Professional Documents
Culture Documents
REVIEW AND
00
APPROVAL
LUKKA RK HAIDER
SA - PID
QA QC
Document No:
.
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
CONTENTS
1. PURPOSE .................................................................................................................................. 3
2. SCOPE ...................................................................................................................................... 3
3. DEFINITION ............................................................................................................................. 3
4. REFERENCES ........................................................................................................................... 3
5. EQUIPMENT, PERSONNEL & SHOP AREA............................................................................... 4
5.1 EQUIPMENT & TOOLS ............................................................................................................. 4
5.2 STAFF.................................................................................................................................... 4
5.3 WORKERS .............................................................................................................................. 4
5.4 SHOP AREA ........................................................................................................................... 4
5.5 RESPONSIBILITY:.................................................................................................................... 5
6. PROCEDURE: ........................................................................................................................... 5
6.1 STORAGE AND HANDLING ....................................................................................................... 5
6.2 CUTTING AND BEVELING: ........................................................................................................ 6
6.3 JOINT ALIGNMENT: ................................................................................................................. 7
6.4 CLEANING:............................................................................................................................. 8
6.5 TACK WELDS: ........................................................................................................................ 8
6.6 PRE HEATING:........................................................................................................................ 8
6.7 WELDING: .............................................................................................................................. 9
6.8 FLUX AND SLAG REMOVAL: .................................................................................................. 10
6.9 CONSUMABLE ITEM .............................................................................................................. 10
6.10 WEATHER CONDITION .......................................................................................................... 10
6.11 Weld Identification………………………………………………………………………………...11
6.12 Pipe Fit-Up and Tolerances………………………………………………………………………11
6.13 Pipe Spools Cleaning/Flushing……………………………………………….........................12
6.14 Pipe Hangers and Supports……………………………………………………………………..13
7. PROCEDURE: ......................................................................................................................... 14
7.1 WELD REINFORCEMENT ........................................................................................................ 14
7.2 INSPECTION: ........................................................................................................................ 15
7.3 REPAIRS: ............................................................................................................................. 16
7.4 PAINTING ............................................................................................................................. 16
7.5 FIELD FABRICATION AND INSTALLATION ................................................................................ 17
8. ATTACHMENTS ..................................................................................................................... 18
Page 2 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
1. PURPOSE
The purpose of this procedure is to describe the system and Constructability of the Shop / field
fabrication for carbon steel Pipe.
2. SCOPE
This procedure covers the requirements for the system and constructability of the Fabrication shop
for carbon steel Pipe which will include the following.
3. DEFINITION
❖ IFC Issued for Construction
❖ ANSI American National Standards Institute
❖ AISC American Institute of Steel Construction
❖ AWS American Welding Society
❖ ASTM American Society For Testing And Materials
❖ NMR Non Material Requirement
❖ PPE Personnel Protective Equipment
❖ RFI Request For Inspection
❖ NCR Non Conformance Report
4. REFERENCES
❖ SAES-L-350 Construction of Plant Piping
❖ SAES-L-105 Piping Material Specification
❖ SAES-L-460 Pipeline Crossing under Roads and Rail roads.
❖ SAES-L-450 Construction of On-Land and Near-Shore Pipelines
❖ SAES-H-200 Storage, Handling and Installation of Externally Coated pipe.
❖ SAES-L-110 limitation on Piping Joints and Components.
❖ SAES-W-011 Welding Requirement for On-Plot Piping.
❖ SAES- W 012 Welding Requirements for Pipelines
❖ ASME-B31.3 Process Piping
❖ ASME- 16.5 Pipe Flanges and Flanged Fittings
❖ ASME-16.25 Butt welding End
❖ 01-SAMSS-010 Fabricated Carbon Steel Piping.
Page 3 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
5.2 Staff
❖ Project Manager
❖ Construction Manager
❖ QA/QC Manager
❖ Piping Engineer
❖ QA/QC Inspector
❖ HSE Officer
5.3 Workers
❖ Foreman
❖ Fitter
❖ Welder
❖ Crane Operator
❖ Helper
Page 4 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
❖ One table (1.2m X 2.4m) having the CS sheet as its top will be provided.
❖ One vice will also be provided having capacity to hold Ø8” pipe.
❖ Power supply will be given to the fabrication shop.
❖ There will be halogen lights for the night time working.
5.5 Responsibility:
5.5.1 The Project Manager is the overall responsibility of the project activities process or
execution.
5.5.2 The Safety Officer is responsible for the development, implementation and
maintenance of safety policy. He shall co-ordinate with the project engineer, supervisor,
foremen and multicast care deployed under the project for its successful
implementation.
5.5.3 The QC Supervisor/ QC Engineer shall report to the QC Manager for all quality
implementation supports.
5.5.4 The QC Engineer and QC inspector shall review all quality related documents, material
certificates and non-conformance prior to taking any action.
5.5.5 The fabrication shop foreman and safety officer are jointly and severely responsible
for all the observances of all safety precaution required by BQ Safety Plan and
applicable to the manufacturer safety plan and applicable to the manufacturer safety
recommendation.
5.5.6 The QC Inspector shall be responsible for the preparation of necessary documents for
inspection.
5.5.7 The QC Supervisor shall review all request for inspection (RFI) forms initiated by QC
inspector and to mark as summary reports on daily basis.
6. PROCEDURE:
6.1 Storage and Handling
6.1.1 Pipe shall not be stored directly on the ground. Pipe shall be placed on mounds or
sleepers.
6.1.2 Stacking of pipes shall be made in manner to avoid damage to pipes or coatings (SAES-
H-200)
Page 5 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.1.4 End Protectors on Pipes, flanges, weld bevels, thread, and socket ends shall be firmly
attached.
6.1.6 During off loading, pipes shall not be dropped on the transport, a crane and suitable
certified slings shall be used. Nylon slings will be used to handle coated piping and
fittings.
6.1.7 The assembly of bolted flanges joints shall be in accordance with SAEP-351
6.1.9 Internally coated pipe shall be handled from the outside Diameter only.
6.1.10 Slings for lifting pipe shall be nylon similar material to prevent damage to the pipe
surface. Wire rope slings are not to be used.
6.2.2 All pressure –containing welds, except for socket welds, shall be made with full penetration
groove weld only.
6.2.3 All pressure containing weld, including socket weld, shall be made with multiple passes.
6.2.4 Full penetration groove joints with included angles less than 30 degree (except for portions
of compound bevels) shall not be used without approval.
6.2.5 For branches with reinforcing pads, the branch attachment weld shall be completed and
inspected prior to installing the reinforcing pad.
6.2.6 Consumable inserts may be used for all application providing the composition matches the
weld metal composition.
6.2.7 The joint should be free of grease, oil, scales, rust or other foreign material.
6.2.8 The primer paint coat on pipe and fitting ends shall be removed prior to bevel end
preparation.
Page 6 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.2.9 Permanent backing rings or strips shall not be used except for the backing strips on sleeve
longitudinal welds. Vents and drains in accordance with SAES-L-110 shall not be installed
unless included in the approved design drawings.
6.2.10 Drains shall not be installed at the bottom of the pipe for buried pipelines.
6.2.11 When a length of pipe is cut from a longer joint of pipe, all vendor markings and other
identifying information shall be transferred to each length of pipe.
6.2.12 A 6mm weep hole shall be drilled for all dummy supports. The weep shall be located near
the base plate for all vertical dummy supports, and near the run pipe at 6 O’clock position
for all horizontal dummy supports.
6.2.14 The details of piping isometric breakdown into spools and joints will be recorded for
references.
6.3.2 Piping components shall be adequately supported and aligned by means of jigs, clamps
or their suitable devices during tacking.
6.3.4 For pipe ends of the same nominal wall thickness, the offset shall not exceed 1.5mm.
6.3.5 If the large offset is caused by dimensional variations, it shall be equally distributed around
the circumference of the pipe.
6.4 Cleaning:
6.4.1 Surfaces to be welded shall be clean and free from paint, oil, dirt, scale, oxides and other
materials detrimental to welding.
6.4.2 Cleaning shall be done in a manner that will not lead to any contamination of the weld or
base metal.
Page 7 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.4.3 All pipes to be internally cleaned of any foreign material before welding.
6.4.4 Upon completion of each welding pass, the weld shall be cleaned of spatter, slag and flux
deposits.
6.5.2 Tack welds shall be of sufficient cross section and length in order to avoid cracks.. The
recommended tack size is 3.2-4.8 mm and length is 12.5-25.4.
6.5.3 Tack welds incorporated into the final weld shall be ground to a feather at each end to
ensure adequate fusion on the root pass.
6.5.4 If any crack is found in the tack weld, it should be grind to the base sound metal before
welding and MT / PT should be done to ensure no defect in the base metal before welding.
6.6.2 Preheat should be applied uniformly around the circumferential weld using gas or electrical
means.
6.6.3 Pre heat shall be measured minimum 75 mm away from the bevel end.
6.6.4 If a weld joint is wet or has surface moisture or condensation, it shall be dried by heating
for a distance of 100 mm from the weld joint and shall be warm to the hand before welding.
6.6.5 Minimum 25 mm of the bevel end shall be cleaned thoroughly to near white metal.
6.6.6 Temperature shall be measured using contact thermometer or indicating crayons of the
melting type.
6.7 Welding:
6.7.1 Each joint will be welded by the qualified welder and the qualified welding procedure (WPS)
shall be used.
6.7.2 The GTAW process shall be used for all passes for butt weld and socket weld in piping
and nozzles less than 33.4 mm OD. This does not apply to Weldolet, Sockolet,
Threadolets, and welding bosses.
Page 8 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.7.3 The second or hot pass shall be added as soon as possible after the completion of the root
pass, but shall not exceed 5 minutes for vertical down welding with cellulosic electrodes or
15 minutes for vertical up welding.
6.7.5 Welds shall be made in sequences such that portions of welds do not remain uncompleted
before welding subsequent joints.
6.7.6 If any grinding reduces the base metal to less than the design minimum, the ground area
shall be re welded and ground flush with the original base metal surface or the component
shall be replaced.
6.7.7 Coated and clad or overlaid surfaces shall be protected from the welding arc, associated
weld spatter, and damage from ground clamps or other associated equipment.
6.7.8 Temporary attachments, back-up strips, or supports welded to any component shall be
made with a compatible material. Under no circumstances shall rebar or galvanized steel
be used.
6.7.9 The GTAW process shall be used for the root pass of butt welds in piping and nozzles of
60.3 mm OD (2”NPS) or less, except for vent and drain piping open to the atmosphere or
for carbon steel in low pressure water services. This does not apply to weldolets, sockolets,
threadolets, and welding bosses.
6.7.10 Adjacent weld beads shall be staggered and not started from the same location.
6.7.11 Sealing compounds or tapes shall not be used on joints that are to be seal welded.
6.7.12 Seal welding of threaded connection shall cover all exposed threads and shall have a
smooth contour between welds.
6.7.13 The minimum distance between parallel butt weld shall be 20 mm or three times the wall
thickness of the wall thickness of the joint, whichever is greater.
6.8.2 Flux, slag and weld spatters shall be completely removed from weld beads and adjoining
material.
Page 9 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.9.2 Electrodes and filler wires shall be kept clean and dry, and properly stored according to
manufacturer recommendation.
6.9.3 No Electrodes or filler wires that are damaged, damp greasy or oxidized may be used.
6.9.4 Low Hydrogen electrodes shall be placed in a holding oven and held at a minimum 120°C
for at least 2 hours prior to use.
6.9.5 Welding electrodes shall be issued for production from holding ovens only and shall be
placed in heated quivers capable of maintaining minimum temperature of 65° C.
6.9.6 After 04 hours (or 08 hours when electrodes have been placed in heated quiver), the
electrodes must brought back to the holding oven at 120°C for 4 hours.
6.9.7 The root pass of single sided groove welds without backing in P. No. 1 carbon steels may
be made with an E XX10 electrode.
6.9.8 F- No. 1 &2 electrodes shall not be used on for pressure-retaining welds.
6.9.9 QA/QC Inspector shall monitor and assure the correct use of welding electrodes.
6.10.3 If weather conditions become too severe, welding operations shall be stopped.
Page 10 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.11.2 The fabricator shall establish and submit for approval an identification system that shall
uniquely identify each member and weld joint. The identification system shall be used all
examinations, surveys, inspections, etc.
6.12.2 Flattening of bends, measured as the difference of between the largest and the smallest
outside diameter at any cross section shall not exceed 5% of the nominal diameter of
the pipe. Flattening of bends and weld ends shall not exceed 3% of the nominal pipe
diameter.
6.12.3 Lateral transition of branches and connection from the center line of the run shall not
exceed +/_ 1.5mm.
6.12.4 Flange bolt holes shall be oriented as follows, unless otherwise indicated on the
construction drawings.
6.12.5 For piping over 3-inch NPS and connected to machinery/equipment, flange alignment
shall be within the following limits unless piping analysis per SAES-L-120 shows that
loads and moments are within the manufacturer’s limits for the machinery/equipment
nozzle:
Page 11 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
6.12.6 In the case where spectacle plate is installed between two flanges, these tolerances
can be increased by 30% except for tolerances for flange face tilt across diameter and
flange face separation.
6.12.7 If the tolerances per paragraphs 9.1 through 9.5 cannot be achieved, the actual
misalignment and piping lay-out shall be reviewed and approved by the chairman of
Piping Standards Committee in CSD.
ii. A 6-mm weep hole shall be drilled for all dummy supports. The weep hole shall be
located near the base plate for all vertical dummy supports, and near the run pipe
at 6 o’clock position for all horizontal dummy supports.
Page 12 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
ii. Provision shall be made to allow angular adjustment of the bearing surfaces during
installation, so that even distribution of the load can be assured.
iii. Low friction supports shall be constructed such that sand or other debris cannot
accumulate on sliding surfaces (by making the top surface larger than the bottom
surface).
iii. All springs shall be in compression, so that failure will not result in the complete
release of load.
iv. Spring shall be factory set to the calculated cold settings by means of travel stops.
Upper stops for load preset and lower stops for hydro-test shall be provided. These
stops shall be banded or locked in place so they easily be dislodged during erection
or hydro-test. The travel stops shall be painted red and shall have bright color tag
indicating “Remove-after-Hydro Test”.
v. Each spring hanger assembly must be capable of sustaining the load during hydro-
testing, which is equal to 2-times the operating load.
i. Rod hangers shall not be used for lines 2” NPS and larger in liquid service or multi-
phase flow.
ii. All hangers shall be provided with means for vertical adjustment.
Page 13 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
iii. Suitable locking devices shall be used at all threaded connections of the hanger
assembly (double-nuts).
v. Practicality for replacing them with rigid pipe supports should be evaluated and
implemented during construction.
7. PROCEDURE:
i. The form for the WPSs and PQRs shall be as suggested in the respective code being used.
ii. Welding shall not commence until the welding procedure has been approved for application
by SA Inspector and returned to the fabricator.
iii. All WPSs, PQRs and Weld and line description Tables shall be available at the work site
for review at any time by the authorized SA Inspector.
7.1.2 Arc strikes shall be avoided. Should this occur, however, the deposit shall be carefully
removed by mechanical means.
Page 14 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
7.1.4 Weld surfaces shall be free of cracks, excessive porosity, slag inclusions and other defects
indicating poor workmanship.
7.2 Inspection:
7.2.1 Client representatives shall have free access to the work at all times.
7.2.2 Client representative shall have the right to inspect the fabrication at any state or stage
and to reject material or workmanship which does not conform to the specified
requirements.
7.2.3 The fabricator shall furnish, install, and maintain in a safe operating condition all necessary
shoring, scaffolding, ladders, walkways, and lighting for a safe and thorough inspection.
7.2.4 Visual Inspection shall be performed before, during and after welding and prior to any NDT.
7.2.5 All appropriate safety precautions shall be taken for each inspection method.
7.2.6 All NDT personnel shall be qualified in accordance with SAEP-1140 or SAEP-1142.
7.2.7 Inspection of all welds shall include a band of base metal at least 25.4 mm wide on each
side of the weld.
7.2.8 All weld preparation, fit-up and weld assemblies will be visually inspected in accordance
with approved ITP, whereas a separate procedure will be issued for welding consumable
control and general welding and its inspection.
7.2.10 Non-Destructive examination for welded joints shall be in accordance with the NDT
Procedures.
Page 15 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
7.3 Repairs:
7.3.1 Welds may be repaired twice. If weld is still not acceptable after the second repair. Then
Client Inspection Representative has the sole authority for the decision to permit additional
repair attempts or to require that the entire weld be cut out.
7.3.2 Cracked welds (except for crater cracks) shall be cut –out unless a repair is approved by
the Client.
7.3.3 Repair welding shall be performed using a properly qualified and approved procedure.
7.3.4 All repaired welds shall, as a minimum, be inspected using the original testing method.
7.3.5 Any weld not meeting the acceptance criteria of the applicable code or standard shall be
cut or repaired.
7.4 Painting
7.4.1 All buried onshore pipes shall be externally coated.
7.4.2 The SAES-H-002 shall be used for below ground and SAES-H-001 shall be used for the
above ground.
7.4.5 FBE coated pipes shall not be stacked directly against each other at any time during
storage or transportation.
7.4.6 Twelve meter joints of pipe shall have at least 3 full encirclement separation pads and
twenty four meter shall have at least 5 full encirclement separation pads.
7.4.7 The completed girth weld area on FBE coated pipes shall be externally coated in
accordance with SAES-H-201.
Page 16 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
• Areas smaller than 1450 mm use thermal melt sticks or an epoxy patching compound
approved by the Responsible Standardization Agency (RSA).
• Areas larger than 1450 mm and smaller than 0.2 m square use an epoxy patching
compound approved by the Responsible Standardization Agency (RSA).
• Areas larger than 0.2 mm square- use fast curing solvent free epoxy system only as
per APCS-113A.
• The repair coating shall overlap the adjacent sound coating by at least 10 mm to
maximum 20 mm.
7.5.1.1 All pipes shall be internally cleaned by air blowing. In addition, for large diameters pipes
rag cleaning should be conducted if found practical.
7.5.1.2 All prefabricated pipe spools shall be visually inspected for cleanliness, and shall have
foreign material removed from the inside.
7.5.1.3 The piping ends shall be covered after inspection to prevent unauthorized removal of
the end cover prior to making the joint to the succeeding section of piping.
7.5.1.4 The method of covering the pipe ends shall be part of the procedures.
7.5.2.1 During assembly and erection, the construction agency shall ensure that no foreign
materials (such as welding consumables, lumbers, gloves, etc.) are left inside the piping
system.
7.5.2.2 After assembly and installation, the piping shall be cleaned inside to remove all loose
material. The cleanliness shall be verified visually inspection techniques.
Page 17 of 18
DOCUMENT TITLE:
SHOP AND FIELD FABRICATION PROCEDURE
7.5.3.1 Buried metallic plant piping (if permitted by SAES-L-310) shall have corrosion protection
in accordance with the applicable Saudi Aramco Coating Standards and SAES-X-600.
7.5.3.3 The minimum cover in paved or stabilized areas shall be in accordance with SAES-L-
460.
7.5.4.1 The transition zones of the metallic piping from above ground to underground shall not
be encompassed by concrete or asphalt. A minimum of 1foot annuals of sweet sand
capped with aggregate shall surround the transition section.
7.5.4.2 At the transition point the external coating shall be extended from the below ground to
a minimum of 1 meter on the above ground section.
8. ATTACHMENTS
The following checklist, inspection forms and test records to document the compliance of the work
activities to the Project Quality Plan and other project requirements are to be filed and kept and to
be submitted to Saudi Aramco at the close of the project.
❖ Survey Report
❖ Field Fabrication Piping Checklist
❖ Shop Test Record (Radiography)
❖ Weld Radiographic Report
❖ Field Installation Checklist
All records of inspections and testing shall be safely kept and filed for Saudi Aramco’s review and
surveillance any time.
Page 18 of 18