You are on page 1of 7

Economical structural design of natural gas

processing plants
Case study of a butane treatment unit illustrates effective structural design procedures
and highlights construction challenges encountered in new and expansion projects

OSAMA BEDAIR
Consultant

N
atural gas processing sepa- process, mechanical, and structural time optimisation models in the
rates hydrocarbons and flu- engineering disciplines. The engi- gas processing industry. The con-
ids from pure natural gas to neering design is normally staged cept enables operating facilities to
produce dry gas suitable for pipe- into several gates that require the respond efficiently and effectively
line transportation. Raw natural gas owner’s approval for funding. to changing feed rates and compo-
is first collected from oil wells then Delays in construction projects due sition, equipment condition, and
processed at collection points using to engineering ambiguities may dynamic processing economics.
separator vessels to remove fluids result in substantial losses in the Liu, et al6 presented modelling and
and other impurities. Gas process- form of interest on construction optimisation tools for the petro-
ing plants convert natural gas to loans, management/staff time, and leum refinery process. Bulasara,
other products such as gasoline, an increase in commodities prices as et al7 presented a study to revamp
ethane, butane, and propane. In a result of the continuous inflation heat exchangers in process plants
some cases, hydrocarbon materials of material prices. to evaluate various commercial
such as ethane, propane, and butane Significant work has dealt with aspects. Lulianelli and Drioli8 pre-
must be extracted from natural gas chemical and mechanical design sented a review of recent develop-
prior to pipeline transportation. improvements compared to ments of gas separation technology
Fractionation converts raw material structural aspects. Patience and used in the petrochemical indus-
into refined products transported Bockrath1 presented a butane oxi- try and refineries. The review also
using pipelines to various process- dation technique used in circulating highlighted the importance of mem-
ing units for further processing. a fluidised bed reactor to produce brane reactors for fuel processing
Liquefied petroleum gas (LPG) anhydride from n-butane Wu, et and membrane-based pretreatments
refers to propane or butane (either al2 presented a study to enhance and integrated membrane gas sepa-
separate or in a mix), maintained catalytic performance for butane ration systems. Other aspects deal-
in a liquid state under specific pres- oxidation. Sáez, et al3 performed ing with process design or butane
sure/temperature within a vessel. experimental tests employing a process plants are presented by
LPG is a valuable energy source diesel oil burner to study the com- Gallagher9 and Meyers10. Bedair11-15
and is widely used as a chemical bustion process of liquid butane. A addressed various design aspects of
feedstock for the petrochemical dual pumping and injection system structural members used in heavy
and agriculture industries. Butane was designed to operate with pres- industry.
is a hydrocarbon gas (C4H10) that is sures varying from 0.8 to 2.0 MPa. Not much information is available
colourless, odourless, flammable, They also performed a feasibility on the structural design improve-
and can be easily liquefied. Butane study to modify the combustion ments of natural gas process-
is used as fuel for portable stoves/ technology of diesel oil burners to ing plants. Most effort is directed
barbecues, a propellant in aero- use liquid butane as an alternative towards process or chemical design
sols, refrigerants, and a feedstock fuel. Yang, et al4 presented a pro- aspects. Investigators and plants
to manufacture ethylene and buta- cess model that utilises n-butane owners have given barely any atten-
diene, a key ingredient of synthetic compounds to extract organic pol- tion to improving structural design
rubber. Butane extractions occur lutants from contaminated water. aspects of hydrocarbon facilities.
in a closed-loop extraction system. Removal efficiencies for hydropho- Minimal literature has addressed
These units are closed, devoid of bic pollutants were greater than structural engineering requirements
atmosphere, and recover the gas to 90%. Removal of residual butane of natural gas processing plants.
its original vessel. in treated effluent was achieved by Furthermore, most of the design
Design cycles of natural gas pro- depressurisation, air stripping, and provisions available in the North
cessing plants are complicated and elevating operating temperature. American codes of practice16-22 deal
require close interaction between Mokhatab and Poe5 introduced real- with residential structures.

www.digitalrefining.com Gas 2022 31


Therefore, it is important to high- • Pumps and compressor house nal concrete foundations. The pumps
light requirements for the structural (PCH) and compressor house (PCH) is
design of natural gas processing • Butane reactor (BR) located in the southwest quadrant of
plants. This article presents a butane • Steel modules (SM-01), (SM-02) the BTU. This facility consists of steel
treatment unit (BTU) case study to • Substation building (SB) framing that partitions each piece of
illustrate effective structural design • Control building (CB) equipment and concrete pad base
procedures and highlight construc- • Heat exchangers, horizontal and supports. Mechanical equipment
tion challenges encountered in new vertical vessels is shown in orange. Steel module
and expansion projects. The layout • Underground services, roads, and SM-01 is placed at the lower half of
of the BTU is presented to describe parking the BTU and supports heat exchang-
the facilities used in gas process- Note that the layout of the BTU ers, pipelines, and cable trays. Some
ing. Then, a brief overview of the may vary depending on the process heat exchangers are stacked to opti-
geometric characteristics of the design. The layout in Figure 1 was mise the floor space. Butane steel
facility is provided to identify load- designed to boost refinery produc- module SM-02 is located in the
ing mechanisms. Structural design tion of synthetic light crude oil to northwest quadrant of BTU and sup-
criteria developed for each facil- 232 mbbl/d. The orange arrow shows ports heat exchangers, pipelines, and
ity’s transportation, installation, the direction of north (N). Two main cable trays. Columns of steel mod-
and operation are also discussed. pipe racks support the pipelines ules (SM01) and (SM-02) are sup-
Simplified numerical modelling transporting process material from/ ported on pile foundations.
strategies are described to simu- or to the BTU. These are denoted as The substation building (SB) is
late load transfer and soil/structure horizontal (HPR) and vertical (VPR) shown in yellow and located in the
interactions. The article also pro- pipe racks in Figure 1. HPR supports southeast quadrant. This building
vides recommendations and guide- pipelines and cable trays running in consists of two elevated floors and
lines for engineers to use in practice. the east-west direction and consists hosts critical electrical equipment.
of seven modules. VPR runs from The building size and layout are
Butane treatment unit description south-north and consists of 13 steel determined by the required inte-
The BTU is part of the naphtha modules. rior equipment spacing. The control
hydrotreating facility and consists of: The butane reactor (BR) is located building (CB) houses critical instru-
• Horizontal (HPR) and vertical in the north-west (NW) quadrant of mentation controls and is occupied
(VPR) pipe racks the BTU and is supported by octago- almost continuously. Plant design
criteria were used to determine the
spacing between control buildings
and process units where explosion
(HPR)
potential is high.
The soil profile consists of four
main soil layers. The first layer is
sandy with pockets of clay, with a
N thickness of 3.0m. The second lay-
(VPR) ers consists of silty clay with traces
(SM-02) of coarse and an average thickness
of 5m. The third layer is made up
of silty sand mixed with very dense
to hard cemented siltstone. This
layer is very stiff and considered the
(BR)
(CB) bearing layer for pile foundations.
Groundwater level was detected at
about 3.0-4.0m depth.

BTU structural design criteria


Steel modules were designed
for erection, operation, testing,
and transportation load condi-
(SM-01) (SB) tions. The dead load consists of
(PCH) the total self-weight of structural
steel, equipment, permanent fix-
tures, fireproofing, insulation,
fixed partitions, piping, and elec-
trical material. The weight of cable
trays, safety ladders, cages, and
junction boxes was also taken into
Figure 1 Butane treating unit plan account. The grating dead load

32 Gas 2022 www.digitalrefining.com


was approximated using linear was approximated using 0.005 times a side angle. On the ground level
load distribution along the runs. factored gravity loads contributed (Z=0), mechanical pumps and hori-
The dead loads of pipes with small by that storey. zontal vessels are directly bolted to
diameters were converted into an the central beams. Pipelines con-
equivalent uniform distribution. Steel module SM-01 necting the mechanical equipment
The pipe hydro-test load was not Steel module SM01 is used at the are shown in green. The figure also
applied concurrently with wind or BTU to support piping, electrical includes examples of vertical and
earthquake loads. Equipment dead cable trays, and mechanical equip- horizontal pipelines, electrical junc-
loads included equipment weight, ment. The size of the steel module tion boxes, and elevated platforms.
insulation, fireproofing, perma- is 5m x 7m x 12.6m and consists The intermediate level (Z)=5m sup-
nent fixtures, and attachments. of three levels. The frame base is ports the horizontal heat exchanger
Fireproofing material density was embedded in concrete foundations. and vertical process vessel. Blue
25 KN/m3. Cable tray weight was Figure 2 shows snapshots for SM-01 electrical cabinets are bolted to the
approximated using linear load dis- to provide insight into the steel steel beams. The third level (Z)=10m
tribution along the supporting beam structure loaded with equipment. supports horizontal vessel span-
spans. Concrete paving weight was The origin is located at the lower ning the y-axis. The vessel supports
approximated as 25 KN/m3. left-hand corner and denoted by O. are connected to the main framing.
Live loads included temporary/ Note that Z is measured from the The platform projections at (Z)=10m
maintenance loads and moveable ground elevation. Different view support electrical cabinets shown in
partitions. Floorplates and grat- layers were used to designate pipes, pink and pipelines. A bolted con-
ing loads were designed for a live structural steel, and electrical cable nection connects the platforms to
load of 4.8 KPa. Static loads and trays. Figure 2a displays the front the primary beams. Vertical pipe-
impact forces at start-up or normal elevation of the module showing lines penetrate the floor gratings to
operation were obtained from the mechanical equipments and pipe- connect mechanical equipment at
mechanical datasheet. Equipment lines to illustrate the loading mecha- various elevations.
load was extracted from vendor nism. Cable trays are shown in blue. Vertical pipe bends require sec-
drawings. Wind, snow, and earth- Vertical cable trays connecting var- ondary steel supports projected
quake loads were calculated using ious module levels are supported from the primary beam or column
NBC (2010). The notional load by horizontal projections from the members. Pipe horizontal bends
was added to the sway effects for primary beams. The structural steel (or expansion loops) are also com-
all load combinations. The trans- is coloured red, and process ves- monly used to reduce pipe stresses,
lational load effect produced by sels are silver. Figure 2b shows an as shown. Two major pipelines
notional lateral loads at each level isometric view of the module from with a diameter of 24in are placed

Connecting pipelines
Z Elevated Equipments
Horizontal vessels Z Horizontal vessel

Vertical cable trays


Vertical vessel

Electrical boxes
Heat exchanger

Y
X
Junction box Y
B
(O)
(O) 2
(a)
A 1

(b)
Fig.(2) SM01 snapshot with installed pipes/equipments
Figure 2 SM01 snapshot with installed pipes/equipment

www.digitalrefining.com Gas 2022 33


tions were modelled. The tempera-
ture change (ΔT) = ±40°C was used
A B 1 2
for steel members. Horizontal fric-
Z Z tion and anchor forces at start-up
2m 7m 5m
and shutdown conditions were also
2.6m PF1 2.6m considered.
PF2
The maximum beam vertical
M3 1m M3
Splice joint deflection is calculated as (δmax)
=14.6mm. The allowable beam ver-
5m
M2 4m M2 tical deflection is (δv)=17.5 mm. The
steel module sway deflection was
Splice joint calculated at several elevations to
assure compliance with the ser-
M1 5m M1 5m
viceability limit state. The maxi-
Y X mum sway deflection was found as
1
(O)
B
(O)
(δHmax) =61mm. The allowable sway
(a) Elevation A (b) Elevation B deflection was minimised to avoid
excessive lateral deflection that
may impact equipment function-
Figure 3 SM01 structural elevations ality. The largest lateral deflection
was (δH)Limit =63mm. The utilisation
on this level. A small platform is three sub-modules (M1, M2, M3) ratio index (UI) was calculated for
placed on the longitudinal beams and was assembled on-site using service limit state (SLS) and ulti-
to facilitate maintenance access dur- heavy lift cranes. The envelopes of mate limit state (ULS) conditions to
ing shutdown. Grating with vertical these modules are shown in Figure confirm compliance with CSA-S16
pipe penetrations were reinforced 3 as dashed rectangles. Pipelines, requirements. The maximum SLS
for holes larger than 300mm in cable trays, and mechanical equip- unity index is (UI)SLS=0.84 and (UI)
diameter. ment were installed and commis- ULS
=0.88.
Figure 3a shows structural eleva- sioned in the fabrication yard and Figure 4a shows the founda-
tions along grid line 1. Cantilever transported to the site. Four lifting tion pile cap layout for SM-01. The
platforms are used at levels (z)=5 points were used on each module. dashed circles denote concrete pile
and 10m. Vertical bracings reduce Orange represents M1, yellow M2, locations. For the erection condi-
tip deflections. A wide bracing and green M3. tion, the maximum SLS column
pattern is used at frame in the two reaction was found as (P)max =616
levels to maximise the access area SM-01 numerical simulation KN, maximum shear reaction (Q)
required for maintenance. Figure The structure was modelled using max
=78 KN, and (T)max =0. The criti-
3b shows the frame elevation along 568 (2D) elements with a total of cal columns for compression and
grid line B. The module along this 7043 degrees of freedom (DOF). shear forces are identified in Figure
grid line consists of three levels. Equipments and vertical piping 4a. Maximum ULS column reaction
Splice joints are also shown on this loads for empty, operational, and for the steel module was found to
elevation. Steel framing is con- testing conditions were considered. be (P)max=827 KN and the maximum
nected to primary beams at (Z)=5m Thermal loads (TL) arising from shear reaction was (Q)max =99 KN.
to support interior equipment. The contraction or expansion of the Section A-A through the pile
steel module SM-01 is divided into members due to temperature varia- cap is shown in Figure 4b. The pile
cap thickness used in this numer-
ical model is 0.6m. The steel skid
of the module SM-01 is partially
1 2
embedded in concrete to minimise
5m 4m
Z
15M @ 150mm 15M @ 150mm
the vibration effect induced during
B
operation. The vertical pile rein-
2m
0.6m forcements are projected into the
(P)max pile cap. The maximum FE pile cap
A A 15M @ 200mm
20-30M
moment is (Mmax) =120 KN-m/m.
7m
The recommended pile cap rein-
15M @ 200mm
(Q)max
forcement is shown in Figure 4b.
B B
20-30M The factored pile cap shear resist-
A ance is (Vc)= 1703 KN > 827 KN.
X
(a) Pile-cap layout (b) Section A-A (c) Section B-B The nominal pile diameter used
is 750mm and the maximum pile
length is 20m. Upon installation, the
Figure 4 SM-01 foundation plan and details pile head is treated as free headed

34 Gas 2022 www.digitalrefining.com


Horizontal cable trays

Pipeline system B

Vertical cable trays

X
(O)

Fig.(5) Snapshot of SM02 with showing installed pipes and cable trays
Figure 5 Snapshot of SM02 with showing installed pipes and cable trays

in the analysis. The allowable pile ment was installed and commis- imum SLS column reaction for
compression capacity in this case is sioned in the fabrication yard and SM-02 was computed as (P)max=526
(P)Cap =2200 KN and shear capacity then transported to the site. KN, maximum shear reaction (Q)max
is (QH)Cap =240 KN. The maximum =68 KN, and (T)max =0. For operating
pile lateral deflection was limited SM-02 numerical simulation and testing conditions, (P)max=851
to 6mm. After casting the concrete, Equipment and piping vertical KN, maximum shear reaction (Q)
the pile head is restrained against loads for empty, operational, and max
=89 KN, and (Tmax) =0. The max-
rotation. The pile lateral capacity testing conditions for SM-02 were imum ULS column reaction for the
for fixed condition is (QH)Cap =231 idealised at five nodes. Horizontal steel module was found to be (P)
KN. The pile group reduction factor friction and anchor forces at max
=1070 KN and the maximum
is 2.1. Figure 4c shows section B-B start-up and shutdown conditions shear reaction (Q)max =115 KN. The
details through the pile. The recom- were considered. The structure was vertical pile reinforcements are
mended vertical bars are 20-30M, modelled using 307 elements with projected into the pile cap. Upon
and spiral reinforcement is 15M @ a total of 1368 DOF. The maximum installation, the pile head is treated
200mm. beam vertical deflection is calcu- as free headed in the analysis. The
lated as (δmax) =8.5mm. The allow- allowable pile compression capac-
Steel module SM-02 able beam vertical deflection was ity in this case is (P)Cap =2200 KN
Steel module SM02 is used in the limited to (δv) =15mm. The sway and shear capacity (QH)Cap =240 KN.
BTU to support pipes, electrical deflection was calculated at several After casting the concrete pile cap,
cable trays, and mechanical equip- elevations to assure compliance the pile head is restrained against
ments. The module size is 10m x with the serviceability limit state. rotation. The pile lateral capac-
6m x 10m and consists of four lev- The maximum sway deflection was ity for a fixed condition is (QH)Cap
els and two bays. Figure 5 shows found as (δH)max =47mm. The allow- =323 KN and the pile group reduc-
a snapshot front elevation for the able sway deflection was limited to tion factor is 1.5. The maximum
steel module SM-02. Cable trays are (δH)Limit =67mm. The maximum SLS (FE) pile cap moment is (Mmax)
shown in green and the structural unity index was found as (UI)SLS =140 KN-m/m. The recommended
steel is red. Some equipment is not =0.67 and the (UI)ULS =0.69. pile cap reinforcement =15M @
shown to maintain clarity of the fig- A pile cap size of 12m x 8m x 150mm (each way). The pile cap
ure. In this module, most pipelines 0.6m with six concrete piles was shear resistance is (Vc) =1703 KN
are located on the upper elevation used to support the structure. >1070 KN.
(Z)=10. Note that vertical cables The lower steel skid of the steel
trays are supported by horizontal model is partially embedded in Pump and compressor house (PCH)
projections from the primary beams. concrete to minimise the vibration The pump and compressor house
The structure was divided into two effect induced during operation. layout is shown in Figure 6a. The
sub-modules and assembled on-site The nominal pile diameter used is primary framing system consists of
using heavy lift cranes. Pipelines, 750mm and the pile length is 20m. four bays and houses four pumps
cable trays, and mechanical equip- For erection conditions, the max- varying in size. The steel framing is

www.digitalrefining.com Gas 2022 35


prior to the casing of the pile cap
11 22 AA BB
and pump pads to determine the
3m
3m ZZ 7m
7m maximum pile reactions. The nomi-
AA 5.5m
5.5m 5.5m
5.5m nal pile diameter is 750mm and pile
YY
11 length is 20m. Upon installation, the
2.5m
2.5m pile head is treated as free headed
BB 3.5m
3.5m in the analysis. The allowable pile
compression capacity in this case
3m
3m XX is (P)Cap =2200 KN and shear capac-
ity (QH)Cap =240 KN. The maximum
(b)
(b)Section
SectionA-A
A-A pile lateral deflection was limited
12m
12m
to 6mm. After casting the concrete
Figure 6 PCH geometric details pile cap, the pile head is restrained
3m
3m against rotation and lateral capacity
beam vertical deflection is calcu- for this condition is (QH)Cap =145 KN.
AA
lated as (δmax) =9.1mm. The allow- Pile group reduction factor is 1.65.
2.5m
2.5m
XX able beam vertical deflection is (δv) For erection conditions, the maxi-
(O)
=16.75mm. The maximum sway mum SLS column reactions are axial
(O) AA
(a)
(a)Plan
Plan deflection was found as (δH)Max compression (Pmax =182 KN, maxi-
=16mm. The allowable sway deflec- mum shear reaction (Q)max =9 KN,
tion was limited to (δH)Limit =20mm. and maximum tension (T)max =0. For
3m (W) x 12m (L) x 3.5m (H). The The maximum unity index (UI)SLS operating/testing conditions, (P)max
base framing at Z=0 is embedded =0.54 and (UI)ULS =0.47. =227 KN, and (Q)max =11.5 KN.
in concrete foundations. Pumps are It is recommended to use the PCH Figure 7b shows section A-A to
seated on four steel frames bolted support system shown in Figure 7a illustrate the interface of the pump
to the base skid. Figure 6b shows to reduce deflections and vibration skid with the concrete pile cap. The
the structural elevation of section during operation. The size of the maximum FE bending moment is
A-A along grid line 1. The two concrete pile cap is 4m (W) x 13m 80 KN-m/m. Recommended top
frames are separated by 1m and (L) x 0.6m (t) and was modelled and bottom reinforcements are 25M
each side contains two pumps. The using 1300 shell elements. The steel @ 200mm (each way). The concrete
pump house was analysed using framing of the PCH at (Z)=0 is par- shear resistance is 791 KN, which
Finite Element for erection, oper- tially embedded in the concrete. exceeds the maximum factored pile
ation, testing, and transportation The numerical FE model was first loads = 227 KN. The vertical pile
load conditions. The maximum analysed for erection conditions reinforcements must be projected
into the pile cap, as shown. Figure
7c shows section B-B through the
pile. The recommended longitu-
1
3m
2 dinal reinforcement is 20-30M,
Y
and spiral reinforcement is 15M @
25M @ 200mm 25M @ 200mm 200mm.

3m Conclusions
0.6m
Current design guidelines for natu-
B ral gas processing plants overlook
15M @ 200mm critical structural aspects. This arti-
A A
cle describes cost-effective meth-
odologies to design the steel and
7m
B B concrete members required in natu-
(b) Section A-A ral gas processing plants. Simplified
models are described to idealise
load transfers. Horizontal and ver-
15M @ 200mm
tical springs along the pile length
simulate soil structural interactions.
A 20-30M
Numerical results were discussed
3m for the design of pumps and com-
X
pressors located at the BTU. Results
(c) Section B-B
also presented modular steel struc-
4m (a) Pile-cap layout tures required in the BTU. The
procedures are computationally effi-
cient and can be used by the oil and
Figure 7 PCH Support plan and details gas industry.

36 Gas 2022 www.digitalrefining.com


future perspectives in emerging applications, on blast resistant design. New York: ASCE.
References
Fuel Processing Technology, 2020, 206, 106464. 18 ASCE. 2010. Minimum design loads and
1 G S Patience, R Bockrath, Butane oxidation
9 J E, Gallagher, Natural Gas Measurement other structures. ASCE/SEI 7. Reston, VA:
process development in a circulating
Handbook, Elsevier Inc., Netherlands, 2007. ASCE.
fluidized bed, Applied Catalysis A: General,
10 R Meyers, Handbook of Petroleum Refining 19 ASCE’s Task Committee on Wind-
2010, 376, (1), 4-12.
Processes, Fourth Edition, McGraw-Hill Induced Forces. 2011. Wind loads for
2 H P Wu, Y Jin, M Sun, M Yang, Enhancing
Education, USA, 2016. petrochemical and other industrial facilities.
catalytic performance of phosphorus-
11 O Bedair, Design Of Mobile Facilities Reston, VA: ASCE.
modified ceria supported VPO catalysts for
used In Surface Mining Projects ASCE, 20 CSA (Canadian Standards Association).
n-butane oxidation, Journal of Molecular
Practice Periodical on Structural Design and 2004. Design of concrete structures. CAN/
Catalysis A: Chemical, 2016, 414, 1-9.
Construction, 2015, 21 (1), 04015007. CSA-A23.3-04. Rexdale, Canada: CSA.
3 A Sáez, A Flores-Maradiaga, M Toledo,
12 O Bedair, Rational Design of Pipe-Racks 21 CSA (Canadian Standards Association).
Liquid butane as an alternative fuel for diesel
Used For Oil Sands and Petrochemical 2007. Limit states design of steel structures.
oil burners, Applied Thermal Engineering,
Facilities, ASCE, Periodical on Structural CAN/CSA-S16-01. Rexdale, Canada: CSA.
2012, 45-46, 1-8.
Design and Construction, 2014, 20 (2), 22 NRC (National Research Council of
4 C Yang, K Teo, Y Xu, Butane extraction of
04014029. Canada), 2010. National building code.
model organic pollutants from water, Journal
13 O Bedair, modern steel design and Ottawa, ON: National Research Council of
of Hazardous Materials, 2004, 108, (1-2), 77-83.
construction used in Canada’s oil sands Canada.
5 S Mokhatab, W Poe, Handbook of Natural
industry, Journal of Steel Design Construction
Gas Transmission and Processing, Elsevier Inc.,
and Research, 2014, 7 (1), 32-40 Osama Bedair is a Senior Consultant with
Netherlands, 2012.
14 O Bedair, Cost-effective modeling significant design experience in heavy
6 Y Liu, A Chang, K Pashikanti, Petroleum
strategies for spliced steel connections. industrial projects that include oil & gas,
Refinery Process Modeling: Integrated
Journal of Applied Mathematical Modelling, petrochemical, mining and pipelines. He
Optimization Tools and Applications, Wiley
2011, 35 (4), 1881-1892. holds an MS and PhD in civil engineering
Publishing Company, New Jersey, USA, 2018.
15 O Bedair, Economical damage from university of Waterloo.
7 V Bulasara, R Uppaluri, A Ghoshal,
classification procedure for blast resistant
Revamp study of crude distillation unit
buildings in petrochemical plants, ASCE,
heat exchanger network Energy integration
Practice Periodical on Structural Design and
potential of delayed coking unit free hot
Construction, 2020, 25(3), 04020020.
streams, Applied Thermal Engineering, 2009,
16 AISC. 2006. Steel Construction Manual,
LINKS
29 (11-12), 2271-2279.
14th ed. Chicago: AISC. More articles from the following
8 A Lulianelli, E Drioli, Membrane
17 AISC. 2010. Design of blast resistant categories:
engineering: Latest advancements in gas
buildings in petrochemical facilities: ASCE Gas Processing and Treatment
separation and pre-teatment processes,
petrochemical committee, task committee
petrochemical industry and refinery, and

www.digitalrefining.com Gas 2022 37

You might also like