You are on page 1of 7

Activity List and Attributes

Project Name :
Activity ID WBS ID Activity Name & Description

M1 Conduct Survey
3.1.1.1
M2 3.1.1.2 Design Network

Planning 3.1.1
M3 Estimate Materials

3.1.1.3

M4 Procure Materials
3.1.1.4

M5 Obtain NOCs
3.1.1.5

M6 Issue Work Orders


3.1.1.6

M7 Shift Materials

3.1.2.1
Construction of Mains (Level 2) 2.1

M8 Excavation of Site

3.1.2.2
Execution 3.1.2

M9 3.1.2.3 Weld Pipes

M10 Lower in Trench

3.1.2.4

M11 Perform Radiographic Testing


3.1.2.5

M12 Perform Pneumatic Testing


3.1.2.6

M13 Perform Backfilling

3.1.2.7
M14 3.1.3.1 Tie-in with TBS

M15
Supply to Hakeem Pura (Level 1)

Perform Radiographic Testing of Tie-in Joint


3.1.3.2
Comissioning 3.1.3

M16 Commission Gas


3.1.3.3
Gas Supply to Hakeem Pura (Level 1

Comissioning 3.1.3
M17 Clear Site

3.1.3.4

M18 Reinstate Area


3.1.3.5
M19 3.2.1.1 Conduct Survey

M20 Design TBS


3.2.1.2

M21
Planning 3.1.1
Estimate Materials

3.2.1.3

M22 Procure Materials


3.2.1.4

M23 Obtain NOCs


3.2.1.5

M24 Issue Work Orders


3.2.1.6
Construction of TBS (Level 2) 2.2

M25 Excavation of Site

3.2.2.1
M26
Execution 3.2.2

Perform Welding and Fabricating


3.2.2.2

M27 Perform Radiographic Testing


3.2.2.3

M28 Construct Foundation

3.2.2.4
M29 3.2.2.5 Install Fencing

M30 3.2.2.6
Paint the TBS and Fencing

M31 3.2.3.1
Tie-in with Existing Network
Comissioning 3.2.3

M32 Perform Radiographic Testing of Tie-in Joint


3.2.3.2

M33 Commission Gas


3.2.3.3
M34 3.2.3.4 Perform Soap Test

M35 Clear Site


3.2.3.5
Construction of TBS (Level 2) 2.2
d Attributes

Predecessors ID Successors ID Duration

1 2 5

2 3 3

3 4 1

4 5 60

2 5 90

5 6 2

6 7 5

7 8 60

8 9 30

9 10 7

10 11 4

11 12 2

12 13 4

13 14 1

14 15 1

35 16 1
16 17 1

17 18 10
1 19 5

19 20 3

19 21 1

21 22 60

22 23 90

23 24 2

24 25 3

25 26 15

26 27 2

27 28 20

28 29 3

29 30 2

30 31 1

31 32 1

32 33 1

33 34 1

34 35 1
Total Project Duration: 2 Yrs.

Total Meterage of Network 3000 Meters Per Day requirement:

Per Day requirement:


(per welding team)
Total Connections 500 nos.
tal Project Duration: 2 Yrs.

50 Meter/Day Days Required For Laying 60 Days

Days Required For total


Connections:
5 nos./day 100 Days

You might also like