Professional Documents
Culture Documents
1 Basic Inputs
Machinery Charges
a) Hydraulic Excavator (capacity) m3 1.00
Ideal production m3 210
Taking efficiency 0.85
Job management factor 0.69
Swing factor 0.88
Actual production m3 108.39
Use rate of Excavator = USD 31.47
Cost of Excavator / m3 = USD 0.29
b) Crawler Dozar 90 HP
Output of Dozar = m3 108.39
Use rate of Dozar = USD 57.35
Cost of Dozar / m3 = USD 0.53
c) Rear Dumper
Capacity Tonne 18.00
Actual Capacity of Dumper = m3 5.18
Cycle Time
a) Loading Time = 5.03 /105.83x60 = Minutes 2.87
b) Spotting Time = Minutes 0.5
c) Turning and Dumping Time = Minutes 2
d) Empty Haul @ 25 Km/Hr. = Minutes 2.4
e) Loaded Haul @ 20 Km/Hr. = Minutes 3
Total Time Required= Minutes 10.77
ii) Machinery charges Total Working Use rate in USD Amount in USD
Hrs / Shift
ii) Machinery charges Working Hrs / Use rate in USD Amount in USD
Shift
a)Drilling Jumbo 1.20 102.68 123.22
c)Loader 3.1m3 0.70 50.60 35.42
d)Dumper 18T 3.50 28.12 98.40
e)Crawler Dozer 90 HP 0.50 57.35 28.67
f)Total Machinery Charges 285.72
Quantity of Rock excavated / shift m3 16.54
Rate of Machinery per m3 USD 17.28
iii) Material charges
Drill steel
Time required for drilling hrs 1.20
Cost of drill steel USD 66.53
Quantity of Rock excavated / cycle m3 16.54
Rate for drill steel per m3 USD 4.02
Explosive
a) Gelatine required per m3 Kg. 1.00
Cost of powergel per Kg. USD 2.41
Rate per m3 USD 2.41
b) Electric Detonators
No. of detonator (one per hole) Nos 44.00
Cost of detonators USD 0.32
Total cost of detonator USD 14.16
Quantity of rock excavated / cycle m3 16.54
Therefore, cost per m3 USD 0.86
c) Other consumables petty stores such as blasting
batteries, galvanometers and blasting wires etc. @ 50% USD 0.43
of item'a'.
Total explosive charges per m3 (a+b+c). USD 3.69
Total charges for drill and explosive USD 7.71
Other expenses
a) Providing of pipe line for air and water for wet drilling USD 0.16
b) Timber for supports packing Rate per m3 USD 0.16
c) Miscellaneous supplies such as safety hats, gumboots,
rain coats, wire ropes, manila ropes, V-clamps rubber
USD 0.16
gloves, shackles and artificial respirator etc.Rate per m 3
L.S.
b) Placement of Concrete
Concrete will be placed through concrete pump of capacity m3 15.00
Work load / hrs. = m3 10.35
Use rate or machinery / hr. USD 22.11
Sub total/ m3 USD 2.14
c) Labour for placement USD 1.07
d) Vibrating charges / m3 including labour USD 0.29
e) Cleaning, curing and finishing etc.
Sand Blasting USD 0.29
Cement for slurry mortar USD 0.29
Cleaning & washing USD 0.29
Curing and finishing USD 0.29
Sub total USD 1.18
f) Catwalks and other aids for concreting USD 0.29
g) Other charges
Electric energy charges USD 0.43
Compressed air charges USD 0.43
Workshop charges USD 0.43
Track trolley charges USD 0.43
Sub total USD 1.71
Grand total for 'b'/m3 USD 10.59
iii) Formwork charges USD 1.87
Prime cost of concrete (i+ii+iii) 59.23
Add overhead charges and contractor's profit @ 20% of prime cost USD 11.85
Grand total USD 71.07
Hence, rate per m3 Say USD 71.07
II) Concrete C15
i) Material charges USD 50.30
ii) Charges for laying concrete
Same as for Concrete C10 USD 10.59
iii) Formwork charges USD 1.87
Prime cost of concrete (i+ii+iii) USD 62.76
Add overhead charges and contractor's profit @ 20% of prime cost USD 12.55
Grand Total USD 75.31
Therefore, rate per m3 Say USD 75.31
III) Concrete C25
i) Material Charges USD 61.99
ii) Charges for laying concrete
Same as for Concrete C10 USD 10.59
iii) Formwork charges USD 2.48
Prime cost of concrete (i+ii+iii) USD 75.05
Add overhead charges and contractor's profit @ 20% of prime cost USD 15.01
Grand total USD 90.07
Therefore, rate per m3 Say USD 90.07
3.2.22 Concreting in Penstock and Forebay.
I) Concrete C10
i) Material charges USD 46.77
ii) Charges for laying concrete
a) Transportation of concrete by truck mounted transit
mixers from Batching and Mixing Plant to placement m3 2.50
site of capacity.
Average lead km 1.00
Speed (Loaded) km/hr 10.00
Loaded Haul = 0.5 x 60/10 min. 6.00
Spoting &Waiting time 3.00
Empting time min. 10.00
Speed (Empty) km 15.00
Empty Haul = 0.5 x 60/15 (15km/hr) min. 4.00
Waiting & Turning time at B&M plant min. 5.00
Total Time min. 25.00
b) Placement of concrete
Concrete will be placed through concrete pump of
m3 15.00
capacity
Work load / hrs m3 10.35
Use rate or machinery / hr. USD 22.11
Sub total/ m3 USD 2.14
c) Vibrating charges including labour /m 3 USD 0.29
b) Placement of concrete
Concrete will be placed through concrete pump of
m3 15.00
capacity
Work load / hrs m3 10.35
Use rate or machinery / hr. USD 22.11
Sub total/ m3 USD 2.14
c) Vibrating charges including labour /m 3 USD 0.29
A
Consolidation grouting (Holes more than 5 m depth)
a Rate of drilling with wagon drill per meter. USD 9.29
b Rate of Grouting per bag of cement. USD 10.16
vi Wiremesh
100 mm thick
Cost of wire net per m2 for 4 Kgs weight of net USD
Fixing Charges USD
Prime Cost USD
Add overhead charges and contractor's profit @ 20%
of prime cost
Sub total USD
Hence, rate of wire net per m2 Say USD
4.41
2.21
0.60
0.44
0.88
8.60
30
50
0.85
0.69
17.595
41.10
0.30
2.50
1.00
20.00
3.00
5.00
10.00
25.00
2.40
5.00
25.40
1.97
4.93
21.71
0.40
37.02
4.60
0.69
14.58
1.46
0.73
1.30
12.79
2.60
15.39
15.40
154.00
151.40
162
313.40
62.70
376.10
4.91
3.68
8.58
1.72
10.30
10.30
3.2.27 Stone masonry in Cement mortar 1:4
i) Material
a) Collection and carriage of stone 1.05 m3 to site USD 4.83
(Including 5% wastage)
b) Dressing charges for 1.05 m 3 USD 0.10
3.2x 1.05* No. cement bags at site of work including
c) USD 14.52
carriage charges
d) 0.45 m3 cost of sand at site of work including carriage USD 9.92
Sub total 29.36
ii) Labour
Direct labour (100 cft.)
Wages in
Regular No. Rate
USD
a) Foreman 0.00 12.24 0.00
b) Explosive Inspector 0.00 7.36 0.00
c) Electrician / Explosive Expert 0.00 7.36 0.00
d) Supervisor / Mason 0.50 7.36 3.68
Sub total USD 3.68
Casual
a) Helper 0.25 4.60 1.15
b) Cableman / Blacksmith 0.00 4.60 0.00
c) Watchman 0.00 4.60 0.00
d) Unskilled 2.00 4.60 9.20
Sub Total USD 10.35
Total direct crew charges / day USD 14.03
Indirect labour (100 cft.)
Add for indirect crew charges.
Regular worker & USD 2.94
Casual worker. USD 5.69
Total indirect crew charges / day USD 8.64
Total crew charges / day USD 22.67
Rate of Labour per m 3 USD 8.00
Total prime cost (i+ii) 37.36
Add overhead charges and contractor's profit @ 20%
USD 7.47
of prime cost
Grand total USD 44.83
Therefore, rate per m3 Say USD 44.83
3.2.28 Placing inverted Filters
Abstract of charges
i) Pump charges USD 0.13
ii) Pipes and accessories USD 0.06
iii) Repair & maintenance charges USD 0.03
Based upon analysis done in 3.2, rates for principal items of civil works are given
hereunder: