FOR FABRICATION
PIPING WORK
I INTRODUCTION
II PROJECT OVERVIEW
IV PROCUREMENT
V SHOP FABRICATION
VI HSE
VII QA/QC
1. General HSE induction and Safety moment.
I. 2. HEC Welcome Address and formal
INTRODUCTION introductions.
3. SUBCONTRACTOR Welcome Address and
formal introductions.
II. - Project information
PROJECT - Project Scope of Work and Schedule in brief
OVERVIEW - Objectives and Commitments
Project Scope and
Project Information Project Objectives
Schedule
• Hyundai Engineering Co., Ltd 1. Scope of Supply: • Zero LTI.
(HEC) is EPCC Contractor • HEC provide detail • Complete work on time
for PETROCHEMICAL engineering, main material. • Welding repair rate (RT film):
COMPLEX IN SOUTH OF • PVC provide construction < 3%
VIETNAM - PACKAGE G engineering, consumable • Build trust and Extend
CENTRAL UTILITY PLANT material. corporation between HEC
(VLSU). 2. Quantity of work: and PVC in LSP project and
• PVC have been awarded as • Total BOQ: 70.932 DI other projects.
Subcontractor for Piping • Total Pipe support: 78 tons
Prefabrication and Piping • Total Painting quantity:
Painting work which is under 18,835 m2
Scope of HEC at LSP-PKG G 3. Project Schedule:
project. • Start: August 2019
• Finish: July 2020
• Duration: 12 months
1. Project Organization
III. 2. Project Communication: Correspondence
PROJECT Procedure, Communication Channel,
MANAGEMENT Documentation, Meeting & Reporting
& CONTROL 3. Progress Measurement & Invoicing Procedure
4. Local Authority Permit
PROJECT DIRECTOR
CONTRACTOR TRAN SY HUAN
PROJECT DIRECTOR tranhuan@pvc-ms.vn
PROJECT MANAGER
CONTRACTOR
PROJECT MANAGER
DOAN VAN DIEP
diepdv@pvc-ms.vn
: Petro Viet Nam Construction Joint Stock Correspondence from HEC to PVC
- PVC
Company
- Letters HEC-PVC-L-XX-0001
- Emails HEC-PVC-E-XX-0001
(3) Sender or Recipient Code - Transmittal HEC-PVC-T-XX-0001
Correspondence from PVC to HEC
- Email :E
- Letters PVC-HEC-L-XX-0001
- Transmittal :T - Emails PVC-HEC-E-XX-0001
- Letter :L - Transmittal PVC-HEC-T-XX-0001
Communication Channel
PVC’s PVC’s
CC (TBA) CC (TBA)
Documentation
(1) Deliverable List
• Master Document Index (MDI) needs to be prepared for both of parties.
• Documents & Drawing shall be controlled by MDI.
HSSE plan ▲ ●
Attendees
Meeting Time Content
HEC PVC
Reporting
Cut off date is on HSSE, QA/QC, planning & progress, Procurement, Area of
Weekly
Friday every week concerns
Manpower, Equipment
Daily Daily
Inspection Note, Daily progress
* Cut-off date for monthly
payment : Follow the contract
condition
Contract
VAT Receive
PVC Breakdown
Invoice Payment
Sheet Submission
N N
Review/ Review/
Approval Approval
HEC
Y
Y
IV.
1. Procurement plan for Consumable
PROCUREMENT
2. Storage Methods of Materials against climate
Note:
• HEC to provide approved vendor list for painting and consumable
material
• PVC to request for additional vendor if any
- All small-sized fittings,
flanges and valves, and all
of gaskets shall be stored
on racks/shelves.
- Large-sized fittings,
flanges and valves shall be
stored on wooden pallets
and no material is allowed
to rest or store directly on
ground at all time.
- Welding rod and painting
to be kept in container.
1 Construction X
Engineering
2 Procurement X For
consumable
material
N/A
3 Construction
Pre-fabrication X
Painting X
NDT, PWHT X
CONSTRUCTION MANAGER
CONTRACTOR
HO DANG DUY
CONSTRUCTION MANAGER dangduy@pvc-ms.vn
GROUP 1 GROUP 2
BLASTING&PAINTING Pipe Support
GROUP 3 GROUP 4
(14 persons) (12 Persons)
Cacbon steel SS/ALLOY
(53 persons) (20 person)
Equipment Mobilization
Manpower Mobilization
3. BOQ & PROGRESS
PIPING PRE-FABRICATED - OVERALL PROGRESS
90,000
78,800 79,588
80,000 79,588 75,648
75,648
66,980
70,000
58,312
60,000
47,280
50,000
INCH DIA
47,280
40,000 35,460 Baseline Plan Cumulative
10,000 3,940
-
-
-
- - - - - - - - - -
PROJECT MONTH
3. BOQ & PROGRESS
14,000
11,820 11,820
12,000
11,032 11,032
10,000
8,668 8,668 8,668
8,000
INCH DIA
3,940
4,000
3,152
2,000
788
-
Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
PROJECT MONTH
3. BOQ & PROGRESS
RAW MAT’
LAYDOUT
II. SHOP PIPING AND PAINTING WORKS
- Case 2 (Spool)
Transportation by HEC Transportation by Shop Subcon Transportation by SMP Subcon
( Equip : Trailer, Crane) ( Equip : Trailer, Crane) ( Equip : Trailer, Crane)
Note:
• Case 2 will be applied.
Material Control Process
Marking traceability
Material receipt Inspection Material. Handling storage
number on material
Make
NDE Welding Tag name Fit up
Packing and
Blasting & Inspection Transportation
Painting Painting to HEC
warehouse
Cutting pipe
Final Painting/ Spools Cleaning Inside
Spools protection End cap/
Trainsportation to Site
V.
1. HSSE Organization
HSSE
2. HSSE Plan
CONTRACTOR HSE MANAGER
VU QUANG HUNG
HSE MANAGER hungvq@pvc-ms.vn
• Project HSE Plan Training HSE for new Weekly HSE Walkabout &
employees Meeting
• Emergency Response
Procedure First Aid training Weekly Toolbox Meeting
Firefighting training Pre-Shift safety briefing
• Radiation Safety Procedure
In-house safety training for
• Permit to work procedure
specific activities. (confined
• Waste Management space, working at height,
Procedure lifting & rigging, etc.)
• Inspection and
Maintenance of Lifting
Equipment Procedure
1. QA/QC Organization
VII.
2. Welding Control Procedure
QA/QC
3. Welding Data Management
QA/QC MANAGER
CONTRACTOR
NGUYEN VAN CONG
QA/QC MANAGER nguyencong@pvc-ms.vn
WELDING ENGINEER
DOC. CONTROLLER
PHAM HONG KIEN
NGUYEN DANG HAI
Ms. VO THI KIM HONG
NGUYEN ANH DUNG
NDE/PWHT
QC INSPECTOR PAINTING DATA INPUT Coordinator
PHAM HONG KIEN INSPECTOR
1. PREPARATION 2. BEFORE
- WPS Qualification WELDING 3. DURING 4. AFTER WELDING
- Welder/ Operator - Material Identification WELDING - Visual inspection
Qualification - Welding consumable - Welding per WPS - PWHT (if any)
- Equipment Calibration/ to be used - Welding condition/ - NDT
Inspection - Fit-Up Inspection Parameter - Weld Repair
- Welding Consumable - Qualified WPS to be - Welding - Record/ Reports
Control applied consumable Control - Welder
- Qualified Welder to Performance
be employed
Note:
• Current available PQR is planned to used for the Work.
• Welder to be qualified one month before start work.
• “IT System” to be applied to input and output welding data. HEC to
provide training one month before start work at PVC’s office.
Data Input Work Flow
Construction Team
(Fit up, Visual & NDT
Request)
NDT/PWHT
(by HEC)