You are on page 1of 25

Gate valve

TYPE: "BW CL 800 (½”) "

THE PASSPORT

When the equipment is transferred to another owner, along with the equipment is transferred
real passport

2020
CONTENT

Section 1. General instructions 3

Section 2. Product basics four

Section 3. Basic technical data 6

Section 4. Completeness 7

Section 5. Resources, life and storage life, and manufacturer's warranties 9

Section 6. Conservation ten

Section 7. Packaging Details eleven

Section 8. Certificate about acceptance 12

Section 9. Product movement during operation 15

Section 10. Repair and accounting of work according to bulletins and instructions
19

Section 11. Technical examination results 22

Section 12. Notes on use and storage 23

Section 13. Disposal information 24

Section 14. Special notes 25

2
Section 1. General instructions

1. Before using the equipment, carefully read the Operation and Maintenance Manual.

2. This passport must be kept with the equipment at all times.

3. When writing in the passport, writing in pencil is not allowed.

4. An incorrect entry should be carefully crossed out and a new one should be written next to it,
which is certified by the person responsible for the operation of the equipment, indicating his
name and position.

5. When the equipment is transferred to another enterprise or to another owner, the final
summarizing records of its operating time are certified by the seal of the enterprise
transferring the equipment.

3
Section 2. Product basics

Valve name Gate valve

Appointment Adjusting the flow of the working medium


Type, model of reinforcement "BW CL 800"
Micon Engineers (Hubli) Pvt Ltd
India, Plot No: C-255, MT Sagar Industrial Estate, Ist
Fittings manufacturer
Gate Gokul Road, (Airport Road), Hubli-580 030,
Karnataka
Valve serial number V593
Valve production date 2020

4
TR CU Declaration of Conformity

Document Number
Validity
Issuing authority
Certification information

Designation of documents
(international rules) for
TR CU 010/2011 "On the safety of machinery and
compliance with which
certification was carried out equipment"
(issuance of permits for use)

5
Section 3. Basic technical data

3.1. Specifications

Parameter name Value

Operational and design parameters of reinforcement


Working environment Air
Nominal diameter, DN, mm 15
Maximum allowable working pressure, MPa 15.2
Test pressure, MPa 20.5
Working temperature (min / max),FROM From minus 48 to 350
Design temperature, ° С -
Weight, kg -
Service life, years 20
Shutter tightness AND
Type of connection to the pipeline Flanged

6
Section 4. Completeness

Product amount Type / Serial


product name Note
designation number

4.1. Main parts:

Gate valve one BW CL / V593 -

7
4.2. Operational documentation:

P/p Documentation Name


No. designation documentation
one - Valve passport
2 - Installation and operating instructions for valves

8
Section 5. Resources, life and storage life, and manufacturer's warranties

Product resource to the first


capital
(medium, capital)

Renovation

5 years
(parameter characterizing the operating time)

over a service life of 20 years, including a shelf life of 1 year


__________________________ in the manufacturer's packaging
__________________________
(in the preservation (packaging) of the manufacturer,

__________________________ in the warehouse __________________________


in warehouses, in open areas, etc.)

Overhaul life
10,000 h.
(parameter characterizing the operating time)

at annual repair (s) during the service life 20 years.


The indicated resources, service life and storage are valid provided that the consumer observes
the requirements of the current operational documentation.

MANUFACTURER'S WARRANTY:

Gate valve, model BW CL

Micon Engineers (Hubli) Pvt Ltd guarantees that the BW CL valve will perform as designed,
subject to the customer's compliance with the operating documentation requirements.

9
Section 6. Conservation

Validity
Position, surname and
the date Job title period,
signature
month

10
Section 7. Packaging Details

PACKING CERTIFICATE

Gate valve
(product name)

BW CL No. V593
(designation) (factory number)

Packed
Micon Engineers (Hubli) Pvt Ltd
(manufacturer's name or code)

according to the requirements stipulated in the current technical documentation.

M.P.
Quality engineer
___________________
(position) (personal signature) (signature decryption)

(year, month, day)

11
Section 8. Certificate of acceptance

CERTIFICATE OF ACCEPTANCE

Gate valve
(product name)

BW CL No. V593
(designation) (factory number)

manufactured and adopted in accordance with the mandatory requirements of state standards,
current technical documentation and recognized as fit for use

Test Test
Wedne Test the
Test and control type pressure, temperat Result
sday duration date
MPa ure

Monitoring compliance
with technical double 2020
requirements
Marking control double 2020
Visual inspection double 2020
Material testing double 2020
Hydraulic tests Water 20.5 - - double 2020
Pneumatic tests double 2020

Leak test double 2020

Functional trials double 2020

12
CERTIFICATE OF ACCEPTANCE

Gate valve
(product name)

BW CL No. V593
(designation) (factory number)

M.P.
Head of Quality Control Department
___________________
(position) (personal signature) (signature decryption)

(year, month, day)

M.P.
Head of the enterprise
___________________
(position) (personal signature) (signature decryption)

(year, month, day)

13
Section 9. Product movement during operation

9.1. Product movement during operation

Running time Signature


of the
Reason
Manufact person who
Where Withdra from the since after for
uring carried out
installed wal date beginning of the last withdraw
date the
operation renovation al
installation
(removal)

15
Running time Reason Signature
Manufact of the
Where Withdra from the since after for
uring person who
installed wal date beginning of the last withdraw
date carried out
operation renovation al
the

16
9.2. Receiving and handing over the product

Basis (name, number Company, position and


the Product
and date of the signature Note
date condition
document)
passed adopted

17
9.3. Information on securing the product during operation

Base
product name Position,
(name, number and date of the
(component part) surname and Note
document)
and designation initials
anchorage detach

18
Section 10. Repair and accounting of work according to bulletins and
instructions

Position, surname and signature


Bulletin Summary Deadline for date of
who completed who checked
number of work completion completion
the work the work

19
Position, surname and signature
Bulletin Summary Deadline for date of
who completed who checked
number of work completion completion
the work the work

20
Position, surname and signature
Bulletin Summary Deadline for date of
who completed who checked
number of work completion completion
the work the work

Section 11. Technical examination results


21
Survey results Should. and
Date of External Hydraulic signature of
survey Documentation Internal the person,
examinatio (pneumatic)
check inspection wire. work
n trials

22
Section 12. Notes on use and storage

the date Disposal information Notes (edit)

Section 13. Disposal information

23
The decision on disposal is made after a set of measures, including an examination of the
state of the reinforcement, an assessment of the residual resource.

24
Section 14. Special marks

__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________

25
(on the back of the last page)

This passport contains numbered and laced sheets

________________________
(signature) (decryption of signature)

M. P.
"____" __________ 20 __

You might also like