Professional Documents
Culture Documents
Institute of Technology
School of Civil and Water Resource Engineering
Zeleke D.
zeladamtie@gmail.com
Mar, 2019
CHAPTER I
Highway planning
• In the present time planning is a pre-requesting
before taking up any developmental programme.
1. Economic studies
2. Financial studies
3. Traffic studies
4. Engineering studies.
Cont’d
1. Economic study: This study involves;
Population studies on area basis in which distribution of
population in villages, towns and other localities is studied.
• The traffic study should be carried out in the whole of the area and on
specific routes and locations, to collect the following information:
i. Traffic volume and its distributions: under this heading vehicle using roads
per day, peak hourly traffic are studied.
ii. Origin and destination studies: this study will indicates the origin and
destination of the traffic and also purpose of journey. This will also indicates
the materials coming in and going out of that place.
iii. Traffic flow pattern: this aspect will indicates types of facilities; area served,
route followed are studied.
vi. Future anticipated traffic volume and pattern of flow are assessed.
Cont’d
4. Engineering studies
• In this study, topography of the area, types of soil, materials of
construction, maintenance and drainage problems are investigated.
• This study is undertaken to plan such a route of the highway, which will
not only be most economical in its construction and maintenance, but
will provide maximum transport facilities and will serve the largest
possible population.
vii. Availability of labor and materials for the constructions of the roads.
Cont’d
• Details Collected in all the above studies are tabulated and plotted on
of plan and should be interpreted in such a way that a sound and most
factual studies.
Relative importance of proposed road system.
Fixing priorities of construction.
Nature of surfacing of a proposed system, commensurate with the
traffic requirements.
Future trend of growth of the area and thus that of road system.
Area of congestion of traffic on the road system, and requiring
immediate attentions of authorities.
Based on present traffic, type, intensity and performance of existing
road structure, a new road structure may be designed using past
experience and collected data.
Cont’d
ii. To prepare master plan of road development programme
showing phasing of plan.
Preparation of plan: various data and information collected
during conducting planning surveys are translated on the
maps and charts.
Following drawings are generally prepared from the collected
data.
i. Topographical map: the plan shows all the physical features of
the area.
iv. Traffic charts and maps: this drawing shows the existing
network of roads with patterns of traffic flow.
Master plan and its phasing
• Master plan is a final plan of road development, likely to be
taken up in the proposed area.
• Environmental pollution
• Energy consumption
• Parking problems
Purposes of road
• It helps in the movement of passengers and freight from
one location to another.
• etc
Highway alignment
o Objective:
– establishment of the new highway’s centerline and
cross-sections in relation to the terminal points and to
the topography through which the highway will pass.
alignment.
• Highway alignment
Horizontal alignment: consists of straight paths and
curves.
Vertical alignment: consists of grades and curves.
Cont’d
Vertical alignment
Horizontal alignment
Cont’d
o Centerline determines
the amount of cut and fill,
cross-section details,
drainage design,
environmental impacts.
o Improper alignment would increase;
Construction cost
Maintenance cost
Accident rate
Cont’d
o Requirements of ideal alignment:
Short : It is desirable to have a shortest path between two terminals. A
straight alignment would be the shortest, however there may be several
practical considerations which would cause a deviation from the shortest
path
Safe: Safe enough for construction and maintenance from the view point of
▪ Safe for traffic operations with easy geometric features such as sharpness
of curves, grades, side slopes and etc.
Traffic
Geometric design
Economics
Other considerations
Cont’d
Obligatory points
Points through which the alignment is to pass
• Bridges sites
• Hospitals, schools
Geometric design:
• Design factors such as maximum gradient, minimum
radius of curve, minimum available sight distance,
maximum allowable super-elevation, etc. should be
within the limits of allowable design values which are
governed by traffic speed to be expected on the road.
Cont’d
Economy:
Total transportation cost including initial construction cost,
maintenance cost, and operation cost.
For example : Deep cuttings, high embankments, no of bridges
that need to be constructed, etc. increases the initial cost of
construction.
• If high embankment and deep cuts are avoided there would
be a decrease in initial cost.
Other considerations:
• Drainage consideration
• Guide the vertical alignment
• Hydrological factors
• Subsurface water level, seepage flow, high flood level
• Political considerations
Route surveying
• Route surveying is of fundamental importance as it provides the basis
for many engineering design decision and subsequent cost estimates,
and the basis for cost and technically effective reproduction of the
design at construction stage.
Purpose of survey
Features to be identified
Level of accuracy
land, and
cadastral boundaries.
Route location survey
• The purpose of the route survey is to fix the road
the ground.
• Desk study
• Reconnaissance surveys
• Preliminary surveys
Highway Engineer
Hydrologist
Chief Surveyor
Bridge/Structural Engineer
topographies, etc)
Cont’d
2nd phase of Reconnaissance: Field Study
– A survey party inspects a fairly broad stretch of land along the proposed
routes identified on the map during the 1st phase and collects all
relevant details not available on the map. Some of the details include:
• valley, ponds, lakes, marshy land, ridge, hills, permanent structures, & other
obstructions;
• geological formation, type of rock, depth of strata, seepage flow, etc to identify
stable sides of a hill
– A rapid field study of the area, especially, when it is vast and the terrain is
difficult may be done by aerial survey
Cont’d
The following are some of the Useful checklists:
details to be collected on Field • Design standards
Study: • Grading & earthwork
• Valleys, ponds, lakes, marshy • Foundation condition
land • Geological conditions
• Approximate values of • Drainage
gradient, length of gradients • Right of way
• Number & type of cross- • Effect on community
drainage structures, max. flood
• Traffic
level
characteristics &
• Soil survey maintenance cost
• Sources of construction
materials, water & location of
stones
Criteria to evaluate the most feasible routes
• Design standards: design standards (max permissible gradient, etc ) are
normally fixed prior to the survey and any one of the feasible routes that
economically fits in these standards would be feasible.
• Traffic Characteristics: how best will a route fit with traffic requirements
of the area.
After evaluating the alternative routes proposed, one or more routes will be
recommended. If more than one routes passed the reconnaissance
survey detail study is made to choose one best route in the preliminary
survey.
3. Preliminary survey
In general, the objectives of preliminary surveys are:
1. Conventional method
I. Ground survey is carried out
• Primary traverse
• Topographic features
• centerline leveling
• X-section leveling
• Intersecting road
– A mass-haul diagram