Professional Documents
Culture Documents
Project Name :
Activity ID WBS ID Activity Name & Description
M1 Conduct Survey
3.1.1.1
M2 3.1.1.2 Design Network
Planning 3.1.1
M3 Estimate Materials
3.1.1.3
M4 Procure Materials
3.1.1.4
M5 Obtain NOCs
3.1.1.5
M7 Shift Materials
3.1.2.1
Construction of Mains (Level 2) 2.1
M8 Excavation of Site
3.1.2.2
Execution 3.1.2
3.1.2.4
3.1.2.7
M14 3.1.3.1 Tie-in with TBS
M15
Supply to Hakeem Pura (Level 1)
Comissioning 3.1.3
M17 Clear Site
3.1.3.4
M21
Planning 3.1.1
Estimate Materials
3.2.1.3
3.2.2.1
M26
Execution 3.2.2
3.2.2.4
M29 3.2.2.5 Install Fencing
M30 3.2.2.6
Paint the TBS and Fencing
M31 3.2.3.1
Tie-in with Existing Network
Comissioning 3.2.3
1 2 5
2 3 3
3 4 1
4 5 60
2 5 90
5 6 2
6 7 5
7 8 60
8 9 30
9 10 7
10 11 4
11 12 2
12 13 4
13 14 1
14 15 1
35 16 1
16 17 1
17 18 10
1 19 5
19 20 3
19 21 1
21 22 60
22 23 90
23 24 2
24 25 3
25 26 15
26 27 2
27 28 20
28 29 3
29 30 2
30 31 1
31 32 1
32 33 1
33 34 1
34 35 1
Total Project Duration: 2 Yrs.