Professional Documents
Culture Documents
1.0 INTRODUCTION
company had a road and bridge project in Nasarawa so I had privilege of learning
I officially started my Industrial Training on 16th of April 2018 but resumed on first
of May 2018 and worked with the survey section in the earlier part of my training.
I also worked with the concrete section, laboratory and Quantity survey section.
I help to provide the various sections I worked with the functionalities they needed.
Tasks carried out, works observed and experiences gained are fully explained in
The industrial training is a training which forms part of the approved minimum
1
The programme is aimed at bridging the gap between theory and practice in
learning, and helps students to gain practical experience in their different fields of
study.
The training exposes students to work methods, work safety, and equipment in
their different fields. This experience also helps prepare the student for ready
Objectives:
To enable students acquire industrial skills and experience in their course of study
To prepare students for the work situation they will be facing after graduation.
Gives students opportunity to appreciate what they have learnt in class by allowing
Helps students better understand different work methods and get insight about
professional practice.
2
1.2 COMPANY INFORMATION
The Company was founded in 2002 with over 95% owned by the renowned Civil
Engineering Company, Italy that has been in existence since 1957. Within this
short time span, the Gitto Costruzioni Generali Nigeria Ltd has over 26 project
sites with an estimated value of $1billion within Nigeria. The growth of the
enlargement of the fleet of vehicles and equipment and the acquisition of vanguard
technologies. The Company throughout its history has been concerned with the
The Company was founded by Cav. Carmelo Gitto in 1957. Over the years, the
ground consolidation. The growth of the Company through the increased volume
of business, qualified staff, enlargement of the fleet of vehicles and equipment and
the acquisition of vanguard technologies, has been acknowledged both in Italy and
in countries in the Middle East and Africa. The Company throughout its history
has been concerned with the honouring of its commitments and its fulfilment of the
3
engagements accepted, as well as attainment of its professional objectives. Civil
Engineering Company now has projects now spread over three continents.
The company has completed jobs worth over US$ 1 Billion in both infrastructure
Wadi Haddada Tunnel in Amman, built in record time and open to the public by
King Hussain four months before the contractual due date and also the Completion
year to meet with the country’s desire of hosting its Independence Day Service in
October 2005.
In Nigeria, the company currently work for both Federal and State Government.
The company has many fully registered professionals as staff and has six distinct
Land surveying
Civil engineering
Architecture
Quantity surveying
Building
4
Administration
Phone: 00234-(0)95242380
Fax: 00234-(0)95242391
The mission of Gitto Construzni Generali Nig. Ltd. is to carry out construction
works and deliver projects effectively and to give its clients, employees and the
clients’ needs and delivers projects no matter the specification, environment and
time.
5
1.5 COMPANY ORGANOGRAM
COMPANY ORGANOGRAM
Board of Directors
General Manager
Laboratory
Safety and
workshop
6
CHAPTER TWO
During the course if my I.T. I worked with the land survey unit, Concrete Unit,
Laboratory Unit, and Quantity Survey Unit. These units make up the technical
department of the company. This section would highlight operations carried out by
I was introduced to survey unit. Firstly, I was instructed to start with the Land
Survey Department to get the basics of all operations carried out in the field
especially of road construction. Field data generated by the land Survey is required
in the design of road and detailing of the road before any form of work commences
on site. If bridges and culverts are required, surveyors generate the levels. The
levels are necessary so that there is a smooth transition along the entire road; the
levels also ensure that water inlet and outlet are correctly located to ensure smooth
flow. Data generated by land survey helping in design of the road and in
7
Total station:
horizontal angles and vertical angles. This Microprocessor unit enables for
Data collected from total station can be downloaded into computer/laptops for
Land surveyors and civil engineers mainly use total stations, either to record
8
Level (instrument):
It is also known as a Surveyors level, Builders level, Dumpy level or the historic
between two or more points, for which an inbuilt telescope and a highly accurate
9
Measuring tapes: is a flexible ruler use to measure length. It comes in various
Pegs: they are wooden or metal usually with a pointed end used to mark points on
site.
Paint: a coloured liquid that put on a surface usually for beautification. Surveyors
Barricade tape: a brightly colored tape (often two colors say red and white) used
Hammer: tool consisting of a piece of metal with a flat end which is fixed onto the
end of a long thin usually wooden handle, used for hitting things. Its used in survey
Machetes: are made of flat metal or steel, having one sharp edge and a handle used
for cutting. In survey, it is used to clear or remove obstacles along survey path and
10
Permanent markers: a thick pen for writing or drawing. Its used in survey to
Calculators: a small electronic device used for doing calculations. Its used in
Some Hazards of road survey are Sunburn, Poison oak, Snakebite, Danger from
2.3 BENCHMARKS
reference level used as a guide to determine every other level on the road. The
entirely new project and there is no pre-existing benchmark close to the site from
which level can be transferred, the surveyor might contact the ministry of works
in-charge of the area. Levels are commonly transferred from a known benchmark
Benchmarks are usually introduced at every 100m interval, the point of new
benchmark must be clearly visible from the immediate previous one; so if at 100m
11
interval along the road the benchmark cannot be seen, the new benchmark should
be placed at the maximum distance at which it can be seen from the previous one.
benchmarks.
public buildings, at bridges etc. Permanent benchmarks are useful for future
references also.
<<
Temporary benchmarks are created by the surveyors in the field to mark the point
in the field up to which the survey is completed. Then, it is easier to continue the
survey from that point after large gap or on the next day of work.
The temporary benchmark point should be decided in a way that the object or point
3. Locate the total station at the previous and determine the horizontal distance
4. Excavate and cast 10cm2 area ensuring that the peg is in center. Ensure that
5. Guard the new benchmark by surrounding it with about three pegs (wooden)
6. After curing of benchmark, paint it but ensure that the paint doesn’t affect
A route survey supplies the data necessary to determine alignment, grading, and
projects such as roads, railroads, pipelines, and utilities. When accuracy matters,
13
2. Assistant surveyor
3. The chainmen
4. General labour
ii. Clearing and grubbing: this the process of removing all bushes, trees, stumps, etc.
iii. Taking Ordinary Ground Level: after the clearing and top soil removal is
completed for a reasonable distance say one kilometer (1km). the survey section
iv. The top soil is removed from the proposed carriageway. The depth of the removal
of top soil or stripping should not be less than 100mm or above 150mm. this is as
stated in the specification for road and bridges of the Federal Republic of Nigeria
clause 6163.
v. The surveyor returns to take the stripped level, after the removal of topsoil. This is
usually done in conjunction or joint with the engineers' hence it is called the joint
vi. The surveyor section returns to give the level of formation either to cut or fill.
14
vii. Formation level is the next to achieve. From the stripped level, the site operators
fill or cut to attain the formation level. Formation level is the foundation of the
road.
viii. The surveyor returns again to take the level of formation as built or constructed.
ix. The surveyor gives the level of sub-base, and an approved material is used to fill
x. The surveyor returns to take the sub-base level as filled and compacted
xi. The surveyor marks out the level of base-course to be filled to and the level as
xii. The surveyor marks out the level of binder course to reach and after the binder
course is done the surveyor returns to take the binder level as built.
xiii. Surveyor returns to gives level to wearing course and after the wearing course is
a. Setting out clearing limits: these are limits or width at which clearing and top soil
removal should stop. This implies that the machine operators should not exceed
this limit while clearing. Pegs are usually planted at both width end of the
proposed road, including shoulders, drain and an excess of two meters (2m). This
is important because it directs the operators where to and not to clear. It also
indicates areas with curves. It is at this stage the clearing of bushes, trees, stumps,
15
and top soil is done. The top soil usually contains organic, dexterous materials.
This layer is usually fertile hence used for cultivation of crops. It has very poor
bearing capacity; it is usually black in color and about 15cm – 60cm deep. The
width of clearing for this project is twenty meters (20m); this includes the
roadway, shoulders, drainage, pedestrian way, and 1m meter excess to both ends.
i. An assistant surveyor uses the total station to set out the centre lines. The chainman
holding the reflector pole is directed to the center point and marks it with the
pointed end of the pole. An offset it made from the center point already marked; a
chainman hold the zero of the measuring tape at the center point and another drags
the tape to eleven meter (11m), then a labourer plants a peg (wooden bush peg) at
the eleven meter reading of the tape. From the same center point, another eleven
meter is offset to the other side of the road and a peg is planted just as previously
done.
This process is repeated for all required chainages. The bulldozer operators
responsible for the clearing and grubbing limits their clearing operation to about a
16
2.5.1 Original Ground level
The original ground level is the ground level along the path of the road before any
level.
The following are the procedures for taking the Existing Ground Level.
First, the total station is used to set out the centerlines in accordance with
chainages say 25m intervals along the length of the road; the total station is
An assistant surveyor targets the total station to a center point at a chainage and
directs the chainman (person holding the reflector pole) to align to the center point
where the instrument is targeted. He confirms the position using the total station
and signal him to mark the point and proceed to the next chainage.
Another assistant surveyor operates the auto level instrument and a staff man is
attached to him. The assistant surveyor begins by setting up his instrument at any
desired point, and reads from the staff placed on the closest benchmark. He records
this reading as his back sight and proceed to taking other readings; for the next
reading, the staff man places the staff at the already established (marked out)
center point. The assistant surveyor using the level instrument reads and records
17
the staff reading. The staff man offsets three meter (3m) to the left from the center
point, the staff is read from the level. He offsets another three meters (3m) to the
left and the assistant surveyor takes the level of the point from the staff. He returns
to the center mark and offsets three metres to the right, the reading is recorded
from the staff and another offset of three metres is taken to the right, read and
recorded. The readings to the left is labelled is indicated in the field book with a
negative sign, under the remarks column, whereas those to the right positive under
19
Reasons for Taking Original Ground Level (OGL)
1. This level is used as guide for all other levels. In other words, the depth of either
This Refers to the Process of removing the top soil along the proposed roadway.
These materials are usually loamy and good for crop cultivation but possess very
materials are usually very low hence, would lead to failure if used in construction
of the road, hence these materials are cut and cart away. In rare cases, if the
material is suitable for construction they are removed and stored. The reason for
removal in this case is to create room for building the road from below the
formation level. The formation level is the foundation of the road hence materials
used must meet the approved standard for sub-grade materials as stipulated in the
approved standards. The level or limit of cut or removal of top soil typically
ranges from 15cm – 60cm, but there is no standard limit stated in the Nigeria
20
Road Construction specification as its left to the discretion of the Engineer. The
CUT TO SPOIL AT KM 48
materials/soil along the roadway. The removal of these materials not suitable for
subgrade is guide by the design level for that project/road. It is at this stage that
the cut and fill is carried to get to the desired or designed subgrade/formation
level.
i. Materials from areas determined unsuitable by laboratory tests results are removed
this is referred to as cut. In other words, cut is the removal of unsuitable materials
21
from roadway. This (cut) is guide by the surveyors’ peg. At every chainage, pegs
are planted at the edges of the road, on these pegs the reduced level to cut to is
ii. Fill: this might come before or after the cut. It refers to replacement of unsuitable
materials with suitable ones. Just like the cut, the level of fill is also guide by the
surveyors’ level. On pegs planted at the edges of the road the positive numbers are
written on the pegs e.g. +0.91. In either the cut and fill cases the operators’
supervisor or site engineer interprets what is written on the peg and directs the
Formation/subgrade level: this is the foundation level of the road. All loads
coming on the road are transferred to this layer; it is usually high than the natural
ground level. All activities of the strip aims at getting to this level. After the fill
and cut as required to attain this level compaction follow immediately, the
compaction is carried out with machines, such as sheep foot rollers, smooth rollers
etc. the approved soil is hauled from an approved borrow pit, and spread across
the proposed road and an approved volume of water is spread across the soil
(mostly laterite). The approval of both water content and materials (laterite) to
apply is generated from laboratory tests results. The level of subgrade is usually
22
higher than the natural surrounding ground level. The volume of water to apply is
the same as the Optimum water Content derived from laboratory tests.
e. 2.5.5 Sub-base: this layer follow the subgrade. Once the level of subgrade is
satisfactorily attained, the surveyor returns to give the level of sub-base. This layer
bearing capacity. The sub-base bears some of the load imposed on the road and
SUB-BASE AT KM 45
23
Using the total station as a guide, the centerlines are first staked out and marked.
The surveyor using the total station directs his chainman until the reflector pole is
correctly placed at the centerline of the road. The chainman marks the point while
the labourer drives a steel peg into the ground with a hammer. Another chainman
offsets from the center peg to both edges of the road. In the case of the Nasarawa
Loko Road Project ten meters (10m) is offset to both sides from the center peg. To
do this a chainman holds the zero end of the tape against the center peg and
another drag the other end and plants a peg at 10m reading of the tape. Another peg
is planted one meter from the last peg (peg placed at 10m offset from center, i.e. at
9m from center peg). This is to protect the main peg from the operators’ machine
or resulting vibration.
The assistant surveyor reduces the level of sub-base at each chainage in line with
The assistant surveyor mounts the level conveniently while his staff man locates
the center peg and puts the staff beside the peg. The assistant surveyor guided by
the design level directs the staff man on how high or low he take the staff along
peg. When the desired level is reached a laborer marks the level of the base of the
staff against the center peg. That peg is painted red and above it white. The
operator is to fill and compact with approved sub-base material to the red mark.
24
f. 2.5.6 Base-Course: This is the layer directly above the sub-base, it is usually made
of boulders, hence it is also called stone base layer. The survey unit/team
undergoes the same procedure as sub-base level to give or mark out the level of
base-course and other subsequent layers including wearing course, binder course,
etc.
g. 2.5.7 Setting-Out Pile Location: this is another operation carried out by the
survey unit. It is done only if construction of bridges is required along the road.
The main purpose of this operation is to mark the exact point where the pile is
buried. This is to direct the excavator operator where exactly to excavate and not
waste time and resources excavating all environs in search of piles. More detail
about pile and pile foundation is given in the concrete section of this report work.
h. 2.5.8 Setting-Out Blinding Perimeter: the survey team make use of the existing
bridge location data to set out the blinding perimeter for excavation.
i. The engineer:
25
ii. The foremen
iii. Carpenters
iv. Mason
v. Iron benders
The Engineer: he is the head and oversea of the concrete section. He instructs and
directs all other members of the section on what operation to carry out at a time
and the method. He possess the highest educational qualification in the section; a
drawing and decide the safest, most economical approach to implement the
The Foremen: the foremen are the most skilled labour in the midst apart from the
more experienced than other artisans. In the absence of the engineer he directs
other artisans on how to carry out construction activities or operation in their fields
in line with the engineers direction. Many a times the engineer gives direct
instruction to him.
26
Artisans: the artisans include carpenters, masons and iron benders they carry out
obstruction from one side to the other. They are usually made from pipes,
that allows traffic and pedestrians to pass above it and water through it
beneath. They are could be of various shapes but the most common are the
box and ring culverts, if a culvert exceeds 3.7m it is called a bridge. The
Culverts constructed in the course of the project are cast-in place concrete.
a. Load capacities
c. Life span
27
Sudden failures of culverts could be catastrophic as it might lead to
Pipe culverts are widely used culverts and rounded in shape. The culverts may be
of single in number or multiple. If single pipe culvert is used then larger diameter
culvert is installed.
Pipe arch culverts means nothing but they looks like half circle shaped culverts.
Pipe arch culverts are suitable for larger water flows but the flow should be stable.
Because of arch shape fishes or sewage in the drainage easily carried to the outlet
Reinforcement is also provided in the construction of box culvert. These are used
to dispose rain water. So, these are not useful in the dry period.
28
Arch culvert is similar to pipe arch culvert but in this case an artificial floor is
v. Bridge Culvert
Bridge culverts are provided on canals or rivers and also used as road bridges for
vehicles. For this culverts a foundation is laid under the ground surface.
b. Bridge Construction:
A bridge is a structure built to span physical obstacles without closing the way
underneath such a body of water, valley, or road, for purpose of providing passage
over the obstacle, usually something that is detrimental to cross otherwise. There
are many designs of bridges for different purposes. The design of bridge depends
on the function or need of the bridge, fund available and nature of terrain where
the bridge is to be situated. There are many types of bridges, some are:
a. Suspension bridge
b. Truss bridge
c. Beam bridge
d. Arch brigde
e. Cantilever bridge
For the purpose of this report, I shall consider only Beam Bridge and girder as this
29
Beam Bridge: beam bridges are horizontal bridges support at each end by
substructure units and can be either simply supported or continuous. When the
beams connect across connect only across a single span, (usually supported by
only the abutments at both ends) it’s said to be simply supported. When there are
multiple spans, the intermediate supports are known as piers. The vertical forces
on the bridge (shear) and the flexural load on the beam is transferred down
through its length to the substructures on either sides and to the foundation and
soil ultimately. Two common types of beam bridges in modern times are the
Girder Bridge: the box girder bridge was under construction during the period of
my I.T. it is a three hundred and seventy five meter (375m) span bridge, with
twenty meter (20m) from one pier to the other. A box girder bride is a bridge in
which the main beams comprise girders in shape of a hollow box. It could be
The concrete section of Gitto Constructioni Nigeria Limited directly carry out all
relevant day to day operations to bringing paper bridge design to the light of the
30
2.6.1.3 PARTS OF BRIDGE:
31
There are three main pasts of a bridge structure, these are:
a. Foundation: this part of the bridge that is closest to the soil and sends all load it
has received to the soil strata. The piles and pile cap make up the foundation of
i. Pile: these usually provide the major and basic support for the bridge as it
makes up the initial foundation. The reinforced concrete post driven into the
ground to serve as leg or support for the bridge. The piles help the weight and
32
stresses applied by the bridge to be transmitted evenly through the ground
making it strong and stable. The material and design of a pile depend upon soil
type, soil stability, load bearing capacity, proximity of other pile foundations,
and others. They usually consist of a bunch of evenly spaced thick steel bars
driven beyond the soft layers of the soil and into the hard soil strata. Any of the
Sheet piles
33
PILE ON GOING
ii. Pile caps: caps provide additional load transferring capacity to the piles. They are
called pile caps because they are right on top of the pile foundation. Caps are
often made of very heavy concrete to give maximum strength to the upper part of
the bridge.
iii. Bents: this is the combination of pile and cap. Multiple bents forms the
substructure.
b. Substructure:
i. Abutments: this refers to as the vertical supports at the ends of the bridge. They
are sufficiently reinforced to endure intense lateral pressures they also function
34
Section View of Abutments Formwork For Nasarawa Bridge Project
ii. Piers: these are necessary in long span bridges, they are vertical supports in
between the abutments and they are mounted at successive distances they also
35
iii. Pier Caps: pier caps are also known as headstock. This functions as a space for
girders to transfer loads on bearings (they distribute the loads evenly among all
the bridge.
i. Girders/Beams: girders joins all the pile caps together by extending over them.
Girders are also referred to as beams, and give supports to the deck. This can be
a single span, or even multiple spans joining all the bents, dependent on the
length o the bridge. Girders usually have a truss design to improve the stress and
36
load resistibility. Hence, pressure is passed towards the foundation. Girders are
ii. Bearings: bearing are structural members capable of transferring loads from the
decks to the substructure. These displaces stresses and load to the piers through
the girders to allow movement between the parts of the bridge. The movement
parts.
iii. Trusses: trusses are made by joining triangular components to divide loads and
bending moments through the bridge. Some types are simple trusses, suspension,
and cantilever trusses. The truss network provides a surface for transportation,
which can be built as a deck truss, pony truss, or through truss. Each truss differs
37
iv. Decks: decks get the direct traffic load. Some basic decks can be made of concrete
and also from metal. These include travel or pedestrian ways, drainage systems,
v. Barriers: these are mainly safety and protection features, they are put on the sides
of the decks. They come I various designs and forms, for better aesthetics they are
made of concrete.
vi. Arches: the usage of this feature in modern bridges are less common nevertheless,
bridges with arcs possess lots of strength. Arches can help control the safety and
38
load bearing ability of the bridge. The quantity of arches and materials used for
This engineering drawing shows in details all components and their corresponding
arrangements needed for the construction of a bridge. All reinforcements i.e. steel
bars, shapes, sizes, diameter, spacing, concrete cover, and others required are
possible. To produce a correct and constructible bridge drawing all forces and
resist and balance them up put in place. The designer must first envision the total
bridge as though it has been completed in his mind hence he can predict all forces
that should act on the structure. These predicted loads and forces suggest the sizes,
length, spacing, shape, and type of reinforcement to use. Safety and economy are
the two major factors that a bridge designer considers while designing. To be safe
the designer uses the present and future load for designing. Aesthetic is also a key
factor put into consideration in modern day bridge design and construction, to
users and lame men the beauty of the structure is what they see hence it matters.
39
1. The bridge engineer or designer
3. The laborers.
In Gitto Construzioni Company where I did my I.T. all units were involved in the
i. Formworks: this part of the formwork gives details shuttering works of various
This aspect of the bridge drawing shows the finished details of various
components of the bridge; including abutments, piles, piers, pier cap, pile caps,
beams, sidewalks and parapets. It shows the all and encompassing dimension of
ii. Reinforcements: these give details of all reinforcement to be used. Shapes, size,
Setting out of reinforcement: is the process of marking out the various points
40
Installation of reinforcements is the process placing the already bent
by the concrete section. The steel bars are placed on site as detailed in
it and directs all other personnel including the foremen and others in his section on
must to present on site to oversee the operation as this a critical phase of the
lead to loss of lives and properties not just failure of the structure.
Reinforcements used were high yield steel bars of various diameters including
The pile foundation contributes majorly to the strength of the structures because all
loads on the bridge are transmitted through the pile soil. The piles are reinforced
heavily to carry all loads on the bridge, in the case of the bridge construction at
Gada Hudu along Loko road in Nasarawa State, Nigeria by Gitto Construction
Company during my I.T. twenty (20 no.) number of 25mm high yield steel bar at a
1000mm diameter. Each pile perimeter contain six (6) piles of length 3000m.
41
INSTALLATION OF REINFORCEMENT
2.8 Supervision
stages, the representatives for the project underway at the time of this report is the
Engineer from the Federal Ministry of Works Power and Housing and his team of
42
supervises and reports daily activities of the concrete section in the bridge
or drilled deep into the ground on site. There are various methods of piling, the
method used according to Nigeria Specification for roads and bridges construction
is type G-steel sheet pile. Once the engineer and his representative satisfies the
work done is ok, they give a written document of approval, then the prepared piles
ii. Reinforcement installation: once the reinforcements for any given stage (example
pile cap) is completed, the engineer gives an approval and casting can commence.
iii. Casting pile caps: before the casting the engineer and his representatives satisfies
that the grade, aggregate, size used for concrete meets all required standards and
specifications before they are used for casting. He also ensures that the shuttering
is correct. After casting, the engineer ensures there are no honeycombs and the
43
iv. Casting of precast beams: the beams used in the construction of the Gada Hudu
Bridge was precast. The engineers’ representative reports to the engineer the
v. Installation of precast beams: after the casting, the precast beams are installed on
the plinth of the pier cap. I did not witness stage of the bridge construction because
2.9 CASTING
Casting is the process of pouring fresh concrete into the prepared reinforcement. It
is the solidified part that is ejected or broken out of the mold to complete the
process. Casting materials are usually metals or various cold setting materials that
cure after mixing two or more components together. In the case of concrete casting
used on site the combined materials are cement, aggregate and water. These
materials are combined in ratio to achieve required grade of concrete. Casting can
pile caps were done mechanically using a boom concrete pump. The casting was
done in layers and compacted using vibrators. The vibration was carried out to
ensure that there are no voids or honeycomb. Voids and honeycombs in cast
44
Concrete Pump
to place concrete accurately. Boom pumps are used on most of the larger
and because of the labour saving nature of the placing boom. They are a
45
2. Line Concrete Pump or Trailer-Mounted Concrete Pump: This is the
manually attached to the outlet of the machine. Those hoses are linked
together and lead to wherever the concrete needs to be placed. Line pumps
normally pump concrete at lower volumes than boom pumps and are used
sidewalks and single-family home concrete slabs and most ground slabs.
46
2.9.1 BATCHING
cement, sand, coarse aggregate and water) before mixing it. When this
Seasonality affects the volume hence is inaccurate. The volume of soil taken
Because of these limitations, this method is not used on site and in Gitto
concrete batching plant. Concrete batching plant is a device that combines various
47
ingredients to form concrete. Various ingredients include sand, water, aggregate
The weighing method is simpler, more flexible and accurate for batching concrete
1. Electronic weigh batcher: the electronic weigh batchers are more trending
nowadays. They have electronic scale, which are suspended by load cells,
electrical signal. Electronic scales measures accurately and does not need to
repair frequently.
2. Mechanical weigh batcher: they have dial type scales, which use spring to
48
Ready mix plants: A ready mix plant combines all ingredients except for water at
the concrete plant. Then discharge the mixture into a ready mix truck. Then we can
add some water to the mix truck, transport mixed material to the job site.
Central mix plants: A central mix plant combines sand, water, aggregate (rocks,
gravel, etc.), fly ash, potash, and cement at a central location. Then the final
product is transported to the job site. Central mix plants are different from ready
mix plants, it can provide more consistent product for the end user, In addition, it
need the help of computer-aided to complete the work, because all the ingredient
Importance of Batching
49
IMAGE CONCRETE BATCHING PLANT
50
Approved Batching Weight for Gitto Constructioni Nigeria Limited.
Concrete Haulage
51
Concrete Haulage is the movement or transportation of concrete from one place to
place. The concrete was mixed in the concrete batching plant and transferred to in-
transit concrete mixer the later conveys the fresh concrete to site; where it is
needed. On arrival, the fresh concrete is transferred to the boom concrete pump
truck, which eases placement of concrete. Three (3) concrete mixers; two of 8.5m 3
form concrete. A typical concrete mixer uses a revolving drum to mix the
components.
In-transit Mixers: are Special concrete transport trucks (in-transit mixers) are
made to mix concrete and transport it to the construction site. They can be charged
with dry materials and water, with the mixing occurring during transport. They can
also be loaded from a "central mix" plant; with this process, the material has
already been mixed prior to loading. The concrete mixing transport truck maintains
the material's liquid state through agitation, or turning of the drum, until delivery.
52
2.9.3 ADMIXTURES:
during mixing to improve or add specific properties to the concrete. In the case of
the bridge project, the admixture used was a plasticizer; the plasticizer increases
the workability of concrete and enable it to flow easily through any channel
without obstructions.
53
Diagram of Admixture Used In Gitto Bridge Construction Company.
Carpenter Pincer tool: are hand tool that require mechanical advantage to pinch,
tie, cut or pull an object. For the bridge project, iron benders for tying and cutting
54
Binding Wire: the binding wire is a type of tying wire used to bind reinforcement
in construction. It is made from mild steel inker, which takes place in form of
Shovels: A shovel is a tool for digging, lifting, and moving bulk materials, such as
soil, coal, gravel, sand. It is use also to mix concrete, cement or mortar manually
55
for small jobs. It consists of the blade and handle. The blade is commonly made of
Diagram of Shovel.
Safety Boots: are protective feet wears meant to prevent unnecessary injury or
casualty on site.
delivers blow to an object in direction of force input and breaks, drives or beats
objects to shape. Commonly it is made of a steel head and a handle. There are
56
hammer, mallet, masons’ hammer. In the course of the bridge project the
carpenters hammer commonly called claw hammer and the masons hammer was
used, the former for driving while the later for breaking.
Diagram of Hammer.
Trowels
It is a hand tool, which has a handle and a steel plate. It is like a short version of
shovel, it is used in carrying out masonry operations like chalking, minor mixing,
Diagram Trowel
57
2.9.5 Concrete
concrete. It is plastic in fresh state and is capable of flowing but when set and
58
hardened takes the shape of its container or formwork. The nature of the formwork
Nail tool: Nail is a pin like object used in construction. One of its end is pointed
and the other flat the later receives direct impact from hammers whereas the former
constructions are tested and approved in the Lab. before bulk usage on field/site.
Some materials tested by the laboratory are soil, steel reinforcements, aggregate
and cement. Tested materials are approved if they (tested materials) conform to
accepted standards (in Nigeria). All acceptable and abducted standards for roads
and bridge construction are contained in the Government of the Federal Republic
Below are some tests carried out by the laboratory during my I.T. or attachment
<
Atterberg Limits
59
The Atterberg limits are a basic measure of the critical water contents of a fine-
grained soil: its shrinkage limit, plastic limit, and liquid limit.
The liquid limits, plastic limits, and plasticity index of soils aare used to correlate
swell, and shear strength. Atterberg defines four stages of consistency of soil
i. Liquid limits
the liquid limit divides the plastic and liquid state and is defined as the water
content at which soil flows to close a standard size groove when shaken in a
standardized device. At this water, content below the plastic limit the soil has an
approximate shear strength of 2.5kpa. the plastic limit separates the plastic and the
semi-solid state. At water content below the plastic limit state the soil cannot be
molded without cracking. The standard reference for this test is ASTM D4318.
grooving tool
60
200-250g of soil passing sieve no. 40 (425um)
Procedure
Soils should be tested starting from the natural water content to ensure that the
The liquid limit is defined as the water content at which a standard groove cut in
the remolded soil sample by a grooving tool closes over a length of 13mm (0.5in)
at exactly 25blows of the liquid limit cup falling from a height of 10mm on a hard
rubber base.
LL= value of water content where the line crosses the 25 blow mark.
1. Mix the soil thoroughly with enough distilled water to reach a consistency
requiring about 25 to 35 blows of the liquid limit device to close the groove.
2. Using a spatula, place an portion of the prepared soil in the cup of the liquid
limit device at the point where the cup rests on the base, squeeze it down,
61
and spread it into the cup to a depth of about 10mm at its deepest point,
3. Form a groove in the soil by drawing the tool, beveled edge forward through
the soil on a line joining the highest point to the lowest point in the rim of
the cup. When cutting the groove hold the grooving tool against the surface
of the cup draw an arc, maintain the tool perpendicular to the surface of the
4. Verify the no crumbs of soil are present on the base or underside of the cup.
Lift and drop the cup by turning the crank at a rate approximately 2 drops
per second until the two halves of the soil pat come in contact at the bottom
6. Quickly remove a slice of soil approximately the width of the spatula, along
the groove.
7. Return the soil remaining in cup to the mixing cup. Wash and dry the cup an
grooving tool and reattach the cup to the carriage in preparation for the next
trial.
8. Remix the entire soil specimen in the dish adding distilled water to increase
the water content of the soil and decrease the no. of blows required to close
the groove.
62
9. Repeat the steps 1-8 for at least two additional trials producing successively
lower no of blows to close the groove. One of the trials shall be for a closure
requiring 25 to 35 blows, one for closure between 20 and 30 blows, and one
Calculation
Plot the relationship between the water content, and the corresponding
number of drops (blows) on the graph provided. Draw the best straight line
Take the water content corresponding to the intersection of the line with the
25-drop abscissa as the required liquid limit of the soil and round to the
Balance
Procedure
63
1. Select about 20g of the material prepared for the liquid limit test.
3. From this plastic limit specimen, select a 1.5 to 2.0g portion. Form the
4. Roll the mass between the palm or fingers and the glass plate to form a
thread of uniform diameter throughout its length. Keeping rolling until the
thread reaches 3.2mm (1/8in) diameter. Compare with 3.2mm metal rod.
5. When the thread has reached a 3.2mm diameter break it into piece and knead
together in a ball. Repeat the rolling and kneading until thread crumbles and
6. Collect the broken pieces in a water content cup and cover to percent further
7. Elect another 20g portion of soil from the plastic limit specimen and repeat
8. Use the 6g of soil to obtain the water content according to procedure for
water content
9. Go through the step 1-8 until you obtained two 6g samples and water
content values. The water content should have a difference not more than
1.4%. The plastic limit is the average of the two water content values.
64
The plasticity index is the difference between the liquid limit and plastic
limit
Mathematically
P.I. = LL – PL
Sample copy of atterberg limit test result carry out by Gitto constructioni
2.9.9.1 COMPACTION
COMPACTION TEST
The compaction is necessary to determine the maximum dry density (MDD) of the
soil and optimum moisture content (OMC). The MDD and OMC as determined by
laboratory tests are applied on the required layer during the construction. Beyond
degree of compaction of a given soil is measured in terms of its dry density. The
dry density is maximum at the optimum water content. A curve is drawn between
the water content and the dry density to obtain the maximum dry density and the
65
Dry density of soil:
5. Sieve, 4.75 mm
6. Oven
7. Desiccator
10.Straight edge
11.Spatula
12.Graduated jar
66
PROCEDURE
1. About 50kg of the sample is air-dried for 8hours under the sun, or oven dried
for 4hours.
2. The sample is removed from the oven and allowed to cool to room
temperature.
4. Excess crumps are broken down using the mallets or fingers where
applicable.
6. Using a pan a net weight of 3kg of the sample is measured and put In a
mixing tray.
7. 4% of the 3kg of water; that is 120ml is measured and poured into the
8. The 3kg sample is mixed with the 4% water and compacted in the mould +
collar. The compaction is done in three layers with 11blows from a 4.5kg
9. Remove the collar and scrap off the excess to the limit or height of the
mould.
67
12.Steps 6 – 10 are repeated four more times with 6%, 8%, 12%, and 16% of
water. Note when the weight of the soil and mould begins to drop stop.
(a)
(b) Rammer
68
GITTO COSTRUZIONI GENERALI NIGERIA LTD
5/3/201
Project:
69
Location: CH 50+500
Depth:
105
Dia. of Mould:
mm Height: 115 mm Volume: 1000
DENSITY DETERMINATION
Wt of Soil + Mould
Wt of Soil in Mould
Wet Density
Dry Density
70
Wt of Can + Wet
Soil (gm) 92.5 93.4 90.6 86.8 86.0 92.1 85.2 78.7
Wt of Can + Dry
Soil (gm) 88.8 89.6 86.0 82.3 80.9 86.5 79.3 73.2
Wt of Water (gm) 3.7 3.8 4.6 4.5 5.1 5.6 5.9 5.5
Wt of Can (gm) 25.0 25.1 27.3 27.5 27.5 25.0 27.6 25.1
Wt of Dry Soil (gm) 63.8 64.5 58.7 54.8 53.4 61.5 51.7 48.1
Water Content % 5.8 5.9 7.8 8.2 9.6 9.1 11.4 11.4
Average Water
2.08
2.05
2.02
1.99
Dry Density gm/cm3
1.96
1.93
1.90
1.87
1.84
1.81
1.78
1.75
5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0
Water Content %
71
Optimum Moisture
72
This is short for California bearing ratio. The process is aimed at determining the
bearing capacity of the soil sample. The California bearing ratio (CBR) is a
subgrades and base courses beneath new carriageway construction. The soil
samples that undergoes these tests are used for subgrade, sub-base, and base course
in road projects. The basic site test is performed by measuring the pressure
soils in place in field), and AASHTO T193. The CBR test is fully described in BS
1377: Soils for civil engineering purposes : Part 4, Compaction related tests, and in
The CBR rating was developed for measuring the load-bearing capacity of soils
used for building roads. The CBR can also be used for measuring the load-bearing
capacity of unimproved airstrips or for soils under paved airstrips. The harder the
surface, the higher the CBR rating. A CBR of 3 equates to tilled farmland, a CBR
of 4.75 equates to turf or moist clay, while moist sand may have a CBR of 10.
High quality crushed rock has a CBR over 80. The standard material for this test is
73
crushed California limestone which has a value of 100, meaning that it is not
The procedure for carrying out both are similar except that for the wet Cbr after
compaction is soaked for a day, two or three. While the dry is not.
Compaction rammer
Filter paper
Weighing balance
Sieve
Hand trowels
74
Scope
1. The sample from the field is air dried for three days.
3. Water is added to the sample till the Optimum moisture content and
4. The soil is then mixed with the water uniformly and all crumps formed are
broken.
7. And compacted with the compacting rod. If the 2.5kg compacting rod is
used then 25 blows are given per layer otherwise if 4.5kg then the 11 blows
are issued
8. Repeat steps 6 and 7 sequentially until the mold and collar is filled and
compacted.
12.Some mixed samples are put in the two moisture cans and weighed.
75
13.The compacted sample in mold is put in the curing tank for 72 hours if the
or base course
14.After the required duration of soaking, the sample is taken to the CBR
testing machine. The plunger of the machine is made to penetrate the from
top of the mold and readings are taking from the dial in the process at
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Of plungers penetration.
computed.
76
Sample of CBR Test Result
77
78
2.9.9.3 SIEVE ANALYSIS/GRADATION
used in civil engineering to assess the particle size distribution (also called
of sieves of progressively smaller mesh size and weighing the amount of material
The size distribution is often of critical importance to the way the material
organic granular materials including sands, crushed rock, clays, granite, feldspars,
coal, soil, a wide range of manufactured powders, grain and seeds, down to a
minimum size depending on the exact method. Being such a simple technique of
Procedure
1. Get about 2000g of sample passing sieve no. 200 (0.075 micrometer).
2. Wash in the no. 200 sieve the sample until all clay property is gone.
3. Oven dry the washed sample at about 1050c for at least 24 hours.
79
4. Arrange the set of sieve to be used in descending order of opening; say –
5. Take 500g of oven dried sample and place in the arranged sieve.
shaker) for five minutes. Ensure that none (no grain) is lost during shaking.
Geotechnical Laboratory
Date 16/1/20
Client: : 18
80
Project
CONTR
Sample No:
Depth(m):1.3-
Retaine
Particle weight
Diametr d Passing
Description (g)
e (mm) % %
Cobbles
75
50
coarse
25
Gravel
19.0 100.0
81
coarse 2.36 19.9 4.0 96.0
Grading curve
100
90
80
70
60
50
% passing
40
30
20
10
0
0.01 0.1 1 10 particle size (mm) 100
82
CONTRACTOR CONSULTANT FMPWH
One of the test in which concrete material can fail is due to crushing under
verify the crushing strength of aggregates. The aggregates should be oven dried,
Apparatus
1. Steel Cylinder
2. Tampering rod
4. Test sieves
8. Rubber mallet
9. Metal tray
Procedure
83
1 Place the cylinder of the test apparatus in position on the baseplate and add the
test specimen in three layers of approximately equal depth, each layer being
subjected to 25 strokes from the tamping rod distributed evenly over the surface of
the layer and dropping from a height approximately 50 mm above the surface of
the aggregate. Carefully level the surface of the aggregate and insert the plunger
so that it rests horizontally on this surface. Take care to ensure that the plunger
2 Place the apparatus, with the test specimen prepared as described in 6.3 and
plunger in position, between the platens of the testing machine and load it at as
uniform a rate as possible (see note) so that the required force of 400 kN is reached
in 10 min ± 30 s. NOTE: When, during the early stages of the test, there is a
rate and variations in the loading rate may occur especially at the beginning of the
test. These variations should be kept to a minimum with the principal object of
3 Release the load and remove the crushed material by holding the cylinder over a
clean tray of known mass and hammering on the outside of the cylinder with the
rubber mallet until the particles are sufficiently disturbed to enable the mass of the
NOTE if this fails to remove the compacted aggregate other methods may be used
but take care not to cause further crushing of the particles. Transfer any particles
84
adhering to the inside of the cylinder, to the baseplate and the underside of the
plunger, to the tray by means of a stiff bristle brush. Weigh the tray and the
aggregate and determine the mass of aggregate used (M1) to the nearest gram.
4 Sieve the whole of the test specimen on the tray on the 2.36 mm test sieve until
no further significant amount passes during a further period of 1 min. Weigh and
record the masses of the fractions passing and retained on the sieve to the nearest
gram (M2 and M3 respectively). If the total mass of the two individual fractions
(M2 plus M3) differs from the initial mass (M1) by more than 10 g, discard the
result and repeat the complete procedure using a new test specimen.
NOTE 1 In all of the procedures described in 3 and 4 take care to avoid loss of
NOTE 2 Mechanical sieving should only be used for aggregates which do not
first decimal place, of the mass of fines formed to the total mass of the test
85
the 2.36 mm test sieve (in g).
2 Calculate the mean of the two results to the nearest whole number. Report the
mean as the aggregate crushing value, unless the individual results differ by more
than 0.07 times the mean value. In this case, repeat the test on two further
specimens, calculate the median of the four results to the nearest whole number,
NOTE The median of four results is calculated by excluding the highest and the
lowest result and calculating the mean of the two middle results.
The aggregates play an important role in the construction industry. There are many
test, which are performed to check the quality of aggregates. Aggregates are a very
aggregates.
movement of vehicles on the road, the aggregates are subjected to impact. It results
in their breaking down into smaller pieces. Therefore, the aggregates should have
sufficient toughness to resist their disintegration due to the impact. This distinctive
property is measured by impact value test. The aggregate impact test value is a
86
measure of resistance to sudden impact or shock, which may vary from its
The following procedure is applied, to find out the impact value of aggregate:
Aggregates for the test sample can be decided by passing it through 12.5 mm
The test sample is filled in 3 layers and each layer is tamped for 25 numbers
of blows.
The crushed aggregate is removed from the test specimen and sieve it
aggregates, used for concrete other than wearing surface. An impact value 35% is
permissible for the bituminous macadam. Maximum permissible impact value for
Shape tests on coarse aggregates such as flakiness index and elongation Index, its
Principle:
Aggregate particles are classified as flaky when they have a thickness (smallest
dimension) of less than 0.6 of their mean test sieve size, this size being taken as the
mean of the limiting sieve apertures used for determining the size fraction in which
separating the flaky particles and expressing their mass as a percentage of the mass
of the sample tested. The test is inapplicable to material passing a 6.3 mm test
88
The elongation index of the given aggregates
3. Test sieves of sizes 63, 50 40, 31.5, 25, 20, 16, 12.5,10 and 6.3mm
elongated particles contained in it. For base course and construction of bituminous
and cement concrete types, the presence of flaky and elongated particles are
89
The Flakiness index of aggregates is the percentage by weight of particles whose
least dimension (thickness) is less than three- fifths (0.6times) of their mean
whose greatest dimension (length) is greater than nine-fifths (1.8times) their mean
dimension. This test is not applicable for sizes smaller than 6.3mm.
Apparatus
1. Steel Cylinder
2. Tampering rod
4. Test sieves
8. Rubber mallet
9. Metal tray
the operation to be used for. Say it is required to use materials retained on sieve
90
63mm, the material is then heated to a consistent dry temperature for about four
hours at 1050c.
1. Sieve the sample through the required test sieves (as specified in the table).
2. Take a minimum of 200 pieces of each fraction to be tested and weigh them.
thickness gauge. The width of the slot used should be of the dimensions
specified in column (4) of the table for the appropriate size of the material.
4. Weigh the flaky material passing the gauge to an accuracy of at least 0.1 per
length gauge. The width of the slot used should be of the dimensions
specified in column (6) of the table for the appropriate size of the material.
91
strength and get a standard mix ration to target a compressive strength for
application in a construction phase with available materials we use the cube test.
The application of the concrete determines the grade; for nominal blinding grade
10/15N/mm2, concrete is used, whereas for serious structural works such as casting
of foundation for bridges grade 25/30N/mm2, might be used. The bridge designer
in the drawing and other project specifications gives the grade. The crushing test is
carried out after 7, 14, 21, 28 days of casting and curing. But in the construction
project the cubes where often tested in 7 and 28 days. The method used to get the
mix ratios are usually trial mixes, in this method various sets of concrete cubes are
cast and cured. After 7 and 28 days they are crushed and the strength determined
by computation. The mix ratio for each set is recorded. There are six cubes in each
BS EN 12390-1:2000
4. Lubricant
92
6. Curing tank
7. Brush
8. Trowel
3. The fresh concrete is put into each cube in three layers each and compacted
with the tamping rod. Each layer receives 35 tamps to remove voids.
6. The concrete are removed from the cubes once they are finally set. The final
setting time for most concrete is 16 – 72 hours. But the removal is usually
after 24 hours.
7. The concrete cubes are transferred to curing tank for curing. The curing tank
8. After 7 days 3 cube are weighed and tested with the compression machine
93
Example of Cube test I witnessed
CHAPTER THREE
During my 6-months training, I encountered some challenges and, below were the
Had less time to interact with my supervisor due to his busy schedule. There are
times when my Boss would be very busy with work and would not want to be
disturbed.
At site, safety was not adequately provided, for training students, we go to site
94
No formal orientation for training students on site on how works are carried out,
Transportation to site of work was not easy. There wasn’t any proper arrangement
site or spend how personal money on transportation. Because of the location of site
organization are very reluctant to answer questions, some feel we have the
potential of stealing there jobs and hence they cannot assist us in doing so. Never
the less there were also a few who showed concerns on our intellectual progress.
Taking-off of complex drawings which I have not done before was challenging.
Being very new to practical application of road and bridges works, it was
challenging to give out certain information from the road and bridge drawings
when required.
Accommodation was also a major challenge. The company did not provide any
form of accommodation for us; the available little houses were not convenient
because most of them were so small and did not have hygienic rest room.
95
High cost of living. The cost of feeding and other necessities for survival was high
<
supply five times in a month on average; in fact, we were paying for darkness in
Lack of security in locality. We suffered from various severe security threats and
weekly reports of murder, kidnaps and robbery. This affects the activities of people
in the area negatively. Example just by the knowledge that one had anything to do
with the company one becomes a target and one’s life is threatened.
Adapting to the various sections I was assigned to work with. It was not very easy
for me leaving a section I was getting more familiar and free with it members for
another. This meant stating all over again to make acquaintances and building a
free relationship for easier flow of knowledge and questioning which takes some
time.
96
CHAPTER FOUR
4.0.1 Conclusion
roads and bridge constructions, understanding more the road construction industry,
shaping my career path, and understanding of the society at large having related
with both professionals and non-professionals within and outside the construction
industry.
97
My industrial training was very useful to me because I worked in a field strongly
company and working under different sections of the technical units and
The training enhanced so much my knowledge in road and bridge drawing and its
construction works and processes and also helped me understand how construction
process is controlled and all materials are tested before use. I learned new skills in
measurement and raising bills, valuation and pricing which was not taught in
4.0.2 RECOMENDATION
98
After having an appreciation of the industrial experience, I would like to urge the
I am also of the opinion that the period of attachment should be made one year
rather than six months, this will give students more time to learn all the necessary
skills they needed to learn. For instance in my case, had it been that the training is
one year I would have had more chance to learn how to prepare longitudinal
beams, bearing seats, placing plinth and how asphalt or coal tar is tested.
The department should also arrange with the industry so that students do not have
The money provided to training students by ITF should be increased and given
within period of training, not after training, because expenses and running cost is
Finally, the industrial attachment is very vital to the performance of students both
in class and in the industry after completion of their studies. The students on their
own should take the training very serious and school should encourage the training
maximally.
99
100