Professional Documents
Culture Documents
Course objectives:
This course will provide students essential knowledge required in power systems for its
analysis and protection. This course also provides the students hands on experience in
high voltage testing of various insulators and cables.
Course outcomes:
After the successful completion of the course, the student will be able to:
1. Analyze the performance of transmission lines and relays
2. Calculate the steady-state power flow in a power system.
3. Analyze different types of short-circuit faults which occur in power systems
4. Analyze the performance of insulators and cables by High voltage testing.
1
EEE DEPARTMENT POWER SYSTEMS LAB
APPRATUS:
THEORY:
Transmission line network is a two port network with four terminals where the
input voltage and input current can be expressed in terms of output voltage and output
current.
Is Ir
a Two port networks d
VS VR
b c
Therefore, the input voltage VS and input current IS of a 3-phase transmission line can
be expressed as:
VS = AVR+ BIR
IS = CVR+ DIR
where VS = sending end voltage per phase
IS = sending end current
VR = receiving end voltage per phase
IR = receiving end current
A, B, C and D (generally complex numbers) are the constants known as generalised
circuit constants parameters of the transmission line. The values of these constants
depend upon the particular method adopted for solving a transmission line. Once the
values of these constants are known, performance calculations of the line can be
easily worked out.
The following points may be kept in mind:
(i) The constants A, B, C and D are generally complex numbers.
(ii) The constants A and D are dimensionless whereas the dimensions of B and C are
ohms and mhos respectively.
(iii) For a given transmission line, A = D & A D -B C = 1
CIRCUIT DIAGRAM:
2
EEE DEPARTMENT POWER SYSTEMS LAB
Procedure:
1. Connect as per the circuit diagram.
2. With the dimmerstat in minimum (zero) output position and DPST2 in open
position, close the supply switch.
3. Vary the dimmerstat slowly and apply the rated voltage then note down the
readings of voltmeter and ammeter.
4. Now reduce the voltage to zero and then close DPST2 switch at receiving end for a
short circuit.
5. Increase the voltage at input side slowly so that the current that flows through the
circuit will not exceed rated current.
6. Tabulate the meter readings.
7. Open the DPST2 switch and reduce the voltage to zero and then the supply switch
is opened.
TABULAR FORMS:
1 short 80 4 4
2 Nominal –T 180 4 4
CALCULATIONS:
VS = AVR +BIR
IS = CVR +DIR
3
EEE DEPARTMENT POWER SYSTEMS LAB
PRECAUTIONS:
RESULT: The ABCD parameters of 220kV EHV transmission line are obtained and
the results are verified.
VIVA QUESTIONS:
4
EEE DEPARTMENT POWER SYSTEMS LAB
Aim: To find the efficiency and regulation of 220kV line using transmission line
simulator.
Apparatus:
Circuit Diagram:
Theory:
5
EEE DEPARTMENT POWER SYSTEMS LAB
This is known as Ferranti Effect. Here the transmission line inductive reactance will
be less than the charging capacitive reactance. Hence the receiving end voltage is
more than sending end voltage. This can be verified by drawing a phasor diagram for
equivalent lumped parameters.
Procedure:
6
EEE DEPARTMENT POWER SYSTEMS LAB
Observation Table:
R2 230 1.34 0.24 -0.2 0.32 0.76 230 0.88 0.2 0 0.2 0.99 83.33 11.76
R3 230 1.52 0.35 -0.1 0.35 0.96 205 1.4 0.29 0 0.29 0.99 82.8 25.36
L1 230 0.58 0.03 -0.15 0.15 0.18 213 0.53 0.02 0.12 0.12 0.13 66.66 20.67
L2 230 0.25 0.04 -0.05 0.07 0.72 183 0.93 0.04 0.17 0.18 0.16 100 40.43
C1 230 1.72 0.17 -0.37 0.39 0.41 285 0.67 0.13 -0.15 0.19 0.68 76.47 -9.82
R1 + 230 0.82 0.15 -0.13 0.19 0.73 207 0.73 0.13 0.09 0.16 0.8 86.66 24.15
L1
R2 + 231 0.81 0.19 0 0.19 0.99 172 1.2 0.16 0.14 0.22 0.76 84.21 49.41
L2
R1 + 229 1.74 0.29 -0.28 0.4 0.73 258 1.08 0.25 -0.12 0.29 0.91 86.20 -0.38
C1
R1 + 232 2 0.47 -0.12 0.47 0.97 222 1.79 0.39 -0.12 0.41 0.95 82.97 15.76
L1 +
C1
7
EEE DEPARTMENT POWER SYSTEMS LAB
Precautions:
1. Transmission line should be charged with some minimum load i.e., 0.5 to 1A
(resistive) and all the compensator capacitors and loading capacitor should be in
off position otherwise receiving end bus voltage rises to a dangerous level.
2. While observing the Ferranti effect receiving end voltage should never exceed
280V between Line to Neutral /485 L-L.
3. Disconnect three-phase supply from the power circuit before switching off the
Single-phase auxiliary supply from the simulator.
Calculations:
% Regulation = ((Vr_NL| –Vr_FL)*100)/ Vr_FL
% Efficiency = (Pr/Ps)*100
Result: The regulation and Efficiency of the given transmission line model are
obtained for various loadings and the readings are tabulated.
Viva Questions
1. How do you classify small medium and long transmission lines?
2. What are the advantages and disadvantages of using pie model of a
transmission line?
3. How to reduce the reactance of a transmission line?
4. What is surge impedance loading?
8
EEE DEPARTMENT POWER SYSTEMS LAB
APPARATUS:
S. Equipment Type Range Qty
No.
1 Ammeter MI 0-10A 1
2 SPST Switch - - 1
3 Lamp Load - Single Phase, 230V, 10A 1
4 Stop Watch Digital mS 1
Theory:
The over current relay is used for the protection of motors and current graded
protection of transmission lines. The inherent inverse characteristics of the
electromagnetic relays are essential for the overload protection of electrical loads.
In an over current relay, there would be essentially a current coil. When
normal current flows through this coil, the magnetic effect generated by the coil is not
sufficient to move the moving element of the relay, as in this condition the restraining
force is greater than deflecting force. But when the current through the coil increased,
the magnetic effect increases, and after certain level of current, the deflecting force
generated by the magnetic effect of the coil, crosses the restraining force, as a result,
the moving element starts moving to change the contact position in the relay.
Plug Setting and Time Multiplier Setting (TMS) are provided for adjusting
the inverse characteristics of the relay.
CIRCUIT DIAGRAM:
9
EEE DEPARTMENT POWER SYSTEMS LAB
PROCEDURE:
i) Direct loading:-
1. Connect the circuit diagram as shown in Fig 1.
2. The SPST connected across the 9 and 10 terminals of the relay is initially kept
closed.
3. Switch on both the supplies
4. By using the plug setting bridge the current setting is kept at a particular value
5. Choose the required time setting by using time setting multiplier.
6. Switch on the 1- load and increase the load until the load current exceeds the
current setting value.
7. Open the SPST and start the stop watch
8. The instant at which the relay trips the circuit, stop the stop watch and note the
operating time.
9. Reset the Flag and Repeat the above procedure for different values of increased
load currents, current settings and time settings.
10. Switch OFF the supply.
TABULAR FORMS:
10
EEE DEPARTMENT POWER SYSTEMS LAB
MODEL GRAPH:
IL IL
(A) (A)
T in sec T in sec
PRECAUTIONS:
10
7
Load Current(A)
5
CS=2.5 TMS=0.2
4 CS=3.75 TMS=0.2
0
0 1 2 3 4 5
Operating Time (Sec)
11
EEE DEPARTMENT POWER SYSTEMS LAB
10
6
Load
4
CS=3.75;
3 TMS=3
2 CS= 3.75;
TMS=0.15
1
0
0 1 2 3 4 5 6
Operating Time (Sec)
RESULT: The Characteristics of Electromagnetic over current relay are obtained for
various current settings and time multiplier settings.
VIVA QUESTIONS:
12
EEE DEPARTMENT POWER SYSTEMS LAB
AIM: To study the characteristics of an earth fault relay for open circuit and
unbalanced loading.
APPARATUS:
S. No. Equipment Type Range Qty
1 Ammeter MI 0-10A 1
2 SPST Switch - - 1
3 Lamp Load - 3- Phase, 400V, 5kW 1
4 Stop Watch Digital mS 1
CIRCUIT DIAGRAM:
13
EEE DEPARTMENT POWER SYSTEMS LAB
THEORY:
Earth fault relays are used for protection of generators, motors, transformers,
capacitor banks, shunt reactors and radial feeders in distribution networks against
earth faults alone.
Ground fault currents are dependent upon system grounding and they produce
zero sequence currents during fault, whereas there is very little zero-sequence current
during normal operation. Thus the pick-up settings of the ground fault relays can be
made more sensitive than those of phase fault relays. Ground fault relays are similar
to over current relays but with only one coil for current in the case of instantaneous,
definite time or inverse time ground fault types.
The Earth fault relay is a non-directional heavily damped induction disc relay
which has an adjustable inverse time/current characteristic with a definite minimum
time. The relay has a high torque movement combined with low burden and low
overshoot. The relay disc is so shaped that as it rotates the driving torque increases
and offsets the changing restraining torque of the control spring. This feature
combined with the high torque of the relay ensures good contact pressure even at
currents near pick-up. Damping of the disc movement is by a removable high
retentivity permanent magnet. The unique method of winding the operating coil
ensures that the time/current characteristics are identical on each of the seven current
taps. Selection of the required current setting is by means of a plug setting bridge
which has a single insulated plug. The maximum current tap is automatically
connected when the plug is withdrawn from the bridge, allowing the setting to be
changed under load without risk of open circuiting the current transformers. The
IDMT relay has an auxiliary unit which is powered by a secondary winding on the
electromagnet through a rectifier and as such a separate auxiliary supply is not
required. The disc unit operates and closes its contacts, the auxiliary element
connected across the secondary winding on the electromagnet operates, and one
normally open contact of the auxiliary element reinforces the disc contact. Two other
contacts of the auxiliary element are brought out to the terminals of the relay
14
EEE DEPARTMENT POWER SYSTEMS LAB
PROCEDURE:
1. Connect the circuit as shown in the circuit diagram
2. SPST across the terminals 9 and 10 is initially kept closed
3. By using plug setting, select a current setting in amperes
4. Use the time setting dial to select a time setting multiplier
5. Apply 3- unbalanced load by closing TPST switch.
6. Vary the load such that the neutral current exceeds the current setting value.
7. SPST is opened and stop clock is started
8. The instant at which circuit breaker trips making a whistling sound, stop watch
is stopped and time of operation is noted
9. Reset the Flag and Repeat the above procedure for different values of
increased unbalance loads, current settings and time settings
10. Switch OFF the supply
PRECAUTIONS:
1.SPST should be closed initially
2.Opening of SPST switch and switching on stop watch should be done
simultaneously
3.Stop watch should be stopped at the instant of closing the relay contacts (i.e. at the
instant of listening the sound of from buzzer)
OBSERVATION TABLES:
MODEL GRAPH:
IN
(A)
T in sec
15
EEE DEPARTMENT POWER SYSTEMS LAB
6
Neutral Current(A)
CS=1A;
2 TMS=0.1
1 CS=1.5A;
TMS=0.1
0
0 1 2 3 4 5
Operating Time (Sec)
7
5
Neutral Current(A)
CS=1.5A;
2 TMS=0.15
1 CS=1.5A;
TMS=0.1
0
0 2 4 6 8 10
Operating Time (Sec)
RESULT: The Characteristics of Electromagnetic Earth fault relay are obtained for
various current settings and time multiplier settings.
16
EEE DEPARTMENT POWER SYSTEMS LAB
VIVA QUESTIONS:
17
EEE DEPARTMENT POWER SYSTEMS LAB
Apparatus Required:
Theory:
The load is connected to the 3 phase AC supply through the contactor. This
closes its contacts when relay gives trip circuit signal through 1 and 3 terminals. The
primary of the PT is connected between R phase and N (230V) and the secondary is
connected to 9 and 10 terminals of the over Voltage Relay (110V).
For normal condition, the relay does not respond. But whenever the voltage
exceeds the pre-set value, the relay operates with definite time and closes the trip
circuit contacts (1 & 3). This makes the transformer to directly connect across R
Phase and neutral, so the output at transformer secondary is obtained which appears
across the full wave centre tapped rectifier with capacitor filter. The output of the
rectifier is given as input to the 12V relay. This makes auxiliary relay terminals 3-8
and 1-7 to separate their contacts, while 6-8 and 4-7 to close its contacts. At this time
the contactors operating coil is de-energized, electrically separating the main supply
from the load circuit.
18
EEE DEPARTMENT POWER SYSTEMS LAB
CIRCUIT DIAGRAM:
PROCEDURE:
19
EEE DEPARTMENT POWER SYSTEMS LAB
Model Graph:
Operating Time in
Seconds
20
EEE DEPARTMENT POWER SYSTEMS LAB
2.5
2
Opertating Time (Sec)
1.5
TSM=1
0.5
TSM=2
0
241 242 243 244 245 246 247
Over Voltage (V)
2.5
Opertating Time (Sec)
1.5
1
TSM=1
0.5
TSM=2
0
253.5 254 254.5 255 255.5 256 256.5
Over Voltage (V)
21
EEE DEPARTMENT POWER SYSTEMS LAB
Result: The characteristics of Inverse time Over Voltage relay are obtained.
Viva-Voce:
22
EEE DEPARTMENT POWER SYSTEMS LAB
APPARATUS:
Theory:
Whenever the alternator is subjected to a fault, the power flow might be
reversed, i.e., the power might flow from the system to the synchronous machine,
making the alternator run as synchronous motor. This motoring action can be
identified by the reversal of power flow and can be detected by a reverse power relay.
So the reverse power relay plays a key role in stability and control of the power
system. A reverse power relay can operate to have definite time characteristics or
inverse time characteristics depending on the requirement and design of the relay.
A definite time reverse power relay operates after a pre determine time, when
power flow reverses and is above the pick-up value.
Time setting adjustment: The operating time of a relay can be set at a desired value
using Time Multiplier Setting (TMS). The TMS can be understood by taking a simple
example .suppose that at a particular value of current or plug setting multiplier
(PSM),the operating time is 4sec,with TMS=1.the operating time for the same current
with TMS=0.2 will be 4*0.2=0.8sec. The operating time adjustment help in achieving
coordination between various protection equipment of the system.
Reverse Power (or) Directional Relay: A directional relay is energized by two
quantities namely voltage and current .torque produced on the disc is proportional to
VIcosΦ. The relay is constructed so as to produce positive torque when Φ<900, and
negative torque when Φ >900 (i.e. between 900and 1800, where Φ is the angle between
voltage and current). At a particular relay location when power flow is normal, the
negative torque is produced. Due to any reason if the power reverses the relay
produces positive torque and the relay operates.
23
EEE DEPARTMENT POWER SYSTEMS LAB
Procedure:
1. Connect the circuit as per the circuit diagram
2. Switch on the 3-Φ AC supply.
3. Adjust a suitable value of TSM.
4. Switch on the load and apply some initial load.
5. Keep the DPDT switch in normal position and observe the response of the relay.
6. Now close the DPDT switch to other direction (current terminals are
interchanged.)
7. Observe the time taken by the circuit breaker to trip the circuit by using a stop
watch.
8. Reset the Flag and the procedure is repeated for different loadings and time
settings.
9. Switch off the supply and remove all the connections
Tabular Forms:
Time setting: 10Sec
S. No I(A) T(Sec)
1 3 22
2 4.6 22
3 7.7 22
Model Graph:
Current in A
Precautions:
1. Stop watch should be stopped at the instant of closing the relay contacts (at the
instant of alarm).
2. The neutral point must be properly connected to the variac otherwise it leads to a
short circuit.
60
50
Opertating Time (Sec)
40
30
20 TS=10 Sec
TS=15 Sec
TS=20 Sec
10
0
0 2 4 6 8 10
Current (A)
25
EEE DEPARTMENT POWER SYSTEMS LAB
Result: The characteristics of definite time reverse power relay are obtained for
various time settings.
Viva Questions:
26
EEE DEPARTMENT POWER SYSTEMS LAB
APPARATUS:
THEORY:
When the applied voltage is balanced, the positive and negative sequence of
linear, symmetrical, static devices are identical. Therefore in a transformer the
positive and negative sequence impedances are identical. Even though the zero
sequence impedance may slightly differ from positive and negative sequence
impedance, it is normal practice to assume the zero sequence impedances as equal to
positive and negative sequence impedance.
27
EEE DEPARTMENT POWER SYSTEMS LAB
CIRCUIT DIAGRAM:
28
EEE DEPARTMENT POWER SYSTEMS LAB
PROCEDURE:
TABULAR FORMS:
1 30 21.5 0.805
PRECAUTIONS:
VIVA QUESTIONS:
1. Why the positive and negative sequence impedances are equal for a transformer?
2. How do you find zero sequence impedance theoretically?
3. What is the relationship between sequence impedances of a transformer?
4. Can you define sequence impedances for a 1-phase transformer?
29
EEE DEPARTMENT POWER SYSTEMS LAB
AIM: To find the positive, negative and zero sequence impedances of an Alternator.
APPARATUS:
S. No. Equipment Type Range Qty
1 Voltmeter MI 0-300V 1
2 Ammeter MI 0-10A 1
3 Ammeter MC 0-2A 1
4 Rheostat TCC 300Ω/1.7A 1
5 Rheostat TCC 360Ω/1.6A 1
THEORY:
30
EEE DEPARTMENT POWER SYSTEMS LAB
CIRCUIT DIAGRAM:
31
EEE DEPARTMENT POWER SYSTEMS LAB
PROCEDURE:
32
EEE DEPARTMENT POWER SYSTEMS LAB
TABULAR FORMS:
Positive Sequence:
OC Test
S.NO If(A) VOC(V)
1 0.4 106
2 0.6 148
3 0.8 180
4 1 192
5 1.2 204
6 1.4 210
7 1.5 214
SC Test
S.No. If(A) ISC(A)
1 1.5 7
CALCULATIONS:
Negative sequence:
Zero sequence:
PRECAUTIONS:
1. When starting the motor the rheostat positions should be kept at initial position.
2. At the time of starting the dimmerstat should be kept at minimum position.
VIVA:
1. What are sequence impedance and sequence networks?
2. What is meant by positive, negative and zero sequence impedances?
3. What is meant by positive, negative and zero sequence reactance diagram?
4. What is the relationship between sequence impedances of an Alternator?
5. Why the positive sequence impedance is more than the negative sequence impedance?
34
EEE DEPARTMENT POWER SYSTEMS LAB
Aim:
To develop a computer program to carry out simulation study of a symmetrical three phase short
circuit on a given power system.
Theory:
Short circuits and other abnormal conditions often occur on a power system. Short circuits are
usually called “faults” by power system engineers. Some defects, other than short circuits are
also termed as faults. Faults are caused either by insulation failures or by conducting path
failures. The failure of insulation results in short circuits which are very harmful as they may
damage some equipment of the power system. Most of the faults in transmission and distribution
lines are caused by over voltages due to lightning or switching surges, or by external conducting
objects falling on overhead lines. Over voltages due to lightning or switching surges causes
flashover on the surface of insulators resulting in short circuits. Short circuits are also caused by
tree branches or other conducting objects falling on the overhead lines. The fault impedance
being low, the fault currents are relatively high. The fault currents being excessive, they damage
the faulty equipment and the supply installation. Also, the system voltage may reduce to a low
level, windings and busbars may suffer mechanical damage due to high magnetic forces during
faults and the individual generators in a power station or group of generators in different power
stations may loose synchronism The symmetrical fault occurs when all the three conductors of a
three-phase line are brought together simultaneously into a short–circuit condition as shown in
Figure 1.
This type of fault gives rise to symmetrical currents i.e. equal fault currents with 120 0
displacement. Thus referring to Figure 5.1, fault currents IA, IB and IC will be equal in magnitude,
with 1200 displacement among them. Because of balanced nature of fault, only one phase needs
to be considered in calculations since condition in the other two phases will also be similar.
A three-phase short circuit occurs rarely but it is most severe type of fault involving largest
currents. For this reason, the balanced short-circuit calculations are performed to determine these
large currents to be used to determine the rating of the circuit breakers.
Flowchart for Short Circuit analysis on a PC:
35
EEE DEPARTMENT POWER SYSTEMS LAB
36
EEE DEPARTMENT POWER SYSTEMS LAB
Algorithm:
Step 1: Read line data, machine data, transformer data, fault impedance etc.
Step 2: Compute [Ybus] matrix and calculate [Ybus]modi.
Step 3: Form [Zbus] by inverting the [Ybus]modi.
Step 4: Initialize count I = 0.
Step 5: Find the bus at which fault occurs I=I+1.
Step 6: Compute fault current at faulted bus and bus voltage at all buses.
Step 7: Compute all line and generator currents.
Step 8: Check if I< number of buses, if yes go to step 5 else go to step 9.
Step 9: Print the results and stop the program.
Sample problem:
For a simple power system as shown in figure, find with the help of bus-impedance matrix
method the post fault currents in all the branches and post-fault voltages at all buses, if a three
phase dead short circuit occurs at bus-3. The pre- fault currents are neglected.
37
EEE DEPARTMENT POWER SYSTEMS LAB
PROGRAM:
%Program for Y Bus
clc
clear all
% Initializing line data
x=[0 0+0.13i 0+0.08i
0+0.13i 0 0+0.03i
0+0.08i 0+0.03i 0];
A=[0+0.25i 0+0.2i 0];
% Admittances
nb=3;
v=[1 1 1];
nl=3;
% Number of Buses
for l=1:nb
for m=1:nb
if(l==m)
y(l,m)=0;
for k=1:nb
if(x(l,k)~=0)
y(l,m)=y(l,m)+(1/x(l,k));
end
end
if A(l)~=0
y(l,m)=y(l,m)+1/A(l);
end
end
if(l~=m)
y(l,m)=-1/x(l,m);
end
end
end
disp(y);
z=inv(y);
%Assuming fault at 3rd bus
fb=3;
fi=v(fb)/z(fb,fb);
for i=1:nb
if (i~=fb)
vf(i)=((z(fb,fb)-z(i,fb))/z(fb,fb))*v(i);
else
vf(i)=0;
end
end
for i=1:nb
for j=1:nb
ifl(i,j)=(vf(i)-vf(j))/z(i,j);
end
end
38
EEE DEPARTMENT POWER SYSTEMS LAB
Output:
Y=
0 -24.1923i 0 + 7.6923i 0 +12.5000i
0 + 7.6923i 0 -46.0256i 0 +33.3333i
0 +12.5000i 0 +33.3333i 0 -45.8333i
z=
0.2111 0.1439 0
ifl =
0 0 - 0.6847i 0 - 1.9898i
0 + 0.6847i 0 0 - 1.2501i
0 + 1.9898i 0 + 1.2501i 0
Result: Program has been developed for fault analysis and the results obtained are noted.
VIVA QUESTIONS:
39
EEE DEPARTMENT POWER SYSTEMS LAB
Aim: To determine the sub-transient reactances (xd’’) and (xq’’) of a synchronous machine.
APPRATUS:
S. No. Equipment Type Range Qty
1 Voltmeter MI 0-300V 1
2 Ammeter MI 0-5A 1
3 Ammeter MI 0-1A 1
Circuit Diagram
40
EEE DEPARTMENT POWER SYSTEMS LAB
Theory:
To understand the behavior of an alternator under transient conditions, the armature and field
resistance is assumed to be negligibly small. If all the three phases of unloaded alternator with
normal excitation are suddenly short circuited there will be short- circuit current flows in the
armature. As the resistance is assumed to be zero, this current will lag behind the voltage by
90o and the MMF produced by this current will be along the d-axis. First conclusion is that this
current will be affected by d-axis parameters Xd ,Xd’ and Xd”only. Further, there will be
demagnetizing effect of this current, but as the flux linkage with field cannot change the effect
field current. This additional induced component of field current gives rise to greater excitation
under transient state and results in more short circuits as compared to the steady state short
circuit current. If field poles are provided with damper bars, then at the instant of three phase
short circuit, the demagnetizing armature MMF induces currents in damper bars, which, in turn,
produces field in the same direction as the main field and hence at this instant, the excitation
further increases and gives rise to further increase in short circuit armature current. This is for a
very short duration, normally 3 to 4 cycles and this period is known as sub-transient period.
Since the field voltage is constant, there is no additional voltage to sustain these increased
excitations during sub transient or transient period. Consequently the effect of increased field
current decreases with a time constant determined by the field and armature parameters and
accordingly the short circuit armature current also decays with the same time constant.
41
EEE DEPARTMENT POWER SYSTEMS LAB
In the above figure a symmetrical wave from for armature short circuit current of phase-A.The
DC component is zero in this phase. The reactance offered by the machine during sub transient
period is known as sub transient reactance. Along the direct axis, it is direct axis sub transient
reactance, X"d and along the quadrature axis, it is quadrature axis sub-transient reactance, X”q.
As these reactance are due to the fact that flux linkages in field circuit during sudden
disturbance remain constant, the sub transient reactancesXd” and Xq” can also be defined as
below:
The field structure is assumed to have damper bars on salient poles. The field winding is
initially unexcited and is short – circuited so that field flux- linkage is zero. Armature currents
now are suddenly applied in such time phase that the peak of varying armature m.m.f. wave is
in direct axis. As per constant flux linkage theorem, the flux linkage before this is zero.Hence, it
remains zero just after the application of armature m.m.f. wave and in order to maintain the flux
linkages zero, current are induced in damper bars, additional rotor circuit formed by pole- body
etc. and the field winding. The field of the varying armature m.m.f. is forced to drive the flux
42
EEE DEPARTMENT POWER SYSTEMS LAB
Fig 10.3: Flux path for d-axis sub transient reactance (Xd”)
The armature flux linkage per ampere under these conditions is known as direct axis sub
Fig 10.4: Flux path for q-axis sub transient reactance (X”q)
This also is defined in a manner similar to Xd”, but in this case, armature currents are applied in
such time phase that the peak of varying armature MMF wave is along the quadrature axis. The
43
EEE DEPARTMENT POWER SYSTEMS LAB
damper bars in the quadrature axis force the field of the varying armature M.M.F. to follow the
As before, the flux linkage with q-axis damper bars must remain constant i.e. zero before and
after the sudden application of armature M.M.F. Under these conditions, the armature flux
linkages per ampere is known as q-axis sub transient inductance Lq” and Xq”=ωLq”. To
determine Xd” and Xq” in laboratory, the above mentioned conditions are created there. Two
phases of the three phase alternator are connected in series and the combination is connected to
a low voltage single phase supply. Field winding is short circuited. The rotor is rotated and
brought along the d-axis once. Xd” can be calculated from the armature current and voltage per
phase of armature in this position. Next, rotor is brought along the q-axis position and Xq” is
determined.
Procedure:
2. Set the variac output voltage to zero and switch on the supply.
3. Gradually increase the variac output voltage and set armature current to a suitable value.
4. Slowly rotate the armature and see the field current and armature current readings. Note the
values of applied voltage and armature current when field current is maximum and also when it
is at zero.
5. Repeat step (4) for other applied voltages. Take care that armature current does not exceed its
44
EEE DEPARTMENT POWER SYSTEMS LAB
Observation Calculations
S.No. Armature Current Direct axis Qud. Axis Average Value
Armature subtransient subtransient
reactance reactance
Voltage Xd"=V/IAmax Xq"= V/IAmin
(V) At At
IAmax. IAmin
Volts Amps. Amps. Ohms Ohms X d" Xq"
(Ohms) (Ohms)
1 50 2.4 1.9 26.31 20.83
28.49 19.70
2 60 3.1 2.0 30 19.35
VIVA QUESTIONS
1. What is the difference between salient pole and non-salient pole alternator?
2. Why do transients occur in a power system?
3. What is synchronous impedance?
4. What is the purpose of damper winding in alternator?
45
EEE DEPARTMENT POWER SYSTEMS LAB
APPRATUS:
1. PC
2. MATLAB Software
THEORY:
Bus admittance matrix is often used in power system studies in most of power system
studies it is necessary to form Y-bus matrix of the system by considering certain power system
parameter depending upon the type of analysis. For example in load flow analysis it is necessary
to form Y-bus matrix without taking into account the generator impedance and load impedance.
In short circuit analysis the generator transient reactance and transformer impedance taken in
account, in addition to line data. Y-bus may be computed by inspection method only if there is
no natural coupling between the lines. Shunt admittance are added to the diagonal elements
corresponding to the admittance.
ALGORITHM:
Step 1: Read the values of number of buses and the number of lines of the given system.
Step 2: Read the self-admittance of each bus and the mutual admittance between the buses.
Step 3: Calculate the diagonal element term called the bus driving point admittance, Yii which is
the sum of the admittances connected to bus i.
Step 4: The off-diagonal term called the transfer admittance, Yij which is the negative of the
admittance connected from bus i to bus j.
Step 5: Check for the end of bus count and print the computed Y-bus matrix.
Step 6: Compute the Z-bus matrix by inverting the Y-bus matrix.
Step 7: Stop the program and print the results.
46
EEE DEPARTMENT POWER SYSTEMS LAB
FLOW CHART:
47
EEE DEPARTMENT POWER SYSTEMS LAB
THEORETICAL CALCULATIONS:
48
EEE DEPARTMENT POWER SYSTEMS LAB
PROGRAM:
Output:
VIVA QUESTIONS:
1. Define bus admittance matrix of a power system.
2. Why bus admittance matrix is sparse matrix?
3. Distinguish between bus admittance and bus impedance matrix.
4. State the applications of bus admittance matrix.
49
EEE DEPARTMENT POWER SYSTEMS LAB
Aim :- To develop the MATLAB program for the load flow analysis of the simple power system
network using gauss saidel iterative method
Equipment required
Theory:
In power engineering, the power-flow study, also known as load-flow study, is an
important tool involving numerical analysis applied to a power system. A power-flow study
usually uses simplified notation such as a one-line diagram and per-unit system, and focuses on
various forms of AC power (i.e.: voltages, voltage angles, real power and reactive power). It
analyzes the power systems in normal steady-state operation.
Power-flow or load-flow studies are important for planning future expansion of power
systems as well as in determining the best operation of existing systems. The principal
information obtained from the power-flow study is the magnitude and phase angle of the voltage
at each bus, and the real and reactive power flowing in each line.
Equations:
Pp jQp
S P* E P* I p I p
E *p
n Pp jQ p
I p Y pq * Eq
p 1 E *p
1 Pp jQ p p 1 n
E pk 1
Y pp E *p
Y pq * E ( k 1)
q Y pq * E k
q
q 1 q p 1
Algorithm:
50
EEE DEPARTMENT POWER SYSTEMS LAB
f pk
new tan 1
ek
p
enew V p cos( new )
sp
1 Pp jQ p p 1 n
E pk 1 *
Y pq * E ( k 1)
q pq q
Y * E k
Y pp E p q 1 q p 1
51
EEE DEPARTMENT POWER SYSTEMS LAB
1. Easy to program.
2. Memory/Storage requirement is very low; with sparsity technique memory requirement is
further low.
3. It is easy to enforce Q-limits.
4. Solution time per iteration is low.
5. Easy to simulate generator and line outages.
6. Total solution time is high,
As no. of iterations proportional to size of the system
KN
(GS cannot be used for large systems.)with optimum value of , the number of iterations
for GS, on various test systems are:
5Bus ---- 10 iterations; =1.40
14Bus ---- 17 iterations; =1.55
30Bus ---- 28 iterations; =1.70
57Bus ---- 58 iterations; =1.70
118Bus---- 92 iterations; =1.70
7. Location of the slack bus influences the convergence of GS method.
8. Fails to converge for heavily loading conditions and other ill-conditioned cases.
[Low x/R ‘or’ three winding transformer, series capacitor]
[ Increases with the loading of power system]
9. GS needs optimum -value. [=Acceleration factor].
52
EEE DEPARTMENT POWER SYSTEMS LAB
Procedure:
1 – j4 1 – j4
0.66 - j2.66
2 – j8
PROGRAM:
%program for load flow Analysis using Gauss Siedal Method
clc
clear all
d2r=pi/180;w=100*pi;
%The y-bus matrix is
myb=[3-12i -2+8i -1-4i 0;
-2+8i 3.666-14i -0.665+2.664i -1+4i;
-1+4i -0.666+2.664i 3.666-14i -2+8i;
0 -1+4i -2+8i 3-12i];
% The given parameters and the initial condition are
p=[0;0.5;0.4;0.3];
q=[0;0.2;0.3;0.1];
mv=[1.06;1;1;1];
v=[mv(1);mv(2);mv(3);mv(4)];
acc=1.6; %input('enter the acceleration consatnt:');
%P-Q buses
for b=2:4
tmp1=(p(b)-1i*q(b))/conj(v(b));
tmp2=0;
for k=1:4
if(b==k)
tmp2=tmp2+0;
else
tmp2=tmp2+myb(b,k)*v(k);
end
end
vt=(tmp1-tmp2)/myb(b,b);
v(b)=v(b)+acc*(vt-v(b));
end
fprintf(' voltage magnitudes are\n');
53
EEE DEPARTMENT POWER SYSTEMS LAB
abs(v)
fprintf('\nvoltage angles are\n');
angle(v)
Output:
voltage magnitudes are
1.0600
1.1614
1.1909
1.3134
voltage angles are
0
0.0246
0.0198
0.0571
Result: Program for Gauss – Seidal Load flow has been developed and the results obtained are
observed and recorded.
VIVA QUESTIONS
1. What is the purpose of conducting load flow studies?
2. How are buses classified in a power system?
3. What are the types of buses in a power system?
4. What are the advantages of using Gauss- Seidal method?
5. What are the types of equations in load flow studies?
54
EEE DEPARTMENT POWER SYSTEMS LAB
APPARATUS:
1. Control panel
2. HV transformer
3. Insulator
4. Grounding equipment
5. Capacitor divider
THEORY:
TESTING OF OVERHEAD LINE INSULATORS:
55
EEE DEPARTMENT POWER SYSTEMS LAB
56
EEE DEPARTMENT POWER SYSTEMS LAB
CIRCUIT DIAGRAM:
PROCEDURE:
Power Frequency One Minute Dry Withstanding Test:
1. Switch on the supply and control panel.
2. Using the toggle switches energize LT and HT windings of transformer
3. Using the UP and Down Toggle switches in the control panel apply voltage to the HVAC
transformer till 1.6 times rated voltage of the insulator and is read through voltmeter on
control panel.
4. Wait for one minute.
5. If no rupture or traces of cracking or chipping of the material is found then the test is
passed. Otherwise it is failed.
6. Reduce the voltage to zero using the toggle switches and switch of the control panel.
7. Earth the HT apparatus.
PRECAUTIONS:
1. Before and after completion of the test, earth the apparatus using the earthing rod.
2. Ensure the gate is closed otherwise Control Panel cannot be switched ON.
3. Turn ON mains and keep key in ON position on the control panel otherwise the HV
transformer can’t be energized.
RESULT: One minute dry withstand test on insulator is conducted and the breakdown voltage is
observed as 17.8kV. Flashover is observed at 47.06kV.
VIVA QUESTIONS:
1. What is disruptive discharge voltage?
2. What is Flashover?
57
EEE DEPARTMENT POWER SYSTEMS LAB
3. What is puncture?
4. What is withstanding voltage?
5. What are self restoring and Non self restoring insulation?
6. What are Type Test and Routine test?
7. What are the various High voltage tests done on insulations?
58
EEE DEPARTMENT POWER SYSTEMS LAB
59
EEE DEPARTMENT POWER SYSTEMS LAB
CIRCUIT DIAGRAM:
PROCEDURE:
Power frequency one minute dry withstanding test
1. Switch on the supply.
2. Using control panel apply voltage to the HVAC transformer till 1.6 times rated voltage of the
insulator and is read through voltmeter on control panel.
3. Wait for one minute.
4. If no puncher is found then the test is passed. Otherwise it is fail.
5. Reduce the voltage to zero to HVAC transformer and switch of the control panel.
PRECAUTIONS:
1. Before and after completion of the test earth the operators.
RESULT: One minute dry withstand test is conducted on a cable and the breakdown voltage is
18.27kV and Flashover is observed at 44.26kV.
VIVA QUESTIONS:
1. What are the necessities of High Voltage Testing?
2. What is disruptive discharge voltage?
3. What is Flashover?
60
EEE DEPARTMENT POWER SYSTEMS LAB
4. What is puncture?
5. What is withstanding voltage?
6. What are the various High voltage tests done on cables?
61
EEE DEPARTMENT POWER SYSTEMS LAB
THEORY:
CORONA: When an alternating potential difference is applied across two conductors whose
spacing is large as compared to their diameters, there is no apparent change in the condition of
atmospheric air surrounding the wires if the applied voltage is low. However, when the appplied
voltage exceeds a certain value, called crical disruptive voltage, the conductors are surrounded
by a faint violet glow called corona.
The phenomenon of violet glow, hissing noise and production of ozone gas in an
overhead transmission line is known as corona.
If the conductors are polished and smooth, the corona glow will be uniform throughout
the length of the conductors, otherwise the rough points will appear brighter. With d.c. voltage,
there is difference in the appearance of the two wires. The positive wire has uniform glow about
it, while the negative conductor has spotty glow.
CORONA FORMATION: Some ionization is always present in air due to cosmic rays, ultra
violet radiations and radio activity. Therefore, under normal conditions, the air around the
conductors contains some ionized particles (i.e., free electrons and positive ions) and neutral
molecules. When potential difference is applied between the conductors, potential gradient is set
up in the air which will have maximum value at the conductor surfaces. Under the influence of
potential gradient, the existing free electrons acquire greater velocities. The greater the applied
voltage, the greater the potential gradient and more is the velocity of free electrons.
62
EEE DEPARTMENT POWER SYSTEMS LAB
When the potential gradient at the conductor surface reaches about 30KV per cm
(maximum value), the velocity acquired by the free electrons is sufficient to strike a neutral
molecule with enough force to dislodge one or more electrons from it. This produces another ion
and one or more free electrons which is turn are accelerated until they collide with other neutral
molecules, thus producing other ions. Thus, the process of ionization is cumulative. The result of
this ionization is that either corona is formed or spark takes place between the conductors.
In order that corona is formed, the value of g must be made equal to the breakdown
strength of air at 76 cm pressure and temperature of 25o C is 30 KV/cm (max) or 21.2KV/cm
(r.m.s) and is denoted by go. If Vc is the phase-neutral potential required under these conditions,
then,
Where
The above expression for disruptive voltage is under standard conditions i.e., at 76 cm of Hg and
25o C.However, if these conditions vary, the air density also changes, thus altering the value of
go. The value of go directly proprotional to air density. Thus the break down strength of air at a
barometric pressure of b cm of mercury and temerature of to C becomes δgo where
63
EEE DEPARTMENT POWER SYSTEMS LAB
Correction must also be made for the surface condition of the conductor. This is accounted for by
multiplying the above expression by irregularity factor mo.
VISUAL CRITICAL VOLTAGE: It is the minimum phase-neutral voltage at which corona glow
appears all along the line conductors.
It has been seen that in case of parallel conductors, the corona glow does not begin at the
disruptive voltage vc but at higher voltage vv, called Visual critical voltage. The phase-neutral
effective value of visual critical voltage is given by the following empirical formula:
Where mv is another irregularity factor having a value of 1.0 for polished conductors and
0.72 to 0.82 for rough conductors.
a) Atmosphere: During stormy or rainy weather corona occurs at much less voltage as compared
with fair weather. Because, ion density around the conductors is much more than that during fair
weather.
b) Conductor Size: The unevenness of the surface of the conductors decreases the breakdown
voltage. Because of this reason with low voltage the insulation will breakdown and create sparks
and corona. That’s why solid conductors are used mostly instead of stranded conductors to
reduce the corona.
64
EEE DEPARTMENT POWER SYSTEMS LAB
c) Spacing between conductors: Larger the gap between the conductors lesser the corona.
d) Line voltage: Every line voltage has a limit. After that limit breakdown will occur and will
create corona and spark. So with the application of small line voltage possibility of occurring
corona is lesser.
CIRCUIT DIAGRAM:
PROCEDURE:
1. Switch on the supply.
2. To set short-circuit time delay in the control panel.
3. Using control panel apply voltage to the HVAC transformer till hissing noise hearing
note down critical disruptive voltage.
4. Again increasing the apply voltage till visual the glow with hissing noise note down
visual critical voltage.
5. Again increasing the apply voltage till break down occur note down the break down
voltage.
6. Reduce the voltage to zero to HVAC transformer and switch of the control panel.
PRECAUTIONS:
1. Before and after completion of the test earth the operators.
RESULT: High voltage AC is applied across an insulator and the visual corona is observed at
43.03kV.
65
EEE DEPARTMENT POWER SYSTEMS LAB
VIVA QUESTIONS:
1. Define Corona phenomena?
2. What type of current drawing by the line during the affect of corona loss?
3. What are the advantages of corona loss?
4. How to minimize the corona loss?
5. What is critical disruptive voltage?
6. What is visual critical voltage?
66
EEE DEPARTMENT POWER SYSTEMS LAB
Aim: To simulate and study a single line to ground fault of a simple power system using
MATLAB/SIMULINK
Apparatus:
1. PC
2. MATLAB Software
Theory: Fault studies on a power system cannot be avoided as the power system is exposed to
atmosphere, which is not under the control of human beings. To avoid damage to the
equipment and to have proper control of the power system, the faulty portion of the system
has to be quickly isolated. For design and choice of power system protection equipment and
switch gear, the fault levels of the system for various kinds of faults have to be known prior
to the erection of the lines. The fault studies are a tool for the engineer to study and calculate
various fault levels in the system.
The study of single line to ground fault on a simple power system is studied by
building a simple power system containing a generator connected to infinite bus through two
transmission lines. The fault is created on a transmission line and the change in voltage,
current and power at the buses can be studied. The simulation and modeling of the system
can be done on Simulink available in MATLAB.
Simulink is a block diagram environment for multi domain simulation and Model-
Based Design. It supports system-level design, simulation, automatic code generation, and
continuous test and verification of embedded systems. It is integrated with MATLAB, which
enables the user to incorporate MATLAB algorithms into models and export simulation
results to MATLAB for further analysis.
Circuit diagram:
67
EEE DEPARTMENT POWER SYSTEMS LAB
Procedure:
1. Open MATLAB
2. Open simulink browser.
3. Create a new ‘.mdl’ file
4. Open ‘simpower systems library’.
5. Copy the required components on to the file from the library.
6. Build the circuit as per the circuit diagram.
7. Save and Run the simulation Model.
8. Observe the obtained plots and take a print out of the graphs.
Precautions:
68
EEE DEPARTMENT POWER SYSTEMS LAB
Result: A line to Ground fault has been simulated using SIMULINK and the waveforms are
obtained.
69
EEE DEPARTMENT POWER SYSTEMS LAB
Viva-Voce:
1. What are the advantages and disadvantages of using MATLAB/Simulink for modeling and
simulation?
2. What are different kinds of faults in a power system? And what are their causes?
3. What is meant by short, medium and long transmission line? What are their approximate
lengths?
4. What is the effect of neutral grounding on the system voltages and fault current levels?
70