METHOD STATEMENT: LIFT with Machine Room
Ref: MOS-CBE-ME-0011 Rev.: 00 Date: 16-02-2022 Page 1 of 15
METHOD STATEMENT
FOR
INSTALLATION OF
LIFT with Machine Room
If, despite best endeavours, a conflict should arise between this Method Statement and the Project
Specification the requirements of the latter shall be observed and this document revised, accordingly.
Amendments History
Rev Clause Changes Made
00 - Original issue of document
01
02
CBE Central Bank in New Elminia-
Elminia
METHOD STATEMENT: LIFT with Machine Room
Ref: MOS-CBE-ME-0011 Rev.: 00 Date: 16-02-2022 Page 4 of 15
1.0 Scope
This method statement covers installation, testing and commissioning and start up and all
documents, inspections, certificates, etc., necessary to regulatory approval of the CRAC.
This report specifies features for:
Floor standing PDX CRAC unit
DX remote condenser unit.
The equipment to be supplied shall be installed so that all provisions for easy access for
inspection, cleaning, maintenance and repair.
2.0 References:
• Project Specification
• Supplier requirement
• QC Technicians:
• Continuous monitoring of and real time reporting to QC Engineers of ongoing concrete
works.
CBE Central Bank in New Elminia-
Elminia
METHOD STATEMENT: LIFT with Machine Room
Ref: MOS-CBE-ME-0011 Rev.: 00 Date: 16-02-2022 Page 6 of 15
• Laboratory Technicians:
• Receipt and checking of concrete delivery tickets.
• Sampling of concrete for workability and other testing as may be required.
• Sampling of concrete for cubes/cylinders, as applicable.
• Maintenance of cubes/cylinders prior to compressive strength testing.
• Compressive strength testing of cubes/cylinders and reporting of results.
• Technical Office:
• Technical and engineering documents management.
• Development and gaining approval of Issued drawings, materials and other technical
submittals and their distribution as required.
4.0 Material
5.0 Procedure
1 Drive the working platform/cabin by hoist to a suitable height to fix the next guide rail
joints.
2 Engage the safety gear and connect the safety / parking chain.
3 Lift the next guide rail and place the guide rail in position. Fix the guide rail to the fish
plate with hand tight bolts. Lower the sliding clamp and remove it. Align the joint and
tighten the bolts.
4 Drive the working platform to the next wall fixing bracket level. Fix the guide rail to the
bracket and align by using the aligner.
5 Install the guide rails up to the top of the elevator shaft.
6 Mark the center line of the counter weight (CWT) guides on to the rear wall using a
radius stick.
7 Mark the CWT plumb lines position as per layout drawing and hang the plumb lines to
the pit.
8 Install the four no lowest CWT guide brackets in position, lift the first CWT guide rail
and fix it to the guide brackets with correct guide clips.
9 Set the alignment tool and align the guide rails, check the Distance between Guides
(DBG). Tighten the bolts and nuts.
CBE Central Bank in New Elminia-
Elminia
METHOD STATEMENT: LIFT with Machine Room
Ref: MOS-CBE-ME-0011 Rev.: 00 Date: 16-02-2022 Page 10 of 15
10 Continue the CWT guide rail installation from the car floor and working platform until
all the CWT guide rails have been installed.
11 Lift and fit the CWT buffer in position and fix it to the pit floor with anchor bolts.
12 Install CWT buffer supports and check the oil level of the buffer. (If necessary add)
13 Install CWT frame and position it as per layout drawing.
1 Install the trunking and conduit according to the elevator shaft layout drawings.
2. Install the shaft bundles until the lowest landing floor.
3 Fix the car top connection box to the car roof.
4 As per the wiring diagram route all the cables to connection box and connect it.
5 Install the deceleration and final limit switches as drawing.
6 Install the oscillator switches on the car top.
7 Do the connection for all gate lock.
8 Install the emergency alarm and pit switch and do the wiring.
9 Install the floor signalization and do wiring.
10 Route and connect the car & counter-weight buffer contact cables to the shaft
bundle.
11 Route and connect the over speed governor rope tension weight contact cables to
the shaft bundle.
12 Place all the covers of the connection boxes and trunking.
13 Fix the car door sill to the car floor and check the level of the sill and the clearance
with landing sill.
14 Install the car door header to the front panel and align. Check the height with
respect to car sill.
15 Install the car door header to the front panel and align. Check the height with
respect to car sill.
16 Install the car door. Check the alignment and couple doors together.
17 Install the decoration car panels and align.
18 Fix the light, fan and intercom unit and do the wiring.
19 Do all car related wiring.
20 Install the landing call station and indicators and do the wiring.
7.0 SAFETY
7.1 PRECAUTIONS
1 The prevailing local safety codes and rules as well as site regulations must be obeyed at all
time.
2 Use of personnel protective equipment (PPE) like safety shoes, helmets, safety harness,
gloves, safety glasses etc.,
3 Covering of all openings that are not used in the machine room during working.
4 Landing door protection at all times
5 Ensure the clear access to the machine room.
6 Availability of First Aid equipment.
7 Ensure proper access to the site.
8 Adequate lighting inside the shaft and machine room. Only proper sockets and cables to be
used for electrical works.
9 Proper storage for materials
10 Check the condition of the hand tools and tackles used.
11 Use of warning signs where applicable.
12 Nobody is allowed to work below in the shaft when the work is carried out above.
13 Close and secure machine room doors when the machine room is unoccupied.
14 Check that rust protection crease is removed from the rails otherwise the safety gear will
not operate correctly.
15 Ensure that the daily safety gear checks are made
7.2 INSPECTION
8.0 HANDOVER
8.1 INTERNAL HANDING OVER
1.1 Will be carried out once the installation and testing is completed.
1.2 Installation supervisor and maintenance supervisor check the lift and complete
Installation/Service hand over form.
Submit the test report and hand over the lift for beneficial use.