Directions:
✓ Answer the following question below:
✓ You can only take this seatwork once. So, make sure you don’t miss anything before
you submit it.
✓ You can attach a separate white paper for your solution and save it as an image format.
Expected Duration
Activity Predecessor Slack
per week
A -- 5
B A 4
C A 6
D B 3
E C 3
F C 2
G D,E,F 9
H G 1
A. Based on the table above, a construct a project network using CPM. (5 points)
B D
A
G H
C E
B. Perform Forward and Backward Pass to determine the project duration. (10 points)
5 B 9 9 D 12
7 4 11 11 3 14
0 A 5
0 5 5
5 C 11 11 E 14 14 G 23 23 H 24
5 6 11 11 3 14 14 9 23 23 1 24
11 F 13
12 2 14
C. Complete the table above. Determine the Slack/Float for each activity. (5 points)
Expected Duration
Activity Predecessor Slack
per week
A -- 5 0
B A 4 2
C A 6 0
D B 3 2
E C 3 0
F C 2 1
G D,E,F 9 0
H G 1 0
5 B 9 9 D 12
7 4 11 11 3 14
S=0
0 A 5
0 5 5 S=0 S=0
S=0 S=0
5 C 11 11 E 14 14 G 23 23 H 24
5 6 11 11 3 14 14 9 23 23 1 24
S=1
11 F 13
12 2 14
CP= A+C+E+G+H
CP= 5+6+3+9+1
CP= 24 weeks