3/23/2020

KOLFE KERANYO SUB-CITY |Sichale O. & Tibebu T. [Supervisors]

SICHALE
BRUK &
FRIENDS WEREDA 01 MANUFACTURING SHADE
CONSULTIN WORK MONTHLY PROJECT STATUS
G REPORT
PARTNERSHI
P

1
TABLE OF CONTENTS

BACKGROUND 3

WORK PROGRESS4

Introduction 4

PHYSICAL PROGRESS 5

PHOTOGRAPHS ON PROGRESS RECORDS 10

Payments to the Contractor and Material Supply 11

Quality [Material, Workmanship, Work, Tests] 11

Claims and variations 11

Works Claim 11

Time Claim 11

Variations 11

Health, Safety and Security 11

Appendices 11

2
1. BACKGROUND

The contract agreement for Wereda 01 Manufacturing Shade Work was signed between Kolfe
Keranyo Sub-City Construction Office and Klinton Yheyis and Their Friends Construction,
Minale Tewodros and Their Friends Construction, Hanan Olyad and Their Friends Construction
on 21/10/2011. The site handover (Which is considered the start date of works) was conducted
on 29/10/2012. The advance payment is prepared and certified by client team [Kolfe Keranyo
Sub-city construction office]. Accordingly the contractor has executed some parts of the work
especially substructure part the project as presented on appendices part later on. The consultant
hired Sichale Bruk and their friends construction consulting partnership have started consultancy
service and supervision after agreement is made on 02/04/2012. Hereunder summary of the work
to be executed is presented.

The contract agreement includes;

SUB STRUCTURE WORK

 EXCAVATION AND EARTH WORK, CONCRETE WORK, MASONRY WORK

SUPER STRUCTURE WORK

 CONCRETE WORK, STEEL STRUCTURE WORK, FINISHING WORK, ROOFING, AND


ELECTRICAL INSTALLATION

The summary of project information is presented in the following table.

Consultant SICHALE BRUK &THEIR FRIENDS P/S


Project: WEREDA 01 MANUFACTURING Contract Period 75days
SHADE LOT-1
Employer: KOLFE KERANYO SUB-CITY Planned Start: 07/06/2012
CONSTRUCTION
Contractor: KLINTON YHEYIS AND THEIR Planned End: 29/08/2012
FRIENDS CONSTRUCTION
Location: WEREDA 01 CHINA CAMP Contract Amount: 1,669,969.86
Contract Signing Date June 29, 2011 Site Handover Date July 17, 2011

Consultant SICHALE BRUK &THEIR FRIENDS P/S


Project: WEREDA 01 MANUFACTURING Contract Period 75days
SHADE LOT-2
Employer: KOLFE KERANYO SUB-CITY Planned Start: 07/06/2012
CONSTRUCTION
Contractor: HANAN OLYAD AND THEIR Planned End: 29/08/2012
FRIENDS CONSTRUCTION
Location: WEREDA 01 CHINA CAMP Contract Amount: 1,669,969.86

3
Contract Signing Date June 29, 2011 Site Handover Date July 17, 2011

Consultant SICHALE BRUK &THEIR FRIENDS P/S


Project: WEREDA 01 MANUFACTURING Contract Period 75days
SHADE LOT-3
Employer: KOLFE KERANYO SUB-CITY Planned Start: 07/06/2012
CONSTRUCTION
Contractor: MINALE TEWODROS AND THEIR Planned End: 29/08/2012
FRIENDS CONSTRUCTION
Location: WEREDA 01 CHINA CAMP Contract Amount: 1,669,969.86
Contract Signing June 29, 2011 Site Handover Date July 17, 2011
Date

2. WORK PROGRESS

2.1 Introduction

This document covers the progress report of Wereda 01 Manufacturing Shade of the project in
terms of time, and quality of works. Challenges, modifications, variations etc. are also included in the
report. Daily record and monthly report are prepared and this report summarizes and presents the status of
individual project and overall project within month of report.

The report is composed in to Eight sections. Section 1 provides brief background, Section 2
describe the physical status of individual projects and the site, Section 3 discuss payments made to the
contractor within month of report and related issues, Section 4 is about quality of materials, workmanship
and works on site, Section 5 states claims (time, financial and variation), Section 6 is about health, safety
and security of the site.

Project Physical
Progress

SUB-STRUCTURE WORK (50%)


100.00%

SUPER-STRUCTURE WORK (25%)


100.00%
Total 100.00%

4
2.1 PHYSICAL PROGRESS

 SUB-STRUCTURE WORK (100.00%)

Works Completed until this report

WORK PROGRESS FOR WEREDA 01 MANUFACTURING SHADE


A. WORK ITEM WEIGHT PROGRESS PROGRESS INDEX
A.SUB STRUCTURE
1 Excavation & Earthwork 30.00 100.00% 30.00%
2 MASONRY WORK 35.00 100.00% 35.00%
3 CONCRETE WORK 35.00 100.00% 35.00%
Total Progress 100.00 100.00%

 SUPER-STRUCTURE WORK (100.00%)

WORK PROGRESS FOR WEREDA 01 MANUFACTURING SHADE


A. . WEIGHT PROGRESS PROGRESS INDEX
1 CONCRETE WORK 15.00 100.00% 15.00%
2 STEEL STRUCTURE WORK 35.00 100.00% 35.00%
3 ROOF WORK 25.00 100.00% 25.00%
4 METAL WORK 10.00 100.00% 10.00%
5 FINISHING WORK 5.00 100.00% 5.00%
6 ELECTRICAL 10.00 100.00% 10.00%
Total Progress 100.00 100.00% 100.00%

5
3.PHOTOGRAPHS ON PROGRESS RECORDS

[THIS PAGE INTENTIONALLY LEFT BLANK]

6
7
8
4. PAYMENTS TO THE CONTRACTOR

 Payment Related
 Contractor's 1st advance payment requested and paid on 25/05/2012 E.C.
 Contractor’s remaining advance payment released on 06/06/2012 E.C.

5. QUALITY [MATERIAL, WORKMANSHIP, WORK, TESTS]

The quality of material, works and workmanship comply with the requirements. Different test
conducted for insuring quality of used materials.

6. CLAIMS AND VARIATIONS

6.1 Works Claim

No works claim is submitted in the reporting month.

6.2 Time Claim

 No separate time claim is submitted in the reporting month.

Valid Delay

No valid delay is recorded in the reporting month

7. Variations

No variation of works was approved in the month of report.

8. Health, Safety And Security

Health

No health problems were reported.

Safety

No health problems were reported. No personal injury or death is reported in both any
events around the site.

Security

There was no security problems reported. The site security is assured with the help of guards.