PROJECT:CHIRO
Client: haramaya university
CONTRACTOR BEREKA CONSTRUCTION
Building : DO-01
PAYMENT 05
Description Description
Variation Work order 3
variation work for water proof
deduct area of WC
-20 0.50
0.65
-6.50 m2
shower rooms
4 2.08 Around hand wash ,L=2.075m ,W=1.865m
1.87
15.48 m2
shower
8 1.20
0.99
9.50 m2
PROJECT:CHIRO
Client: haramaya university
CONTRACTOR BEREKA CONSTRUCTION
Building : DO-01
PAYMENT 05
CONTRACTOR........................ SUPERVISOR.........................
haramaya university
- -
- -
- -
- -
CONTRACTOR........................ SUPERVISOR.........................
Contructor Bereka Construction DO 01 22
PROJECT:CHIRO
Client: haramaya university
CONTRACTOR BEREKA CONSTRUCTION
Building : DO-01
PAYMENT 05
Description Description
Varation Work order 1
6- Steel structures
pcs
pcs
pcs
7- Finishing Work
7.06-semi dressed stone pavment (width = 1.50m)
Around enterance of the Buliding
1 28.11 L=9.80+1.62+2.90+10.13+1.10+2.56=28.11m,W=1.50m
1.50
42.17 m2
PROJECT:CHIRO
Client: haramaya university
CONTRACTOR BEREKA CONSTRUCTION
Building : DO-01
PAYMENT 05
CONTRACTOR........................ SUPERVISOR.........................
haramaya university
7.FINISHING
7.06
semi dressed stone pavment (width = 1.50m) all around the
building and including 400mm thick selected compacted fill
and 100mm thick red ash base and joints in cement mortar
mix 1:2 m² 148.00 157.99 157.99 645.00 95,460.00 101,901.36 101,901.36
7.07
half ditch dia 400 mm concrete pipe for storm water drainage
around the pavment. Price shall include red ash or equivalent
bedding material and jointed in cement mortar mix 1:2. ml 134.50 124.63 124.63 624.00 83,928.00 77,769.12 77,769.12
CONTRACTOR........................ SUPERVISOR.........................
Summary of Measurement
PROJECT:
Client:
Contractor: ---------------------------------------------------------
Building type :
Detail of Work executed and/or Material Supplied
Sub - Total
Item No. Description
Building
A. Sub - Structure
1 Excavation & Earth Work 118,452.52
2 Concrete Work 370,305.19
3 Masonry Work 46,330.00
Total A 535,087.71
B. Super - Structure
1 Concrete Work 1,262,205.58
2 Block Work 311,785.15
3 Roofing 253,798.56
4 Carpentry & Joinery 308,974.20
5 Aluminium Work 550,177.40
7 Finishing 519,139.00
8 Painting 163,262.00
9 Glazing 10,000.00
Total B 3,379,341.89
C. Utilities/Facilities
Total C 737,986.27
VAT 697,862.38
I/we ___________________ here by certify that the above figures are correct
and that the total value of work executed and / or material supplied to
date is 1672770.54
Contractor's Consultant's
¾¡õÁ ØÁo TÖnKÁ lØ` 05
Summary of Measurement No. 05
Y^¨<
PROJECT:
አሠሪዉ
Client:
ሥራ ተsራß
0.00
¾Q”í¬ ›Ã’ƒ
Building type : Dormitory
DO-01
1 4,652,415.87 #REF!
DO-02
2 4,652,415.87 #REF!
’@/— ________________________ Ÿ²=I uLà ¾}²[²\ƒ” H>dx‹ ƒ¡¡M SJ“†¨<” u²=G<U Sc[ƒ eŸ³_
É[e ¾}W^¨< Y^“ ¨ÃU ¾k[u¨< °n ÖpLL ªÒ #REF!
SJ’<” “[ÒÓ×K”::
I/we ___________________ here by certify that the above figures are correct and that the total value of work
executed and / or material supplied to date is #REF!
#REF!
15 % VAT #REF!
No Date AMOUNT Deductions Total with vat #REF!
1st 2.Rebate %
3rd 4.Others
This payment
certificate #REF!
last payment
certificate remaining
Total Previous Payment - casyh payment
The value of work executed and/or material supplied todate is Birr #REF!
Previous Payment and vat
No Date Net Payment VAT Deductions
Advance 4,525,349.36 678,802.40 1.Total Previous Payment 7,213,572.91
VAT PAYMENT
Amount of Advance Taken Birr 4,525,349.36 Total Executed Amount after advane #REF!
4.00 +first floor) 111.80 m2 net area on axis 3 along A to P (1st floor)
4 10.50
0.10
m3 above toilet window on axis A/ 2' -3 & P/ 2' -3 (ground
4.20 +first floor)
70.570 m2 total area of formwork
25.76 m2 partition separating shower from toilet….ground floor A. to internal & external HCB wall
2 4.60 i. to internal HCB
3.00 106 5.65 L= 2.8m(ground)+ 3.0m(first floor)= 5.8m
27.60 m2 partition separating shower from toilet….first floor 2.60
1,111.76 m2 total area of 15cm thick HCB 1,557.14 m2 On axis 3 along A to P
106 2.83
2.021. 100mm thick HCB 2.85
16 2.10 853.43
1.25 -53 1.50
42.00 m2 partition within toilet 1.50
4 1.30 (119.25) m2 deduction for window W1
2.10
10.92 m2 partition within shower -53 1.00
2.10
2.03. Cladding Construction (111.30) m2 on axis 1 along A' to >O
4 5.40 L= 2.6m(ground)+ 2.8m(first floor)= 5.4m 24 2.83
0.90 2.85
19.44 m2 On axis A', H, I & >O along axis 1….front side 193.23 m2 deduction for columns on ground floor
2 0.60 28 2.83
2.80 2.60
3.36 m2 On axis H & Ialong axis 1 on 1st floor….front side 205.66 m2 deduction for columns on first floor
11 5.40 L= 2.6m(ground)+ 2.8m(first floor)= 5.4m 1 2.83
1.50 2.60
89.10 m2 On axis B,C,D,E,F,G,J,K,L,M,N along axis 1/front 7.35 m2 deduction for window W1
1 5.40 m2 net area of plastering on axis 1 along A' to >O
1.80 -53 1.50 L= 2.6m(ground)+ 2.8m(first floor)= 5.4m
9.72 m2 On axis O along 1/front side 1.50
10 5.40 (119.25) m2. Two side plastering for partitions on axis 2'-3 along A-P
1.50 2 2.85
81.00 m2 On axis 3 along C,D,E,F,F,G,J,K,L,M,N/rear side 2.83
2 5.40 16.10 m2 deduction for columns on ground floor
1.70 4 2.60
18.36 m2 On axis H & I along 3/rear side 5.65
1 5.40 58.76 m2 deduction for columns on first floor
m2. Net area of two side plastering for partitions on axis 2'-3
0.50 along A-P
2.70 m2 B/n windows on H & I along 3/rear side -53 1.50 L= 2.6m(ground)+ 2.8m(first floor)= 5.4m
223.68 m2 total area of cladding 1.50
(119.25) m2. Two side plastering for partitions on axis 1-2 along A'->O
3. Roofing
3.04 Metal Copping 40 1.30
2 14.16 2.30 m2 deduction for columns on ground floor
28.32 m. Left and right side copping 0.00
1 48.06 16 3.40
48.06 m. Front side copping 0.75 m2 deduction for columns on first floor
m2. Net area of two side plastering for partitions on axis 1-2
76.38 m total length of copping 40.80 along A'->O
1 51.05 51.05 m total length of facia board….(item3.05) 4 4.6 L= 2.8m(ground)+ 3.0m(first floor)= 5.8m
0.50
4. Carpentary and Joinery 9.20 m2 On axis 2' along A to P corridor internal face
53.00 total number of D2 doors 8 5.30
0.50
5. Metal Work 21.20 m2 deduction for wall intersection on ground floor
8 2.00
53.00 total number of W1 windows 0.75
-4 1.00 12.00 m2 deduction for wall intersection on first floor
2.10
(8.40)
2,497.42 m2 deduction for lobby in the toilet
supply lay and connect poly propelene(PPR- Supply and fix high quality Urinal made of approved
PN 20). Pipes for cold and hot water supply as quality vitreous china with extended lipped to be fixed
per the drawing shown.complete with all the with screws on the wall with connection to the water
necessory connecting supply line necessary accessories.
for WC, L=4.60m+3.13+2.83+2.27+2.87= 15.70 8.00 pcs TOTAL FOR ITEM 10.5
62.80
1 1 1 45.85 Ground Floor city main
under septic tank slab cover on massonry wall 43.20 TOTAL FOR ITEM 23-e
Form work
23-d-a SEPTIC TANK COVER
1 1 1 4.70 L=4.70, width =3.70
3.70
17.39 m2
eadge of septic tank cover
Item
No Description Unit Quantity Unit Rate Total Amount
A. SUBSTRUCTURE
1. EXCAVATION AND EARTH WORK
2.3
10cm thick reinforced concrete floor slab in
concrete class C-20, with minimum cement of m2 215.00 242.15 52,062.25
320 kg/m3 well spread & leveled (steel bar
measured separately)
B. SUPERSTRUCTURE
1. CONCRET WORK
3.2 acrylic transparent roof cover on & including m2 28.00 270.00 7,560.00
frame
Flashhing in flat metal sheet developemnt
3.3 ml 36.00 230.00 8,280.00
L=35cm
3.5 3cm thick cement screed over light weight m2 100.00 104.68 10,468.00
oncrete
3.6 Bitumat with 4mm thick sand finished or m2 125.00 251.54 31,442.50
equivalent water proofing material
Total Carried to Summary 253,798.56
Item
No Description Unit Quantity Unit Rate Total Amount
Window
5.1 Size:-390*280cm N0 1.00 28,392.00 28,392.00
5.2 Size:-382*280cm N0 1.00 27,809.60 27,809.60
5.3 Size:-180*190cm N0 2.00 8,892.00 17,784.00
5.4 Size:-130*190cm N0 1.00 6,422.00 6,422.00
5.5 Size:-200*190cm N0 2.00 9,880.00 19,760.00
5.6 Size:-182*190cm N0 1.00 8,990.80 8,990.80
5.7 Size:-80*190cm N0 3.00 3,952.00 11,856.00
5.8 Size:-230*190cm N0 1.00 11,362.00 11,362.00
5.9 Size:-360*190cm N0 1.00 17,784.00 17,784.00
5.10 Size:-158*115cm N0 1.00 4,724.20 4,724.20
5.11 Size:-468*100cm N0 7.00 12,168.00 85,176.00
5.12 Size:-510*100cm N0 1.00 13,260.00 13,260.00
5.13 Size:-337*100cm N0 1.00 8,762.00 8,762.00
5.14 Size:-398*100cm N0 1.00 10,348.00 10,348.00
5.15 Size:-134*100cm N0 1.00 3,484.00 3,484.00
5.16 Size:-120*100cm N0 1.00 3,120.00 3,120.00
5.17 Size:-204*100cm N0 1.00 5,304.00 5,304.00
5.18 Size:-129*100cm N0 1.00 3,354.00 3,354.00
5.19 Size:-317*100cm N0 1.00 8,242.00 8,242.00
5.20 Size:-140*100cm N0 2.00 3,640.00 7,280.00
5.21 Size:-158*115cm N0 2.00 4,724.20 9,448.40
Window doors
5.22 Size:-132*120+200*280cm N0 1.00 18,678.40 18,678.40
5.23 Size:-380*280 over all N0 1.00 27,664.00 27,664.00
5.24 Size:-380*280 (wooden type) N0 1.00 24,472.00 24,472.00
5.25
PVC partition wall for wc complate work all
according to manufactures instruction m2 75.00 1,200.00 90,000.00
Stair case hand rail & baluster
complete work
5.26 H=90cm m 21.00 2,950.00 61,950.00
5.27
Balcony handrail&baluster complete work m 5.00 2,950.00 14,750.00
Item
No Description Unit Quantity Unit Rate Total Amount
6.6 Tid wooden celing nailed on & including m² 157.00 340.00 53,380.00
4*4cm zigeba batten at c/c 60cm both ways
price includes corner list complete work
6.7
6mm thick glazed ceramic wall tile beded on &
including cement mortar backing and joints m² 122.00 480.00 58,560.00
grouted in white cement
6.8
9mm thick non slippery ceramic floor tile
beded on & including 41mm thick cement m² 149.00 760.00 113,240.00
sand screed and joints grouted.
6.9 Ceramic tile skirting stuck to wall with cement 40.00 238.00 9,520.00
mortar m
6.10 2mm thick plastic tile flooring laid with m² 274.00 650.00 178,100.00
approved type adhesive glue
su 7. PAINTING
m
prepare the surface and apply three coat of
plastic emulsion paint.to
7.1 External plasterd surface m2 866.00 45.00 38,970.00
7.2 Internal plasterd surface m 2
1,796.00 45.00 80,820.00
7.3 plasterd ceiling surface m 2
627.00 48.00 30,096.00
7.4 plasterd stair case belly & sides surface m2 60.00 45.00 2,700.00
7.5 wooden celilng cerface (Varnish paint) m2 157.00 68.00 10,676.00
Total Carried to Summary 163,262.00
8. GLAZING
Supply and fix quality clear glass glazed to
metal beads and putty ( for top fun light
wooden doors)
8.1 4mm thick m² 20.00 500.00 10,000.00
Total Carried to Summary 10,000.00
9. SANITARY INSTALLATION
Item
No Description Unit Quantity Unit Rate Total Amount
-
Specified PP-R(OD)
diameter 15 mm diameter 25 mm ml 62.00 78.00 4,836.00
diameter 20 mm diameter 32 mm ml 20.00 89.00 1,780.00
diameter 32 mm diameter 50 mm ml 78.00 130.00 10,140.00
diameter 40 mm diameter 63 mm ml 26.00 200.00 5,200.00
2 Supply and fix vesbo type gate valve, on PP-R
pipe lines complete with PP-union CP brass
head /hand wheel
diameter 15 mm No 4.00 415.00 1,660.00
diameter 20 mm No 2.00 450.00 900.00
diameter 32 mm No 5.00 730.00 3,650.00
diameter 40 mm No 1.00 765.00 765.00
3
Supply and fix crome angel valve,omplete with
union, hand wheels & all necessary acceeories
No 24.00 115.00 2,760.00
or approved quality for each fixturer.All as per
Bs -5154 or its equivalent.
diameter 15 mm internal
Sanitary Fixtures and Fittings
Supply & fix Hand wash Basin of approved
quality in while vitreous china, Complete with
concealed fixing bracket,plugs, chains smell
4
traps, flexible pipe cold hot water taps,
adapters etc
Supply and fix enameled cast iron shower tray No 9.00 3,196.00 28,764.00
complate with chrome plated arm valve and
6 adjustable shower head
Site works -
POWER OUTLET
3
Philips TCS 020/136 EBT M2+1x36w fl lamp No 4.00 468.00 1,872.00
4 Philips TCS 120/136 EBT M2+2x36w fl lamp No 4.00 730.00 2,920.00
6
Philips TCS 020/218 EBT M2+2x18w fl lamp No 36.00 468.00 16,848.00
Lombardo LB 51122+1*23w energy saving
7 lamp No 5.00 450.00 2,250.00
pilux /Danpex MAL1.18DLTHSER +1x18w fl
8 lamp No 9.00 436.00 3,924.00
Lombardo LB 14221+1*15w energy saving
9 lamp No 8.00 420.00 3,360.00
Massive 70748/02/43 +2*15w energy saving
10 lamp No 12.00 460.00 5,520.00
Massive 81748/02/43 +1*15w energy saving
11 lamp No 18.00 460.00 8,280.00
RZB 33 709.004 +18w energy saving lamp
12
No 12.00 460.00 5,520.00
Item
No Description Unit Quantity Unit Rate Total Amount