Professional Documents
Culture Documents
: 00
TABLE OF CONTENTS
Page 2 of 5
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
1.0 S COP E
Each ethylene plant design project must issue a Basis of Process Design (BOD).
The Basis of Process Design defines the basis by which the ethylene plant is to be
designed in accordance with client requirements and in agreement with Shaw
management. This Basis of Process Design (Generic) is in the format of the
individual project document and is used to generate the Basis of Process Design for
each individual project.
The Project Procedures and Specifications document (DTP-T-P-01001) has the
Purpose, Scope, Definitions, Responsibilities and Procedure for issuing the Basis of
Process Design document. There is some discussion in DTP-T-P-01001 of the
BOD content. This guideline is meant to be supplementary and more detailed.
2.0 AS S OCIATED GUIDELINES
Project Procedures and DTP-T-P-01001 Previously
Specifications 3_1_1/2/3WP1
Ethylene Plant Design Standards DTS-T-P-03001 Previously 3410P001A
Ethylene Plant Process Team DTP-T-P-03001 Previously 3410P002A
Guidelines (Generic)
3.0 AS S OCIATED DOCUMENTS
Invitation to Bid (ITB)/Proposal
Minutes of Meeting from Kick-off Meeting
Contractual information including Guarantees.
Correspondence with Client (as applicable)
Shaw Divisional Input
• Process Marketing
• Process Technology/Business Development
• Project Management
• Project Engineering
Input information shall include but is not limited to the following:
• Background and General Information
• Plant Capacity and Operating Factor
• Design and Rating Cases
• Feedstock Specifications
• Feedstock Contaminants (e.g. Hg, As, COS)
• Product Specifications
• Component Recovery Criteria
• Turndown Requirements
• Auxiliary and Start-up Material Specifications
• Battery Limit Conditions and Source/Destination for Feed and Products
Page 3 of 5
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Revamp Considerations
• Other input information may be required for revamp work in addition to the
information mentioned above. Revamp input information may include but is
not limited to the following:
▬ Yields from existing (or planned) facilities.
▬ Philosophy and procedure to be used with proprietary equipment or
units licensed by others.
▬ Recycles or other feeds from outside units.
▬ Equipment or other physical constraints such as re-using existing
equipment or limited plot space.
▬ Existing equipment data sheets including compressor wheel curves and
tower/vessel internals .
▬ Existing equipment inspection data.
Team Guidelines
Project Design Data(PDD)
4.0 BACKGROUND
The Basis of Process Design is the central project document that relays contractual
obligations and performance guarantees to the process team. It is completed by
the Process Lead Engineer or his/her designee and approved by the Olefins
Section Manager. The Basis of Process Design is issued at the beginning of the
project prior to initiating the process engineering design effort. The Basis of
Process Design is not to state any design criteria that is stated in another
document, with the exception of compiling and repeating information given in one or
several client documents in order to have a single Shaw document with which to
work.
Often, the client’s ITB has a similar Basis of Design as the process BOD. It is
important that the Basis of Process Design be “owned” by the Shaw process team
instead of having it “owned” and approved by the client, even though the
information may be repeated.
The Basis of Process Design is meant to be “external” as well as “internal”; that is, it
is issued to Projects and the client and is often one of the first chapters of the Basic
Design Engineering Package (BDEP) produced for the project. It does not contain
proprietary information. It is a form of communication to the client in terms of
design criteria used.
There may be some information that normally written in the Team Guidelines (see
DTP-T-P-03001) that is moved to the Basis of Process Design due to client
preference (for instance, heat exchanger fouling resistances or pump efficiencies).
The lead or designee should try to minimize this in order to standardize the division
of these two documents for consistency.
Page 4 of 5
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
6.0 AP P ENDICES
6.1 APPENDIX A: STANDARD BASIS OF PROCESS DESIGN
Page 5 of 5
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
S HAW (LOGO c a n b e a d d e d )
J .O. No . 12345.10
REVISION 0 1 2 3 4 5
APPROVAL DATE
PREPARER
LEAD PROCESS ENGINEER
TECHNOLOGY
OLEFINS SECTION MANAGER
This document contains the proprietary and confidential information of The Shaw Group Inc. and is to be returned upon request. Its contents
may not be copied, disclosed to third parties, or used for other than the express purpose for which it has been provided without the written
consent of The Shaw Group Inc.
Page 1 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
TABLE OF CONTENTS
Page 2 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
1. INTRODUCTION (TYPICAL)
XYZ Corporation has requested that Shaw provide a Basic Engineering Package for an
ethylene plant to be located at their plant site in nowheresville, world.
The plant design shall include Shaw's proprietary Advanced Recovery System (ARS)
technology and the Olefins complex will include the following units:
1. The Ethylene Plant
2. Pyrolysis Gasoline Hydrotreating (PGH) Unit
3. C3 Hydrogenation Unit (Single Stage)
4. C4 Cut Hydrogenation Unit
The PDP packages for the PGH Unit, C3 Hydrogenation Unit (Single Stage), and the C4
Hydrogenation Unit will be developed by IFP and will be integrated into the complex by
Shaw. The design of the Ethylene Plant is to be carried out by Shaw. This Basis of
Design only addresses the Ethylene Plant.
Turndown: 70%
Page 3 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
3.1.2 Feeds
The quantities and specification of the fresh feeds and the supplemental feeds are listed
in the following tables:
Page 4 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
PONA Analysis WT %
N-Paraffin 36.9
I-Paraffin 37.1
Naphthenes 20.7
Aromatics 5.3
Page 5 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Distillation ºC
IBP 34
5 46
10 54
30 81
50 114
70 155
90 240
95 277
FBP 317
RESIDUE, % 2.0
LOSS,% 3.0
Page 6 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
COMPONENTS WT %
Propane 60
Isobutane 14
N-Butane 26
CONTAMINANTS VALUE
COS 10 ppmw
Arsenic 20 ppbw
NOTE: LPG should account for 50% of the fresh feed for
Alternative Feed Case.
3.1.3 Studies
Two studies will be performed during project execution:
C3 Splitter Heat Pump Study: Determine whether the C3 Splitter has a heat
pump.
Page 7 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
COMPONENTS VALUE
Page 8 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
The furnace yields are to be included in the Basis of Process Design if a separate
Basis of Process Design is not prepared for the furnace section.
In addition to ethylene and propylene the plant will produce the following products:
Page 9 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Page 10 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Page 11 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Page 12 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
The quality of Fuel Oil has changed from combined LFO and HFO to only HFO, as the
LFO will be used as fuel in the Gas-turbine.
Page 13 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
section will still produce the same hourly rate of ethylene using only 5 USC-U furnaces
and the recycle furnace, by increasing the loading of the operating liquid cracking USC-
U furnace.
For the 100% Algerian Condensate feed case, 5 of the 6 USC-U furnaces will be
cracking Light Condensate and the 6th furnace will crack the Heavy Condensate. When
one of the 5 furnaces cracking the Light Condensate is undergoing decoking, the other
4 furnaces will increase their ethylene production to compensate for the decoking
furnace. When the Heavy Condensate furnace is undergoing decoking, the 5 furnaces
cracking the Light Condensate will increase their ethylene production to achieve the
same ethylene hourly rate. The fractionated Heavy Condensate will be sent to the
Heavy Condensate day tank, which shall have the necessary capacity to store the
heavy condensate while the Heavy Condensate furnace is out of operation.
For the 50% LPG/50% Light Naphtha feed case, the LPG cracking furnaces shall
receive the LPG as a vapor stream.
Each USC-96U furnace shall be of twin-cell design with two radiant boxes, each with 48
radiant coils. There will be a common convection box for the two radiant boxes. There
are three different types of furnaces in this plant:
Five USC-96U furnaces with capability to handle gas-turbine exhaust(GTE) and capable
of cracking Light Naphtha liquid feed, or Light Condensate liquid feed, or LPG vapor
feed.
One USC-96U furnace with capability to handle gas-turbine exhaust(GTE) and capable
of cracking Light Naphtha liquid feed, or Heavy Condensate liquid feed.
One recycle USC-8M furnace capable of cracking the ethane recycle with a design to
use ambient air ONLY for fuel combustion.
Gas-turbine exhaust will be ducted to only 4 USC-96U furnaces. In the future, when
another gas turbine is installed all other furnaces except the recycle furnaces will have
the capability to be ducted. Presently it has not been finalized as to the type of burners
that will be used for the furnaces which are not presently ducted with the GTE.
Any excess Gas-turbine exhaust for the initial design will be sent to a waste-heat
recovery exchanger before atmospheric discharge.
When the ethane recycle furnace is out of service for decoking or mechanical cleaning,
the ethane recycle can be evenly distributed to three liquid cracking furnaces and co-
cracked with the liquid feeds.
Cracking furnace decoking effluent will be routed back to the furnace fire box.
Page 16 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
The scope of work of Shaw in the PGH Unit is to develop P&IDs from the PDP package
provided to Shaw by IFP for the PGH unit. In addition the interaction of this unit for the
overall material balance with the Ethylene plant will be part of Shaw’s scope. Hence, an
understanding of the raw pyrolysis gasoline (RPG) processing scheme is essential.
Please see Basis of Process Design for the PGH Unit.
Shaw’s scope of work is to ensure that the proper streams are interconnected between
the Ethylene unit and incorporate the IFP's PDP package into the P&IDs.
5.2.6 Miscellaneous
6. UTILITIES
Refer to Project Design Data for utilities (steam, BFW, cooling water, machine cooling
water, service water, fire fighting water, drinking water, instrument air, service air, inert
gas, and electricity). PROCESS WILL NOT INCLUDE UTILITY DATA. PROJECT
MUST PREPARE UTILITY DATA.
7. EFFLUENTS (TYPICAL)
Normally, a separate Environmental Basis of Design will be issued for each project
and/or Project Design Data will contain environmental information. If a separate
Environmental Basis of Design is not prepared, then this section may be included in the
Process Basis of Design.
PARAMETERS LIMITS
pH 6 - 10
Temperature up to 50oC
Page 18 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
OG - 60 mg/l
Phenols - 50 mg/l
NH3-N 30 kg 30 mg/l
Phosphorus 10 kg 10 mg/l
Ag 42 g 0.05 mg/l
As - 0.50 mg/l
Ba - 5.0 mg/l
Cd 34 g 0.05 mg/l
Cu 90 g 0.20 mg/l
Fe 12 kg 7.0 mg/l
Se - 0.05 mg/l
V - 1.0 mg/l
Page 19 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
B - 5.0 mg/l
Sn - 4.0 mg/l
Fluoride - 10 mg/l
Table 8.1.-1 shows the BATTERY LIMIT conditions for the feeds.
Table 8.1.-2 shows the BATTERY LIMIT conditions for the products.
Ethylene Shaw
To Storage -97 18.5 Liquid
To Complex 38 42.5 Vapor
Propylene Shaw
To Storage 12.5 24.1 Liquid
To Complex 38 32.0 Liquid
Page 20 of 21
Ethylene Plant Basis of Design No.: DDP-T-P-03205 Rev.: 00
Page 21 of 21