The Ho Chi Minh Green Transport Development Project

Detailed Design Report

APPENDIX 10-19: DESIGN REPORT OF


FOOTBRIDGE NO.19

(NEW STEEL FOOTBRIDGE - Km 3+139.95)

Table of Contents

APPENDIX 10-19: DESIGN REPORT OF FOOTBRIDGE NO.19 ....... 1


INTRODUCTION ...............................................................................................................2

DESIGN OF SUPERSTRUCTURES .................................................................................3


MAIN GIRDER GEOMETRY ...................................................................................3
SLENDERNESS EFFECTS .......................................................................................5
CHECKING COMPONENT ......................................................................................6

DESIGN OF SUBSTRUCTURE ......................................................................................42


Geometry ...................................................................................................................42
CHECKING COMPONENT ....................................................................................44

DESIGN OF CONNECTION ...........................................................................................65


Welding .....................................................................................................................65
Bolts connection ........................................................................................................74

DESIGN OF CONCRETE SUBSTRUCTURE ..............................................................122


PILE CAP DESIGN ................................................................................................122
PILE DESIGN – TYPE B .......................................................................................140
PILE DESIGN OF STAIRCASE ............................................................................146

Joint Venture of MVA Hong Kong Limited and SYSTRA S.A. Page A1
The Ho Chi Minh Green Transport Development Project
Detailed Design Report

INTRODUCTION

Footbridge No.19, located at Km3+139.95, is new steel footbridge. The works proposed for this
bridge is to construct new bridge structures and access staircases for pedestrian passengers. Roof will
be also constructed on the bridges and staircases in harmonizing with overall architectural concept
of BRT project.
This report presents the detail design of the main structures of footbridge. For staircases and roof
design, refer to APPENDIX 21. DESIGN OF STEEL STAIRCASE AT STEEL FOOTBRIDGE
and APPENDIX 22. DESIGN REPORT OF ROOF.

Joint Venture of MVA Hong Kong Limited and SYSTRA S.A. Page A2
The Ho Chi Minh Green Transport Development Project
Detailed Design Report

DESIGN OF SUPERSTRUCTURES

MAIN GIRDER GEOMETRY

Typical section of main girder

40300
250 1900 26000 10000 1900 250

PIER P1
PIER P2 PIER P3

Figure: Elevation of Steel Pedestrian Bridge


MAIN GIRDER ANTI-SLIP STEELPL6 CROSS BEAM MAIN GIRDER
I600x300x11x18 I200x100x7x10 I600x400x11x18

L63x63x6 BRACING

Figure: Typical plan view of main girder and cross beam for Steel Pedestrian Bridge

3000

I200x100x7x10
CROSS BEAM

ANTI-SLIP STEEL PL6

I600x300x11x18 I600x400x11x18
MAIN GIRDER
MAIN GIRDER
I400x300x10x16

C200x100x7x10

C280x100x9x13

D350x16 D350x16

3000

Figure: Typical Cross section of main girder for Steel Pedestrian Bridge

Joint Venture of MVA Hong Kong Limited and SYSTRA S.A. Page A3