Seatwork 5

NAME: MYCELL S. TENA SCORE: ____/35


SECTION: BSIT 3C-SMP DATE SUBMITTED:03/27/23

Directions:
✓ Answer the following question below:
✓ You can only take this seatwork once. So, make sure you don’t miss anything before
you submit it.
✓ You can attach a separate white paper for your solution and save it as an image format.

Test I- Project Management Tool using CPM

Expected Duration
Activity Predecessor Slack
per week
A -- 5
B A 4
C A 6
D B 3
E C 3
F C 2
G D,E,F 9
H G 1

A. Based on the table above, a construct a project network using CPM. (5 points)

B D

A
G H
C E

[ITEL305 – System Integration and Architectures 2]


Seatwork 5 Page 1 of 3
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna

B. Perform Forward and Backward Pass to determine the project duration. (10 points)

5 B 9 9 D 12
7 4 11 11 3 14

0 A 5
0 5 5

5 C 11 11 E 14 14 G 23 23 H 24
5 6 11 11 3 14 14 9 23 23 1 24

11 F 13
12 2 14

C. Complete the table above. Determine the Slack/Float for each activity. (5 points)

Expected Duration
Activity Predecessor Slack
per week
A -- 5 0
B A 4 2
C A 6 0
D B 3 2
E C 3 0
F C 2 1
G D,E,F 9 0
H G 1 0

[ITEL305 – System Integration and Architectures 2]


Seatwork 5 Page 2 of 3
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna

D. Determine the Critical Path (5 points)


S=2 S=2

5 B 9 9 D 12
7 4 11 11 3 14
S=0

0 A 5
0 5 5 S=0 S=0
S=0 S=0
5 C 11 11 E 14 14 G 23 23 H 24
5 6 11 11 3 14 14 9 23 23 1 24

S=1
11 F 13
12 2 14
CP= A+C+E+G+H
CP= 5+6+3+9+1
CP= 24 weeks

E. Create a GANTT chart to represent the project schedule. (10 points)

[ITEL305 – System Integration and Architectures 2]


Seatwork 5 Page 3 of 3