d. Find the Critical Path and Expected Project Completion Time (5 points)
A 4.5 1.36
B 8.5 2.25
C 9.5 2.25
E 14.5 2.25
G 4 0.4
41 weeks 8.51
e. Create a GANTT Chart for this table and use the Mean duration for your timeline (5 points)
2. Assuming that the Critical Path is ACEGH, complete the table below. Find the mean duration
and variance. (5 pts)
Duration (week) Mean
Activity Variance
O M P Duration
A 1 2 3 2 0.11
B 2 3 4 3 0.11
C 1 2 3 2 0.11
D 2 4 6 4 0.44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 0.11
[ITEL305– SIA2]
Seatwork 3 Page 3 of 4
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna
3. What is the probability of the project time completion within 16 weeks (use a standard normal
distribution table)? (5 pts)
A 2 0.1
C 2 0.1
E 4 1
G 5 1.7
H 1 0.1
15weeks 3
Sigma2 = 3
Sigma = Sqrt(3)
= 1.73weeks