You are on page 1of 9

EE206: Electromechanics Lab

Lab Report
Experiment 3: To Study Three – Phase
Transformer Connections

Course Instructors: -
Dr. Saifullah Payami and Dr. A. V. Ravi Teja
Department of Electrical Engineering
Indian Institute of Technology, Ropar

Submitted By: - (Group 3)


Dinesh 2020EEB1166
Rahul Chaudhary 2020EEB1195
Ravish Badgujar 2020EEB1196
Prashant Hansda 2020EEB1192
.

Date: 15th February, 2022


Report content…….

1. Objective of the experiment


2. Circuit diagram
3. Equipment
4. Observations
4.1 Open Circuit test
4.2 Short Circuit tes
4.3 Simulation results
4.4 Efficiency
4.5 Voltage Regulation
4.6 Power factor
5. Calculations
6. Precautions
7. Conclusions

2
1. Obeservation:

To study three phase transformer connections.

2. Circuit diagram (with ratings of instruments)


For ∆ - Y connection

3
For Y - ∆ connection:

For ∆ - ∆ connection:

4
For Y – Y connection:

3. Equipment needed (quantity and ratings)


Name of the Equipment Range Quantity

Three Phase Variac detail KVA = 12.21 01


Input V = 415V
Output V = 0 - 470V
Current = 15A

AC Voltmeter 0 - 250 - 500V 02

AC Ammeter 0 - 5 - 10A 02

AC Ammeter 0 - 10 - 20A 02

UPF Wattmeter 5 - 20A, 150 - 300 - 600V 04

LPF Wattmeter 1 - 2A, 150 - 300 - 600V 02


Table-4.1: Equipment quantity and ratings

5
NAME PLATE DETAILS OF 3- PHASE TRANSFORMERS
Name of the Range Quantity
Equipment

Main Transformer (T1) KVA = 10 01


PRI ‘V’ = 200+200V
PRI ‘I’ = 14.43A
PH =3
SEC ‘V’ = 200+200V
SEC ‘I’ = 14.43A

Table-4.2: Transformer name plates

4. Observations
The following tables were obtained after performing the simulations on MATLAB:

6
5. Calculation:
Line Voltage T/F ratio:
The turn ratio of each transformer is a:1=1:1. Therefore, a=1.
Let the input phase voltage be V.
For connection:

For connection:

For connection:

7
For connection:

Efficiency:

Voltage Regulation:

For connection:

For connection:

For connection:

For connection:

8
6. Precautions

1. In the SC Test, the input voltage should be varied slowly because a small
variation in the input voltage can cause a huge variation in the current.
2. Make sure that the windings are connected in the proper phase
relationships.
3. The power should be turned on when the circuit is checked completely.

4. Connecting leads should be perfectly insulated.

5. The voltage across the terminals of the transformer should not increase
the rated voltage. This could destroy the insulation in the transformer.
6. The current in the coils of the transformer should not exceed the rated
current. This could burn up the transformer windings.
7. When connecting three-phase transformers, the secondary Δ side should

never be closed until a test is first made to determine that the voltage
within the Δ is zero.

7. Conclusions
1. Three phase transformers connections Y-Y, Y-D, D-Y and D-D were
simulated in simulink.
2. Y-Y three phase transformer results of load test were noted and
compared with the practical results provided.
3. Various loads were tested on the implementation and results were
consistent with the theory studied.
4. All the results are within permissible limits. Although some practical

results were a little different from the simulated results due to the
experimentation errors.

You might also like