FRIENDS WEREDA 01 MANUFACTURING SHADE
CONSULTIN WORK MONTHLY PROJECT STATUS
G REPORT
PARTNERSHI
P
1
TABLE OF CONTENTS
BACKGROUND 3
WORK PROGRESS4
Introduction 4
PHYSICAL PROGRESS 5
Works Claim 11
Time Claim 11
Variations 11
Appendices 11
2
1. BACKGROUND
The contract agreement for Wereda 01 Manufacturing Shade Work was signed between Kolfe
Keranyo Sub-City Construction Office and Klinton Yheyis and Their Friends Construction,
Minale Tewodros and Their Friends Construction, Hanan Olyad and Their Friends Construction
on 21/10/2011. The site handover (Which is considered the start date of works) was conducted
on 29/10/2012. The advance payment is prepared and certified by client team [Kolfe Keranyo
Sub-city construction office]. Accordingly the contractor has executed some parts of the work
especially substructure part the project as presented on appendices part later on. The consultant
hired Sichale Bruk and their friends construction consulting partnership have started consultancy
service and supervision after agreement is made on 02/04/2012. Hereunder summary of the work
to be executed is presented.
3
Contract Signing Date June 29, 2011 Site Handover Date July 17, 2011
2. WORK PROGRESS
2.1 Introduction
This document covers the progress report of Wereda 01 Manufacturing Shade of the project in
terms of time, and quality of works. Challenges, modifications, variations etc. are also included in the
report. Daily record and monthly report are prepared and this report summarizes and presents the status of
individual project and overall project within month of report.
The report is composed in to Eight sections. Section 1 provides brief background, Section 2
describe the physical status of individual projects and the site, Section 3 discuss payments made to the
contractor within month of report and related issues, Section 4 is about quality of materials, workmanship
and works on site, Section 5 states claims (time, financial and variation), Section 6 is about health, safety
and security of the site.
Project Physical
Progress
4
2.1 PHYSICAL PROGRESS
5
3.PHOTOGRAPHS ON PROGRESS RECORDS
6
7
8
4. PAYMENTS TO THE CONTRACTOR
Payment Related
Contractor's 1st advance payment requested and paid on 25/05/2012 E.C.
Contractor’s remaining advance payment released on 06/06/2012 E.C.
The quality of material, works and workmanship comply with the requirements. Different test
conducted for insuring quality of used materials.
Valid Delay
7. Variations
Health
Safety
No health problems were reported. No personal injury or death is reported in both any
events around the site.
Security
There was no security problems reported. The site security is assured with the help of guards.
9
APPENDICES
10