Professional Documents
Culture Documents
4.1.1 The CD cooling tower (CD CLT) shall meet the same requirements as
specified for the peacetime outdoor cooling towers as well as the
following:-
All tests and measurements shall be in SI units. Within one (1) month
completion of the testing in the laboratory, a comprehensive formal
test report shall be submitted by the certified CTI tester for the review
and acceptance by the Authority.
May 2008
MW/4/3
4.2.1 The air handling units (AHUs) for the generator shall meet the same
requirements as specified for peacetime AHUs as well as the following:-
a) The AHU fan motor and drive shall be installed outside the hot air
stream to ensure sufficient motor cooling
4.3.1 CD ventilation system fans include but are not limited to the CD gas filter
fans, CD cooling tower booster fans, CD Generator intake and exhaust air
booster fans, CD pantry fan, CD toilet exhaust fans, and CD fuel tank and
pump room ventilation fan. They shall have similar requirements as
specified for peacetime fans as well as the following:-
b) For the CD gas filter fan, it shall be the centrifugal type. All
components, which are in contact with the intake air, shall be made up
of materials, which are resistant to warfare bio-chemical agents. For
May 2008
MW/4/4
CD fuel tank and pump room fan, all components which are in contact
with the corrosive fuel vapour shall be made up of materials which are
resistant to fuel vapour.
c) All frames and supports for the fans shall be made of hot-dipped
galvanised steel.
4.4.1 The pump heads specified in the equipment schedules in the Authority’s
Drawings are for tendering purpose only, and are calculated based on
assumed equipment pressure drops and indicative pipe routing as shown
on the Authority’s Drawings. The Contractor shall be required to recalculate
and submit for the Engineer’s acceptance the exact pump head required
according to the pressure drops of equipment being offered and the actual
pipework routing before ordering the pumps. Any additional cost on the
May 2008
MW/4/5
4.4.2 The pumps and pump installations in the Civil Defence stations shall also
comply with the “Civil Defence Requirements” section of the Technical
Specification. All equipment and associated accessories and services such
as pipework, cabling, etc shall be shock mounted in compliance with the CD
shock requirements. The Contractor shall submit a full set of shock load
calculations to Engineer for review and acceptance.
4.4.3 Stainless steel, flexible corrugated connector shall be used for connecting
the piping to the pump.
4.5.1 General
i) At the gas filter intake air ducts where they terminate at the
Intake Air Plenums (IAP);
d) The air flow direction shall be clearly and conspicuously marked with
an arrow on the gas-tight shut-off valve body.
case of larger valves, the test pressure and other conditions shall be
defined on a case-by-case basis by the Independent Test Authority.
4.5.3 Approvals
a) The gas-tight shut off valve shall be designed and type tested by an
Independent Testing Authority which has been appointed by the
national civil defence authority of the country of origin of the valve to
carry out such tests and which has the necessary expertise,
experience, equipment and apparatus to carry out the required tests.
The Independent Testing Authority shall be required to certify that
the valves have successfully passed the type tests in accordance
with the requirements specified herein. The Contractor shall submit
all relevant information relating to the Independent Testing Authority
including organisation structure, testing facilities, track record, etc.,
for the Engineer’s review and acceptance.
c) For the submission of the type test results, the following documents
shall be submitted:-
May 2008
MW/4/8
i) For the shock test, the valve shall be fixed onto a mechanical test
bed and subject to a shock of no less than 12.5 g’s in both directions
(one at a time) along each of the 3 major axes. After the shock, the
valve shall be inspected for any damage or loosening of its
components.
ii) For the blast test, valve shall be subjected to a test blast of
overpressure and impulse at no less than 2 bars and 1.5 bar-
millisecond (bar ms) respectively inside a shock tube. After the blast
test, the valve shall be inspected for any damage or loosening of its
components and tested for air tightness.
iii) For the air tightness test, the valve shall be closed and subject to a
static overpressure of 1 bar using compressed air. The maximum
valve leakage rate shall not exceed 0.27 X 10-4 m3 per sec for every
m2 of valve opening cross sectional area when subject to a pressure
of 1000 Pa.
4.5.4 Information
On the gas-tight shut-off valve, a clear and visible label with the following
information shall be provided:-
May 2008
MW/4/9
vii) Nominal air flow rate when fully opened (in CMH).
4.6.1 The main purpose of the volume control dampers is for adjusting and
balancing the air passing through the OVs as the damper is fixed manually
in the required position between fully opened and fully closed.
4.6.2 Iris dampers or approved equivalent type shall be provided on the OVs for
air adjustment and balancing.
4.6.3 All VCDs shall comply with DW/142 or approved equivalent standard and
shall each be provided in separate purpose-made flanged casing of rigid
construction conforming to the same standard of air-tightness.
4.6.4 Dampers shall be of rigid construction, free from vibration in any position
and shall be substantially air tight when closed. Dampers shall be accurately
installed in relation to their quadrants so as to permit the free movement of
up to 90 degrees for indicating open and closed position. Materials for
dampers in all cases shall be mild steel (hot-dip galvanized) or extruded
aluminum.
4.6.5 The diameter of the dampers shall be the same as the diameter of the OVs.
4.6.6 Immediately after final CD testing (ORAT and IST) and adjustments, all
dampers shall be clearly marked on the surface in a permanent manner for
both the Conventional and Filtration mode positions.
4.6.7 All VCDs for OVs shall be shocked mounted in compliance with the CD
shock requirements. The Contractor shall submit a full set of shock load
calculations to Engineer for review and acceptance.
May 2008
MW/4/10
4.7.1 The over-pressure gauges each of a suitable operating pressure range (in
Pascals) shall be provided at the various locations for the following
purposes:-
4.7.2 The Contractor shall allow in his Tender Price for the supply and installation
of approximately twenty-five (25) numbers of pressure gauges (dial type)
per station that are suitable for CD use and acceptable to the Engineer. The
exact quantity of pressure gauges shall be determined from the Authority’s
Drawings of each station. The supply and installation of all the necessary
copper tubes and fittings such as 3-way isolation valves, etc for
measurement of the pressures as described in Clause 4.7.1 shall also
deemed to have been included in the Tender Price. The exact location of
the pressure gauges shall be determined at a later stage after Contract
Award as agreed by the Engineer.
4.7.3 The pressure gauges shall be of the dial type with a spring action
membrane and scale indication. It shall be possible to read pressure values
of between 0 and 450 Pa (0 to 45 mm of water gauge) with an accuracy of ±
10% from the gauges. The smallest graduation unit on the gauge shall not
be more than 10 Pa.
4.7.4 The pressure differential gauges shall be mounted on the wall of the test
area about 1.5 metres above the finished floor level and about 2 metres
away from CD doorway leading from the test area to the adjacent room with
which the room pressure is to be compared with. The pressure differential
May 2008
MW/4/11
4.7.5 The measuring tube must be drained before measurements are carried out,
since water in the tube will give to an erroneous measured value.
4.7.6 Every over-pressure gauge with its measuring tube protruding into an
unprotected area shall be fitted with a pressure attenuator to prevent any
let-through blast effects from damaging the gauge. The gauge shall be
subjected to a test blast of overpressure and impulse at no less than 2 bars
and 1.5 bar-millisecond (bar-ms) respectively inside a shock tube.
4.7.9 Batch test of each production batch of overpressure gauges shall be carried
out on 1 gauge randomly selected from their batch. The test shall comprise
shock test, blast test and functional test.
a) For the shock test, the gauge shall be fixed onto a mechanical test
bed and subject to a shock of no less than 12.5 g’s in both directions
(one at a time) along each of the 3 major axes. After the shock, the
gauge shall be inspected for any damage or loosening of its
components.
May 2008
MW/4/12
c) For the functional test, the gauge shall be tested for its accuracy and
precision when subject to a range of test pressures (but not less than
0 to 450 Pa) which the gauge is designed for.
4.8.1 Intake air ducts from the Intake Air Plenum (IAP) to the Gas Filters shall
be constructed of heavy-duty, AISI type 316L stainless steel schedule 10
pipes to ASTM or approved equivalent standards. For pipes of diameter
equal or less than 150 mm, it shall be seamless type. All joints shall be
continuously welded. The Gas Filters shall be connected to the intake air
ducts of the Gas Filters by means of flexible rubber connectors (using
gas-tight connector clips) supplied by the Gas Filter supplier as part of the
Gas Filter assembly. The maximum allowable leakage rate of the Gas
Filter ducts including the intake air ducts shall be 0.27 × 10-4 m3/(sec.m2)
at 1000Pa.
4.8.2 All Gas Filter Intake Ductwork shall be shock mounted in compliance with
the CD shock requirements. The Contractor shall submit a full set of shock
load calculations to Engineer for review and acceptance.
4.9.1 Flexible ducting used to connect the air distribution equipment and terminals
to distribution system ducts shall comply with the FSSB requirement of
resistance to fire penetration and spread of flame.
4.9.2 Flexible ducts shall not exceed 3m length except for the flexible ducts
designed for connection to the trains in the track ways during CD operation.
CD flexible ducts shall be of lightweight construction but must be durable
and not tear or hole easily.
4.9.3 The bending radius must be sufficient to prevent tensioning of the outside of
the bend and restriction of the throat, which will likely to cause deformation
and/or leakage. In no case shall the flexible ducts be used to connect
misaligned ducts.
4.9.5 Jointing and connection of the flexible ducts to the air distribution equipment
and rigid distribution ducts shall be to the manufacturer's recommendation
and shall be submitted for acceptance by the Engineer.
May 2008
MW/4/13
4.9.6 The specifications and materials for the flexible duct insulation and vapour
barrier shall be similar to the insulation requirement specified for the supply
air ducts in the “Insulation” section of the Technical Specifications.
4.9.7 All flexible ducts including CD ducts for air supply to the trains shall be
shock mounted in compliance with the CD shock requirements. The
Contractor shall submit a full set of shock load calculations to Engineer for
review and acceptance.
May 2008