Professional Documents
Culture Documents
Page
2 of 13
TABLE OF CONTENTS
1. GENERAL ............................................................................................................................................................. 3
1.1 INTRODUCTION ................................................................................................................................................. 3
1.2 PURPOSE ......................................................................................................................................................... 3
1.3 DEFINITIONS .................................................................................................................................................... 3
7. DOCUMENTATION............................................................................................................................................... 7
8. SUBCONTRACTORS/SUBVENDORS................................................................................................................. 7
9. HANDLING ............................................................................................................................................................ 7
9.1 PACKAGING AND SHIPPING ............................................................................................................................... 7
9.2 PRESERVATION AND STORAGE ......................................................................................................................... 7
Page
3 of 13
1. GENERAL
1.1 Introduction
This Design General Specification defines the technical requirements for the furnishing and
installation of all masonry and accessories.
1.2 Purpose
This Design General Specification is provides criteria for the furnishing of all materials, equipment
and installation of all masonry and accessories as outlined on the DRAWINGS, in the contract and
this specification.
1.3 Definitions
Where used in this specification, the following terms shall have the meanings indicated below
unless otherwise clearly indicated by context of their use.
COMPANY: ABU DHABI GAS INDUSTRIES LTD. (GASCO).
CONCESSION REQUEST: A deviation requested by the CONTRACTOR or VENDOR, usually after
receiving the contract documents or purchase order. Often, it refers to an authorization to use,
repair, recondition, reclaim, or release materials, components or equipment already in progress or
completely manufactured but which does not meet or comply with the COMPANY requirements. A
CONCESSION REQUEST is subject to COMPANY approval.
PROJECT: To be defined.
CONTRACTOR: the party(s) which carries out all or part of the design, engineering, procurement,
construction, commissioning or management of the PROJECT.
MANUFACTURER/VENDOR/SUPPLIER: The party(s) which manufactures and/or supplies the
material/equipment, and provides technical documents/drawings and services to perform the duties
specified by COMPANY/CONTRACTOR.
SUBCONTRACTOR/SUBVENDOR: The party(s) which carries out all or part of the design,
procurement, installation and testing of the System(s) as specified by the
CONTRACTOR/VENDOR.
PROJECT MANAGEMENT TEAM (PMT): The COMPANY authorized party responsible for the
overall day-to-day execution of the Project. The PMT is to serve as the liaison between the
COMPANY and the CONTRACTOR(S) on the PROJECT.
SHALL: Indicates a mandatory requirement.
SHOULD: Indicates that the requirement is strongly recommended to be adhered to
DRAWINGS: Drawings provided by the CONTRACTOR.
Page
4 of 13
Page
5 of 13
3. REFERENCE DOCUMENTS
The following reference documents, to the extent specified herein, form a part of this specification.
When an edition date is not indicated for a document, the latest edition in force at the time of
contract award shall apply.
Page
6 of 13
4. DOCUMENT PRECEDENCE
It shall be the CONTRACTOR‘S responsibility to be, or to become, knowledgeable of the
requirements of the referenced Codes and Standards.
The CONTRACTOR shall notify the PMT of any apparent conflict between this specification, the
related data sheets, the Codes and Standards and any other Design General Specifications noted
herein. Resolution and/or interpretation precedence shall be obtained from the PMT in writing before
proceeding with the design / manufacture.
In case of conflict, the order of precedence shall be:
Purchase Order or Contract including Project Drawings and Specifications
Design General Specifications and Standards
Industry Codes and Standards
Page
7 of 13
The CONTRACTOR shall identify in documents to its VENDOR‘s and SUBCONTRACTOR‘s all
applicable QA/QC requirements imposed by the COMPANY, and shall ensure compliance.
On request, CONTRACTOR shall provide objective evidence of its vendor and subcontractor
QA/QC activities.
7. DOCUMENTATION
The construction drawings shall be issued by CONTRACTOR (or a SUBCONTRACTOR) and
―approved for CONSTRUCTION‖ before the work commence.
The procedures for title block, issuing of the documentation shall be strictly followed.
8. SUBCONTRACTORS/SUBVENDORS
The CONTRACTOR shall assume unit responsibility and overall guarantee for the works.
It is the CONTRACTOR‘s responsibility to enforce all Purchase Order and Design General
Specification requirements on its SUBCONTRACTORS /VENDORS.
The CONTRACTOR shall submit all relevant SUBCONTRACTORS / VENDORS
engineering/design data to the COMPANY.
The CONTRACTOR shall obtain and transmit all SUBCONTRACTORS / VENDORS warranties to
the COMPANY.
9. HANDLING
10. MATERIALS
The CONTRACTOR shall submit an ―Affidavit of Compliance‖ before beginning construction. The
Affidavit shall confirm that all material meets the requirements of this specification.
11.1 General
Page
8 of 13
11.2 Materials
Aggregate for Grout: BS EN 12620, coarse aggregate size No. 8 and fine aggregate size No. 1.
All cement shall be the product of a single manufacturer.
11.3 Execution
Page
9 of 13
When conditions are such as to cause drying of the mortar, batch size shall be such that all
materials will be used within two hours.
Mortar on the board shall be kept well tempered with water, so long as its cementing material has
not started to set, so that it will be soft and workable when placed in the wall. No retempering of
mortar will be permitted. All mixers, mortar boxes, etc., shall be cleaned out at noon and at night.
11.3.3 Grouting
Place reinforcement before grouting. Place before or after laying masonry units, as required by job
conditions.
Prior to grouting, inspect and clean grout spaces. Remove dust, dirt, mortar droppings, loose pieces
of masonry and other foreign materials from grout spaces. After final cleaning and inspection, close
cleanout holes and brace closures to resist grout pressures.
Do not place grout until entire height of masonry to be grouted has attained sufficient strength to
resist displacement of masonry units and breaking of mortar bond. Install shores and bracing, if
required, before starting grouting operations.
Limit grout pours to sections that can be completed in one working day with not more than one hour
interruption of pouring operation. Place grout in lifts that do not exceed 1500 mm. Allow not less
than 30 minutes, nor more than one hour between lifts of a given pour. Rod or vibrate each grout lift
during pouring operation. When more than one pour is required to complete a given section of
masonry, extend reinforcement beyond masonry as required for splicing. Pour grout to within 40
mm of top course of first pour. After grouting masonry is cured, lay masonry units and place
reinforcement for second pour section before grouting. Repeat sequence if more pours are
required.
12.1 General
12.1.3 Manufacturers
Local manufacturers (precast vendors) in UAE shall be approved by COMPANY for the proposed
application.
12.2 Materials
The references of codes and standards, materials, manufacturers or suppliers specified in this
section are intended to establish a standard of quality or a level of performance and are not
intended to prevent the use of equivalent or superior products. Other references of materials,
manufacturers or suppliers are acceptable only after the approval from COMPANY for the proposed
application. Material approval shall be obtained prior to the procurement/construction.
Page
10 of 13
12.2.2 Reinforcement
Masonry horizontal reinforcement shall consist of welded steel wire, truss type, with 5mm diameter
(minimum) deformed side rods connected with 4mm diameter (minimum) diagonal cross rods.
Prefabricated corner pieces shall be used at all corners. Reinforcement shall be properly sized for
the type of construction and thickness of wall. Joint reinforcement shall comply with ASTM
A951/A951M.
Steel reinforcing bars and rods for use as vertical reinforcement and in bond beams and lintels shall
conform to type 2, Grade 460 in accordance with BS 4449 or ASTM A615/A615M Grade 60.
Details of reinforcement including placement and protection shall conform to Building Code
Requirements for Masonry Structures (ACI 530/ASCE 5).
12.3 Execution
Page
11 of 13
13.1 General
13.1.4 Design
The design of Masonry Units shall be in accordance with Specification DGS-1882-001, Structural
Design Basis.
13.2 Materials
Page
12 of 13
Concrete block used to construct the exterior walls shall be smooth masonry units.
All concrete masonry units shall have a uniform texture and be smooth faced, as required.
Special shapes shall be supplied as required by the DRAWINGS.
All exterior concrete block, including precast lintels, shall contain the recommended amount of
integral water-repellent admixture.
Acceptable manufacturers for integral water-repellent admixtures shall be considered for approval
upon review of information submitted to the COMPANY.
No other admixtures or additives should be used unless written approval is given by the integral
water-repellent admixture MANUFACTURER.
Obtain Concrete Masonry Units from one Manufacturer throughout job, uniform in texture and color,
and cured by one process.
13.2.3 Manufacturers
Acceptable manufacturers or suppliers shall be approved by CONTRACTOR and COMPANY.
13.3 Execution
13.3.1 Installation
All walls shall be built true to dimensions, plumb, and square. All work shall be laid to line, in level
courses and all individual face units shall be kept ―in plane.‖
All unit masonry shall be laid using running bond. Joints shall run straight and plumb. Block cores
shall be reinforced as indicated on the DRAWINGS.
All masonry units shall be laid in a full bed of mortar with full head joints. All such mortar shall
contain the recommended amount of integral water-repellent admixture mortar admix for water
repellency and to assure proper bond strength.
All required cutting of masonry units shall be done with power equipment which will produce true
edges free of chipping and undamaged surfaces.
Where fresh masonry joins masonry that is partially or totally set, the exposed surface of the set
masonry shall be cleaned and wet lightly so as to obtain the best possible bond with the new work.
All loose masonry and mortar shall be removed. If it is necessary to ―stop off‖ a run of masonry, this
shall be done by raking back one-half unit length of each course. No toothing will be permitted.
Joints in all exposed masonry work shall be firmly and neatly tooled, when mortar is thumbprint
hard, to a slightly concave profile, unless indicated otherwise. All concealed joints shall be cut off
flush and surplus mortar shall be brushed off as work progresses.
a. Brick work/block work shall be carried up in a uniform manner with no one portion being raised
more than 1.0 M above another at any time unless special circumstances render this
impracticable.
b. The maximum height which is to be built in one day is 1.5 M. In the case of walls built using
retarder mortars, the maximum height which is to be built in one day shall be 1.0 M.
c. Walls built using retarder mortar shall be adequately cured for a period of not less than 24 hours
before any further work on the wall can take place.
Page
13 of 13
d. The mortar beds and vertical joints shall be 10 MM nominal thickness and shall not exceed 15
MM.
Other trades shall be consulted and provisions made to permit installation of their work in a manner
which will avoid cutting and patching as the work progresses.
Tapping of units shall not be permitted after mortar has taken its initial set. Irregular work shall be
replaced with fresh mortar.
Masonry wall intersections shall be bonded with joint reinforcing, except at control joints.
Masonry joints shown to be caulked shall be raked back 12 mm. Sides of caulking recess shall be
free of mortar.
All loose lintels (steel, precast concrete, etc.) shall be installed by the SUBCONTRACTOR.
All bond beams shall be built in as indicated on the DRAWINGS. They shall be reinforced and filled
as detailed.
All masonry reinforcement, control joints, and flashings shall be installed as specified in Masonry
Accessories section.
13.3.2 Protection
All masonry work shall be properly protected from staining, the elements, and from damage at all
times. Top of all walls shall be covered at end of each workday.
13.3.4 Cleaning Up
Upon completion of the work all surplus materials, debris, tools, and equipment shall be removed
from the site.