Professional Documents
Culture Documents
Cement Production
CLIENT : NEOM
TABLE OF CONTENTS
SECTION CONTENT PAGE
1 SCOPE OF WORK
2 MOBILIZATION
4 MATERIAL REQUIREMENTS
7 RESPONSIBILTIES
9 FINAL INSPECTION
10 MANPOWER REQUIREMENT
12 PLANT INSTALLATION
Al-MUHAYLIB Group Co. Cement Production
2.0 MOBILIZATION
2.1) SCOPE:
The scope of work described in this statement is applicable for site mobilization
works for all works.
Lifting plan.
Lifting sequence.
Site Location.
DRWAING
Proposed location for Client office, Engineering office, Site laboratory, Warehouse, Workshop.
Plumbing Layout Diagram Activity Hazard Analysis
It is a continuous and unobstructed way of exit travel from any point in a building or
structure to a public way, and consists of three separate and distinct parts:
1- The way of Exit access, Is that portion of a means of egress which leads to an
entrance to an exit
2- The Exit, Is that portion of a means of egress which is separated from all other
spaces of the building or structure by construction or equipment to provide a
protected way of travel to the exit discharge
3- The Exit discharge, Is that portion of a means of egress between the termination of
an exit and a public way. Must lead directly outside or to a street, walkway, refuge
area, public way, or open space with access to the outside . . .(This area) must be large
enough . . .
- Welfare Facilities
- Emergency Signs to be Installed
7.) RESPONSIBILITIES
- Fully responsible to supervise the dismantling and erection of the batch plant
by following the procedure and to make sure the safety of his team to finish the
work on safe and to meet the schedule.
- To monitor the daily activities of the erection team and ensure all work done
according to safety policy
- Ask to conduct daily housekeeping to avoid from, slip, trip and fall hazards.
Al-MUHAYLIB Group Co. Cement Production
I- METHOD OF BP ERECTION
6 12 hours Fixing of steel beam supports for central drum mixer 2 units-50 ton
crane
7 (2nd day) Erecting central drum mixer.
9.1) to be carried out by operation and informed Al Rajhi for schedule of Final Inspection
10.1) STAFF
* Mobile Cranes
* Trailer trucks
* Generator Set
* Welding Machine
* Risk Assessment
The installation site should be leveled with a solid foundation and the pit in the ground should be slightly
above the ground to prevent the water flowing into the pit. In addition, the bearing capability of the
Al-MUHAYLIB Group Co. Cement Production
foundation should reach the required demand to avoid the influence on equipment operation caused by
late sedimentation.
Use cranes to hoist the mixer hoist. The four legs, cross bracing, diagonal bracing, ladders, and up and
down tracks of the main structure should be installed aligning with the pits. The equipment should be
positioned in the same horizontal plane and the track frame shall not be twisted and misaligned.
You also should consider whether the ancillary projects like power, water, rainproof measures and
transport corridors of the materials sites meet the mix requirements. The supporting legs and the
embedded part should be welded firmly and there should be no impurity in the welding seam.
The supporting legs must be vertical to support the mixer weight. The diagonal bracing must be firmly
welded and fastened with the supporting legs to ensure the mixer's integrity.
preliminarily and according to the import and export position try to keep the interface tube in a vertical
position. After the interface tube is welded, and then fixed conveyor finally.