Professional Documents
Culture Documents
AC1900736
ASSIGNMENT #8
The installation of a sewer line includes the first step of determining how far the pipe
needs to go and the various depths that each end of the pipe. Depth of each end can also
be referred to the elevation. The sewer pipe starts where the residential unit main drain
exits the foundation and slopes to a connection on the main sewer line called a tap. The
slope or gradient of the flow line is a factor to consider in the flow capacity of diameter
of the pipe being used. Finding the proper slope is critical to the design of the sewer. This
information can be found on the engineering drawings, and are accessible to the
contractor, who has to excavate to the indicated depth. Pipes on steeper slopes have larger
capacities versus those on shallow slopes. Slopes should have a minimum of 2 feet of
drop per 100 feet run. Too steep a slope and the liquid will flow too quickly leave the
solids behind, and a slope that is too gentle does not allow for proper drainage due to low
velocity.
At each instance where a sewer changes in diameter of the pipeline, or slope or direction,
a manhole is a necessary. The distance between two manholes is called the reach. These
chambers allow for maintenance and inspection of the sewer line and are built from
reinforced concrete or masonry units. Inspection of the sewer may also include sampling
and measuring the flow. To guide the builder in placing the pipeline at the right slope, he
refers to the invert elevation at the end of each reach. The invert point can be found on
Batter boards are used to use to temporarily mark out or reference building corners or
other structures such as slabs and foundations. Another use of this simple horizontal
wooden plank, supported by two vertical posts, is to give line and grade for the flow of
the pipeline. To locate the pipes, stakes are placed intervals of fifty feet and there is also
an offset between three and six feet from that center line of the pipe. Batter boards also
have the function of controlling grade and line of works and is used by both the builder or
the surveyor. Batter boards are built away from the corners and in that way the opposite
boards support whatever material is used to make the line whether it be wire, building
twine/carpenter’s line. This line is so run, so as to fall directly in the center of the
pipeline. The boards themselves are at a constant level above the pipeline or works that is
being marked out. With the advent of technology lasers are used more and more.
Surveyors are taught to use notebooks to store field data, even when modern day
technology allows for electronic storage. The devices used such as transits, total station,
or a theodolite are used for measurement of distances and angles and offer means to store
and manipulate data. When it comes to field notes, redundancy is key. These books are so
ruled to appropriately organize the data collected. The entries must be legible and a
timestamp is necessary for each entry. If there is an error with an entry it must be neatly
lined out and corrected. The error should remain legible after the correction is done, per
adventure there would be a need to refer to it. A profile drawing is a graph illustration of
must be proper labels for each axis of the graph complete with dates and other useful
information.
Sewer trench excavation is dug between two points, and as previously stated this length is
called the reach. The excavation process must be done properly so as to not disturb the
soil above and around the trench. After compacting the bottom of the trench, a sand bed
is laid to offer proper support throughout the length of the pipe. Sand is also very good at
Nathanson J., Lanzafama M.T., Kissam P., 2011, Surveying Fundamentals and