Professional Documents
Culture Documents
N
C
T
S
pg. 1
Contents
1 INTRODUCTION............................................................................................................................................ 1
4 ANALYSIS.................................................................................................................................................... 2
4.2.1 CONCRETE.............................................................................................................................................. 3
4.2.2 STEEL REINFORCEMENT....................................................................................................................... 3
4.2.3 COVER TO THE REINFORCEMENT........................................................................................................3
5 LOADS 4
6 LOAD CASES................................................................................................................................................ 4
7 LOAD COMBINATIONS................................................................................................................................ 4
8 CONSTRUCTION.......................................................................................................................................... 5
10 DRAWINGS................................................................................................................................................... 9
11 DESIGN 14
Construction is the process of erecting a structure or infrastructure. The construction of buildings and
infrastructure is critical to a country's progress. Construction varies from manufacturing in that
manufacturing includes mass manufacture of similar things without an identified purchaser, whereas
construction occurs on-site for a known client.
Construction begins with the planning of a building or infrastructure for construction, the design of a
construction layout, and the finance or budget required for construction. Construction on a modest
scale comprises the construction of houses, residential units, and structures, among other things.
Residential projects, bridges, infrastructure, and other large-scale construction projects are examples
of large-scale construction. Large-scale building necessitates the collaboration of numerous
disciplines, and is frequently referred to as a megaproject.
Appendix 2 SCOPE OF THE REPORT
This scope of the report limits to structural design Building which includes design considerations,
loading conditions, safety requirements, material properties for concrete and reinforcement,
structural analysis and design.
a) EN – 1991-1
Appendix 4 ANALYSIS
4.1 DESIGN METHODOLOGY
The design of RCC frame for Building project is done by considering 3D structure on a raft and the
foundation is designed as raft supported on natural ground. The structure is analysed and designed
for respective loadings based on the operational condition and loads provided. The most critical load
combinations expected during life of structure are considered for concrete and reinforcement design
and the deformations are checked as per codal provisions to satisfy serviceability requirements
4.2 MATERIAL PROPERTIES
The following section generally define the main construction material properties used for the design.
These conform to the specifications for materials included in the technical specifications.
4.2.1 CONCRETE
The grade of concrete shall be according to euro code, The M25 concrete has been envisaged for
Building i.e. the concrete has characteristic compressive strength of 25MPa for the 150mm cube at
28 days. Unit weight of reinforced concrete is adopted as 25 kN/m3.
Appendix 5 LOADS
The following loads were considered for structural design of GIS Building:
III. Floor finish load for GIS floor is Applied in Staad =1.0 kN/m2
1 DEAD LOAD
2 LIVE LOAD
Appendix 8 CONSTRUCTION
For the construction of this project there are two parts to consider, Steel structure and concrete
structure.
Pre contract
Project Location
Plan for Building
Design
Following the design of the construction plan, a structural engineer creates the structure's frame.
Based on the soil study and the load of the superstructure, the type of foundation is then determined
and developed.
Estimates quantity, various items of work, and prepares a document including the cost.
This report need to be completed before the construction is designed. The engineer must understand
the soil qualities on the construction site; else, the foundation design cannot be completed. This
report includes soil parameters, soil kinds, load-bearing capacity, and other information.
Building Permit
To begin construction activities, the City Development Authority must provide consent.
Post-contract
Site Works
The first process is site preparation. It entails clearing the project site of removing unwanted material
and loose soil, existing buildings, sloping grounds, and designating the location of subterranean
services.
Compaction
Foundation
It is the bottom portion of the structure that transfers loads from the structure to the soil beneath. As
a result, it necessitates significant attention and precision during construction.
Placing PCC alone, setting up formworks, placing reinforcements, pouring concrete, and finally curing
the concrete to achieve the specified strength are all part of the construction process.
Following the completion of the foundations and plinth beams, rcc column built. The process entails
building a column kicker, installing steel bars, erecting formwork, pouring concrete, and curing the
concrete.
It is critical to check the verticality of columns during construction to avoid deviations from their
placements.
Following the completion of the ground level column construction, the slab and beam construction
would begin. Placing formworks and introducing reinforcements for beams and slabs based on
designs, embedding additional items and lastly curing the concrete are all part of the process.
Masonry Wall
Lintels
Lintels are used to carry masonry work across openings such as windows and doors.
Roof Slab
The roof slab is built after all of the building's storeys have been completed.
These work may or may not be totally linked to a civil engineer. The site engineer, on the other hand,
should prohibit any acts that have a negative impact on structural elements.
Finishing Works
Roof
Sometimes, after the plastering has been done, the roof surface will be applied with water proofing
agents to avoid leakage.
8.2 STEEL STRUCTURE
Steel structure construction includes the installation of foundations, columns, beams, and floor
systems.
The foundation is the first step in the building of a steel-framed structure. If the strength of soil is
inadequate and the load is significant, a pile foundation is sensible.
Steel Column
The installation of steel columns is the next step in the construction. The steel section is specified
based on the load acting on it. And column sections come available in different sizes, and these steel
columns are frequently manufactured in advance.
Erection of Beams
There are several pre-built beam sections are in the market for use in the construction of a multi-
story steel frame structure. Beams are widely used to carry loads from floors and roofs to columns.
Steel beam members can span up to 18m.Column to beam connections and beam to beam
connections are encountered while erecting steel beams.
Floor systems of many varieties can be employed in the construction of steel frame structures. Floors
are frequently placed while the beams are being built.
Bracings are used to withstand lateral forces imposed on structures by transferring lateral loads to
columns and subsequently to the footing.
Appendix 9 LETTER TO THE CLIENT
To
The client,
Good Day!
It has come to my attention that you would like the option of converting the aquarium into a museum
area. It is actually a wise decision to make the building future-proof. And this must be decided and
designed throughout the design stage. To make the change, I'll explain how we can do it in simple
terms.
The first step is to remove the acrylic aquarium tank, which entails emptying the tank and properly
dismantling it. To accomplish this, the steel framework and steel roof must be demolished. Aquarium
tanks can be safely removed with the use of appropriate lifting equipment. Following the successful
removal of the aquarium tank from the structure, several modifications are required for the installation
of a mezzanine level in the structure. The greatest solution in our instance will be a freestanding
concrete mezzanine level. Concrete mezzanine floors are durable and long-lasting, whereas
freestanding mezzanine floors allow for future development if more space is required. Columns and
braces for supplementary support for heavy weights must be added for proper installation.
If you have any questions or concerns about this, please do not hesitate to contact me.
Respectfully
Appendix 10 DRAWINGS
Appendix 11 DESIGN
11.1 SLAB DESIGN