This Manual discribes how to drain the Cooling Agent Tyfoxit F from a single VFD
without switching off the whole Chiller Unit. This Manual describes the major points,
because not all VFD´s are identical.
All local Regulations and Safety Precautions have to be followed by example
Working on Life Systems and the general handling of Tyfoxit F.
Returnvalve
Supplyvalve
The VFD has always a Flowline ( cold fluid )and a Return Line ( warm fluid ). Don’t be
confused by the colours of the Valves, the red one is for the Flowline the blue for the
Return Line. The adjustment of the Flow is realized with the blue Valve. The red
Valve is only for a complete isolation.
1
How to drain cooling fluid from a powerstack and
keep all other VFD’s in operation
- Manual -
4. Close the Red Valve and count the Rotation to the Close Position and write it
down.
5. Now close the Blue Valve and count the Rotation until the close Position has
been reached.
Notes:
2
How to drain cooling fluid from a powerstack and
keep all other VFD’s in operation
- Manual -
Make sure that the adapter is in the close position. This is indicated if you can see
the Hexhead and that there is a gap between the Hose adapter and the little
Handwheel. The adapter has to be tightened but don´t bring in to much force.
3
How to drain cooling fluid from a powerstack and
keep all other VFD’s in operation
- Manual -
Attention: At the new Drain hoses there is a high flexible ½“ Water hose .There is no
Elbow Adapter necessary
Check that the Hoses are fully tight and that the GEKA Adapter has good seals.
4
How to drain cooling fluid from a powerstack and
keep all other VFD’s in operation
- Manual -
Now where both Valves are fully in Close Position the Pressure is trapped and
hydraulically isolated.
At the Hose ends a Canister or other adequate Item has to be attached to take the
approx. 5L of Cooling Fluid.
Now the Adapter on the Red Valve has to be opened (Hand wheel) to release the
pressure. After no more Fluid is coming out of the Hose open the Adapter on the Blue
Valve to allow the Drainage of the full Stack by gravity. After this is done it is possible
to use an Airgun to “ help” with a Little Air pressure on the Blue Valve Hose.
It is handy to have always enough oil racks to remove spills. Wiping is not enough,
use some Water to thin the salt based fluid.
Filling and Bleeding Off the Power stack
After Change of the Power stack and re-connection of the Hoses it is necessary
to bleed of the Air from the new Stack.
Now open slowly the Red Supply valve and check all Connections on spills.
Now there is a Air/Fluid Mixture within the Power stack and this has to be
drained on the Blue Draining Valve Hose.
Open slowly the Adapter on the Blue Valve and drain the Mixture in the
Canister. Be aware not to drain all the System pressure , this will cause in
a shut down off of all VFD´s. If System pressure is low , fill up the Chiller
Unit until pressure Level is reached. System pressure is engraved at the
Chiller unit. Flush out the Power stack until clear fluid is flowing out. After
this remove the Draining Adapter and close the Cover on the Valve head.
Now the Return Valve can be opened.