Well drilling operation
5

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


6

DRILLING
PERSONALS

Owner

Contractor

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


7

Contractor company
Drilling contractor Service comp Owner

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


01 Hoisting System
Introduction

Main Rig 02 Rotating System

Systems
03 Drill string handling equipment

04 Mud Circulating System

05 Power Generation System

06 Blowout Prevention System

Eng. Elsayed Amer Eng. El Sayed Amer


9

01

Hoisting System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


10

Hoisting System

Used for raising and lowering the drilling assembly, running drill pipes,
casing, completion equipment and other tools in and out of the hole.

Hoisting System Components

Substructure
Derrick
Crown block
Travelling assembly
Draw works
Drilling line

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


11

Hoisting System
Main Components

Derrick

Substructure

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


12

Hoisting System
1. Substructure

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


13

Hoisting System
1. Substructure

The substructure is the supporting


base for:
Derrick or mast,
draw work
rotary table,
Rig floor,

Consist of steel beams, that can easily


be dismantled, and rests on concrete
foundations around the cellar.
Its height varies from a few meters up
to 10 m in the largest rigs.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


14

Hoisting System
1. Substructure

API name plate contains:


01 Name of the builder

02 Address

03 API standard (ie API 4f)

04 Maximum static load of rotary table

05 Serial number

06 Height (ft)

07 Maximum setback static load

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


15

Hoisting System
1. Substructure

Substructure specification example of 2000 hp rig:

▪ Substructure Height: 35 ft.


▪ Casing capacity: 1,000,000 lbs.
▪ Setback capacity: 800,000 lbs.
▪ Combined Capacity: 1,800,000 lbs.
▪ Clearance from bottom of rotary beam: 30 ft.
▪ BOP handling system capacity: up to 150 T.
▪ Large drill floor: Approx. 39 x 46 ft.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


16

Hoisting System
1. Substructure
Depth reference

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


17

Hoisting System
1. Substructure

1.1 Cat walk


Rig floor

Catwalk Is an elongated platform about


1 m high,
Cable tray
Located near the rig floor where pipe is
laid in and lifted into the rig floor by
Product Name
special lifting equipment Cat Walk
The catwalk is connected to the rig floor Pipe rack
by a pipe ramp.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


18

Hoisting System
1. Substructure
1.1 Cat walk

• Hydraulic Catwalk System • Mechanized Catwalk System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


19

Hoisting System
1. Substructure
1.2 vee door

▪ A vee-door is the opening shaped like


an upside down V in one side of a
derrick, which allows long pipes and vee-door
tools to be lifted onto the rig floor.
▪ Also called pipe ramp

Cat Walk

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


20

Hoisting System
1. Substructure
1.3 Cable Tray Cable tray

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


21

Hoisting System
1. Substructure
1.4 Stairs

Mud system
stair

Main stair

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


22

Hoisting System
1. Substructure Mast supports
1.5 Rig Floor

Rig tongue
Dog house

Rotary table
Driller console

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


23

Hoisting System
1. Substructure
1.6 BOP Crane

BOP cranes

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


24

Hoisting System
2. Derrick

✓ The derrick is an open-framework structure of steel


beams,
✓ Provide a vertical height to permit the vertical
movement of the travelling block for a distance
greater than the equivalent of one stand.
✓ The derrick is designed to resist the loads tripped in
and out of the well in the operating phases, which
induce both static and dynamic stresses.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


25

Hoisting System
2. Derrick

Dual derrick Mast

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


26

Hoisting System
2. Derrick

The range of Derricks & Masts designs:

✓ Static Derricks (Jack Ups & Platforms)


✓ Dynamic Derricks
✓ Dual Derricks
✓ Offset Derricks
✓ Cantilever
✓ Folding Masts
✓ Telescoping Masts
✓ Bootstrap Masts

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


27

Hoisting System
2. Derrick

Drilling rig derrick capacity


✓ Every derrick has a rated load capacity,
Max. Derrick Load 450,000 lbs
defined by API (American Petroleum
Institute) standards, which establish the Static Hook Load 333,000 lbs ( 8 lines )

maximum hook load Static Hook Load 357,000 lbs ( 10 lines )

Setback Capacity 225,000 lbs

Max. Derrick Load 450,000 lbs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


28

Hoisting System
2. Derrick

Derrick are normally used on Offshore rigs and can


be divided into categories:

• Stationary Derrick :
Derrick used on offshore fixed structures
• Dynamic Derrick:
Heavyweight derrick used on floating rigs
subjected to marine stress.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


29

Hoisting System
2. Derrick

Nameplate Information

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


30

Hoisting System
2. Derrick
Crown block

Mast frame Monkey board

Drilling line
Travelling block
Traveling block

A - Frame Top drive

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


31

Hoisting System
Monkey board

The small platform that the derrickman stands


on when tripping pipe.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


32

Hoisting System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


33

Hoisting System
Draw Work

A drawworks is the primary hoisting machinery


component of a rotary drilling rig.

Its function is to provide a means of raising and


lowering the traveling block.

The capacity of the drawworks that


characterizes a rig and indicates the depth
rating for the boreholes that can be drilled.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


34

Hoisting System
Draw Work

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


35

Hoisting System
Draw Work

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


36

Hoisting System
Draw Work

Depending on the engines on the rig, the drawworks


can be either:

MECHANICAL

✓ Diesel engines are directly connected


(compounded) to the draw work by chain.
✓ This system is still in use for small Drilling Rigs
(under 1500 HP), but is no longer used on
medium-Hi powered rigs( 1500 & 3000 HP).

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


37

Hoisting System
Draw Work

Depending on the engines on the rig, the drawworks


can be either:

Electrical

✓ Electrical system are normally used today on land


rigs and is the only system in use on offshore rigs.
✓ The drawworks are generally connected to 1000
HP D.C. engines, although A.C. engines are now
being used as well.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


38

Hoisting System Auxiliary Brake


Main Brake
Draw Work
Main Drum

A modern drawworks consists of five main parts:


Main Drum
Catheads
Main Brake
Auxiliary brake

The apparatus can be powered by AC or DC

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


39

Hoisting System
Draw Work

a. Main Brake

The main brake, usually operated


manually by a long handle, may be a
friction band brake,

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


40

Hoisting System
Draw Work

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


41

Hoisting System
Draw Work

b. Catheads & Breakout


Cathead

Catheads are winches with pneumatic


clutch and are mounted on the
extremity of the secondary drum of the
drawworks.
The make up cathead is located
beside the driller's console and the
break-out cathead is located on the
opposite side of the driller's console.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


42

Hoisting System
Draw Work

b. Auxiliary brake
• The auxiliary brakes are used only when going in the hole on a trip. These are used to prevent
burning the band-type brakes.
• The auxiliary brakes are of two types:
A. The hydro-dynamic type braking is provided by water being impelled in a
direction opposite to the rotation of the drum.

B. The electromagnetic type braking is provided by two opposing magnetic fields.


The magnitude of the magnetic fields is dependent on the speed of rotation and the
amount of external excitation current supplied.

• In both types of auxiliary braking systems, the heat development must be dissipated using a
liquid cooling system.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


43

Hoisting System
Drilling Line

❖ The drilling line contained in the hoist drums consists of


helically-wound steel-wire strands around a plastic,
vegetable fiber or steel core.
❖ The first end of the drilling line (fast line) is wound around
the hoist drum,
❖ The factors to consider in the drilling line choice are:
❖ Diameter Breaking strength
❖ Flexibility Elasticity
❖ Corrosion strength Abrasion resistance
❖ Distortion strength

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


44

Hoisting System
Drilling Line

❖ Wire Rope is composed three parts:


- the core,
- the strand and
- the wire.
❖ slipping and cutoff, is performed when
a given value of the work carried out by
the line has been reached.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


45

Hoisting System
Drilling Line
Types of Wire Rope Lay

Right Lang Lay

Left Lang Lay

Right Regular Lay

Left Regular Lay

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


46

Hoisting System
Drilling Line

Type of Wire Rope Construction

Shallow: 1” to 1-1/8” diameter

Deep: 1-1/4” to 2” diameter

Contruction: 6 x 19 S or 6 x 21 S or 6 x 25 FW, RRL, IPS or EIP, IWRC

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


47

Hoisting System
Drilling Line

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


48

Hoisting System
Drilling Line

6 X 7 with 6 X 19W with 6 X 19S with 6 X 19 with


fiber core fiber core fiber core IWR core

6 X 21 6 X 25 6 X 25 6 X 25 Seal
Filler Wire Filler Wire Filler Wire with IWR
with fiber with fiber with IWR core
core core core

6 X 27 Seal 6 X 31 Seal
IWR = Independent Wire with IWR with IWR
Rope core core

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


49

Hoisting System
Crown Block

The crown block is a fixed set of pulleys


(called sheaves) located at the top of the
derrick or mast, over which the drilling line
is threaded.
❖ consists of a set of sheaves (usually
from 3 to 7) supported by a framework
of steel beams.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


50

Hoisting System
Crown Block
Sheaves

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


51

Hoisting System
Traveling Block

❖ The Travelling Block is a set of


sheaves (pulleys) that move up and
down in the derrick. (one fewer
than for the crown block),
❖ The number of sheaves in the
crown and travelling block is
chosen on the basis of the rated
capacity of the tower
The number of the pulleys used on the two
Blocks can vary from 5 to 8, providing a variable
capacity to the Hoisting system.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


52

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


53

Hoisting System
Traveling Block

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


54

Hoisting System
Hook

o high-capacity J-shaped equipment


used to:
▪ hang various equipment,
particularly the swivel and
Kelly, the elevator bails or top
drive units.
▪ The hook is attached to the
bottom of the traveling block
and provides a way to pick up
heavy loads.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


55

Hoisting System
Drilling Line spool

o The drilling line is stored on a spool


Periodically, some of the drilling line is
cut off at the draw works and
additional line is pulled off the spool to
replace the cut line

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


56

Hoisting System
Deadline anchor

❖ deadline anchor is used to tie down the drill


line and measure the load suspended from
the top drive, i.e. hook load. The wire drum
attached to the anchor is designed to rotate
during a slip-and-cut procedure

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


57

Hoisting System
Deadline anchor

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


58

Hoisting System
Driller panel

❖ The control panel, located


on rig floor, where the
driller controls drilling
operations.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


59

Hoisting System
Driller panel

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


60

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


61

Hoisting System
Air hoist

❖ An air hoist or horse , man


ride is a safer way to lift
heavy objects to rig floor.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


62

Hoisting System
Dog house

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


63

02

Rotating System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
64

Function Swivel
Kelly

The system of rotation is intended to cause Kelly Bushing


the drill string to rotate. K.B. Elevation
Rotary Table

Rotating System Components

Rotary table
Kelly or Top Drive
Drill Pipe
Kelly Bushing
Master Bushing
Top drive System Drill Collars

Bit

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
65

Top Drive

o The top drive is a relatively recent piece of equipment,


introduced towards the mid-1980s, grouping together
in a single unit
o The equipment for connecting the drill pipes, rotation
of the drill string and circulation of the fluid
o The top drive unit is suspended from the hook and is
guided by two vertical rails fixed to the derrick, which
provide the reactive torque necessary to prevent the
rotation of the whole complex and to allow free
vertical movement.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
66

Top Drive
Top
drive

‘A’ frame

Guide
rails

Rig floor Drill pipe


Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses
Rotating System
67

Top Drive

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
68

Top Drive

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
69

Top Drive

the use of the top drive instead of the rotary table offers numerous advantages, including:

1 Allow fewer connections where it connect stand by stand (30 m) in


one connection

2 Contain its own swivel assembly

3 Performing trip-out operation while circulating mud and rotating the string
(back reaming),

4 Allow rotation while lifting ( back reaming )

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
70

Swivel

o The rotary tool that is hung from the hook


of the traveling block to suspend the
drillstring and permit it to rotate freely.
o It also provide connection for the rotary
hose and provide passageway for the flow
of drilling fluid into the drill stem.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
71

Kelly

o Old fashion
o It transmits the power from the
rotary table to the drill string.
o At the same time it serves as a
conduit for the drilling fluid,
o It absorbs torque from the drill string
and carries the entire axial load.
o It is the most heavily loaded
component of the drill string.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
72

Kelly

o Due to Kelly length (12 m) only one


joint could be added
o The Kelly is a square or hexagonally
shaped pipe

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
73

Kelly

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
74

Kelly

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
75

Kelly Bushing

o used to transmit torque from the rotary


table to the Kelly. The Kelly bushing is
designed to be the connection between
the rotary table and the Kelly.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
76

Master Bushing

o A device that fits into the rotary table to


accommodate the slips and drive the Kelly
bushing so that the rotating motion of the
rotary table can be transmitted to the Kelly.
Also called rotary bushing.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
77

Master Bushing

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
78

Rotary table

o A rotary table is a mechanical device on a


drilling rig that provides clockwise
rotational force to the drill string to
facilitate the process of drilling a
borehole.
o Most rotary tables are chain driven

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
79

Rotary table

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Rotating System
80

Rotary table

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


81

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


82

03

Tubular Handling Equipment

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
83

Drill string

o Is an assemblage of hollow pipes of circular section,


extending from the surface to the bottom of the hole.
o It has three functions:
✓ it takes the drilling bit to the bottom of the
hole, while transmitting its rotation and its
vertical load to it.
✓ It permits the circulation of the drilling fluid to
the bottom of the hole.
✓ it guides and controls the trajectory of the hole.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
84

Drill string

o Drilling String Components:


The Drill String includes all tubular equipment
between the Kelly Swivel and the bit
✓Kelly
✓Surface Safety Valves
✓Drill Pipe
✓Heavy Weight Drill Pipe
✓Drill Collar
✓Jars - Shock Subs - Bumper Subs - Junk
Baskets - Accelerators etc...

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
85

Drill Pipe

o The drill pipes are hollow steel pipes


of various types, with two tool joints
welded at their ends.
o They are standardized according to
API standards and classified on the
basis of their length (usually about 9
m), their outside diameter, their
linear weight and their steel grade.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
86

Drill Pipe

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
87

Drill Pipe

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
88

Drill Pipe

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
89

Drill Pipe

No Grooves = Grade E-75


1 Groove = Grade X-95
2 Grooves = Grade G-105
3 Grooves = Grade S-135

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


90

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
91

Stab in Guides

o Prevent damage to threads or seals


while joints are being added to or
removed from the string.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
92

Heavy Weight Drill pipe

o Hevi-Wate drill pipe is an intermediate


weight drill stem member. It consists of
heavy-wall tubes attached to special extra-
length tool joints. It has drill pipe dimensions
for ease of handling. Because of its weight
and construction, Hevi-Wate drill pipe can
be run in compression the same as drill
collars in small diameter holes and in highly
deviated and horizontal wells.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
93

Heavy Weight Drill pipe

o Similar in appearance to a drill pipe, HWDP has


the following different dimensional
characteristics; the tube wall is heavier about
1”thick in most sizes, the tool joints are longer,
and the tube section has a larger diameter at
mid length to protect the pipe from wear.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
94

Heavy Weight Drill pipe

Heavy Weight Drill Pipes Function


HWDP is used to absorb the stresses being
transferred from the Drill Collars to the Drill Pipe.
The major HWDP benefits are:
o Increased wall thickness
o Longer tool joints
o Uses more hard facing
o May have a long central upset section

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
95

Drill Collar

An 8” OD drill collar weighs 150 lbs/ft or 4500


lbs each
o Drill collars have larger outer diameter
and smaller inner diameter than drill
pipe. The functions of drill collars are:
▪ Provide the required weight on bit Drillpipe
while drilling Drill collar
▪ Maintain drill string in tension which
reduces bending and fatigue failures.
▪ Provide stiffness for directional
control

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
96

Drill Collar

Types
o Comes in many OD and ID sizes
o Typically 3 1/8" to 11" OD, Most commonly in
lengths of 30 - 31 ft
o Both slick and spiral drill collars are used.
o Spiral collars where there is chance of getting stuck
o where differential sticking is a possibility spiral drill
collars and spiral HWDP should be used in order
to minimize contact area with the formation.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
97

Drill Collar

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
98

Subs

o A short, threaded piece of pipe used to adapt parts of the drilling string
that cannot otherwise be screwed together because of difference in
thread size or design.
o These consist of:

Bit Sub
Crossover Sub
Kelly Saver Sub
Lifting Sub
Bent Sub

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
99

Subs

o Subs are classified into four main categories:

Bit Sub or crossover subs are used to connect the drill bit to the first piece of BHA equipment or to
crossover connections in the drill string. Drill bits are manufactured with a pin, making make-up
impossible without a bit sub.

Lifting Sub or handling subs are used to lift BHA components from the catwalk to the rig floor.

Top drive subs or saver subs serve as the sacrificial element between the drill string and the top drive,
reducing repair and maintenance costs.

Workover subs or circulating subs are used to limit the allowable fluid-circulation rates.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
100

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
101

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
102

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
103

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
104

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
105

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
106

Subs

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
107

Handling Equipment

o Equipment used to move, make and break connection, suspend tubular on the
rig. These include the following:

Top drive Links Pipe Spinner


Elevator Bit Breaker
Lifting Subs Safety Clamp
Lifting Sub Tongs
Slips Thread Protectors
Safety Clamps

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
108

Handling Equipment

Top drive Links

o Equipment attached onto the top drive in order to suspend


the Elevators.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
109

Handling Equipment

Pipe Elevator

o Clamps that grip a stand of casing, tubing, drill


pipe or drill collars so that the stand or joint can
be raised from or lowered into the hole opening
of the rotary table.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
110

Handling Equipment

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
111

Handling Equipment

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
112

Handling Equipment

Slips
o Slips is a device used to grip and hold the upper part of a drill string to the drill
floor on an oil rig.
o hanging the string on rotary table

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
113

Handling Equipment

Slips

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
114

Handling Equipment

Slips

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
115

Handling Equipment

Slips

Drill collar Slips Drill Pipe Slips Casing slips

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
116

Handling Equipment

Safety clamp

o used on tubular above the slips to


prevent dropping the string should the
slips fail to hold.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


117

Safety clamp

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
118

Handling Equipment

Single Joint Elevators

o designed to replace unsafe rope slings for hoisting


collar- type pipe into position.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
119

Handling Equipment

Rig tong
o Used to make up and brake down drill string.

Make up Tong Breakout Tong


Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses
120

Rig tong

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


121

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
122

Rig tong
Handling Equipment

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
123

Handling Equipment

pipe Spinner

o A pneumatically operated device


usually suspended on the rig floor
used to make fast connections
and spin off of drill pipes.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


124
pipe Spinner 5.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
125

Handling Equipment

Bit breaker

o A device that is placed on top of


the rotary table to enable the bit
to be made up to drill string.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Tubular Handling
126

Handling Equipment

Drifts

o Sometimes referred to
as rabbits Normally the
drift is used to establish
that the tubular has a
predetermined inside
diameter.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


127

04

Mud Circulation System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
128

System

Function

o A major function of the fluid circulating system is to remove the rock cuttings
from the hole as the drilling progresses
Principal Components:

Mud Pump Shale Shaker


Standpipe Desander
Swivel De-silter
Drillstring Degasser
Return Line Mud Pit

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


129

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
130

System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
131

Mud pumps

o A large, high-pressure reciprocating


pump used to circulated the mud
on a drilling rig.
o The mud pumps take the fluid from
the pit and pump it into the well
• Triplex pumps
• Duplex pumps
o Receive their power from an
electric motor independent from
other uses.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
132

Mud pumps

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
133

Mud pumps

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
134

MUD PUMP ACCESSORIES


A) Pulsation Dampeners.
o to absorb the mud pump's
pressure surges (changes in
flow velocity), creating a
steady-state (non-surging)
flow of mud under more-or-
less constant pressure, which
lessens wear on the hose
(and other mud system
components).

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
135

MUD PUMP ACCESSORIES


A) Pulsation Dampeners.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
136

Stand pipe manifold

o its purpose is to divert the


flow of mud in desired path.
towards the drill line or
toward the drill string
o it also has the connection
ports where pressure the
temperature sensor are
connected.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
137

Stand Pipe

o The fluid is pumped up the standpipe and


through the rotary hose into the swivel

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
138

Rotary hose

o large-diameter (3- to 5-in.inside


diameter),
o high-pressure flexible line used to
connect the standpipe to the swivel.
o This flexible piping arrangement
permits the kelly (and, in turn, the
drillstring and bit) to be raised or
lowered while drilling fluid is pumped
through the drillstring.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
139

Rotary hose

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
140

Mud return

o The passageway of the drilling fluid as it comes out of the well.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
141

Shale Shaker From mud


return line

o An equipment the uses a


POSSUM
vibrating screen to remove BELLY
cuttings from the
circulating fluid in rotary
drilling operations.
Vibrator motor Shale shaker

Screens

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


142

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
143

Desander

o A centrifugal device for


removing sand from the
drilling fluid to prevent
abrasion of the pumps.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
144

Desander

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
145

Desilter

o Also a centrifugal device for


removing free particles of
silt from the drilling fluid to
keep the amount of solids
in the fluid at the lowest
possible point.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
146

Degasser

o A device that removes air or gases (methane, H2S, CO2 and others) from drilling
liquids.
o There are two generic :
I. by pulling a vacuum on the mud
II. by increasing the surface area available to the mud so that bubbles
escape
o If the gas content in the mud is high, a mud gas separator or "poor boy
degasser" is used, because it has a higher capacity than standard degassers and
routes the evolved gases away from the rig to a flaring area complete with an
ignition source.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
147

Degasser

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
148

Mud tanks

o Used to store drilling


fluid on a drilling rig.
They are also
called mud pits.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
149

Mud tanks

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
150

Reserve Pit

o The reserve pit may be used


to store spare or waste mud,
base oil or brine. In
operations on land, the
reserve pit is usually a
plastic-lined, earthen pit, in
which waste mud is stored
until final disposal.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
151

Reserve Pit

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


152

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Mud Circulation
153

Mixing hopper

o The reserve pit may be used to store


spare or waste mud, base oil or brine.
In operations on land, the reserve pit is
usually a plastic-lined, earthen pit, in
which waste mud is stored until final
disposal.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


154

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


155

05

Power system

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
156

Power Generation system

o The power system of a rotary drilling rig has to supply


power to all the other systems.
o the system must provide power for:
I. pumps in general,
II. rig light,
III. air compressors, etc.
o Since the largest power consumers on a rotary
drilling rig are:
I. the hoisting,
II. the circulation system, and the rotary system,

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
157

Power Generation system

o the sources of energy are diesel fueled


engines.
o Most rigs use 1 to 5 engines to power
the drawworks and rotary table.
o The engines are usually rated between
400 and 800 hp.
o As guideline, power requirements for
most onshore rigs are between 1,000 to
3,000 hp.
o Offshore rigs in general use much more
power.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
158

Power Generation system

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


159

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
160

SCR

o The power on modern rigs is most commonly generated by diesel-


electric power units.
o The power produced is AC current which is then converted to DC
current by the use of SCR (Silicon Controlled Rectifier).
o The current is delivered by cables to electric motors attached
directly to the equipment involved such as:
I. mud pumps,
II. rotary table,
III. Drawworks etc

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
161

SCR

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Power system
162

Diesel Tank

o Fuel tank for generator

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


163

05

Well control System

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
164

Function
o BOP system is designed and used to prevent uncontrolled release of fluids and
liquids by sealing, controlling, and monitoring oil and gas wells.
A

Principal Components:

Annular Blowout Preventer P

Ram Blowout Preventer


B
Diverter
Manifold, Valves and Sensors
Accumulator
S
Inside BOP
P

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
165

BOP stack

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


166

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
167

Diverter BOP
is an annular preventer with a large piping system
underneath. It is utilized to divert the kick from the rig
and it can be used when the conductor pipe is set. Mud return line

Flare Line

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
168

BOP stack

o large valves located on the wellhead during


drilling operations ,able to fully shut-in the
well in just a few tens of seconds, whatever the
working conditions.
o Consists of:
i. Annular BOP
ii. Ram BOP

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
169

BOP stack
i. Annular BOP
Annular blowout preventer (Annular BOP)
is a special mechanical device used to seal,
control, and monitor oil & gas well.
Annular BOP is placed on the top of ram
preventers. It is called annular due to its
structure; it surrounds top of the wellbore
in a shape of a ring or an annulus.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
170

Annular BOP

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
171

BOP stack
ii. Ram BOP
a special assembly used during drilling
as part of blowout prevention system.
The shut-off valves in ram preventers
close by forcing or ramming themselves
together. Ram BOPs close the well by
rams which operate in unison and
actuated by hydraulic cylinders. Ram
BOP has several types of rams, such as
pipe ram, blind ram, shear ram and
blind shear ram.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


172

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
173

BOP Ram

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
174

BOP stack

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
175

BOP stack

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
176

Subsea BOP

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
177

BOP control Panel

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
178

Choke manifold
o The arrangement of piping and
special valves, called chokes,
through which drilling mud is
circulated when the blowout
preventers are closed to control
the pressures encountered
during a kick.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
179

DRILLING CHOKE
CONTROL PANEL

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Well control system
180

accumulator
o The storage device for
nitrogen pressurized
hydraulic fluid, which is used
in operating the blowout
preventers.

Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses


Sino Tharwa Drilling Company 181

ST 4 Rated Drilling Depth Mud Tanks


2000 hp drilling rig
20,000 ft. with 5” drill pipe. Total number 6 tanks
Total capacity 2250 bbl

Derrick Power Supply


Static load capacity 1,000,000 lb
Height 149 ft 3 ea. Engine Cat 3512 B

Draw Works Well Control Equipment

2000 hp • 21 ¼” x 2000 psi diverter system


drilling line 1 1/2”
• 13 5/8” annular preventer 5000 psi.
• 13 5/8” double ram preventer 10000 psi.
Hook load
• 13 5/8” single ram preventer 10000 psi
Rated capacity 1,000,000 lb • Accumulator unit 3000 psi working
pressure with 210 gallon capacity & 20
bottle installed
Rotary Table
Max. Opening 37-1/2”
Safety Equipment
Height 29.5 ft
As required by regulations

Mud Pumps Camp


Two Triplex To accommodate 80 person
Eng. Elsayed Amer |
1600 hp Rated input power
Email : Eng20072007@gmail.com
5000 psi working pressure | Eng. Elsayed Amer
YouTube : PetroleumandNaturalgasCourses
182

Drilling Time & Cost Impact


Original Design Cost Benefit
Section Time Savings Dayrate Cost
Lengths (Days) ($70k / day) Casing Cost Cement Cost Total Cost
26" Hole 1500 Base Case $ - $ 81,000.00 $ 41,000.00 $ 122,000.00
16" Hole 6445 Base Case $ - $ 278,075.00 $ 118,000.00 $ 396,075.00
14" Hole 4740 Base Case $ - $ 378,000.00 $ 110,000.00 $ 488,000.00
12 1/4" Hole 2315 Base Case $ - $ 465,000.00 $ 106,000.00 $ 571,000.00
8 1/2" Hole 3430 Base Case $ - $ - $ - $ -
Total Depth 18430 Base Case $ - $ 1,202,075.00 $ 375,000.00 $1,577,075.00

Revised Design Cost Benefit


Section Time Savings Dayrate Cost
Lengths (Days) ($70k / day) Casing Cost Cement Cost Total Cost
26" Hole 1500 0.00 $0.00 $ 81,000.00 $ 41,000.00 $ 122,000.00
16" Hole 6855 0.57 $39,861.11 $ 292,425.00 $ 125,506.59 $ 457,792.71
14" Hole 4081 (1.83) ($128,138.89) $ 328,575.00 $ 94,706.75 $ 295,142.86
12 1/4" Hole 2303 (0.03) ($2,333.33) $ 456,909.00 $ 105,450.54 $ 560,026.21
8 1/2" Hole 3393 (0.10) ($7,194.44) $ - $ - $ (7,194.44)
Total Depth 18132 (1.40) ($97,805.56) $ 1,158,909.00 $ 366,663.89 $1,427,767.33

Estimated Total Savings = $149,307.67


Eng. Elsayed Amer | Email : Eng20072007@gmail.com | YouTube : PetroleumandNaturalgasCourses