You are on page 1of 6

ABCD

Minimizing the Impact of SCR/SNCR


Retrofits on the
Ljungstrom Air Preheater
Louis P. Bondurant III, Wayne S. Counterman and Robin B. Rhodes
ALSTOM Power Air Preheater, Inc.
3020 Truax Road
Wellsville, NY 14895

Abstract Introduction

Experience in the US and overseas has shown Optimizing of the NOx removal process has
that conventional regenerative air preheaters been ongoing since early implementation in
are susceptible to fouling with ammonium Japan and Germany in the 1980s. Migration
bisulfate deposits. Without appropriate design to the United States has presented a new and
considerations, addition of ammonia based unique set of fuel specific design and
NOx removal equipment is likely to lead to operational requirements. Experience has
more frequent unit outages for the purpose of proven that conventional regenerative air
water washing the air preheater. preheaters are susceptible to fouling with
ammonium bisulfate salt deposits. Unless
The temperature range at which ABS appropriate features are incorporated into the
deposition occurs onto regenerative air design of a downstream air preheater, losses
preheater elements has been identified and in unit availability for air preheater washes are
verified. Countermeasures to minimize the likely.
impact of ABS include modification of the
temperature profiles within the air preheater This paper will reflect on the lessons learned
and elimination of certain problematic features by Ljungstrom air preheater suppliers in
in this critical temperature zone. These Germany, Japan and the US. Discussion will
measures, coupled with reasonable control of include the identification of specific features
ammonia slip, will dramatically reduce found to be problematic in conjunction with
requirements for air preheater washes. SCR/SNCR systems as well as potential
solutions, which have been identified for each.
Also discussed are the implications of revised
system static pressure and terminal Retrofit installation of high dust SCR equipment
temperatures. Identifying and allowing for generally alters both the temperatures and
these revised conditions in the project planning static pressures for the combustion air
stage are key to managing implementation preheater. Modifications can make the air
costs. preheater better suited to meet post-retrofit
operational requirements. The modifications
discussed will focus on optimizing unit
reliability and availability without jeopardizing
and potentially improving unit heat rate.

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 1 of 6
ABCD
Formation of Ammonium Sulfate and
Ammonium Bisulfate At or below 300 Degrees F, ABS has solidified
into a consistency, which can be managed by
Numerous chemical reactions occur within sootblowing equipment. For this reason,
either an SCR or SNCR NOx removal system. significant ABS deposits are rarely noted in the
The single most troublesome reaction to the cold end element layer. It should be noted,
regenerative air preheater results in the however, that higher SO3 levels would elevate
formation of ammonium bisulfate (NH3 + SO3 the sulfuric acid dew point. [5] Cold end
+ H2O ⇒ NH4HSO4). Ammonium bisulfate fouling with a moist and sticky mixture of fly
(ABS) forms a sticky deposit on the transfer ash and condensed acid should be considered
surface of the heat exchanger, which a possibility.
subsequently attracts and collects flyash.
700
These deposits foul flow passages, resulting in
restriction to flow and losses in thermal 600
Max. Metal Temp.

efficiency.

Gas Side Temperature, °F


500
ABS Dewpoint Min. Metal Temp.

When the ratio of NH3 to SO3 is more than 2:1, 400

ammonium sulfate is formed. (2 NH3 + SO3 + 300


ABS Deposition Zone

H2O ⇒ (NH4)2 SO4 = ammonium sulfate (AS)).


Ammonium sulfate is a dry powder at all air 200

preheater operating temperatures and does 100

not create a fouling problem. However, based Cold End


Layer
Intermediate
Layer
Hot End
Layer
0
upon the sulfur content of most American 0 10 20 30 40 50 60

coals, predominantly ammonium bisulfate will Axial Displacement, Inches from Cold End

form and the ammonia slip level will be the


Figure 1 - In high dust applications, a 40° F
controlling factor in the extent to which these
buffer exists between the ABS dewpoint and
deposits interfere with routine unit operation.
the deposition zone.
Even with low ammonia slip designs, fouling
has often been observed due to increases of
Controlling the impact of ABS becomes a
slip during transient load conditions, from flow
matter of evaluating the temperature profiles
stratification or mal-distributions of ammonia
for a given unit and minimizing the tendency
or NOx, system control problems and catalyst
of deposits to accumulate in this critical
degradation.
temperature zone. Evaluation of expected
operating conditions on conventional air
preheaters reveals that the deposition zone
Critical Temperature Zone
generally includes much or all of the
A correlation first identified by Japanese and
intermediate layer of heat transfer surface. In
German experience has been confirmed by
many cases, this zone expands to include a
initial U.S. experience between the formation
part of the hot and/or cold end layers.
of ABS deposits and the operational metal
Reconfiguration of such units is essential if the
temperatures of air preheater heat transfer
probability for frequent water washes is to be
surface. [2 & 3] On high dust applications,
held to a reasonable level.
the maximum metal temperature at which
deposits are expected to form is 40 degrees F
below the ABS dewpoint. In the case of low
Problematic Features
dust systems, however, the deposit zone is
known to extend up to the ABS dewpoint. [4]
Identification of root cause of ABS fouling in
This is attributed to the fact that a significant
regenerative air preheaters has been an
portion of the ABS formed collects on the ash
ongoing process for the past 15+ years. In
particles, and carries through the air
fact, rather than a single point cause, a
preheater. Without this phenomenon, ABS
number of contributing factors have been
deposition will extend into higher temperature
identified as problematic features. By
zones. Additionally, fly ash does provide some
removing these problematic features in the
degree of abrasive cleaning.
critical ABS temperature zone, the rate of

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 2 of 6
ABCD
accumulation of ABS deposits on air preheater temperature zone. Either mild steel or low
can be minimized. alloy steel surfaces corrode when exposed to
condensing ABS salt and/or sulfuric acid. This
not only has the effect of wasting away mass,
8 but provides a rough oxide surface finish,
improving deposit adhesion. Porcelain enamel
Gas Side Pressure Drop (In. WG)

coated heating elements, on the other hand,


7
maintain a comparatively smooth surface finish
throughout life.

Experience in Germany and the US in using


6 porcelain enamel coated heating elements has
0 1000 2000 3000 4000
Operating Hours
demonstrated significantly lower rates of ABS
ABS Across Layer Split ABS Confined to Single Layer accumulation. To quantify these results
exposure tests have been run at Southern
Company’s Plant Crist. [7] As shown by
Figure 2 – In a standard design air preheater
Figure 4, this test revealed dramatically lower
the ABS deposition zone may span multiple
deposit accumulation for enamel coated
layers of heat transfer surface.
surface at both moderate and low ammonia
slip levels. At an ammonia slip level of 3.3
PPM, deposits accumulated in enamel coated
The first feature to be identified as problematic
element were approximately 15% of the levels
was the occurrence of an element layer split in
measured on uncoated surfaces. At a slip level
the temperature zone at which ABS is expected
of 0.7 PPM, the enamel coating demonstrated
to condense. Testing by EPRI in 1986 [6] and
deposit accumulation comparable to 25% that
work done in Japan by ABB KK have confirmed
of uncoated surfaces.
a very rapid pressure drop increase when the
ABS deposition zone bridges across an element
layer split. As shown by the ABB KK
experience in Figure 3, ABS deposition across 140
a layer gap can increase fouling rates by over 120
four times.
Ounces of Deposit

100

80

60

40

Hot End Layer 20

0
ABS Zone
Carbon Steel Low Alloy Steel Enamel Coated

Intermediate Layer 3.3 ppm NH3 slip 0.7 ppm NH3 slip

Cold End Layer


Rotor
Center
Line
Figure 4 – Field tests at Plant Crist reveal that
enamel coated surfaces are less prone to
accumulate ABS deposits.
Sootblower

To manage ABS deposition rates over time, a


Figure 3 – The occurrence of ABS deposition heat transfer surface must be capable of
across element layer splits significantly effects maintaining this smooth surface finish under
pressure drop trend exposure to highly corrosive conditions. ABS
deposits are corrosive as determined by both
lab and field tests. Results of corrosion tests
A second problematic feature relates to the on the Plant Crist unit revealed that exposure
surface finish and corrosion resistance of the of carbon steel and low alloy steel to
heat transfer surface in this critical operational ABS can result in corrosion rates

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 3 of 6
ABCD
10 times that of enamel coated element work, a higher efficiency, fully closed channel
surfaces. The need for enhanced corrosion surface has been developed (type DNF™
resistance will be far more pronounced in the profile). Figure 6 illustrates the results of
US with its higher sulfur fuels. laboratory tests performed to compare the
sootblowing energy characteristics of DU, UNU
12 and DNF heat transfer surfaces.
10

8
% Corrosion Loss

Residual Impact
4

Pressure
2

0
Carbon Steel Low Alloy Steel Enamel Coated

3.3 ppm NH3 slip 0.7 ppm NH3 slip


200 PSI Source 320 PSI Source

DU UNU DNF™
Figure 5 – Same test at plant Crist
demonstrates that enamel-coated elements
better resist corrosion in an ABS environment Figure 6 – Residual impact pressure is a
measure of remaining cleaning media after
passing through a given depth of heat transfer
A third feature which influences the rate at surface. Higher values indicate improved
which ABS accumulates is the tendency of the cleanability characteristics.
heat transfer surface to dissipate cleaning
media energy. Experience has proven it best
to avoid element layer splits between the Sootblowing & Water Washing
critical temperature zone and the cold end
cleaning device. Likewise, open channel Effective sootblowing from the cold side of the
surfaces should be avoided in or below this air preheater is essential to managing deposit
temperature zone. An open channel surface is accumulation on even the best-designed and
one which permits radial or skew flow as fluids controlled system. Sootblowing from the hot
pass axially through the heat transfer surface. side will provide some level of
Open channel surfaces include DU, DL, CU supplementation to the cold end blowing, but
and FNC surface profiles and are alone is generally inadequate to control
characterized by the presence of many single deposits. Also, it should be noted that a loose
point contacts at the interface between packed surface (such as DL type surface) does
adjacent element sheets. Closed channel not demonstrate superior cleaning
surfaces, on the other hand, utilize multiple characteristics with sticky ABS deposits.
continuous line contacts to separate adjacent
sheets, as demonstrated in NF6, NF3 and Whether the cleaning medium is steam or
DNF surface profiles. compressed air, adequate quality is critical to
prevent introduction of excess moisture.
Early development by ABB-AGT, of a more Excessive blowing frequency or pressure should
efficient closed channel surface resulted in a be avoided, as this can have a significant
new surface, dubbed the UNU heat transfer negative impact on the life of the heat transfer
surface. This surface, while not a fully closed surface. The key to deposit control is selection
channel design, does reduce the skew flow of appropriate heat transfer surfaces and
area, thereby offering improved cleanability. materials, not aggressive sootblowing
Enamel coated UNU surface has been used practices.
extensively for SCR applications in Germany.
As the result of more recent US development Provided a system is properly configured and
operated at low ammonia slip levels,

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 4 of 6
ABCD
unscheduled outages for air preheater water
washes should not be required. None the less,
Multi-media Cleaner

it is advisable to perform an air preheater


wash during scheduled unit outages. This
practice serves to both clear the heat transfer Hot End Layer
surface of any accumulated deposits and to
limit ABS corrosion (see Figure 7) during this
idle lay-up period. Since ABS is hygroscopic, ABS Zone

air heaters with ABS deposits should be Cold End Layer

washed as soon as practical after coming off- Rotor


Center

line. An air preheater wash is most effective if Line

performed on both the hot and cold sides of


the rotor. This can be performed in either an Sootblower

alternating or concurrent mode with a typical


duration in the range of 12 to 24 hours Figure 8 – Properly configured, an air
preheater can be cleaned without excessive
Corrosion Rates in Mils per Year at
sootblowing pressure or frequency
Various Concentrations
Grams ABS/
5 12.5 20 30 Revised Operational Requirements
100 ml H2O
Carbon steel 531 641.2 644.3 825.9
The addition of SCR catalyst plus the required
LACR 536.5 639 743.4 785
ducting and transitions will add resistance to
Enamel 0.1 0.3 0.7 1 the flow of flue gas on the back end of the
Figure 7 – ABS deposits combined with water boiler system. In the case of “tight” retrofit
are very corrosive. Lab tests reveal corrosion units, this increase in resistance may be
rates of 3 common materials at various significant to the air preheater. The term “hot
concentration levels. end pressure differential” is used to identify the
static pressure differential between the air
It should be noted that these washes generate preheater air outlet and gas inlet ducts. It is
a significant volume of effluent (possibly in an important design parameter as it directly
excess of 5 million gallons) which may require effects air to gas leakage levels and impacts
neutralization or further treatment. High- the structural design of the rotor, the housing
pressure water washing in combination with and sealing system components separating the
the normal wash provides a means to flow streams. In many cases, retrofit
substantially reduce the volume of water installation of an SCR system will increase this
required for an air preheater wash. air preheater hot end differential by over 25%.
Additionally, high-pressure washing may be At a minimum, a structural review should be
the only option for achieving complete performed based upon planned future
cleaning, based upon the composition and pressure levels. Such a review would focus on
magnitude of flyash which accumulates on top the structural adequacy of key components for
of the ABS. which failure could lead to a forced outage
involving significant repairs.
If high-pressure washing is pursued in addition
to high volume washing, multi-media cleaners In addition to reliability concerns associated
can facilitate faster implementation. Multi- with these higher-pressure levels is the
media cleaners are dual-purpose devices, corresponding increase in air to gas leakage.
which serve as sootblowers when the unit is on This increase will be roughly proportional to
line and high pressure washing devices when the increase in air preheater hot end pressure
the unit is off line. As personnel do not have differential. Numerous techniques have been
to enter the ducting to operate this equipment, developed to reduce leakage in the
water washes can be started up to 12 hours Ljungstrom air preheater. Such measures
earlier in the cool-down phase of a unit should be evaluated in the process of
shutdown. retrofitting an SCR system, as they will offset
the effect of these increased pressures. In

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 5 of 6
ABCD
some cases this reduction in air preheater Conclusion
leakage can be adequate to offset the need for
replacement of an existing induced draft fans. The installation of ammonia based NOx
controls imposes a new set of operating
Consideration should be given to expected gas requirements for the combustion air preheater:
inlet and desired gas outlet temperatures a) Fouling and corrosion from the formation of
following SCR retrofit. Often included as an ammonium bisulfate, b) Increased SO3 related
integral part of such a project, is the addition fouling and corrosion, and c) Higher pressure
of an economizer bypass to maintain SCR differentials. Conventional air heater
temperature under low load conditions. If this configurations are ill suited for operation
bypass system results in an increase in the under these new requirements.
minimum gas temperature to the air
preheater, it may open the door for a thermal Proper reconfiguration of the heating element
efficiency upgrade. A number of options to arrangement, profiles and materials will
improve air preheater thermal efficiency have dramatically reduce the rate of ABS
become available in recent years. The results accumulation, corrosion and the probability of
of these options range from a reduction in gas unplanned unit shutdowns for air preheater
outlet temperature of a few degrees to 40+ water washes. In the process of updating the
degrees F. If conditions in and downstream of air preheater configuration for these new
the air preheater allow such an upgrade, a requirements, a review of thermal
meaningful reduction in unit heat rate will be performance and air heater leakage may offer
realized. reductions in both implementation costs and
future unit operational costs.

References

[1] Saleem, M. Galgano, and S. Inaba, “Hitachi-Zosen DeNOx Process for Fossil Fuel-Fired Boiler,”
Proceedings of the Second NOx Control Technology Seminar, Hosted by EPRI, Denver, CO, Nov. 8-9,
1978, FP-1109-SR
[2] Wagner, P.A., Wiedinger, G. F. , Talbot, W.C., and Bullock, D.W., “Multiple Coal Plant Experience – A
U.S. Generating Company Perspective,” ICAC Forum 96, “Living with Air Toxins and NOx Emissions
Controls,” Baltimore, MD, 1996
[3] EPRI TR-111797, “Assessment of Air Preheater Fouling due to Utilization of SNCR and SCR Systems”,
(1998)
[4] “Regenerative Heat Exchangers Combined with Catalytic Measures for NOx Reduction” from E. Kraft
(Rothemuehle) and H. Mueller-Odenwald (ABB AGT) published in the book "Dampferzeugertechnik" (~
"steam power plant technology") at Vulkan-Verlag, Part X/3. 1992.
[5] H. Farwick and V. Rummenhohl, “SCR Catalyst, Five Years of Operating Experience with all Types of SCR
Plants and the Conclusions and Measures Developed as a Result“, VGB Kraftwerkstechnik 73 (1993),
Number 5
[6] EPRI CS-4386, “Selective Catalytic Reduction for Coal-fired Power Plants – Pilot Plant Results”, (1986)
[7] Innovative Clean Coal Technology, “Demonstration of Selective Catalytic Reduction (SCR) Technology
for the Control of Nitrogen Oxide (NOx) Emissions from High-Sulfur, Coal-Fired Boilers”, DE-FC22-
90PC89652, March 1996

Copyright ALSTOM Power Air Preheater, Inc. – 1999 – All rights Reserved Page 6 of 6

You might also like