You are on page 1of 6

VISVESVARAYA TECHNOLOGICAL UNIVERSITY

BELAGAVI – 590018

A TECHNICAL SEMINAR REPORT


ON
“BOX PUSHING TECHOLOGY”
A Technical Seminar Report Submitted In Partial Fulfilment Of The
Requirements For Eight Semester, Bachelor Of Engineering Degree In
Civil Engineering.

Submitted by,
AKASH M S (4RA18CV008)

Under the Guidance of


Mr. HARSHITH H.J B.E., M.Tech.
Assistant Professor
Dept. of Civil Engineering

DEPARTMENT OF CIVIL ENGINEERING


RAJEEV INSTITUTE OF TECHNOLOGY
Plot 1-D, Growth Centre, Industrial Area, B-M Bypass Road, Hassan, Karnataka 573201
2021 – 2022
VISVESVARAYA TECHNOLOGICAL UNIVERSITY, BELAGAVI
RAJEEV INSTITUTE OF TECHNOLOGY, HASSAN
DEPARTMENT OF CIVIL ENGINEERING

CERTIFICATE

This is to certify that the project work entitled “BOX PUSHING TECHOLOGY”
carried out by AKASH M S (4RA18CV008) are bonafide students of Rajeev Institute of
Technology in partial fulfilment of the requirements of the eight semester, Bachelor of
Engineering degree in Civil Engineering of Visvesvaraya Technological University,
Belagavi during the year 2021-2022.

Signature of the Guide Signature of the Project Signature of the HOD


Co-Ordinator

Mr. Harshith H J Mr. Raghunandan Yadav C Mr. Sujay S


Mrs. Supriya C L
Assistant professor Assistant Professors Head of the Department
Dept. of Civil Engineering Dept. of Civil Engineering Dept. of Civil Engineering
RIT, Hassan RIT, Hassan RIT, Hassan

Date: Examiners:
Place: HASSAN 1.
2.
ACKNOWLEDGEMENT

We express our deep sense of gratitude and indebtedness to institute “RAJEEV


INSTITUTE OF TECHNOLOGY” which has provided excellent facility to complete this
project.
We greatly thank Dr. A N RAMAKRISHNA, Principal Rajeev Institute of Technology,
Hassan, for his unstinted support.
We greatly thank Mr. SUJAY S Asst. Professor and Head of Department, Department of
Civil Engineering, R.I.T, Hassan, for his support and encouragement.
We greatly thank our guide Mr. HARSHITH H J Asst. Professor, Department of Civil
Engineering, R.I.T, Hassan, for his valuable guidance throughout this project work both in
field and in office and bringing out this report in this present form.
We wish to express our deep sense of gratitude to our beloved Projector Co-Ordinators Mr.
RAGHUNANDAN YADAV C and Mrs. SUPRIYA C L, Asst. Professors, Dept. of Civil
Engineering, R.I.T, Hassan, for their valuable guidance throughout this project work both in
field and in office and bringing out this report in this present form.
We extent our heartful thanks to all the faculty members, teaching and non-teaching staff of
Depart of Civil Engineering, R.I.T, Hassan who have helped us directly or indirectly.
We also thank our batchmates for the kind cooperation in completing this project work.
Lastly, we thank persons who have helped me directly or indirectly in completing this project
work.

AKASH M S (USN: 4RA18CV008)


ABSTRACT

The intersection of railway track and the road at a similar level is alluded to a level
intersection. In the urban territories the level intersection are for the most part observed by
qualified railway work force who screen the train development and close the level
intersection entryway to stop the meddling road traffic yet such shutting of doors prompts
blockage in road traffic and furthermore makes loss of time road clients. Road under
extension and road over scaffold are considered as answers for keeping away from level
intersections of roads and railway track.
There are 3 principle methods in development of road under extension. Box pushing
method, Cut and spread method, Rolling procedure utilizing RH support. In this we examine
about the executes, soil rubbing, impacts required, limit of jacks and there utilizations, skew
edges and at square edges.

Keywords: Road under Bridge, Level Crossing, Box Pushing Method and RUB etc…
CONTENTS
CHAPTERS PAGE NO

CHAPTER 1
Introduction 1-2
CHAPTER 2
Objectives 3
CHAPTER 3
Method of Level Crossing 4-5
CHAPTER 4
Components Used 6–8
CHAPTER 5
Methods in Construction 9 - 11
CHAPTER 6
Case Study 11 – 14
CHAPTER 7
Problems and disadvantages 15

CONCLUSION 16

REFRENCES 17
LIST OF FIGURES

FIGURES PAGE NO
Figure 1: Box Pushing Technology 2

Figure 2: Methods of elimination of level crossings 4

Figure 3: Box pushing method of RUB. 5

Figure 4: Box pushing method of ROB. 5

Figure 5: Construction of thrust bed with shear keys. 6

Figure 6: MS Plate/Front Shield for Box Pushing in RUB. 7

Figure -7: Hydraulic jack used for pushing. 7

Figure 8: Pre casted box pushed one by one. 11

Figure 9 South central railway construction 12

of road under bridge between Fathenagar