Professional Documents
Culture Documents
Schedule of Requirements
Delivery shall take place in compliance with the dates, duration, and locations indicated below:
Delivery Date
Line Item Final
Description of Physical Final
Quantity Destination as Earliest
No Goods unit Delivery
specified in BDS Delivery Date
Date
1. 2 3 4 5 6 7
Motorized
Electric
1 Units 2
hemispherical
valve DN 200
Pressure
2 Units 2
reducing valve
Gate valve
3 Units 4
DN300
Gate valve
4 Units 2
DN200
5 Gate valve DN80 Units 2
Gate valve DN80
6 with opening Units 2
indicator
Check valve
7 Units 1
DN80
Gate valve
DN150 with Store of UT3A As early as 180 days
8 Units 2
opening HPS from
possible
indicator signing the
contract
Gate valve
9 Units 4
DN100
Gate valve
DN100 with
10 Units 2
opening
indicator
Spherical Ball
valve DN150
11 Units 2
with opening
indicator
Note: The date of effectiveness of contract shall be as of signing the contract.
81
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
3. Technical Specification
3.1 Introduction
NEA, Upper Trishuli 3A Hydro Power Station, Salletar, Rasuwa intends to purchase different
Valves for Power house's Technical water supply system.
The manufacturers of the GOODS supplied under this contract must have valid ISO 9001
certificate and the quality of the GOODS must meet according to ISO/SAE/AWS/ASTM/
BS/DIN/NS/IS or equivalent international standards from all respect. The Bidders are strictly
advised to submit the original Product’s technical Data Sheet, other specifications of relevant
manufacturer that will be helpful in judging the quality. The NEA reserves the right to decline
the acceptance of proofs which to its own judgment are not convincingly satisfying for the
intended use.
NEA's Requirements
S.N. Items Bidder's Offer Remarks
Descriptions Requirements
Motorized Country of
Must Specify
Origin
Electric
1 hemispherical Manufacturer Must Specify
82
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Assembly ) following:
a. Supply and
delivery
b. Factory Inspection
test before dispatch
c. Site acceptance
test
d. Installation
e. commissioning,
testing and linking
with main SCADA
system of the plant
The assembly should
contain following:
a. valve body
Assembly
b. actuating motor
components
c. control system
d. wire and cables
e. others as required
Valve body
PQ940F-25 or
Model
equivalent
Nominal
DN200 (mm)
diameter
Valve fitting
285mm (±1% tol.)
width
Bolts hole in
As per site
flange
83
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Stainless steel
housing and Cast
Material iron disc or as per
actual site (Ut3A)
valve
Actuating
motor
Actuating motor YDF-WF or
model equivalent
Control system
Should operate by
Operation SCADA of UT3A
HPS
Others
84
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Following spare
items should be
supplied :
a. Steel reinforced
Spare Supply gasket – 6Nos.
b. SS bolts 8.8 grades
30 Nos.
c. Mechanical
Packing seal – 4Nos.
Manufacturer's Must be submitted
authorization during bidding
ISO certificate
Quality/Standard should be submitted
during bidding
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Test a. Factory test
requirements b. Site acceptance
test
c. Installation
d. commissioning,
testing and linking
with main SCADA
system of the plant
85
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Reducing Origin
Valve
Manufacturer Must specify
(Complete
Assembly ) The Contractor must
perform the
following:
a. Supply and
delivery
b. Factory Inspection
test before dispatch
Scope of works
c. Site acceptance
test
d. Installation
e. commissioning,
testing and linking
with main SCADA
system of the plant
The assembly should
contain following:
a. valve body
Assembly b. Controlling
components components
c. Pressure switch
d. wire and cables
e. others as required
Valve body
ZJY46H-25P-Q1 or
Valve model
equivalent
86
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Nominal
DN200
diameter
0.45-0.5Mpa
Outlet Pressure
(adjustable)
Medium Water
Valve fitting
593mm (0.5% tol.)
width
Cooling water supply
Location line after Electric
Valve
Controlling
Components
It should contain:
a. Main control valve
Major (elec./Mech)
controlling b. Jet pump
components c. Directional valves
d. Pipes lines and
pressure gauge
Pressure
transmitter
MPM583 Digital
Model display pressure
switch
Others
87
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other bolt holes and size
requirement should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
components:
a. Steel reinforced
gasket – 6Nos.
b. SS bolts 8.8 grades
-30Nos (for
Coupling)
Spare Supply
c. Main control valve
– 4Nos.
d. Jet pump – 4Nos.
e. Directional valve –
2 complete set (all)
f. Pressure gauge – 2
set (inlet and outlet
side two each)
Manufacturer's Must be submitted
authorization during bidding
ISO certificate
Quality/Standard should be submitted
during bidding
88
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Stainless steel or
equivalent to site
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Test a. Factory test
requirements b. Site acceptance
test
c. Installation
d. commissioning,
testing and linking
with main SCADA
system of the plant
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Gate Valve
3 Scope of works b. Site acceptance
DN300
test
d. Installation and
commissioning and
testing of at least one
Valve
Z41H-16C or
Model
equivalent
Nominal DN300 (mm)
89
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
diameter
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
Valve fitting 500mm (1%
width tolerance)
16 bolt
Bolts hole in symmetrically. It
flange should match with
actual site fitting
Cooling water supply
from Penstock
Fitting location
tapping through 300
mm pipe tapping line
The valve should be
operated manually. It
is used for either
Functional
complete opening of
requirements
closing condition at
pressured water flow
condition
The supplied
component should be
Specific
identical or
requirement
equivalent to site's
component.
a. Valve shall be
fitted by supplier at
site. The bolt holes
and size should
Other match exactly at the
requirement location
b. Supplier should
provide complete
drawing and catalog
along with goods
90
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
Gate Valve
4
DN200 a. Supply and
Scope of works delivery
b. Site acceptance
test
d. Installation and
commissioning and
91
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
92
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
components for each
valve::
a. Steel reinforced
Spare Supply gasket – 6Nos.
b. SS bolts 8.8 grades
-30Nos (for
Coupling)
c. Mechanical seal- 2
set for each valve
ISO certificate
Quality/Standard
should be submitted
a. Body bonnet-
WCB
b. Gate –WCB
Materials c. Valve Stem-
WCB/2Cr13
d. Stem Nut –
Ductile iron or Brass
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Country of
Must specify
Origin
Gate Valve
5
DN80 Manufacturer Must specify
Scope of works The Contractor must
93
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
perform the
following:
a. Supply and
delivery
b. Site acceptance
test
d. Installation and
commissioning and
testing of at least one
Valve
Model Must specify
Nominal
DN80 (mm)
diameter
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
278 mm (1% tol.)
Valve fitting
width Measure at site
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Fire fighting pump
Fitting location
water intake line
The valve should be
operated manually. It
is used for either
Functional
complete opening of
requirements
closing condition at
pressured water flow
condition
94
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
equivalent to site's
component.
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other bolt holes and size
requirement should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
components for each
valve:
a. Steel reinforced
Spare Supply gasket – 6Nos.
b. SS bolts 8.8 grades
-20Nos (for
Coupling)
c. Mechanical seal- 2
set
ISO certificate
Quality/Standard
should be submitted
Valve body and
Casing Should be of
Materials
Stainless steel or
equivalent to site
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
95
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Scope of works b. Site acceptance
test
d. Installation and
commissioning and
testing of at least one
Valve
Gate Valve Model Must specify
DN80 with
6 Nominal
opening DN80 (mm)
diameter
indicator
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
205 mm (1% tol.)
Valve fitting
width
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Fire fighting pump
Fitting location
water outlet line
The valve should be
operated manually. It
Functional is used for either
requirements complete opening of
closing condition at
pressured water flow
96
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
condition
The supplied
component should be
identical or
Specific
equivalent to site's
requirement
component. It should
contain opening
indicator.
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other bolt holes and size
requirement should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
components for each
valve:
a. Steel reinforced
Spare Supply gasket – 6Nos.
b. SS bolts 8.8 grades
-20Nos (for
Coupling)
c. Mechanical seal- 2
set
ISO certificate
Quality/Standard
should be submitted
Valve body and
Casing Should be of
Materials
Stainless steel or
equivalent to site
Product catalog To be submitted
(Similar during bidding
97
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Scope of works b. Site acceptance
test
d. Installation and
commissioning and
testing of at least one
Check Valve
7
DN80 Valve
DRUZ-160 or
Model
equivalent
Nominal
DN80 (mm)
diameter
Class 1.6 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
Valve fitting 175 mm (1% tol.)
width
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Fitting location Fire fighting pump
98
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
99
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Scope of works b. Site acceptance
test
d. Installation and
commissioning and
testing of at least one
Gate Valve
DN150 with Valve
8
opening
indicator ZK45X-10Q or
Model
equivalent
Nominal
DN150 (mm)
diameter
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
263 mm (1% tol.)
Valve fitting
width
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Cooling water supply
Fitting location
safety line
100
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
101
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Scope of works b. Site acceptance
test
d. Installation and
Gate Valve
9
DN100 commissioning and
testing of at least one
Valve
Model Must specify
Nominal
DN100 (mm)
diameter
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
Valve fitting 300mm (1% tol.)
width
102
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Cooling water supply
Fitting location
filter backwash line
The valve should be
operated manually. It
is used for either
Functional
complete opening of
requirements
closing condition at
pressured water flow
condition
The supplied
component should be
Specific
identical or
requirement
equivalent to site's
component.
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other bolt holes and size
requirement should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
components for each
valve:
a. Steel reinforced
Spare Supply gasket – 6Nos.
b. SS bolts 8.8 grades
-20Nos (for
Coupling)
c. Mechanical seal- 2
103
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
set
ISO certificate
Quality/Standard
should be submitted
Valve body and
Casing Should be of
Materials
Stainless steel or
equivalent to site
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
following:
a. Supply and
delivery
Gate Valve
Scope of works b. Site acceptance
DN100 with
10 test
opening
d. Installation and
indicator
commissioning and
testing of at least one
Valve
Model Must specify
Nominal
DN100 (mm)
diameter
Class 1.0 MPa
Working 1.5 MPa
104
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Pressure
Temperature less than 80 deg. C
Valve fitting 230mm (1% tol.)
width
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Cooling water supply
Fitting location
filter backwash line
The valve should be
operated manually. It
is used for either
Functional
complete opening of
requirements
closing condition at
pressured water flow
condition
The supplied
component should be
identical or
Specific
equivalent to site's
requirement
component. It should
contain opening
indicator.
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other bolt holes and size
requirement should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
along with goods
Should Supply
following spare
Spare Supply components for each
valve:
a. Steel reinforced
105
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
gasket – 6Nos.
b. SS bolts 8.8 grades
-20Nos (for
Coupling)
c. Mechanical seal- 2
set
ISO certificate
Quality/Standard
should be submitted
Valve body and
Casing Should be of
Materials
Stainless steel or
equivalent to site
Product catalog To be submitted
(Similar during bidding
product) process
Dimensional It should fit
requirement accurately at site
without modifying
the existing system.
Country of
Must specify
Origin
Manufacturer Must specify
The Contractor must
perform the
Spherical
following:
Ball Valve
a. Supply and
11 DN150 with
delivery
opening
Scope of works b. Site acceptance
indicator
test
d. Installation and
commissioning and
testing of at least one
Valve
106
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
0341F-25P or
Model
equivalent
Nominal
DN150 (mm)
diameter
Class 1.0 MPa
Working
1.5 MPa
Pressure
Temperature less than 80 deg. C
Valve fitting 355 mm (1% tol.)
width
8 bolt symmetrically.
Bolts hole in
It should match with
flange
actual site fitting
Spiral case drainage
Fitting location
line
The valve should be
operated manually. It
is used for either
Functional
complete opening of
requirements
closing condition at
pressured water flow
condition
The supplied
component should be
identical or
Specific
equivalent to site's
requirement
component. It should
contain opening
indicator.
a. Valve shall be
fitted by supplier at
site without
modifying the
existing system. The
Other
bolt holes and size
requirement
should match exactly
at the location
b. Supplier should
provide complete
drawing and catalog
107
UT3AHPS-2080/081-MST-01 Section V. Schedule of Requirements
Notes:
Bidders are strictly advised to complete the TECHNICAL DATA SHEET and submit the
detail catalogue that justifies the filled data, as required; otherwise, the BID might be
treated as NON-RESPONSIVE BID.
Non-acceptance by the bidder for the requirement mentioned as above Technical Data
Sheet shall consider being non-responsive bid.
The GOODS and services supplied under this contract should meet the relevant
equivalent standard in all respect of engineering design, manufacturing and operation
point of view.
Locally casted and made valve are not accepted
1. A pre-dispatch inspection of the manufactured Valves shall be done for BOQ 1 and 2
items only.
108