You are on page 1of 17

Daelim Industrial Co.

, Ltd Tel : +65 6595 1300


102A Eu Tong Sen Street #01-01 Fax : +65 6342 1360
Singapore 059820

TRANSMITTAL SHEET

Transmittal No.: T222/DES/4328A No. of Sheets 1 of 1

To : Land Transport Authority Project : Contract T222,


Thomson-East Coast Line(C4)-T222 Construction of Outram Park Station and
102A Eu Tong Sen Street Tunnels for Thomson-East Coast Line
#01-02, Singapore 059820

Attn: Mr. Tay Sze Beng


Engineer's Representative

We issue the following drawings / documents :

Subject SHOP DRAWINGS FOR CATLADDER 50A,50B, 51 & 52 & ROOF ACCESS HATCH DETAIL

Purpose: Acceptance/Approval . √ Review . Information . Others .

Response Required by : Engineer's Representative (T222)


Contractor's Transmittal
Reference NO: T222/TELC4/D19.005.000 ( )
Issued by Name Kim, Hyun / Project Manager SUBMISSION DATE:
Sign Digitally signed by DIC-Kim Info Act Reply Info Act Reply

DIC-Kim
Hyun
DN: cn=DIC-Kim Hyun, D[C4]TEL E&M
o=DIC-T222, ou=Project
Manager,

Hyun email=kimhyun@daelim.co.
DD SURVEY
kr, c=SG
Date: 2020.10.12 18:47:42 SPM DM
+08'00'
Date PM ARUP
SPE ARCHI
Received by Name EPE CD (ARIEL)
POIC (HANIE) ENGINEERS
Sign SAFETY File

Date
Drawings / Documents :
Drawing/Document No Rev Title Qty Size / Media
BASEMENT ROOF LEVEL 50A & 50B CATLADDER SETTING-
M/T222/OTP/ADMS/7931 A 1 (A1) Soft Copy
OUT PLAN
BASEMENT ROOF LEVEL 51 & 52 CATLADDER SETTING-OUT
M/T222/OTP/ADMS/7932 A 1 (A1) Soft Copy
PLAN

M/T222/OTP/ADMS/7933 A ROOF LEVEL DETAILED CATLADDER SETTING-OUT PLAN 1 (A1) Soft Copy

M/T222/OTP/ADMS/7934 A ROOF LEVEL DETAILED CATLADDER SETTING-OUT PLAN 1 (A1) Soft Copy
BASEMENT ROOF LEVEL CATLADDER 50A SETTING-OUT
M/T222/OTP/ADMS/7935 A 1 (A1) Soft Copy
BLOW-UP PLAN & DETAIL SECTION
BASEMENT ROOF LEVEL CATLADDER 50A SETTING-OUT
M/T222/OTP/ADMS/7953 A 1 (A1) Soft Copy
BLOW-UP PLAN & DETAIL SECTION
BASEMENT ROOF LEVEL CATLADDER 50B SETTING-OUT
M/T222/OTP/ADMS/7954 A 1 (A1) Soft Copy
BLOW-UP PLAN & DETAIL SECTION
BASEMENT ROOF LEVEL CATLADDER 51 SETTING-OUT
M/T222/OTP/ADMS/7955 A 1 (A1) Soft Copy
BLOW-UP PLAN & DETAIL SECTION
BASEMENT ROOF LEVEL CATLADDER 52 SETTING-OUT
M/T222/OTP/ADMS/7956 A 1 (A1) Soft Copy
BLOW-UP PLAN & DETAIL SECTION
BASEMENT ROOF LEVEL CATLADDER 47SETTING-OUT BLOW-
M/T222/OTP/ADMS/7957 _
UP PLAN & DETAIL SECTION
M/T222/OTP/ADMS/7958 A ROOF ACCESS HATCH DETAILED SECTION 1 (A1) Soft Copy
BASEMENT ROOF LEVEL CATLADDER SETTING-OUT
INTERMEDIATE LANDING BLOW-UP PLAN, ELEVATIONS &
M/T222/OTP/ADMS/7960 _ 1 EMAIL
DETAIL SECTIONS

Cc: 1 QP(S), 1 Arup


Contract T222, DOC. NO. : T222/DES/4328
Construction of Outram Park Station & Tunnels for Thomson East REV. NO. : A
Coast Line

SHOP DRAWINGS FOR CATLADDER 50A, 50B, 51, 52 & ROOF ACCESS HATCH DETAILS

CONTRACT T222,
CONSTRUCTION OF OUTRAM PARK STATION & TUNNELS
FOR THOMSON EAST COAST LINE

SHOP DRAWINGS FOR


CATLADDER 50A,50B,51,52 & ROOF
ACCESS HATCH DETAILS

Prepared by Checked by Confirmed by

DIC-
Digitally signed by DIC-Ariel Digitally signed by

DIC-Ariel Tolentino
DN: c=SG, cn=DIC-Ariel HWAN Digitally signed by
HWANG CHI HOON
DIC-Kim Hyun
DN: cn=DIC-Kim

Kim
Tolentino, DN: cn=HWANG CHI Hyun, o=DIC-T222,

Tolentino
email=ariel.tolentino@daelim.c
o.kr G CHI HOON, o=DAELIM, ou,
email=chhwang@daeli
m.co.kr, c=SG
ou=Project Manager,
email=kimhyun@daeli
m.co.kr, c=SG

Hyun
Date: 2020.10.09 09:19:32
+08'00'
Ariel Tolentino HOON Date: 2020.10.12
18:48:17 +08'00'
Hwang, Chi Hoon
Date: 2020.10.12
18:47:57 +08'00'
Kim, Hyun
Project Coordinator (Archi) Design Manager Project manager
DOC. NO. : T222/DES/4328
Contract T222, REV. NO. : A
Construction of Outram Park Station & Tunnels for Thomson East
Coast Line

SHOP DRAWINGS FOR CATLADDER 50A, 50B, 51, 52 & ROOF ACCESS HATCH DETAILS

DOCUMENT REVISION LOG

Rev No Date Description of Revision


- 2020.15.04 First Issue
A 2020.09.10
2020.05.10 Additional Intermediate Landing for the Catladder
REPLY TO COMMENT SHEET

DS DAR No. : T222/DES/4328/- DAR No.: T222/DES/4328/A


Comment Date: 12-MAY-2020 Date Responded: 09
05 OCT 2020

DAR Title: Shop drawing Submission for CATLADDER 50A,50B,51 & 52 ROOF ACCESS HATCH DETAIL
Reviewed by:

Comments
S/N Dwg/Doc No No. Contractor’s Reply Code
LTA Comment’s

1 General Comments 1.1 1. Please comment from QPS & QPD Drawing revised as per 2
comment

1.2 -1. Please submit PE endorsement for each drawing. Please refer to the drawing nos. 1
M/T222/OTP/ADMS/7931/A
M/T222/OTP/ADMS/7932/A
M/T222/OTP/ADMS/7933/A
M/T222/OTP/ADMS/7934/A
M/T222/OTP/ADMS/7953/A
M/T222/OTP/ADMS/7954/A
M/T222/OTP/ADMS/7955/A
M/T222/OTP/ADMS/7956/A
M/T222/OTP/ADMS/7957/
M/T222/OTP/ADMS/7958/A
M/T222/OTP/ADMS/7960/-
2 Shop Drawing for Catladder 2.1 - Please submit DGN file as per LTA cad standard requirements. Please note the DGN file is too 2
50A, 50B, 51, 52 and Roof big unable to send via EMAIL.
Access hatch Details We can send via
WETRANSFER but LTA not
allowed. That’s why we just
submitted the PDF.
REPLY TO COMMENT SHEET

DS DAR No. : T222/DES/4328/- DAR No.: T222/DES/4328/A


Comment Date: 12-MAY-2020 Date Responded: 05
09 OCT 2020

DAR Title: Shop drawing Submission for CATLADDER 50A,50B,51 & 52 ROOF ACCESS HATCH DETAIL
Reviewed by:

Comments
S/N Dwg/Doc No No. Contractor’s Reply Code

- Please ensure to clear shop drawing prior to fabrication/ installation. Noted

-Please ensure to comply with cat ladder requirements. As per requirements we will
comply.
-All cat ladder ensure to comply with CDC requirements. Yes, Please refer to the
drawing
-Refer to attached mark-up with comments and please revise & re-submit. We will submit accordingly.

QP(S)

1. T222/DES/4328A -Please submit AEDAS and QPD) Arup comments ( if any) for our records. Ok, Noted Please refer to 2
drawing submission
-Please submit endorse by PE drawings. As per agreed by AE and LTA 2
during Archi-meeting, we will
re-submit the drawings with PE
endorsement once we clear
the approval.
-Please submit material 70x12mm SS bar support bracket 70x70x8mm SS Please refer to Material
mounting bracket, 150x150x10mm thk, base plate, FBN II M12 bolts, M16 submission MAT-4028 for
bolts, washer and nuts. Anchorage Bolt.
REPLY TO COMMENT SHEET

DS DAR No. : T222/DES/4328/- DAR No.: T222/DES/4328/A


Comment Date: 12-MAY-2020 Date Responded: 09
05 OCT
OCT 2020
2020

DAR Title: Shop drawing Submission for CATLADDER 50A,50B,51 & 52 ROOF ACCESS HATCH DETAIL
Reviewed by:

Comments
S/N Dwg/Doc No No. Contractor’s Reply Code

-Welding and mechanical anchorage bolt systems are required to be tested Noted
and to conform with LTA M&W specification.

AE Comments

1 DAR No. T222/DES/4328/- Ok, Noted 3


Shop Drawing for Catladder 1. Check actual site condition before fabrication. Please refer to the Drawing
50A, 50B, 51 & 52 Roof Access Nos:
Hatch Details M/T222/OTP/ADMS/7931/A
M/T222/OTP/ADMS/7931/- 2. Refer to other comments in attached drawings. M/T222/OTP/ADMS/7932/A
M/T222/OTP/ADMS/7932/- M/T222/OTP/ADMS/7933/A
M/T222/OTP/ADMS/7933/- 3. Hatches shall not be obstructed by any roof services Coordinated drawing M/T222/OTP/ADMS/7934/A
M/T222/OTP/ADMS/7934/- not subitted. M/T222/OTP/ADMS/7953/A
M/T222/OTP/ADMS/7953/- M/T222/OTP/ADMS/7954/A
M/T222/OTP/ADMS/7954/- M/T222/OTP/ADMS/7955/A
M/T222/OTP/ADMS/7955/- M/T222/OTP/ADMS/7956/A
M/T222/OTP/ADMS/7956/- M/T222/OTP/ADMS/7957/
M/T222/OTP/ADMS/7958/- M/T222/OTP/ADMS/7958/A
M/T222/OTP/ADMS/7960/-

Comment Code :

1: Minor 2: Moderate 3: Major


4

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7931 A
SHOP DRAWING SUBMISSION
CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7932 A
SHOP DRAWING SUBMISSION
CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS7933 A
SHOP DRAWING SUBMISSION
CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS7934 A
A A

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

A ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
A PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7953 A
A

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7954 A
A
A

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

A
A

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7955 A
A

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

A A
THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7956 A
SHOP DRAWING SUBMISSION
CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7957 -
8

4 5
ADMS7958A ADMS7958A
10

10
7
3

9
ADMS7958A

SHOP DRAWING SUBMISSION


CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
11

OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF


THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

6 ARUP'S REVIEW
11
ADMS7958A

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7958 A
SHOP DRAWING SUBMISSION
CONTRACTOR'S DECLARATION:

THE CONTENTS IN THIS SUBMISSION HAVE BEEN PREPARED ACCORDING TO THE LATEST
WORKING AND APPROVED DRAWINGS. COORDINATION WITH ALL RELEVANT DISCIPLINES
AND PARTIES (ARCH, C&S, E&M SWC, ETC) HAVE BEEN CARRIED OUT AND ALL THEIR
REQUIREMENTS HAVE BEEN INCORPORATED INCLUDING ALSO RELATED INFORMATION
AND RESPONSES PROVIDED IN OTHER FORUMS (EG, RFI, DCR, EMAILS, MEETINGS ETC).

AEDAS'S REVIEW

THIS REVIEW IS FOR GENERAL COMPLIANCE WITH THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECTNESS OF
DIMENSIONS, QUANTITIES AND DETAILS, CORRECTNESS AND COMPATIBILITY OF
MATERIALS, METHOD OF MANUFACTURER AND EQUIPMENT USED IN THE INSTALLATION.
COMMENTS/CORRECTIONS WHERE MADE IN THIS REVIEW DO NOT RELIEVE CONTRACTOR
OF THE RESPONSIBILITY TO COMPLY WITH THE SPECIFICATIONS. THE ENDORSEMENT OF
THIS DRAWING DOES NOT IN ANY WAY CONSTITUTE AN ARCHITECT'S INSTRUCTION UNDER
THE CONTRACT NOR DOES IT AFFECT THE RESPONSIBILITY OF THE CONTRACTOR UNDER
THE CONTRACT. WHEN COMPLETED, THE SYSTEM SHALL OPERATE AS AN INTEGRAL
WHOLE AND SHALL PERFORM IN ACCORDANCE WITH THE SPEIFICATIONS.

ARUP'S REVIEW

THIS REVIEW CHECKS THE GENERAL CONFORMANCE AND COMPLIANCE WITH THE DETAILS
STIPULATED IN THE WORKING DRAWINGS. IT EXCLUDES REVIEW ON DIMENSIONAL SETTING
OUT, BAR BENDING SCHEDULE, COMPLETENESS OF E & M REQUIREMENTS ON OPENINGS,
PENETRATIONS AND CAST-IN ITEMS. THE APPROVAL DOES NOT RELIEVE THE CONTRACTOR
OF THEIR DUTY TO COMPLY WITH THEIR CONTRACTUAL OBLIGATIONS IN COORDINATING
WITH ALL INTERFACING PARTIES, CARRYING OUT CROSS DISCIPLINE CHECKS AND
SHOP DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL UNDUE OMISSIONS,
ERRORS AND DEVIATIONS FROM THE CONTRACT, DRAWINGS AND SPECIFICATIONS
REGARDLESS IF THESE WERE IDENTIFIED OR COMMENTED DURING REVIEW.

FOR ACCEPTANCE

SHANGHAI
DAELIM
CHONG KEE

TE17 OUTRAM PARK STATION

M/T222/OTP/ADMS/7960 -

You might also like