
6.5.3 If there is foreseen future use, then based on the inspection report, Depot Head
prepares R-11/15 and forwards it to CPH for approval. If the repair estimate is
below 3 (Three) lakh INR then Depot Head can start repair with intimation to CPH.
If repair estimate exceeds 3 (Three) lakh INR then it is sent to CPH for approval. If
the repair estimate exceeds 30 (Thirty) lakh INR then it is sent to CTO with
justification from CPH.
6.5.4 Once the repair plan in the form of R-11/15 is approved by CPH, then spares and
services shall be organised through Depot stores/ procurement department -
responsibility of Depot Head in coordination with CPH.
6.5.5 After receipt of spares/ services, equipment shall be repaired, tested and handed
over to depot stores for dispatch. Intimation of equipment repair completion shall
be sent to Plant dept. HO - Responsibility of Depot Head.
6.5.6 Final Commissioning of Equipment shall be done at the receiving site and the
Equipment Commissioning cum Decommissioning Report R-3/15 shall be sent to
depot with a copy to HO - Responsibility of Site Plant In charge.
6.5.7 Induction training for GTE’s shall be conducted at depot for initial 6 month period.
Crane operator training on need basis shall also be conducted at depot.
8.0 RECORDS
R-14/15: Justification & Approval of Plant Hire from Outside - Site Plant In charge
DAYS
MAINTENANCE HRS
PREV.MTH CLSG. (B)
CURRENT MONTH
SL.NO./ REG. No.
SITE
REMARKS
2ND SHIFT
1ST SHIFT
CLSG. (A)
SL.NO.
NOTE : The report should be prepared from 1st to 31st of that month. This report should reach HO by the 2nd of every month.
Sunday -
Holiday -
*Note Availble Hours per days will be 10 hours for Single Shift and 20 hours for Double Shift
Working Days is Available days excluding Sundays and Holidays
Cumulative Reading is the total running hours from the date of purchase.
Tick the appropriate box Good Bad Needs repair Can be directly use
NOTE : The sending "Site Plant Incharge" shall send Tax Invoice copy to CPH after the dispatch of Plant
Decommissioning cum commissioning report for Major Plant to be sent duly signed
cc:Dispatching site
cc: Receiving site
cc:Plant HO
PROJECT NAME : FOR THE HALF YEAR ENDING :MARCH / SEP YEAR:
PROJECT CODE :
EQUIPMENT DESCRIPTION
SL.NO/CHASSIS NO.
TI NO /IRN NO
TI NO /IRN NO
SITE /DEPOT
SITE /DEPOT
CONDITION
Elec/Diesel
REMARKS
CAPACITY
CAPACITY
REG. NO
MODEL
MODEL
SL.NO
MAKE
MAKE
SL.NO
DATE
DATE
Similar plant on
Sl. Equipment Immediate Surplus
Capacity Releasing Site Condition of Plant Remarks hire at other
No. Description (Yes/No)
sites
Quantity: Date:
Remarks:
Managing Director :
This form should be used for all items of Capital Expenditure including Furniture,Household,Eequipment Temporary Building,Site
Installation etc., Separate forms should be used for each type of equipment
WRKD HRS IDLE HRS MAINT HRS B/D HRS FUEL ENGINE OIL HYD OIL TRANSMISSION OIL
REMARKS:
PLANT INCHARGE
NAME:
SIGNATURE:
NOTE : THIS FORMAT TO BE MAINTAINED WITH EACH EQUIPMENT IN THE FORM OF BOOK (DUPLICATE)
The white copy should be handed over to the plant department by the operator /driver everyday for updation.
1000 -1500 hrs maintenance 250 -300 hrs Maintenance 60 - 50 hrs Maintenance
to be done to be done to be done
Month:
Equipme Previous
SL NO CCL NO
nt Date/ Hrs 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1
EQUIPMENT DESCRIPTION
PLANT CODE (CCL NO)
SL. NO /REG.NO.:
REPAIR/ MAINTENANCE APROVAL REQUEST CUM COMPLETION REPORT RECORD NO.: R-11/15
Approved by CTO
Name :
Signature :
Note :
1. If repair estimate is below 1 lakh INR then Site Plant incharge can start repair with intimation to Project Incharge and DPC. R-11/15 Not reqd.
2. If repair estimate is below 3 lakh INR then take approval from DPC. R-11/15 Not required.
3.If the repair estimate exceeds 3 lakh INR then it is sent to CPH for approval. R-11/15 Required.
4. If the repair estimate is more than 30 lakh INR then it sent to CTO for approval. R-11/15 Required.
Project Name:
Project Code:
REQUIREMENT,
PLANT AS PER MAX. M/C AVAILABILITY, YEAR IMMEDIATE
SL. NO. REMARKS
DESCRIPTION FTS NO. Months AVAILABLE FROM SHORTFALL
Months Months Months Months Months Months Months Months Months Months
PROJECT NAME :
PROJECT CODE :
JUSTIFICATION & APPROVAL OF PLANT HIRE FROM OUTSIDE RECORD NO.: R-14/15
CUMULATIVE QUANTITY TO DATE Quantity Unit DD/MM/YY DD/MM/YY Unit Rate Amount
Total upto this WO No. Dated
Budget / FTS
Variance (+)/(-) for current PO
Justification --> Saving in Avg Unit Rate
5. RECOMMENDATIONS *
Site Plant/ Site Commercial Site Project Project Director Division Head Sign. Corporate Plant
Procurement Incharge Sign. & Incharge/ Manager Sign. & Date & Date Head & Date
Incharge Sign. & Date Date Sign. & Date
6. APPROVAL **
Site Project Project Director Division Head Sign. CTO Sign & CCO Sign & ++Managing Director
Incharge/ Manager Sign. & Date & Date Date Date
Sign. & Date
Note: 1) Enclose the SPI duly concurred by CPH for outside hire.
2) For all recommendation & Approval, follow relevant authority level matrix as per DS 3/15 for External Plant hire approval.
3) ++In the event of cost exceeding the budget, approving authority shall be Managing Director
PROJECT NAME:
PROJECT CODE : FOR THE MONTH : YEAR :
MMM-YY MMM-YY
Sl. Hire Rate Rate per Rate per
Plant Description CCL No. Unit Qty. Remarks
No. for Shift Month Day Days Hire Days Hire
th
Note: The report should be prepared on monthly basis. This report should reach site by 7 of every month
FOR DIV-II:-
FOR DIV-III:-
FOR DIV-IV:-
FOR DIV-V:-
Note: The report should be prepared on monthly basis by 10 th of the following month
Crane Tata 320 Crane ,Tata TFC -280 Crane, Hind 101 – MK, QU-20
16 TIL hydra 825,Escorts Hydra Crane C8000/K10
Kobelco SCX -900-2
17 Tower crane Jianglu JL 5015
18 Electrical hoist / Material winch % ton & above
19 Compressor : 250 cfm and above.
20 Chilling plant :141 TR and above
21 Ice Flake Plant :40 TPD and above
22 Pilling Winch : 71/2 Ton Capacity
23 DP Rig with Winch
24 Rotary Rig Soilmec RT-3 ST /SR 40,HY-40,Cem Drill ,Mait HR 180 / Maicat 180
25 Stone Crusher Jaw crusher ,Cone crusher ,VSI
26 Hot Mix Plant
27 Wet Mix Plant
28 Asphalt Sensor Paver
29 Wet Mix Paver
30 Tandem Roller Walk behind roller ,Baby roller, Tandem roller 8T & above
31 Soil compactor Escorts EC 5250D,Bomag greaves BW 212D 2(2A)
32 Pneumatic Tyre IR RTR 220 / PT 20 R, Hamm GRW 15
Roller
33 Kerb laying machine Apollo KP 40
34 Desander Casagrande BE 50 /SD 1500 /D10 Z
35 Pile Driving Hammer Delmag ,BSP Rig,Walker Rig, ICE,PTC
Balance on hire
Available in
Factor Hr. (Each) on cost cost
month month cost cost
house
Sl. Description of
Total
No. Plant Unit
machine Mode of Amou
Max no (No.) (%) (Each) (Each) (Each) Unit Qty. (MT/M3/H (Each) (Each) (Each) (Each)
months at deployment nt
r.)
site
(1) (2) (3) (3) a (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
Signature: Signature:
DATA SHEET : DS – 3/15 : EXTERNAL PLANT HIRE ORDER APPROVING AUTHORITY MATRIX
Project Name:
1 2 3 4 5 6 7 8 9 10
New / Existing /
Peak No at site
months at site
Total machine
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Plant /
S.N.
Shift/day
Equipment Hire
1
2
3
4
DATA SHEET: DS – 5/15 TYPICAL INTERNAL PLANT HIRE DETAIL – TO BE UPDATED SEPARATELY FROM TIME TO TIME
MONTHLY
PLANT DESCRIPTION INTERNAL HIRE REMARKS
RATE
PILING & DW EQUIPMENTS :
Fixed for
1 Hydraulic Piling Rig16/18 ton.m (SR40, HR180, Maicat180) 750000.00 single/double shift
Fixed for
2 Hydraulic Piling Rig 20 ton.m (BG20H) 1200000.00 single/double shift
Fixed for
3 Hydraulic low height Piling Rig 6 ton.m (CF6- Tescar) 700000.00 single/double shift
Fixed for
4 Mechanical Rotary Rig 21 ton.m (Soilmec RT3ST -NEW) 450000.00 single/double shift
Fixed for
5 Mechanical Rotary Rig 20 ton.m (Soilmec RT3ST) 450000.00 single/double shift
Reverse Circulation Drilling (RCD) Rig (R1820 with initial Fixed for
6 1050000.00 single/double shift
43M drill string & Hammer Grab H1425A).
Fixed for
7 Lo drill + Excavator Ex 350 - Low height Piling Rig 700000.00 single/double shift
Fixed for
8 Desander 50m³/hr. Soilmec BE-50, 75000.00 single/double shift
Fixed for
9 Desander 100m³/hr. Soilmec SD 100, Casagrande D10Z 75000.00 single/double shift
Fixed for
10 BP Winch 7.5 ton. 20000.00 single/double shift
Fixed for
11 BP Winch 5 ton. 15000.00 single/double shift
Fixed for
12 DP Winch 7.5 ton. 20000.00 single/double shift
Fixed for
13 BSP Pneumatic Hammer 5 to 6.5 ton. 130000.00 single/double shift
14 Vibro Hammer 30 kg.m PTC 30H2L 325000.00 Single shift
15 Vibro Hammer 46 kg.m ICE 815C 425000.00 Single shift
16 Vibro Hammer 50 kg.m PTC 50HD2 425000.00 Single shift
17 Hydraulic Impact Hammer 106KJ (BSP CX110) 250000.00 Single shift
18 Diesel Impact Hammer 360KJ (Delmag D100-13) 750000.00 Single shift
CRANES :
1 Hydraulic Crawler Crane 90 MT.(Hitachi Sumitomo SCX 900) 700000.00 Single shift
HOISTS :
Fixed for
1 Elec. Hoist 70T 35000.00 single/double shift
Fixed for
2 Elec. Hoist 50T 25000.00 single/double shift
Fixed for
3 Elec. Hoist 40/45T 25000.00 single/double shift
Fixed for
4 Elec. Hoist 20/25T/30t 20000.00 single/double shift
Fixed for
5 Elec. Hoist 7.5/10/15T 15000.00 single/double shift
EXCAVATOR /LOADER /DOZER :
1 Excavator 7 ton class EX70 75000.00 Single shift
2 Excavator 10/13 ton class EX100/110, PC 130 100000.00 Single shift
3 Excavator 20 ton class EX200, Zaxis 200, SK210 LC 140000.00 Single shift
4 Backhoe Loader. JCB3D, CAT 424B, 55000.00 Single shift
5 Front End Wheel Loader 3m³/5 ton. CLG 856, L90, Liebherr 120000.00 Single shift
6 Dozer CAT D6G-160hp, BEML BD65 160000.00 Single shift
CONCRETING EQUIPMENTS :
1 Concrete Pump 30 m³/hr. BP 350D 75000.00 Single shift
2 Concrete Pump 60 m³/hr. BP 1500/1800; BSA 1407D 85000.00 Single shift
3 Concrete Pump 100 m³/hr. BP 2800 150000.00 Single shift
4 Concrete Pump 90 m³/hr.(long distance) BSA 2109D, 80C 190000.00 Single shift
5 Transit mixer 6 m³ with Chassis 70000.00 Single shift
6 Transit mixer 10 m³ with Chassis 110000.00 Single shift
7 Transit mixer 10 m³ without Chassis 32000.00 Single shift
8 Mobile Mixer (Ajax Fiori) 60000.00 Single shift
9 Truck mounted placer boom pump- 32 m 240000.00 Single shift
10 Trailer mounted Mobile Batching Plant 18m³/hr 115000.00 Single shift
11 Batching Plant 25 m³/hr. MA25 / Maxomix 110000.00 Single shift
12 Batching Plant Millar 30m³/hr. 50000.00 Single shift
13 Batching Plant 30 m³/hr. CP30, Allen Builder 140000.00 Single shift
14 Batching Plant 30 m³/hr. CP30 + Compartment Batcher 160000.00 Single shift
15 Batching Plant 60 m³/hr. M1, Maxmech 265000.00 Single shift
16 Batching Plant 120 m³/hr. Stetter H3N 350000.00 Single shift
17 Circular Distributor. Stetter RVM-14 25000.00 Single shift
Fixed for
18 Silo Loading System 15000.00 single/double shift
Fixed for
19 Cement silo 200/300T 25000.00 single/double shift
Fixed for
20 Cement Silo 80m³ 15000.00 single/double shift
Fixed for
21 Flyash Silo 80m³ 15000.00 single/double shift
DEMOLITION EQUIPMENTS :
1 Rock Splitter 100000.00 Single shift
2 Hyd. Rock Breaker GH6 50000.00 Single shift
3 Hyd. Rock Breaker GH10 80000.00 Single shift
4 Terminator TX200 40000.00 Single shift
VEHICLE PLANT :
1 Dumper 25 ton 60000.00 Single shift
2 Tipper 16 ton 25000.00 Single shift
3 Water Tanker 27500.00 Single shift
4 Diesel Bowser 55000.00 Single shift
5 Tractor Trailer 9500.00 Single shift
6 Tractor Dozer 70000.00 Single shift
7 Utility Vehicle 15000.00 Single shift
8 Bolero/ Tata Sumo- 7 Seater 18000.00 Single shift
9 Tata Mobile 12000.00 Single shift
ROAD EQUIPMENTS :
1 Motor Grader.200 hp - Sany PQ190C 105100.00 Single shift
2 Motor Grader.180 hp - Volvo G710B 160000.00 Single shift
3 Motor Grader.140 hp - CAT 120H 140000.00 Single shift
4 Motor Grader.136 hp - Komatsu GD 511A-1 140000.00 Single shift
5 Soil Compactor 10T. BW 212D-2A, EC5250D, CA 212D 76000.00 Single shift
6 Tandem Roller 8T. BW151 ADH2, HAMM HD85 68000.00 Single shift
7 Electronic Sensor Paver. 10mtr. Vogle S1800-2, BB68C 145600.00 Single shift
8 PTR- 15T. RTR220, HAMM GRW15. 97500.00 Single shift
9 Hot Mix Plant 120-125 TPH. Speco. 247000.00 Single shift
10 Hot Mix Plant 160 TPH 280000.00 Single shift
11 Hot Mix Plant 200 TPH 460000.00 Single shift
12 Bitumen Bowser 55000.00 Single shift
13 WMM Plant 100 TPH. Apollo PUGMIL 43000.00 Single shift
GENERATORS :
1 Lighting Mast 15 kVA 21000.00 Single shift
2 Generator 20 KVA 5000.00 Single shift
3 Welding cum lighting Generator 15000.00 Single shift
4 Generator 40 KVA Minor plant 7500.00 Single shift
5 Generator 50 KVA 10000.00 Single shift
6 Generator 62.5 KVA 13000.00 Single shift
7 Generator 82.5 /100 KVA 20000.00 Single shift
8 Generator 125 KVA 25000.00 Single shift
9 Generator 160/180 KVA 30000.00 Single shift
10 Generator 250/320 KVA 45000.00 Single shift
11 Generator 500/600 KVA 55000.00 Single shift
12 Generator 725/750 KVA 60000.00 Single shift
COMPRESSORS :
1 335 cfm Air Compressor 15000.00 Single shift
2 365 cfm Air Compressor 15000.00 Single shift
3 400/450 cfm Air Compressor 17500.00 Single shift
4 600 cfm Air Compressor 20000.00 Single shift
5 580 cfm Air Compressor (new) 20000.00 Single shift
6 Electric Air Compressor 500 cfm 6500.00 Single shift
7 Electric Air Compressor 335 cfm 5000.00 Single shift
MISCELLANEOUS EQUIPMENTS :
Survey Equipment
1 Theodolite 6750.00 Fixed
2 Leveling Instruments 2650.00 Fixed
3 Total station 26650.00 Fixed
Dewatering & Submersible Pumps:
1 Pump upto 5hp 1125.00 Fixed
2 Pump 6hp to 15hp 2250.00 Fixed
3 Pump 20hp to 30hp 3000.00 Fixed
4 Vacseal pump 4'' (40hp) 3750.00 Fixed
5 Vacseal pump 6'' (60hp) 4500.00 Fixed
High Head Pumps:
1 Triplex Pump, GOMA 40hp; WASP 30hp. 4500.00 Fixed
2 DSM-3/4 Pump 4500.00 Fixed
Grout Pumps & Allied:
1 Colcrete Mixer 3000.00 Fixed
2 Guniting Machine (Cement Gun) 2250.00 Fixed
3 Cementation Pump 3000.00 Fixed
4 Colomono Pump 3000.00 Fixed
5 Hand Injection Pump 750.00 Fixed
6 Helical Pump/ Roto Pump 7500.00 Fixed
7 MI Pump, Atlas Copco grout pump 22500.00 Fixed
Light Concreting & Reinforcement Equipment
1 Concrete Mixer 10/7 2250.00 Fixed
2 Concrete Mixer 14/10 5250.00 Fixed
3 Concrete Mixer with batcher 5250.00 Fixed
4 Concrete Placer - Pneumatic 3900.00 Fixed
5 Builder Hoist 1/1.5 ton. 8250.00 Fixed
6 Bar Bending m/c 13125.00 Fixed
7 Bar Cutting m/c 13125.00 Fixed
8 Bar Cogging m/c 33000.00 Fixed
Finishing & Compaction Equipment
1 Concrete Vibrators 3hp 1500.00 Fixed
2 High frequency Converter 6000.00 Fixed
3 Shutter Vibrator : Transformer (4:1) 5250.00 Fixed
4 Screed Vibrator 2025.00 Fixed
5 Power Trowel 2025.00 Fixed
6 Plate / Earth Compactor 1500.00 Fixed
7 Walk behind Vibro roller. 9750.00 Fixed
Welding & Lighting Equipments:
1 Welding Transformer 1800.00 Fixed
2 Welding Rectifier 400 Amps 3750.00 Fixed
3 Welding Inverter 400i 3900.00 Fixed
4 Welding Inverter 600i 4500.00 Fixed
Special Note :
a) "Wear Parts Cost" of all plants (Crusher, Paver, Hotmix, Batching Plant, DP & BP Winch i.e Liners and all other Plants) will be charged to Project/Contract.
b) "Spares Parts Cost" will be charged to Plant Dept..
c) Operator cost, Fuel & Lub. Cost, Tyre, Batteries, Vibrating Needles and Misc. consumables cost will be charged to Project/Contract
d) Dismantling & Erection Cost by the Project.
e) Transportation, unloading, etc. to be borne by the receiving project.
f) Transportation of any such Plant which is to be transferred to any of our depot, due to no taker within the division Or company to be borne by sending Project.
g) All RTO, entry tax, exit tax, toll tax & service tax related to plant for projects will be charged to project/Contract.
h) Any Project specific Plant Insurance will be charged to Project/Contract.
i) SEPARATE PLANT RENTAL AGREEMENT OR PO TO BE FINALISED FOR RENTAL TO JV PROJECTS.
j) Monthly Hire Charges is considering 26 days in a month.
k) For PLANTS under "Miscellaneous Equipment" monthly rental 'Fixed' will be charged from the day plant reaches site upto the day of release.
l) For plant levy where "Single" is mentioned, additional levy of 50% to be charged for double shift usage.
m) If any plant remains under breakdown for more than 3 days continuously, hire charges may be reduced accordingly.
DATA SHEET : DS – 6/15 : TYPICAL PLANT LIFE CYCLE - TO BE UPDATED SEPARATELY FROM TIME TO TIME
2 CRANES
5 CONCRETING EQUIPMENTS
7 DEMOLITION EQUIPMENTS
1 Rock Splitter 10
2 Terminator TX200 10
1 Dumper 25 ton 10
2 Tipper 16 ton 10
3 Water Tanker 10
4 Diesel Bowser 10
5 Tractor Trailer 10
6 Tractor Dozer 10
7 Utility Vehicle 10
8 Bolero/ Tata Sumo- 7 Seater 10
9 Tata Mobile 10
15 MISCELLANEOUS EQUIPMENTS
1 Theodolite 5
2 Leveling Instruments 5
3 Total station 5
4 Auto Level Digital Sokkia SDL-1X 5
1 PUMP - UPTO 5 HP 5
1 Colcrete Mixer 15
2 Guniting Machine (Cement Gun) 15
3 Cementation Pump 15
4 Colomono Pump 15
5 Hand Injection Pump 15
6 Helical Pump/ Roto Pump 15
7 MAI Pump, Alas Copco grout pump 15
LIGHT CONCRETING & REINFORCEMENT EQUIPMENTS (USEFUL LIFE 10
(E)
YEARS)
1 Concrete Mixer 10/7 10
2 Concrete Mixer 14/10 10
3 Concrete Mixer with batcher 10
4 Concrete Placer - Pneumatic 10
5 Builder Hoist 1/1.5 ton. 10
6 Bar Bending m/c 10
7 Bar Cutting m/c 10
8 Bar Cogging m/c 10
9 Bar Straightening Machine 10
1 Welding Transformer 12
2 Welding Rectifier 400 Amps 12
3 Welding Inverter 400i 12
4 Welding Inverter 600i 12
5 Welding Generator 12
6 Generator up to 6 KVA 12
7 Generator 15 Kva 12
8 Transformer 500 kva 12
9 Transformer 300Kva 12
1 Lathe machine 15
2 Vertical Drilling m/c 15
3 Pedestral Drilling m/c 15
4 Shaper 15
5 Plate Bending m/c 15
(J) JACKS & POWER PACKS (USEFUL LIFE 12 YEARS)
(L) OTHER SMALL TOOLS & MISC EQUIPMENTS (USEFUL LIFE 5 YEARS) 5
NOTE:- THE USEFUL LIFE IS IN THE LIFE FROM THE 1st TIME COMMISIONING OF NEW PLANT
AT SITE / DEPOT ETC.
1.0 PURPOSE
To establish a system of preventive maintenance for all major & critical minor
equipment so as to ensure minimal breakdowns and increase the plant up keep time
which shall result in high productivity and also enhance the plant life.
2.0 SCOPE
The scope of this procedure is limited to all major & critical minor equipment working
at project sites & All Plant & Machinery & Equipment, vehicles used in the site which
are owned, hired and brought by our subcontractors
3.0 RESPONSIBILITY
3.1 Direct responsibility of maintaining this procedure shall be at Project Site with Site
Plant In charge & the Project In charge .This shall be monitored by the Division Plant
Coordinator periodically.
4.0 DEFINITION
4.1 Major Plant : Major Plants are as listed in the Data Sheet (DS-1/15) .These are the
equipment whose breakdown maintenance is expensive & time consuming .They
are not easily available for hire at local market.
4.2 MCPS : Monthly Consolidated Plant Statement
START
PM
Prepare & Maintain PM Schedule (Formats) for major &
minor equipments as indicated by OEM
schedule
End
6.0 PROCEDURE
All the major and minor equipment which are bearing the Plant code shall be
commissioned at site. The decommissioning cum commissioning report should be
prepared for the major & few critical minor equipment so as to ensure that the
equipment is commissioned to the full satisfaction with regards to capacity and
safety. Responsibility of Site Plant In charge
6.1 The site shall maintain Preventive maintenance Schedule (PM Formats) for all such
equipment deployed at site and bearing Plant Code from the date of commissioning
at site .The PM schedule shall be sent along with the equipment when it moves from
one site to another – Responsibility of Site Plant In Charge
6.2 The Site Plant In-charge shall identify preventive maintenance spares requirement as
per manufacturers recommendations specified in the O & M manual based on the
last preventive maintenance carried out at the previous site - Responsibility of Site
Plant In charge
6.3 The Site Plant In-charge shall ensure that the data are updated in the equipment
Daily Log sheet from the data of commissioning of equipment at site - Responsibility
of Site Plant In charge.
6.4 The Plant Engineer shall carry out the preventive maintenance checks of the
equipment as per the schedule OEM and record 50-60 hours, 250-300 hours & 1000-
1500 hours completion to Format R-9/15 .The site Plant In charge shall record the
data in the equipment daily log sheet.
a. After 10 hours or Daily whichever is earlier.
b. After 50 hours or Weekly whichever is earlier.
c. After 250 hours or Monthly whichever is earlier.
d. After 1000 hours or Quarterly whichever is earlier.
6.5 The site shall forward the preventive maintenance spares requirement for all the
equipment to stores in the form of Minimum Stock indent - Responsibility of Site Plant
In Charge
6.6 The Site Plant In Charge shall plan the preventive maintenance of equipment
deployed at site in consultation with the Project In Charge and shall indicate man
power requirement to do the same. The activities are scheduled in such a way that
the site production is not hampered - Responsibility of Site Plant In Charge.
6.7 Once the preventive maintenance is scheduled, the Site Plant In-charge shall
carryout the anticipated repairs/checks with the help of the crew members and after
repairs / checks shall release the equipment to site for production – Responsibility of
Site plant In charge.
6.8 The preventive maintenance carried out at site shall be recorded in the Preventive
Maintenance Chart R-9/15 and sent to DPC if asked - Responsibility of Site Plant In
charge.
6.9 Spares indented during the preventive maintenance should be arranged on priority,
so that the spares are available to replace during the next Preventive Maintenance
schedule.
6.11 The Site Plant In Charge shall plan for the next preventive maintenance date & other
related activities in-line with the site requirements- Responsibility of Site Plant In
charge
6.12 To facilitate the purpose of getting the feedback on the monitoring of the preventive
maintenance of all the major & minor equipment, certain formats have been
introduced. A brief note on formats and their schedule is given below. Also to
facilitate preventive maintenance of equipment at site, certain other formats have
also been introduced and maintained as per departmental control document
reference no., DCD/P/001/2012
1.0 Purpose
To establish a system to analyse & review break-down of all equipment bearing plant code so as
to ensure that the equipment are repaired and brought to functional status in least possible time
which shall increase the equipment availability for production.
2.0 SCOPE
The scope of this procedure is limited to All Plant & Machinery & Equipment, vehicles used in the
site which are owned, hired and brought by our subcontractors
3.0 RESPONSIBILITY
3.1 Direct responsibility of maintaining this procedure shall be at Project Site with Site Plant In
charge & the Project In charge .This shall be monitored by the DPC periodically.
4.0 DEFINITION
START
Observe performance
(Site Plant In charge)
End
6.0 PROCEDURE
6.1 After any breakdown has occurred at site, the site Plant in Charge shall analyse the
reasons or the breakdown in consultation with the crew members, if required and
shall prepare a detailed repair plan. Responsibility of Site Plant In charge
Note: If after assessment the plant requires repair, then R-11/15 is prepared. If the
repair estimate is below 1 lakh INR then Site Plant In-charge can start repair with
intimation to Project In-charge and DPC. If repair estimate is below 3 lakh INR then it
is sent to DPC for approval and if the repair estimate exceeds 3 lakh INR then it is
sent to CPH for approval. If the repair estimate is more than 30 lakh INR then it sent
to CTO for approval.
6.2 R-11/15 duly filled in all respect shall be sent to Corporate Plant Head for any repair.
Sites under following circumstances will raise the R-11/15 for all repairs.
i) Preventive Maintenance of Plant & Equipment at site.
ii) Major Repair and Overhauling of Plant & Equipment at site.
iii) Repair of planned plant & equipment before mobilization.
R-11/15 will be prepared by Site Plant Department and sent to Corporate Plant Head
for approval attached with the spares list details along with recommendation of DPC,
Plant shall check the sparebility of materials from other sites & depots and dispatch
the same to needy sites. Otherwise approval is given for Local purchase /HO
purchase. Approved Copy will be sent to respective sites for their information & follow
up. The repair plan shall specify the spares/services required to attend the
breakdown. It shall also specify the manpower requirement along with the time
required to complete the repairs for releasing the equipment for production. –
Responsibility of Site Plant In Charge
6.3 The repair budget shall be prepared based on materials available at site and balance
material requirement by the way of R-11/15. The breakdown repair estimated cost
shall be recorded in the daily breakdown report and shall be sent to Corporate Plant
Head. Responsibility of Site Plant In charge
6.4 If the repair activity is time consuming ,a stand-by unit may be arranged in case the
production is hampered .The same shall be recommended to DPC in consultation
with the Project In charge. -Responsibility of Site Plant In charge
6.5 The site Plant In charge shall send the repair budget (R-11/15) to Corporate Plant
Head for approval before starting the repairs.-Responsibility of site Plant In-Charge
6.6 After obtaining approval, the local purchase of material and services shall be
arranged by the site. - Responsibility of Site Plant In-Charge
6.7 The equipment shall be repaired, tested and released for production .The nature of
breakdown & hours shall be logged in the equipment daily log sheet and the same
shall be updated in the MCPS.- Responsibility of Site Plant In Charge.
6.8 The performance of repaired equipment shall be observed to ascertain the quality of
repairs being carried out. – Responsibility of Site plant In charge.
6.9 Corporate Plant Head shall be informed about repair completion - Responsibility of
Site Plant In charge.
6.10 To facilitate the purpose of getting the feedback on repair of major & critical minor
equipment certain formats have been introduced and maintained as per departmental
control document reference no., DCD/P/001/2012