You are on page 1of 265

PEKERJAAN PENUTUP LANTAI

1 1 m2 Pasang lantai ubin warna akuran 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.4.1
6.630 Bh Ubin warna 40 x 40 cm @ Rp. 163,900.00 = Rp 1,086,657.00
9.800 Kg Semen portland @ Rp. 1,525.00 = Rp 14,945.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 1,108,477.00
Upah An. SNI ( Revisi ) 6.4.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 1,142,752.38

2 1 m2 Pasang lantai ubin warna akuran 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.5.1
11.200 Bh Ubin warna 30 x 30 cm @ Rp. 6,500.00 = Rp 72,800.00
8.360 Kg Semen portland @ Rp. 1,525.00 = Rp 12,749.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
0.600 Kg Semen warna @ Rp. 9,500.00 = Rp 5,700.00
Sub total : = Rp 95,274.00
Upah An. SNI ( Revisi ) 6.5.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 129,549.38

3 1 m2 Pasang lantai ubin teraso akuran 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.7.1
6.250 Bh Ubin teraso 40 x 40 cm @ Rp. 7,500.00 = Rp 46,875.00
8.800 Kg Semen portland @ Rp. 1,525.00 = Rp 13,420.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 66,907.50
Upah An. SNI ( Revisi ) 6.7.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 102,932.88

4 1 m2 Pasang lantai ubin teraso akuran 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.8.1
11.200 Bh Ubin teraso 30 x 30 cm @ Rp. 7,300.00 = Rp 81,760.00
10.000 Kg Semen portland @ Rp. 1,525.00 = Rp 15,250.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.600 Kg Semen warna @ Rp. 9,500.00 = Rp 5,700.00
Sub total : = Rp 106,472.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 95
Upah An. SNI ( Revisi ) 6.8.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.125 Oh Tukang batu @ Rp. 107,250.00 = Rp 13,406.25
0.013 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,350.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 37,365.63
Total upah+bahan : = Rp 143,838.13

5 1 m2 Pasang lantai ubin granito akuran 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.9.1
6.250 Bh Ubin granito 40 x 40 cm @ Rp. 22,176.00 = Rp 138,600.00
9.800 Kg Semen portland @ Rp. 1,525.00 = Rp 14,945.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 160,157.50
Upah An. SNI ( Revisi ) 6.9.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 194,432.88

6 1 m2 Pasang lantai keramic Exensa 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.10.1
6.250 Bh Keramic esensas 30 x 30 cm @ Rp. 16,480.00 = Rp 103,000.00
10.000 Kg Semen portland @ Rp. 1,525.00 = Rp 15,250.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 124,862.50
Upah An. SNI ( Revisi ) 6.10.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.125 Oh Tukang batu @ Rp. 107,250.00 = Rp 13,406.25
0.0130 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,404.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 35,669.63
Total upah+bahan : = Rp 160,532.13

7 1 m2 Pasang lantai marmer akuran 60 x 60 cm


Bahan An. SNI ( Revisi ) 6.13.1
2.940 Bh Ubin teralux marmer 60 x 60 @ Rp. 48,469.39 = Rp 142,500.00
8.190 Kg Semen portland @ Rp. 1,525.00 = Rp 12,489.75
0.045 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,875.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 165,714.75
Upah An. SNI ( Revisi ) 6.13.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 201,740.13
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 96
8 1 m2 Pasang lantai marmer akuran 100 x 100 cm
Bahan An. SNI ( Revisi ) 6.13.1
1.060 M2 Ubin teralux marmer 1 x 1 m2 @ Rp. 142,500.00 = Rp 151,050.00
8.190 Kg Semen portland @ Rp. 1,525.00 = Rp 12,489.75
0.045 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,875.00
0.250 Kg Semen warna @ Rp. 9,500.00 = Rp 2,375.00
Sub total : = Rp 173,789.75
Upah An. SNI ( Revisi ) 6.13.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. @ Rp. = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 209,815.13

9 1 m2 Pasang teraso cor ditempat nat kaca 4Cm x 5 mm


Bahan An. SNI ( Revisi ) 6.31.1
0.0036 m3 Bahan teraso cor @ Rp. 101,200.00 = Rp 364.32
12.285 Kg Semen portland @ Rp. 1,525.00 = Rp 18,734.63
0.095 m3 Pasir pasang @ Rp. 175,000.00 = Rp 16,625.00
2.000 m1 nat kaca @ Rp. 2,250.00 = Rp 4,500.00
1.000 Kg Semen warna @ Rp. 9,500.00 = Rp 9,500.00
Sub total : = Rp 49,723.95

Upah An. SNI ( Revisi ) 6.31.2


0.900 Oh Pekerja @ Rp. 75,000.00 = Rp 67,500.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Biaya poles. Lumsum = Rp 2,250.00
Sub total : = Rp 80,863.88
Total upah+bahan : = Rp 130,587.82

10 1 m2 Pasang TRASO cor ditempat nat kuningan


Bahan An. SNI ( Revisi ) 6.31.1
0.0036 m3 Bahan teraso cor @ Rp. 518,000.00 = Rp 1,864.80
12.285 Kg Semen portland @ Rp. 1,525.00 = Rp 18,734.63
0.095 m3 Pasir pasang 0.00 175,000.00 = Rp 16,625.00
2.000 m1 nat kaca @ Rp. 7,500.00 = Rp 15,000.00
1.000 Kg Semen warna @ Rp. 9,500.00 = Rp 9,500.00
Sub total : = Rp 61,724.43
Upah An. SNI ( Revisi ) 6.31.2
0.900 Oh Pekerja @ Rp. 75,000.00 = Rp 67,500.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Biaya poles. Sub total : = Rp 2,500.00
Sub total : = Rp 81,113.88
Total upah+bahan : = Rp 142,838.30
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 97
11 1 m1 Pasang lantai keramik artistik 5 x 20 cm / Lis / Ban
Bahan An. SNI ( Revisi ) 6.36.1
5.000 Bh Ubin keramik artistik 5x20 cm @ Rp. 10,000.00 = Rp 50,000.00
0.850 Kg Semen portland @ Rp. 1,525.00 = Rp 1,296.25
0.0022 m3 Pasir pasang @ Rp. 175,000.00 = Rp 385.00
0.080 Kg Semen warna @ Rp. 9,500.00 = Rp 760.00
Sub total : = Rp 52,441.25
Upah An. SNI ( Revisi ) 6.36.2
0.090 Oh Pekerja @ Rp. 75,000.00 = Rp 6,750.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0450 Oh Mandor @ Rp. 108,750.00 = Rp 4,893.75
Sub total : = Rp 22,268.25
Total upah+bahan : = Rp 74,709.50

12 1 m1 Pasang lantai keramik artistik 7,5 x 25 cm / Lis / Ban


Bahan An. SNI ( Revisi ) 6.37.1
5.000 Bh Plint keramik artistik 10x20 cm @ Rp. 13000 = Rp 50,000.00
1.063 Kg Semen portland @ Rp. 1,525.00 = Rp 1,620.31
0.003 m3 Pasir pasang @ Rp. 175,000.00 = Rp 481.25
0.100 Kg Semen warna @ Rp. 9,500.00 = Rp 950.00
Sub total : = Rp 53,051.56
Upah An. SNI ( Revisi ) 6.37.2
0.090 Oh Pekerja @ Rp. 75,000.00 = Rp 6,750.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Sub total : = Rp 17,863.88
Total upah+bahan : = Rp 70,915.44

13 1 m2 Pasang lantai keramik 20 x 20 cm


Bahan An. SNI ( Revisi ) 6.42.1
1.050 m2 Ubin keramik 10x20 cm @ Rp. 44,500.00 = Rp 46,725.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.350 Kg Semen warna @ Rp. 9,500.00 = Rp 3,325.00
Sub total : = Rp 78,582.45
Upah An. SNI ( Revisi ) 6.42.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 112,857.82

14 1 m2 Pasang lantai keramik 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 30 x 30 Cm @ Rp. 53,400.00 = Rp 56,070.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 87,452.45
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 119,477.82
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 98
15 1 m2 Pasang lantai keramik 40 x 40 cm (Motif)
Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 40 x 40 Cm @ Rp. 60,000.00 = Rp 63,000.00
7.454 Kg Semen portland @ Rp. 1,140.00 = Rp 8,497.45
3.926 Kg Kapur bubuk @ Rp. 2,375.00 = Rp 9,324.49
0.0420 m3 Pasir pasang @ Rp. 142,500.00 = Rp 5,985.00
0.200 Kg Semen warna @ Rp. 7,125.00 = Rp 1,425.00
Sub total : = Rp 88,231.93
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 43,000.00 = Rp 9,460.00
0.100 Oh Tukang batu @ Rp. 62,500.00 = Rp 6,250.00
0.012 Oh Kepala tukang @ Rp. 65,000.00 = Rp 780.00
0.013 Oh Mandor @ Rp. 80,500.00 = Rp 1,046.50
Sub total : = Rp 17,536.50
Total upah+bahan : = Rp 105,768.43

16 1 m2 Pasang lantai keramik 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 40 x 40 Cm @ Rp. 47,000.00 = Rp 49,350.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.200 Kg Semen warna @ Rp. 9,500.00 = Rp 1,900.00
Sub total : = Rp 79,782.45
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 29,880.38
Total upah+bahan : = Rp 109,662.82

17 1 m1 Pasang lantai keramik 30 x 30 cm anti slip / Rock tile


Bahan An. SNI ( Revisi ) 6.48.1
1.050 M2 Ubin keramik 30x30 anti slip @ Rp. 62,000.00 = Rp 65,100.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 96,482.45
Upah An. SNI ( Revisi ) 6.48.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 128,507.82

18 1 m2 Pasang lantai mosaik 30 x 30 cm.


Bahan An. SNI ( Revisi ) 6.51.1
1.050 m2 Mosaik 30x30cm @ Rp. 62,500.00 = Rp 65,625.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.042 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 97,007.45
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 99
Upah An. SNI ( Revisi ) 6.51.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 129,032.82

19 1 m2 Pasang lantai karpet 100% wool


Bahan An. SNI ( Revisi ) 6.52.1
1.050 m2 Feltex carpet 100% T-21 @ Rp. 195,000.00 = Rp 204,750.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 217,525.00
Upah An. SNI ( Revisi ) 6.52.2
0.170 Oh Pekerja @ Rp. 75,000.00 = Rp 12,750.00
0.170 Oh Tukang @ Rp. 107,250.00 = Rp 18,232.50
0.017 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,836.00
0.0085 Oh Mandor @ Rp. 108,750.00 = Rp 924.38
Sub total : = Rp 33,742.88
Total upah+bahan : = Rp 251,267.88

20 1 m2 Pasang lantai karpet 80% wool, 20% nylon


Bahan An. SNI ( Revisi ) 6.53.1
1.050 m2 Carpet 80% wool, 20% nylon @ Rp. 155,000.00 = Rp 162,750.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 175,525.00
Upah An. SNI ( Revisi ) 6.53.2
0.170 Oh Pekerja @ Rp. 75,000.00 = Rp 12,750.00
0.170 Oh Tukang @ Rp. 107,250.00 = Rp 18,232.50
0.017 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,836.00
0.0085 Oh Mandor @ Rp. 108,750.00 = Rp 924.38
Sub total : = Rp 33,742.88
Total upah+bahan : = Rp 209,267.88

e:\ANALISA-2009\SNI.12-A.wk4\2012. Halaman : 100


21 1 m2 Pasang lantai parquet jati
Bahan An. SNI ( Revisi ) 6.56.1
1.050 m2 Parquet jati @ Rp. 192,500.00 = Rp 202,125.00
0.600 Kg Lem vinyl @ Rp. 36,500.00 = Rp 21,900.00
Sub total : = Rp 224,025.00
Upah An. SNI ( Revisi ) 6.56.2
0.650 Oh Pekerja @ Rp. 75,000.00 = Rp 48,750.00
0.350 Oh Tukang @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0325 Oh Mandor @ Rp. 108,750.00 = Rp 3,534.38
Sub total : = Rp 93,601.88
Total upah+bahan : = Rp 317,626.88

22 1 m2 Pasang dinding porselin 11 x 11 cm, putih


Bahan An. SNI ( Revisi ) 6.58.1
83.000 Bh Porselin 11x11 cm @ Rp. 375.00 = Rp 31,125.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.500 Kg Semen warna @ Rp. 9,500.00 = Rp 4,750.00
Sub total : = Rp 55,519.71
Upah An. SNI ( Revisi ) 6.58.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 41,469.38
Total upah+bahan : = Rp 96,989.09

23 1 m2 Pasang dinding porselin 11 x 11 cm, warna


Bahan An. SNI ( Revisi ) 6.59.1
83.000 Bh Porselin 11x11 cm, warna @ Rp. 395.00 = Rp 32,785.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.500 Kg Semen warna @ Rp. 9,500.00 = Rp 4,750.00
Sub total : = Rp 57,179.71
Upah An. SNI ( Revisi ) 6.59.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 41,469.38
Total upah+bahan : = Rp 98,649.09

24 1 m2 Pasang dinding keramik 20 x 25 cm


Bahan An. SNI ( Revisi ) 6.69.1
1.050 M2 Keramik 20 x 25 cm @ Rp. 46,600.00 = Rp 48,930.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.400 Kg Semen warna @ Rp. 9,500.00 = Rp 3,800.00
Sub total : = Rp 72,374.71

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 101


Upah An. SNI ( Revisi ) 6.69.2
0.248 Oh Pekerja @ Rp. 75,000.00 = Rp 18,600.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 43,297.50
Total upah+bahan : = Rp 115,672.21

25 1 m2 Pasang dinding keramik 20 x 35 cm


Bahan An. SNI ( Revisi ) 6.69.1
1.050 M2 Keramik 20 x 35 cm @ Rp. 55,700.00 = Rp 58,485.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.250 Kg Semen warna @ Rp. 9,500.00 = Rp 2,375.00
Sub total : = Rp 80,504.71
Upah An. SNI ( Revisi ) 6.69.2
0.230 Oh Pekerja @ Rp. 75,000.00 = Rp 17,250.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 41,947.50
Total upah+bahan : = Rp 122,452.21

26 1 m2 Pasang dinding marmer


Bahan An. SNI ( Revisi ) 6.70.1
1.020 m2 Marmer @ Rp. 142,500.00 = Rp 145,350.00
2.000 Bh Paku pancing 60x230 @ Rp. 1,750.00 = Rp 3,500.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
0.400 Kg Semen warna @ Rp. 9,500.00 = Rp 3,800.00
Sub total : = Rp 175,996.00
Upah An. SNI ( Revisi ) 6.70.2
0.720 Oh Pekerja @ Rp. 75,000.00 = Rp 54,000.00
0.650 Oh Tukang batu @ Rp. 107,250.00 = Rp 69,712.50
0.065 Oh Kepala tukang @ Rp. 108,000.00 = Rp 7,020.00
0.0350 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 134,538.75
Total upah+bahan : = Rp 310,534.75

27 1 m2 Pasang dinding bata pelapis 7 x 3 x 24 cm


Bahan An. SNI ( Revisi ) 6.71.1
1.050 M2 Bata pelapis dinding @ Rp. 80,000.00 = Rp 84,000.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
Sub total : = Rp 107,346.00
Upah An. SNI ( Revisi ) 6.71.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 41,523.75
Total upah+bahan : = Rp 148,869.75
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 102
28 1 m2 Pasang dinding bata klinker 5 x 5 x 24 cm
Bahan An. SNI ( Revisi ) 6.72.1
1.050 M2 Bata pelapis klinker @ Rp. 80,000.00 = Rp 84,000.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
Sub total : = Rp 107,346.00
Upah An. SNI ( Revisi ) 6.72.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 146,508.00

29 1 m2 Pasang dinding batu paros


Bahan An. SNI ( Revisi ) 6.73.1
1.050 m2 Batu paros @ Rp. 48,000.00 = Rp 50,400.00
11.750 Kg Semen portland @ Rp. 1,525.00 = Rp 17,918.75
0.0350 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,125.00
Sub total : = Rp 74,443.75
Upah An. SNI ( Revisi ) 6.73.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 113,605.75

30 1 m2 Pasang dinding batu tempel hitam


Bahan An. SNI ( Revisi ) 6.74.1
1.050 m2 Batu tempel hitam @ Rp. 25,000.00 = Rp 26,250.00
11.750 Kg Semen portland @ Rp. 1,525.00 = Rp 17,918.75
0.0350 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,125.00
Sub total : = Rp 50,293.75
Upah An. SNI ( Revisi ) 6.74.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 89,455.75

31 1 m2 Pasang lantai vinyl oscar / xsintetis 30 x 30 cm KL 1


Bahan An. SNI ( Revisi ) 6.75.1
11.050 Bh Vinyl oscar/sintetist 30x30 cm @ Rp. 5,158.37 = Rp 57,000.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 69,775.00
Upah An. SNI ( Revisi ) 6.75.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 99,548.13

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 103


32 1 m2 Pasang lantai vinyl karet 30 x 30 cm
Bahan An. SNI ( Revisi ) 6.76.1
11.050 Bh Vinyl karet 30x30 cm @ Rp. 5,882.35 = Rp 65,000.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 77,775.00
Upah An. SNI ( Revisi ) 6.76.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 107,548.13

33 1 m2 Pasang lantai vinyl motif kembang 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.78.1
11.050 Bh Vinyl mtf kembang 30x30 cm e @ Rp. 5,502.26 = Rp 60,800.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 73,575.00
Upah An. SNI ( Revisi ) 6.78.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 103,348.13

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 104


PEKERJAAN PAVING STONE

1 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm.
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 1350.000 = Rp 48,600.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 60,600.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 93,776.97

2 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm.
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 2279.000 = Rp 82,044.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 94,044.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 127,220.97

3 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 1710.000 = Rp 61,560.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 73,560.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 106,736.97

4 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 2170.000 = Rp 78,120.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 90,120.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 123,296.97

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 105


5 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1350.000 = Rp 47,250.00
0.12 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 59,250.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 92,426.97

6 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1937.000 = Rp 67,795.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 79,795.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 112,971.97

7 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1730.000 = Rp 60,550.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 72,550.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 105,726.97

8 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 2140.000 = Rp 74,900.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 86,900.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 120,076.97

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 106


9 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
14 Bj Paving type "Segi empat" @ Rp. 946.000 = Rp 13,054.80
0.060 m3 Pasir urug 10 Cm. @ Rp. 109,000.00 = Rp 6,540.00
Sub total : = Rp 19,594.80
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 43,000.00 = Rp 8,264.60
0.151 Oh Tukang batu @ Rp. 62,500.00 = Rp 0.00
0.016 Oh Kepala tukang @ Rp. 65,000.00 = Rp 0.00
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 0.00
Sub total : = Rp 8,264.60
Total upah+bahan : = Rp 27,859.40

10 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46 Bj Paving type "Ssgi empat" @ Rp. 2,030.00 = Rp 93,380.00
0.060 m3 Pasir urug 10 Cm. @ Rp. 109,000.00 = Rp 6,540.00
Sub total : = Rp 99,920.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 43,000.00 = Rp 8,264.60
0.151 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,466.88
0.016 Oh Kepala tukang @ Rp. 65,000.00 = Rp 1,007.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 623.88
Sub total : = Rp 19,362.85
Total upah+bahan : = Rp 119,282.85

11 1 m2 Pasang PAVING STONE warna merah TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46 Bj Paving type "Ssgi empat" @ Rp. 2360.000 = Rp 108,560.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 109,000.00 = Rp 13,189.00
Sub total : = Rp 121,749.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 43,000.00 = Rp 8,264.60
0.151 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,466.88
0.016 Oh Kepala tukang @ Rp. 65,000.00 = Rp 1,007.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 623.88
Sub total : = Rp 19,362.85
Total upah+bahan : = Rp 141,111.85

12 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
26 Bj Paving type "Ssgi ENAM" @ Rp. 1732.000 = Rp 45,032.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 109,000.00 = Rp 13,189.00
Sub total : = Rp 58,221.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 43,000.00 = Rp 8,264.60
0.151 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,466.88
0.016 Oh Kepala tukang @ Rp. 65,000.00 = Rp 1,007.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 623.88
Sub total : = Rp 19,362.85
Total upah+bahan : = Rp 77,583.85

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 107


13 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
26 Bj Paving type "Ssgi ENAM" @ Rp. 2850.000 = Rp 74,100.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 109,000.00 = Rp 13,189.00
Sub total : = Rp 87,289.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 43,000.00 = Rp 8,264.60
0.151 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,466.88
0.016 Oh Kepala tukang @ Rp. 65,000.00 = Rp 1,007.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 623.88
Sub total : = Rp 19,362.85
Total upah+bahan : = Rp 106,651.85

PEKERJAAN KANSTIN / SKERB.

1 1 m1 Pasang KANSTIN / SKERB Model lengkung Uk. 18 x 50 x 30 Cm.


Bahan An. SNI ( Revisi )
2 Bj Skreb lengkung @ Rp. 35,000.00 = Rp 70,000.00
0.050 m3 Pasir pasang @ Rp. 175,000.00 = Rp 8,750.00
1.000 Ls Spesi utk sambungan @ Rp. 1,450.00 = Rp 1,450.00
Sub total : = Rp 80,200.00
Upah An. SNI ( Revisi )
0.200 Oh Pekerja @ Rp. 43,000.00 = Rp 8,600.00
0.150 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,375.00
0.015 Oh Kepala tukang @ Rp. 65,000.00 = Rp 975.00
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 644.00
Sub total : = Rp 19,594.00
Total upah+bahan : = Rp 99,794.00

1 1 m1 Pasang KANSTIN / SKERB Model lurus Uk. 8 x 40 x 20 Cm.


Bahan An. SNI ( Revisi )
3 Bj skerb" @ Rp. 27,500.00 = Rp 68,750.00
0.030 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,250.00
1.000 Ls Spesi utk sambungan @ Rp. 1,450.00 = Rp 1,450.00
Sub total : = Rp 75,450.00
Upah An. SNI ( Revisi )
0.200 Oh Pekerja @ Rp. 43,000.00 = Rp 8,600.00
0.150 Oh Tukang batu @ Rp. 62,500.00 = Rp 9,375.00
0.015 Oh Kepala tukang @ Rp. 65,000.00 = Rp 975.00
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 644.00
Sub total : = Rp 19,594.00
Total upah+bahan : = Rp 95,044.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 108


PEKERJAAN GEBALAN RUMPUT

1 1 m2 Penanaman Rumput LAMUR.


Bahan An. SNI ( Revisi )
1 m2 Rumput lamur @ Rp. 12,500.00 = Rp 12,500.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 14,600.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 43,000.00 = Rp 2,580.00
0.015 Oh Tukang batu @ Rp. 62,500.00 = Rp 937.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 644.00
Sub total : = Rp 4,161.50
Total upah+bahan : = Rp 18,761.50

2 1 m2 Penanaman Rumput GAJAH.


Bahan An. SNI ( Revisi )
1 m2 Rumput gajah. @ Rp. 14,000.00 = Rp 14,000.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 16,100.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 43,000.00 = Rp 2,580.00
0.015 Oh Tukang batu @ Rp. 62,500.00 = Rp 937.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 644.00
Sub total : = Rp 4,161.50
Total upah+bahan : = Rp 20,261.50

3 1 m2 Penanaman Rumput JEPANG.


Bahan An. SNI ( Revisi )
1 m2 Rumput jepang. @ Rp. 18,000.00 = Rp 18,000.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 20,100.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 43,000.00 = Rp 2,580.00
0.015 Oh Tukang batu @ Rp. 62,500.00 = Rp 937.50
0.008 Oh Mandor @ Rp. 80,500.00 = Rp 644.00
Sub total : = Rp 4,161.50
Total upah+bahan : = Rp 24,261.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 109


Strouss
36 1 m3 Membuat kolom beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.40.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 0.00 = Rp 0.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 0.00 = Rp 0.00
1.600 Ltr Minyak bekisting @ Rp. 0.00 = Rp 0.00
157.500 Kg Besi beton polos @ Rp. 11,000.00 = Rp 1,732,500.00
2.250 Kg Kawat beton @ Rp. 0.00 = Rp 0.00
336.000 Kg Semen portland @ Rp. 1,125.00 = Rp 378,000.00
0.540 m3 Pasir beton @ Rp. 130,000.00 = Rp 70,200.00
0.810 m3 Koral beton @ Rp. 162,000.00 = Rp 131,220.00
0.120 m3 Balok kayu borneo @ Rp. 0.00 = Rp 0.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 0.00 = Rp 0.00
32.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 2,311,920.00
Upah An. SNI ( Revisi ) 6.40.2
5.300 Oh Pekerja @ Rp. 40,000.00 = Rp 212,000.00
0.275 Oh Tukang batu @ Rp. 60,000.00 = Rp 16,500.00
1.300 Oh Tukang kayu @ Rp. 60,000.00 = Rp 78,000.00
1.050 Oh Tukang besi @ Rp. 60,000.00 = Rp 63,000.00
0.265 Oh Kepala tukang @ Rp. 65,000.00 = Rp 17,225.00
0.265 Oh Mandor @ Rp. 70,000.00 = Rp 18,550.00
Sub total : = Rp 405,275.00
Total upah+bahan : = Rp 2,717,195.00
DAFTAR HARGA BAHAN BANGUNAN
DAN UPAH KERJA
PDAM KABUPATEN SIDOARJO
SEBELUM PPn UNTUK TAHUN ANGGARAN 2014

DAFTAR HARGA SATUAN BAHAN BANGUNAN PERIODE TAHUN 2014

Ke
lom NO. NAMA / JENIS BAHAN SATUAN HARGA
pok SATUAN BAHAN
1 2 3 4 5
A. BAHAN PASIR
1 Pasir Urug / Tanah katel. M3 Rp. 100,000.00
2 Pasir Pasang M3 Rp. 175,000.00
3 Pasir Cor M3 Rp. 198,000.00
4 Pasir Cor Kg Rp. 198.00
5 Sirtu urug M3 Rp. 61,000.00
6 Tanah Urug M3 Rp. 62,700.00
7 Tanah grosok M3 Rp. 85,800.00
8 Tanah taman M3 Rp. 90,200.00
B. BAHAN BATU 0.00
1 Batu Kali Pecah 15/20 ( tangan ) M3 Rp. 121,000.00
2 Batu Kali/ batu Quary M3 Rp. 132,000.00
3 Batu Kali Pecah 7/10 ( tangan ) M3 Rp. 146,000.00
4 Batu Kali Pecah 5/7 ( tangan ) M3 Rp. 210,000.00
5 Batu Kali Pecah 3/5 ( mesin ) M3 Rp. 215,000.00
6 Batu Kali Pecah 2/3 ( mesin ) M3 Rp. 215,875.00
7 Batu Kali Pecah 0.5 - 1 ( mesin ) M3 Rp. 242,000.00
8 Batu Kali Pecah 1/2 ( mesin ) M3 Rp. 200,000.00
9 Batu pecah tersaring untuk laston M3 Rp. 280,000.00
10 Batu pecah tersaring untuk LPA M3 Rp. 265,000.00
11 Batu pecah tersaring untuk LPB M3 Rp. 215,000.00
12 Koral Beton 1/2 M3 Rp. 200,000.00
13 Koral Beton 1/2 Kg Rp. 90.91
14 Koral Beton 2/3 M3 Rp. 181,000.00
15 Koral Beton 2/3 Kg Rp. 82.27
16 Batu kerikil Granito. M3 Rp. 518,000.00
17 Batu kerikil Traso. M3 Rp. 101,200.00
18 Batu tempel. M2 Rp. 102,500.00
19 Batu bata tebal 5,5 cm. Bakaran kayu Bh Rp. 500.00
20 Batu bata tebal 5,5 cm. Bakaran sekem. Bh Rp. 400.00
21 Batako. Bh Rp. 4,700.00
C BAHAN PAVING STONE. #VALUE!
1 Paving stone abu-2 tb. 6 cm (3 berlian-DT1) Bj Rp. 1,350.00
2 Paving stone abu-2 tb. 6 cm (4 persegi pjng ) Bj Rp. 1,260.00
3 Paving stone abu-2 tb. 6 cm (type-DT1 / S) Bj Rp. 1,350.00
4 Paving stone abu-2 tb. 6 cm (type-DT2) Bj Rp. 946.00
5 Paving stone abu-2 tb. 6 cm (type-DT7) Bj Rp. 946.00
6 Paving stone abu-2 tb. 8 cm (3 berlian-DT1) Bj Rp. 1,937.00
7 Paving stone abu-2 tb. 8 cm (4 persegi pjng ) Bj Rp. 2,030.00
8 Paving stone abu-2 tb. 8 cm (type-DT11 / S) Bj Rp. 2,279.00
9 Paving stone abu-2 tb. 8 cm (type-DT2) Bj Rp. 2,150.00
10 Paving stone abu-2 tb. 8 cm (type-DT7) Bj Rp. 2,150.00
11 Paving stone merah tb. 6 cm (3 berlian-DT1) Bj Rp. 1,730.00
12 Paving stone merah tb. 6 cm (type-DT1 / S) Bj Rp. 1,710.00
13 Paving stone merah tb. 6 cm (type-segi enam) Bj Rp. 1,732.00
14 Paving stone merah tb. 8 cm (3 berlian-DT1) Bj Rp. 2,140.00
15 Paving stone mrh tb. 8 cm (4 persegi pjng-) Bj Rp. 2,360.00
16 Paving stone merah tb. 8 cm (type-DT1) Bj Rp. 2,170.00
17 Paving stone merah tb. 8 cm (type-segi enam) Bj Rp. 2,850.00
1 2 3 4 5
18 Paving stone / beton blok kelas I M2 Rp. 0.00
19 Paving stone / beton blok kelas II M2 Rp. 0.00
20 Rooster beton bh Rp. 5,400.00
21 Bata berongga bh Rp. 3,600.00
22 Hollow block 10 bh Rp. 0.00
23 Hollow block 15 bh Rp. 0.00
24 Hollow block 20 bh Rp. 0.00
25 Conblock 10 bh Rp. 0.00
26 Conblock 15 bh Rp. 0.00
27 Conblock 20 bh Rp. 8,100.00
D BAHAN SEMEN / P.C. 0.00
1 Semen Gresik 40 kg Zak Rp. 61,000.00
2 Semen Gresik 1kg 1Kg Rp. 1,525.00
3 Semen warna 1Kg Rp. 9,500.00
4 Semen Tiga Roda 50 kg Zak Rp. 65,000.00
5 Semen putih ( Azano / Tiga Roda ) Zak Rp. 74,250.00
6 Semen merah M3 Rp. 175,000.00
E BAHAN KAPUR. 0.00
1 Kapur bubuk M3 Rp. 88,000.00
2 Kapur bubuk 1Kg Rp. 2,500.00
3 Kapur bubuk 1 sak. 1 Sak Rp. 4,900.00
4 Kapur gamping 1Kg Rp. 3,000.00
F BAHAN LANTAI. 0.00
1 Tegel ubin Warna 30 x 30 cm Bh Rp. 6,500.00
2 Porselin putih 11 x 11 Bh Rp. 1,500.00
3 Porselin warna 11 x 11 Bh Rp. 1,700.00
4 Tegel Ubin Warna 40 x 40 cm Bh Rp. 163,900.00
5 Tegel teraso 30 x 30 cm Bh Rp. 7,300.00
6 Tegel teraso 40 x 40 cm Bh Rp. 7,500.00
7 Tegel wafel / Badag 30 x 30 cm Bh Rp. 1,900.00
8 Tegel keramik Granito 40 x 40 cm ( KW I ) M2 Rp. 138,600.00
9 Keramic Esensa 40 x 40 cm . M2 Rp. 103,000.00
10 Tegel keramik lis 7,5 x 25 cm ( KW I ) Bh Rp. 13,000.00
11 Tegel keramik lis 5 x20 cm ( KW I ) Bh Rp. 10,000.00
12 Tegel keramik 20x20 cm ( KW I ) M2 Rp. 44,500.00
13 Tegel keramik 25x35 cm ( KW I ) M2 Rp. 55,000.00
14 Tegel keramik 30x30 cm ( KW I ) M2 Rp. 53,400.00
15 Tegel keramik rock tile 30x30 cm ( KW I ) M2 Rp. 62,000.00
16 Tegel keramik 40x40 cm ( KW I ) M2 Rp. 47,000.00
17 Tegel keramik motif 30x30 cm M2 Rp. 50,000.00
18 Keramik dinding 20x25 cm ( KW I ) M2 Rp. 46,600.00
19 Keramik dinding 25x35 cm ( KW I ) M2 Rp. 55,700.00
20 Vinil Oscar / sintetis Kw1 M2 Rp. 57,000.00
21 Vinil karet M2 Rp. 65,000.00
22 Vinil oscar / sintetis motif kembang. M2 Rp. 60,800.00
23 Marmer M2 Rp. 142,500.00
24 Mosaik M2 Rp. 62,500.00
25 Tera kota M2 Rp. 80,000.00
G BAHAN KAYU. 0.00
1 Kayu jati balok 6,15, 8/12. panjang 3mtr. M3 Rp. 16,000,000.00
2 Kayu reng jati 2/3, panjang 4 mtr. M3 Rp. 12,400,000.00
3 Kayu jat usuk 3/5; 4/6 ; 5/7 panjang 4 mtr. M3 Rp. 15,600,000.00
4 Papan jati papan 2/20 ; panjang 2 mtr M3 Rp. 16,000,000.00
5 Kayu Kamfer balok 8/12, 6/15 M3 Rp. 7,750,000.00
6 Kayu kamfer usuk 5/7 M3 Rp. 7,700,000.00
7 Kayu kamfer papan 3/30 , 3/20, 2/20. M3 Rp. 8,150,000.00
8 Kayu Kamfer reng 2/3 M3 Rp. 5,472,000.00
9 Kayu kruing / bengkirai / kempas papan 2/20 M3 Rp. 6,000,000.00
10 Kayu kruing /bengkirai/kempas blk 8/12,6/15 M3 Rp. 5,600,000.00
Halaman : 123
1 2 3 4 5
11 Kayu kruing / bengkirai/kempas usuk 5/7 M3 Rp. 5,500,000.00
12 Kayu kruing / bengkirai/kempas usuk 4/6 M3 Rp. 5,500,000.00
13 Kayu kruing reng 2/3 M3 Rp. 4,150,000.00
14 Kayu meranti balok 8/12, 6/15 M3 Rp. 4,200,000.00
15 Keyu meranti usuk 5/7 M3 Rp. 4,400,000.00
16 Kayu meranti papan 3/25/400 M3 Rp. 5,000,000.00
17 Kayu glugu usuk 5/7 4meter 1 Btg Rp. 70,000.00
18 Papan begesting (MC) M3 Rp. 3,025,000.00
19 Rangka plavon kamper potongan M3 Rp. 3,950,000.00
20 Rangka plavon meranti potongan M3 Rp. 3,000,000.00
21 Kayu gelagar jembatan meranti.8/15 pj.4 mtr M3 Rp. 5,550,000.00
22 Kayu dolken gelam Btg Rp. 54,000.00
23 Kayu Sirap M2 Rp. 106,000.00
24 Kayu Sirap Lbr/ 1m' Rp. 75,000.00
25 Kayu bakar. M3 Rp. 3,790,000.00
26 I j u k KG Rp. 12,900.00
26 Gedek M2 Rp. 17,000.00
H BAHAN TRIPLEKS / KAYU LAPIS. 0.00
1 Teakwood 90.210. x 4 mm lbr Rp. 88,600.00
2 Teakwood 110.210. x 4 mm lbr Rp. 88,200.00
3 Teakwood 122.244. x 4 mm lbr Rp. 86,750.00
4 Triplek lapis aluminium lbr Rp. 87,500.00
5 Triplek lapis formika lbr Rp. 87,500.00
6 Triplek 90.210. x 3 mm lbr Rp. 40,800.00
7 Triplek 90.210. x 4 mm lbr Rp. 58,900.00
8 Triplek 120.240. x 2 mm lbr Rp. 62,000.00
9 Triplek 120.240. x 3 mm lbr Rp. 77,500.00
10 Triplek 120.240. x 5 mm lbr Rp. 88,500.00
11 Triplek 120.240. x 6 mm lbr Rp. 99,000.00
12 Triplek 120.240. x 9 mm lbr Rp. 110,000.00
13 Triplek 120.240. x 12 mm lbr Rp. 145,000.00
14 List plafond 1,5/4 profil kayu kamper m' Rp. 9,000.00
15 List plafond 1/5 m' Rp. 6,000.00
I BAHAN BESI..
1 Aluminium putih / silver 3" M1 Rp. 90,000.00
2 Aluminium putih / silver 4" M1 Rp. 96,000.00
3 Aluminium coklat / brown 3" M1 Rp. 96,000.00
4 Aluminium coklat / brown. 4" M1 Rp. 102,000.00
5 Aluminium slimar putih / silver 3" M1 Rp. 90,000.00
6 Aluminium slimar coklat / brown 3" M1 Rp. 120,000.00
7 Karet penjepit kaca / multipleks. M1 Rp. 7,500.00
8 Hak window Bh Rp. 18,000.00
9 Besi beton Polos diameter 5 mm Lonjor Rp. 17,040.00
10 Besi beton Polos diameter 6 mm Lonjor Rp. 32,380.00
11 Besi beton Polos diameter 8 mm Lonjor Rp. 47,750.00
12 Besi beton Polos diameter 10 mm Lonjor Rp. 67,500.00
13 Besi beton Polos diameter 12 mm Lonjor Rp. 98,500.00
14 Besi beton Polos diameter 16 mm Lonjor Rp. 160,000.00
15 Besi beton polos. Kg Rp. 10,500.00
16 Besi beton Ulir. Kg Rp. 11,825.00
17 Besi konstruksi ( WF ; H ; INP ; SIKU ) Kg Rp. 11,825.00
18 Besi lempeng / bulat / strip (Beugel) Kg Rp. 11,825.00
19 Kawat bendrat Kg Rp. 14,700.00
20 Kawat duri M1 Rp. 18,300.00
21 Kawat bronjong Kg Rp. 14,000.00
22 Kawat ikat Kg Rp. 18,200.00
23 Kawat harmonika. M1 Rp. 20,000.00
24 Kawat nyamuk. besi M1 Rp. 18,000.00
25 Kawat KASA. / kawat burung. M1 Rp. 15,000.00
Halaman : 124
1 2 3 4 5
26 Paku reng KG Rp. 14,000.00
27 Paku usuk KG Rp. 14,000.00
28 Paku eternit KG Rp. 14,000.00
29 Paku sekrup KG Rp. 23,000.00
30 Mur baut kuda-kuda KG Rp. 14,250.00
31 Mur baut kuda-kuda Bh Rp. 14,250.00
32 Plat kuda-kuda Bh Rp. 14,250.00
33 Mur baut gording Bh Rp. 7,000.00
34 Paku payung Kg Rp. 25,000.00
35 Ankur kusen Kg Rp. 8,500.00
36 Pagar BRC 90.240 cm Unit Rp. 370,000.00
37 Pagar BRC 120.240 cm Unit Rp. 400,000.00
38 Besi siku 30x30x3 panjang 6 m Ljr Rp. 95,000.00
39 Besi siku 40x40x3 panjang 6 m Ljr Rp. 110,000.00
40 Besi siku 40x40x4 panjang 6 m Ljr Rp. 129,000.00
41 Kawat berduri 50 m M' Rp. 18,000.00
J BAHAN PIPA BESI.. 0.00
1 Pipa air galvanis medium 1/2" Ljr Rp. 118,000.00
2 Pipa air galvanis medium 3/4" Ljr Rp. 142,000.00
3 Pipa air galvanis medium 1" Ljr Rp. 328,000.00
4 Pipa air galvanis medium 1,25" Ljr Rp. 625,000.00
5 Pipa air galvanis medium 2" Ljr Rp. 825,000.00
6 Pipa air galvanis medium 3" Ljr Rp. 860,000.00
7 Pipa air galvanis medium 4" Ljr Rp. 925,000.00
K BAHAN PIPA P.V.C.. 0.00
1 Pipa PVC AW dia 1/2" 4 m Ljr Rp. 22,200.00
2 Pipa PVC AW dia 3/4" 4m Ljr Rp. 26,000.00
3 Pipa PVC AW dia 1".4m Ljr Rp. 32,250.00
4 Pipa PVC D dia 2" 4 m Ljr Rp. 59,100.00
5 Pipa PVC D dia 3" 4 m Ljr Rp. 105,000.00
6 Pipa PVC D dia 4" 4m Ljr Rp. 164,000.00
7 Talang " U " Maspion 4m Ljr Rp. 87,500.00
8 Pengait talang PVC Bh Rp. 9,000.00
L BAHAN BUIS BETON.. 0.00
1 Buis beton bulat dia 15 cm, 1 m' Mtr Rp. 31,000.00
2 Buis beton bulat dia 20 cm, 1 m' Mtr Rp. 36,500.00
3 Buis beton bulat dia 30 cm, 1 m' Mtr Rp. 40,200.00
4 Buis beton bulat dia 40 cm, 1 m' Mtr Rp. 44,550.00
5 Buis beton bulat dia 50 cm, 1 m' Mtr Rp. 76,750.00
6 Buis beton bulat dia 60 cm, 1 m' Mtr Rp. 97,500.00
7 Buis beton bulat dia 80 cm, 1 m' Mtr Rp. 105,000.00
8 Buis beton bulat dia 100 cm, 1 m' Mtr Rp. 147,500.00
9 Buis beton U - 20cm , m' Mtr Rp. 25,500.00
10 Buis beton U - 30cm , m' Mtr Rp. 30,000.00
M BAHAN PENUTUP ATAP. 0.00
1 Genteng lokal ex Mojokembamg Bh Rp. 825.00
2 Genteng Nglayur Bh Rp. 1,550.00
3 Genteng bubungan Nglayur Bh Rp. 4,100.00
4 Genteng beton Bh Rp. 7,400.00
5 Genteng flam pres lokal Bh Rp. 20,000.00
6 Genteng kaca Bh Rp. 15,400.00
7 Genteng keramik Bh Rp. 12,500.00
8 Genteng kodok model karang pilang Bh Rp. 2,000.00
9 Genteng kodok karang pilang ( bambe) Bh Rp. 3,900.00
10 Bubungan genteng bambe. Bh Rp. 8,500.00
11 Bubungan glazur Kanmuri / KIA.enteng bambe. Bh Rp. 12,650.00
12 Eternit 1x1m tebal 6 mm Bh Rp. 20,500.00
13 Eternit 1x1m tebal 5 mm Bh Rp. 14,250.00
14 Acustik ukuran 30 x 60 Cm. Bh Rp. 50,100.00
Halaman : 125
1 2 3 4 5
15 Acustik ukuran 60 x 120 Cm. Bh Rp. 81,500.00
16 Calsiboardt 1x1m Calsibort 5 mm Bh Rp. 23,000.00
17 Asbes datar tebal 4 mm Bh Rp. 29,000.00
18 Asbes datar tebal 3,5 mm Bh Rp. 27,500.00
19 Asbes gelombang besar 225 x 110 Lbr Rp. 111,000.00
20 Asbes gelombang besar Per M2 M2 Rp. 38,600.00
21 Asbes gelombang kecil 225 x 105 Lbr Rp. 73,250.00
22 Asbes gelombang kecil Per M2. M2 Rp. 25,800.00
23 Bubungan Asbes Gelombang besar Bh Rp. 79,750.00
24 Bubungan Asbes Gelombang kecil Bh Rp. 61,700.00
25 Seng plat BJLS 30.80.300 cm Lbr Rp. 81,400.00
26 Seng gelombang BJLS 28 Lbr Rp. 95,200.00
27 Seng gelombang BJLS 30 Lbr Rp. 98,400.00
28 Seng plat BJLS 28 Lbr Rp. 74,000.00
29 Seng plat BJLS 30 Lbr Rp. 76,400.00
30 Seng Galvalum DJLS 45 warna lebar efektif 73 M1 Rp. 175,000.00
31 Seng Galvalum DJLS 45 polos lbr efektif 73 Cm M1 Rp. 185,000.00
N BAHAN PENGECATAN + POLITUR.. #VALUE!
1 Kertas gosok lbr Rp. 5,000.00
2 Plamur tembok Kg Rp. 15,500.00
3 Plamur kayu " PEDANG "(dempul kayu) Kg Rp. 17,000.00
4 Cat kayu / besi EMCO/setara Kg Rp. 65,000.00
5 Cat tembok "wathershilt" merk Duluk ; Jotun. Kg Rp. 70,000.00
6 Cat tembok "DECOLITH" Kg Rp. 32,500.00
7 Cat tembok "PARAGON" Kg Rp. 27,500.00
8 Cat kayu dasar Kg Rp. 28,500.00
9 Cat tembok "ICI Catilac" Kg Rp. 45,000.00
10 Cat meni "PEDANG" Kg Rp. 24,500.00
11 Dempul kayu Kg Rp. 37,500.00
12 Minyak cat / thiner B Ltr Rp. 10,500.00
13 Tinner A Ltr Rp. 17,750.00
14 Spiritus Ltr Rp. 14,300.00
15 Plitur jadi Ltr Rp. 43,750.00
16 Vernis Ltr Rp. 54,800.00
17 Lem putih " RAJAWALI " Kg Rp. 10,500.00
18 Lem kayu aica aibon Kg Rp. 36,500.00
19 Teer Kg Rp. 10,500.00
20 Cherlag Kg Rp. 58,000.00
O BAHAN KACA. 0.00
1 Kaca bening 3 mm m2 Rp. 49,500.00
2 Kaca bening 5 mm m2 Rp. 73,000.00
3 Kaca raybend 5 mm m2 Rp. 80,000.00
4 Kaca buram 5 mm m2 Rp. 66,000.00
5 Kaca cermin 5 mm m2 Rp. 140,000.00
6 Kaca cermin 6 mm m2 Rp. 370,000.00
7 Kaca patri warna 5 mm m2 Rp. 375,000.00
8 Kaca painting 5 mm m2 Rp. 260,000.00
9 Kaca nako + rangka "NIKY" Dn Rp. 32,500.00
P BAHAN PENGANTUNG + KUNCI. 0.00
1 Kunci "ALPHA Bulat" 1 x putar Bh Rp. 76,000.00
2 Kunci "SILINDER" 1 x putar Bh Rp. 65,250.00
3 Kunci "ANCHOR" / UNION / Yale 2 x tanam Bh Rp. 96,000.00
4 Kunci "KUDA TERBANG" 2 x putar Bh Rp. 117,000.00
5 Kunci tanam "ANTIK" 2 x putar Bh Rp. 123,500.00
6 Kunci selot kuningngan panjang 25 Cm Bh Rp. 69,750.00
7 Kunci selot kuningngan panjang 15 Cm Bh Rp. 34,100.00
8 Kunci selot hitam panjang 25 Cm Bh Rp. 20,000.00
9 Kunci selot hitam panjang 15 Cm Bh Rp. 13,700.00
10 Kunci lemari 808. Bh Rp. 9,800.00
Halaman : 126
1 2 3 4 5

11 Door holder / pegangan pintu antik / baik. Unit Rp. 374,000.00


12 Rel pintu dorong Unit Rp. 201,000.00
13 Engsel Nylon "ARCH" asli pintu Bh Rp. 19,000.00
14 Engsel jendela Bh Rp. 14,000.00
15 Grendel injak Bh Rp. 30,000.00
16 Grendel tanam pintu Bh Rp. 67,500.00
17 Grendel jendela Bh Rp. 11,500.00
18 Door closer Bh Rp. 236,750.00
19 Door STOP Bh Rp. 27,500.00
20 Kait angin sikutan yang baik. Psg Rp. 27,000.00
21 Hak angin Psg Rp. 9,500.00
Q BAHAN SANITAIR. 0.00
1 Kran air "SAN EI" Bh Rp. 43,200.00
2 Kran air "AMICO 1/2" Bh Rp. 29,600.00
3 Kran air "AMICO 3/4" Bh Rp. 31,000.00
4 Pompa air "GOLD STAR" Bh Rp. 565,000.00
5 Pompa air "NASIONAL" Bh Rp. 567,000.00
6 Floor drains / plastik. Bh Rp. 15,000.00
7 Closed Jongkok trasso Bh Rp. 119,000.00
8 Closed Jongkok keramic INA warna Bh Rp. 150,000.00
9 Closed duduk monoblock. Bh Rp. 900,000.00
10 Tutup bak mandi Bh Rp. 17,500.00
11 Lem paralon Bh Rp. 6,000.00
12 Westafel Bh Rp. 382,250.00
13 Urinoir keramic. Bh Rp. 67,000.00
14 Sumur + pompatangan dragon terpasang Unit Rp. 1,350,000.00
15 Septiktank + resapan komplit 1 M3 Unit Rp. 3,671,000.00
16 Septiktank + resapan komplit 2 M3 Unit Rp. 4,487,000.00
17 Septiktank + resapan komplit 6 M3 Unit Rp. 5,890,000.00
Septiktank + resapan komplit 8 M3 Unit Rp. 9,838,000.00
18 Septiktank + resapan komplit 10 M3 Unit Rp. 12,239,000.00
R BAHAN ELEKTRIKAL. 0.00
1 Pasang listrik /Wirring. Ttk Rp. 213,500.00
2 Lampu TL 1 x 10 w PHILIPS Bh Rp. 0.00
3 Lampu TL 1 x 20 w PHILIPS Bh Rp. 85,000.00
4 Lampu TL 1 x 40 w PHILIPS Bh Rp. 0.00
5 Lampu pijar 5 - 10 w PHILIPS LED Bh Rp. 75,000.00
6 Isolator Bh Rp. 5,000.00
7 Las Doof Bh Rp. 5,000.00
8 Fiting Plafoond Bh Rp. 8,500.00
9 T dos PVC Bh Rp. 2,300.00
10 Stop Kontak "BROCO" Bh Rp. 20,000.00
11 Saklar tunggal "BROCO" Bh Rp. 18,500.00
12 Saklar ganda " BROCO " Bh Rp. 26,100.00
13 Kabel NYA 1000 Volt 1,5 mm M1 Rp. 3,700.00
14 Kabel NYA 1000 Volt 2,5 mm M1 Rp. 5,400.00
15 Kabel NYA 1000 Volt 4 mm M1 Rp. 8,800.00
16 Sekrering Tunggal "LN" biasa Bh Rp. 20,900.00
17 Sekering ganda "LN" biasa Bh Rp. 33,700.00
18 Sekering 1 group + MCB Unit Rp. 95,000.00
19 Sekering 2 group + MCB Unit Rp. 230,000.00
20 Sekering 3 group + MCB Unit Rp. 307,000.00

Halaman : 127
DAFTAR HARGA TERTINGGI UPAH KERJA ORANG per HARI

NO. URAIAN TENAGA SATUAN UPAH PERHARI

1 2 3 4

1 MANDOR Org / hr Rp. 108,750.00


2 KEPALA TUKANG GALI TANAH Org / hr Rp. 108,000.00
3 KEPALA TUKANG BATU Org / hr Rp. 108,000.00
4 KEPALA TUKANG KAYU Org / hr Rp. 108,000.00
5 KEPALA TUKANG BESI Org / hr Rp. 108,000.00
6 KEPALA TUKANG CAT Org / hr Rp. 108,000.00
7 KEPALA TUKANG LISTRIK Org / hr Rp. 108,000.00
8 TUKANG GALI TANAH Org / hr Rp. 107,250.00
9 TUKANG BATU Org / hr Rp. 107,250.00
10 TUKANG KAYU Org / hr Rp. 107,250.00
11 TUKANG BESI Org / hr Rp. 107,250.00
12 TUKANG CAT Org / hr Rp. 107,250.00
13 TUKANG ASPAL Org / hr Rp. 107,250.00
14 TUKANG PLITUR Org / hr Rp. 107,250.00
15 TUKANG LISTRIK Org / hr Rp. 107,250.00
16 PEKERJA TUKANG GALI TANAH. Org / hr Rp. 75,000.00
17 PEMBANTU TUKANG BATU Org / hr Rp. 75,000.00
18 PEMBANTU TUKANG KAYU Org / hr Rp. 75,000.00
19 PEMBANTU TUKANG CAT Org / hr Rp. 75,000.00
20 PEMBANTU TUKANG BESI Org / hr Rp. 75,000.00
21 PEMBANTU TUKANG LISTRIK Org / hr Rp. 75,000.00
22 SOPIR TRUK. Org / hr Rp. 107,250.00
23 PEJAGA API Org / hr Rp. 75,000.00
24 PEJAGA MALAM Org / hr Rp. 75,000.00

Sidoarjo, 3 Januari 2015

PDAM DELTA TIRTA SIDOARJO


Kabupaten Sidoarjo.
DIREKTUR UTAMA

H. SUGENG MUJIADI, ST. MT


NIK. ………………….
Sidoarjo, 20 Juni 2008.

Menyetujui: Disurvey dan disusun oleh :


Plt. Kasubdin Tata Bangunan Staf Perencanaan Teknik Ta- Ba.
Dinas PU Cipta Karya dan Permukiman Dinas PU Cipta Karya & Permukiman
Kabupaten Sidoarjo. Kabupaten Sidoarjo.

BUDI UTOMO, ST.MM. KUSDI


Penata
Nip. 110 022 647.

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 128


Berapa
Dimqna

cvampa
kapan
aku
apakah
dimana
zaman
beber
hanya
lama
fase
ANALISA HARGA metode S.N.I. DT 91-0006-2007
PEKERJAAN PEMBORONGAN
PERIODE JANUARI 2014 ( PERUBAHAN HARGA Semester SATU )

PEKERJAAN PERSIAPAN
1. 1 m2 Pembersihan Lapangan dan Peralatan
Harga 1 m2 = Rp 12,937.50

2. 1 m' Pengukuran dan Pasang Papan Bowplank


Total Upah dan Bahan = Rp 107,928.75

3. 1 m' Pagar sementara dari kayu tinggi 2 m


Total Upah dan Bahan = Rp 456,281.50

4 1 m' Pagar sementara dari kawat duri tinggi 1.8 m


Total Upah dan Bahan = Rp 579,944.00

5 1 m2 Pembuatan kantor sementara, dengan lantai plesteran (Direksi keet)


Total Upah dan Bahan = Rp 1,567,460.00

6 1 m2 Pembuatan gudang semen dan alat-alat


Total Upah dan Bahan = Rp 2,115,627.50

7 1 m2 Pembuatan rumah jaga/konstruksi kayu


Total Upah dan Bahan = Rp 1,766,937.50

8 1 m2 Pembuatan bedeng buruh


Total Upah dan Bahan = Rp 2,547,852.50

9 1 m2 Pembuatan bak adukan ukuran ( 40 x 50 x 25 ) cm


Total Upah dan Bahan = Rp 267,520.00

10 1 m2 Pembuatan stegger dari bambu


Total Upah dan Bahan = Rp 53,129.75

11 1 m2 Pembuatan jalan sementara


Total Upah dan Bahan = Rp 119,237.50

12 1 m3 Bongkaran beton bertulang


Total Upah = Rp 536,238.75

13 1 m3 Bongkaran dinding tembok bata merah


Total Upah = Rp 503,613.75

14 1 m' Pagar sementara dari seng gelombang tinggi 2 m


Total Upah dan Bahan = = Rp 556,211.50
Halaman : 1
15. 1 m' Pasang pagar kawat jaring galvanis(Harmonikaq), tinggi 1 meter.
Total Upah dan Bahan = = Rp 17,015.50

16. 1 m' Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm tinggi 1 meter


Total Upah dan Bahan = = Rp 415,879.40

PEKERJAAN TANAH

1. 1 m3 Galian Untuk Tanah Biasa sedalam 1 m


Total Upah = Rp 58,968.75

2. 1 m3 Galian Untuk Tanah Biasa sedalam 2 m


Total Upah = Rp 72,393.75

3. 1 m3 Galian Untuk Tanah Biasa sedalam 3 m


Total Upah = Rp 86,036.25

4. 1 m3 Galian Untuk Tanah keras sedalam 1 m


Total Upah = Rp 78,480.00

5. 1 m3 Galian Untuk Tanah cadas sedalam 1 m


Total Upah = Rp 119,025.00

6. 1 m3 Galian Untuk Tanah lumpur sedalam 1 m


Total Upah = Rp 94,893.75

7. 1 m2 Pekerjaan stripping setinggi 1 m


Total Upah = Rp 4,293.75

8. 1 m3 Pembuangan tanah sejauh 30 m


Total Upah = Rp 25,837.50

9. 1 m3 Urugan kembali
Total Upah = Rp 16,466.25

10. 1 m3 Pemadatan tanah konvensional.


Total Upah = Rp 42,937.50

11. 1 m3 Urugan pasir dengan pasir urug.


Total Upah + bahan = Rp 143,587.50

12. 1 m3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 Tnh liat.


Total Upah + bahan = Rp 227,239.60

13. 1 m3 Lapisan pudel campuran 1 Kp : 5 Tnh liat


Total Upah + bahan = Rp 215,492.00

14. 1 m3 Pemasangan 1M2 lapisan ijuk tebal 10 Cm.


Total Upah + bahan = Rp 90,281.25

15. 1 m2 Pembuatan jalan sementara, tebal 25 cm


Total Upah + bahan = Rp 130,875.00

Halaman : 2
MENGURUG DENGAN SIRTU
TANPA PEMADATAN & CUKUP DIGELAR / DIRATAKAN DGN TENAGA MANUSIA.

16 1 m3 Urugan sirtu
Total Upah + bahan = Rp 143,587.50

MENGURUG DENGAN SIRTU UNTUK PARTAI BESAR ( DIATAS 200 m3 )


DENGAN ARMADA TRUK TRONTON + PEMADATAN DENGAN DOSER..

1 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 10 Km)
Total Biaya / M3 = Rp 145,087.50

2 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 20 Km)
Total Biaya / M3 = Rp 146,650.00

3 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 30 Km)
Total Biaya / M3 = Rp 147,337.50

4 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 40 Km)
Total Biaya / M3 = Rp 148,462.50

5 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 50 Km)
Total Biaya / M3 = Rp 150,587.50

6 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 60 Km)
Total Biaya / M3 = Rp 151,900.00

MENGURUG DENGAN SIRTU UNTUK PARTAI KECIL ( KURANG DARI 200 m3 )


DENGAN ANGKUTAN TRUK DISEL 3/4. TANPA PEMADATAN (Cukup digelar dan diratakan)

1 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 10 Km)
Total Biaya / M3 = Rp 145,600.50

2 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 20 Km)
Total Biaya / M3 = Rp 148,225.00

3 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 30 Km)
Total Biaya / M3 = Rp 148,912.50

4 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 40 Km)
Total Biaya / M3 = Rp 150,262.50

Halaman : 3
5 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)
(Jarak dengan penggambilan sirtu +/- 50 Km)
Total Biaya / M3 = Rp 152,950.00

6 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 60 Km)
Total Biaya / M3 = Rp 154,525.00

PEKERJAAN PONDASI
1. 1 m3 Pasang pondasi batu kosong (Aanstamping)
Total upah+bahan : = Rp 297,180.75

2. 1 m3 Pasang pondasi batu kali 1 Pc : 1 Ps


Total upah+bahan : = Rp 798,811.25

3. 1 m3 Pasang pondasi batu kali 1 Pc : 2 Ps


Total upah+bahan : = Rp 769,023.75

4. 1 m3 Pasang pondasi batu kali 1 Pc : 2.5 Ps


Total upah+bahan : = Rp 734,473.75

5. 1 m3 Pasang pondasi batu kali 1 Pc : 3 Ps


Total upah+bahan : = Rp 729,611.25

6. 1 m3 Pasang pondasi batu kali 1 Pc : 4 Ps


Total upah+bahan : = Rp 676,261.25

7. 1 m3 Pasang pondasi batu kali 1 Pc : 5 Ps


Total upah+bahan : = Rp 639,286.25

8. 1 m3 Pasang pondasi batu kali 1 Pc : 6 Ps


Total upah+bahan : = Rp 613,286.25

9. 1 m3 Pasang pondasi batu kali 1 Pc : 8 Ps


Total upah+bahan : = Rp 573,636.25

10. 1 m3 Pasang pondasi batu kali 1 Kp : 1 Sm : 1 Ps


Total upah+bahan : = Rp 458,603.75

11. 1 m3 Pasang pondasi batu kali 1 Kp : 1 Sm : 2 Ps


Total upah+bahan : = Rp 394,253.75

12. 1 m3 Pasang pondasi batu kali 1 Pc : 1/4 Kp : 4 Ps


Total upah+bahan : = Rp 620,859.75

13. 1 m3 Pasang pondasi batu kali 1 Pc : 3 Kp : 10 Ps


Total upah+bahan : = Rp 482,104.75

14. 1 m3 Pasang pondasi batu kali 1/4 Pc : 1 Kp : 4 Ps


Total upah+bahan : = Rp 514,496.75

15. 1 m3 Pasang pondasi siklop 60 % BETON Camp. 1 PCX:2Psr:3Krl. dan 40 % batu kali
Total upah+bahan : = Rp 2,118,110.00
Halaman : 4
16. 1 m3 Pasang pondasi sumuran Ø 100 cm
Total upah+bahan : = Rp 778,325.25

17. 1 m' Pembuatan tiang pancang ( 40 x 40 ) cm, beton bertulang


Total upah+bahan : = Rp 946,639.50
Jadi harga 1 Meter Tiang pancang ukuran 40 x 40 = Rp 946,639.50

18. 1 m' Pembuatan tiang pancang ( 35 x 35 ) cm, beton bertulang


Total upah+bahan : = Rp 739,940.00
Jadi harga 1 Meter Tiang pancang ukuran 35 x 35 = Rp 739,940.00

PEKERJAAN BETON TUMBUK & BETON BERTULANG


BETON TUMBUK.
1. 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
Total upah+bahan : = Rp 754,842.50

2. 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr


Total upah+bahan : = Rp 725,587.50

3. 1 m3 Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr


Total upah+bahan : = Rp 696,117.50

4. 1 m2 Membuat lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr tebal 5 Cm


Total upah+bahan : = Rp 37,742.13

BETON BERTULANG.
5. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
Total upah+bahan : = Rp 776,192.50

6. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr


Total upah+bahan : = Rp 840,962.50

7. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 2.5 Kr


Total upah+bahan : = Rp 1,002,925.00

8. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1.5 Ps : 3 Kr


Total upah+bahan : = Rp 941,587.50

9. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1.5 Ps : 2.5 Kr


Total upah+bahan : = Rp 970,372.50

10. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1 Ps : 2 Kr


Total upah+bahan : = Rp 1,099,637.50

11. 1 m3 Membuat beton tiang pancang prestressed beton


Total upah+bahan : = Rp 1,178,237.50

12. 1 m3 Membuat beton dengan puzzdith - 100 XR


Total upah+bahan : = Rp 970,392.50

13. 1 m3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr


Total upah+bahan : = Rp 1,435,022.50

14. 1 m3 Membuat beton kedap air dengan storox - 100


Total upah+bahan : = Rp 1,227,907.50
Halaman : 5
PEMBESIAN.

15 1 Kg Pembesian dengan besi polos


Total upah+bahan : = Rp 14,020.73

15.a 1 Kg Pembesian dengan besi ulir


Total upah+bahan : = Rp 14,020.73

16 1 Kg Kabel presstessed polos/strands


Total upah+bahan : = Rp 12,432.38

17 1 Kg Jaring kawat baja


Total upah+bahan : = Rp 25,747.88

BEGESTING.

18 1 m2 Pasang bekisting untuk pondasi


Total upah+bahan : = Rp 198,770.50

19 1 m2 Pasang bekisting untuk sloof


Total upah+bahan : = Rp 213,895.50

20 1 m2 Pasang bekisting untuk kolom


Total upah+bahan : = Rp 430,245.25

21 1 m2 Pasang bekisting untuk balok


Total upah+bahan : = Rp 442,845.25

22 1 m2 Pasang bekisting untuk lantai


Total upah+bahan : = Rp 517,545.25

23 1 m2 Pasang bekisting untuk dinding ( shear wall )


Total upah+bahan : = Rp 432,545.25

24 1 m2 Pasang bekisting untuk tangga


Total upah+bahan : = Rp 399,470.25

25 1 m2 Membuat begesting jembatan cor


Total upah+bahan : = Rp 133,282.50

PONDASI BETON
26 1 m3 Membuat pondasi beton bertulang ( 150 Kg besi + bekisting )
Total upah+bahan : = Rp 4,027,788.50

Sloof
27 1 m3 Membuat sloof beton bertulang ( 300 Kg besi + bekisting )
Total upah+bahan : = Rp 4,359,881.50

28 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 5 dia 19 mm + beugel dia 8 mm .
Total upah+bahan : = Rp 5,491,904.16

29 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 5 dia 16 mm + beugel dia 6 mm .
Total upah+bahan : = Rp 4,293,418.18
Halaman : 6
30 1 m3 Membuat sloof beton bertulang ukuran 15 x 20 Cm dengan besi 4 dia 12 mm + beugel dia 6mm .
Total upah+bahan : = Rp 4,173,824.39

31 1 m3 Membuat sloof beton bertulang ukuran 15 x 20 Cm dengan besi 4 dia 10 mm + kegesting .


Total upah+bahan : = Rp 2,782,142.04

Kolom
32 1 m3 Membuat kolom beton bertulang ( 300 Kg besi + bekisting )
Total upah+bahan : = Rp 4,828,325.25

33 1 m' Membuat kolom penguat ( kolom praktis ) beton bertulang ( 11 x 11 ) cm


Catatan : besi memakai diameter 12 mm beugel diameter 5 mm.
Total upah+bahan : = Rp 77,307.25

Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 77,307.25


Analog biaya / = 77,307.25 x 82.63 = Rp 6,387,898.07

34 1 m' Membuat kolom penguat ( kolom praktis ) beton bertulang ( 11 x 11 ) cm


Catatan : besi memakai diameter 10 mm beugel diameter 5 mm.
Total upah+bahan : = Rp 61,199.75

Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 61,199.75


Analog biaya / = 61,199.75 x 82.63 = Rp 5,056,935.34

Balok
35 1 m3 Membuat balok beton bertulang ( 200 Kg besi + bekisting )
Total upah+bahan : = Rp 5,231,532.75
36 1 m3 Membuat balok beton bertulang ( 150 Kg besi + bekisting )
Total upah+bahan : = Rp 6,967,512.50
37 1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm
Catatan : besi memakai diameter 12 mm beugel diameter 5 mm.
Total upah+bahan : = Rp 103,007.50

Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 103,007.50


Analog biaya / = 103,007.50 x 60.61 = Rp 6,243,284.58

38 1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm


Catatan : besi memakai diameter 10 mm beugel diameter 5 mm.
Total upah+bahan : = Rp 74,217.80

Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 74,217.80


Analog biaya / = 74,217.80 x 60.61 = Rp 4,498,340.86

39 1 m3 Membuat dinding beton bertulang ( 150 Kg besi + bekisting )


Total upah+bahan : = Rp 5,921,188.50

40 1 m3 Membuat tangga beton bertulang ( 200 Kg besi + bekisting )


Total upah+bahan : = Rp 6,348,735.00

Halaman : 7
Plat Lantai
41 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm , pembagi 8 mm.
Total upah+bahan : = Rp 756,227.20
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 10 - 12
dan besi polos dia 8 - 15 = Rp 756,227.20
Analog biaya / = 756,227.20 x 8.33 = Rp 6,299,372.58

42 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 12 mm , pembagi 10 mm.
Total upah+bahan : = Rp 435,191.95
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 12 - 15
dan besi polos dia 10 - 15 = Rp 435,191.95
Analog biaya / = 435,191.95 x 8.33 = Rp 3,625,148.94

43 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm jarak 15 , pembagi 10 mm.
Jarak 15 rangkap atas bawah ( doble wappening)
Total upah+bahan : = Rp 876,877.68
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm penulangan rangkap dengan besi dia 10 - 15
dan besi polos dia 8 - 15 (doble wappening) atas bawah. = Rp 876,877.68
Analog biaya / = 876,877.68 x 8.33 = Rp 7,304,391.03

PEKERJAAN PASANGAN
1. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps
Total upah+bhn /m2 : = Rp 236,462.50
Total per : M3 = Rp 909,471.15

2. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps


Total upah+bhn /m2 : = Rp 222,210.00
Total per : M3 = Rp 854,653.85

3. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps


Total upah+bhn /m2 : = Rp 207,970.00
Total per : M3 = Rp 799,884.62

4. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps


Total upah+bhn /m2 : = Rp 198,636.25
Total per : M3 = Rp 763,985.58

5. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps


Total upah+bhn /m2 : = Rp 193,577.50
Total per : M3 = Rp 744,528.85

6. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps


Total upah+bhn /m2 : = Rp 192,960.00
Total per : M3 = Rp 742,153.85

7. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps


Total upah+bhn /m2 : = Rp 175,852.00
Total per : M3 = Rp 676,353.85

Halaman : 8
8. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 1 Ps
Total upah+bhn /m2 : = Rp 118,493.75
Total per : M3 = Rp 911,490.38

9. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps


Total upah+bhn /m2 : = Rp 106,485.00
Total per : M3 = Rp 819,115.38

10. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps


Total upah+bhn /m2 : = Rp 99,850.50
Total per : M3 = Rp 768,080.77

11. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps


Total upah+bhn /m2 : = Rp 95,998.75
Total per : M3 = Rp 738,451.92

12. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps


Total upah+bhn /m2 : = Rp 93,573.25
Total per : M3 = Rp 719,794.23

13. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps


Total upah+bhn /m2 : = Rp 92,199.25
Total per : M3 = Rp 709,225.00

14. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps


Total upah+bhn /m2 : = Rp 89,598.75
Total per : M3 = Rp 689,221.15

15. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps


Total upah+bhn /m2 : = Rp 81,279.35
Total per : M3 = Rp 625,225.77

16. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1 Ps


Total upah+bhn /m2 : = Rp 75,697.70
Total per : M3 = Rp 582,290.00

17. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Ps


Total upah+bhn /m2 : = Rp 77,089.60
Total per : M3 = Rp 592,996.92

18 1 m2 Pasangan dinding conblock ( CB. 20 ) campuran 1PC : 3Psr.


Total upah+bhn /m2 : = Rp 391,866.38

19 1 m2 Pasangan dinding roster/terawang ( 12 x 11 x 24 ) cm camp. 1PC : 4 Psr.


Total upah+bhn /m2 : = Rp 220,836.25

20 1 m2 Pasangan bata berongga ( 5 x 11 x 24 ) cm


Total upah+bhn /m2 : = Rp 68,788.75
Total per : M3 = Rp 286,619.79

27. 1 m2 Pasangan dinding anyaman bambu, rangka kayu


Total upah+bhn /m2 : = Rp 100,906.00

Halaman : 9
PEKERJAAN PLESTERAN
1. 1 m2 Plesteran, 1 Pc : 1 Ps, tebal 15 mm
Total upah+bahan : = Rp 60,238.60

2. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 15 mm


Total upah+bahan : = Rp 49,763.00

3. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 15 mm


Total upah+bahan : = Rp 47,002.00

4. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 15 mm


Total upah+bahan : = Rp 45,225.00

5. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 15 mm


Total upah+bahan : = Rp 44,233.00

6. 1 m2 Plesteran, 1 Pc : 6 Ps, tebal 15 mm


Total upah+bahan : = Rp 43,432.00

7. 1 m2 Plesteran, 1 Pc : 8 Ps, tebal 15 mm


Total upah+bahan : = Rp 42,387.00

8. 1 m2 Plesteran, 1 Pc : 0.5 Kp : 3 Ps, tebal 15 mm


Total upah+bahan : = Rp 45,118.00

9. 1 m2 Plesteran, 1 Pc : 3 Kp : 10 Ps, tebal 15 mm


Total upah+bahan : = Rp 39,359.00

10 1 m2 Plesteran, 1 Pc : 3 Kp : 8 Ps, tebal 15 mm


Total upah+bahan : = Rp 39,456.80

11 1 m2 Plesteran, 1 Pc : 3 Kp : 5 Ps, tebal 15 mm


Total upah+bahan : = Rp 39,691.00

12 1 m2 Plesteran, 0.5 Pc : 1 Kp : 4 Ps, tebal 15 mm


Total upah+bahan : = Rp 40,249.23

11. 1 m2 Plesteran, 1 Kp : 1 Sm : 1 Ps, tebal 15 mm


Total upah+bahan : = Rp 37,737.00

12. 1 m2 Plesteran, 1 Kp : 1 Sm : 2 Ps, tebal 15 mm


Total upah+bahan : = Rp 38,261.00

13. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 20 mm


Total upah+bahan : = Rp 65,281.92

14. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 20 mm


Total upah+bahan : = Rp 61,328.71

15. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 20 mm


Total upah+bahan : = Rp 58,959.38

Halaman : 10
16. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 20 mm
Total upah+bahan : = Rp 57,636.71

17. 1 m2 Plesteran, 1 Pc : 6 Ps, tebal 20 mm


Total upah+bahan : = Rp 56,452.04

18. 1 m2 Plesteran, 1 Kp : 1 Sm : 2 Ps, tebal 20 mm


Total upah+bahan : = Rp 50,577.00

19. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 25 mm


Total upah+bahan : = Rp 74,137.08

20. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 25 mm


Total upah+bahan : = Rp 69,535.42

21. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 25 mm


Total upah+bahan : = Rp 66,573.75

22. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 25 mm


Total upah+bahan : = Rp 64,920.42

23. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 30 mm


Total upah+bahan : = Rp 87,079.75

24. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 30 mm


Total upah+bahan : = Rp 81,557.75

25. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 30 mm


Total upah+bahan : = Rp 78,003.75

26. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 30 mm


Total upah+bahan : = Rp 76,019.75

27. 1 m2 Berapen, 1 Pc : 5 Ps, tebal 30 mm


Total upah+bahan : = Rp 34,840.25

28. 1 m2 Berapen, 1 Pc : 5 Ps, tebal 15 mm


Total upah+bahan : = Rp 33,055.25

29. 1 m2 Plesteran beton, 1 Pc : 2 Ps, tebal 15 mm


Total upah+bahan : = Rp 61,681.25

30. 1 m2 Plesteran beton, 1 Pc : 3 Ps, tebal 15 mm


Total upah+bahan : = Rp 58,630.50

31. 1 m2 Plesteran skoning, 1 Pc : 2 Ps


Total upah+bahan : = Rp 13,784.50

32. 1 m2 Plesteran granito, 1 Pc warna : 2 Granito, tebal 10 mm


Total upah+bahan : = Rp 74,237.56

33. 1 m2 Plesteran Teraso, 1 Pc warna : 2 batu teraso, tebal 10 mm


Total upah+bahan : = Rp 70,760.61

34. 1 m2 Plesteran ciprat ,( kamprotan) 1 Pc : 2 Ps


Total upah+bahan : = Rp 40,602.25

Halaman : 11
35. 1 m2 Plesteran siar / setrikan adukan, 1 Pc : 2 Ps
Total upah+bahan : = Rp 29,771.50

36 1 m' Benangan
Total upah+bahan : = Rp 15,243.75

PEKERJAAN KAYU
KUSEN PINTU + JENDELA
1. 1 m3 Pasang kusen pintu & jendela kayu jati ( kayu klas.I).
Total upah+bahan : = Rp 20,496,925.00

2. 1 m3 Pasang kusen pintu & jendela kayu kamper (Kayu klas II )


Total upah+bahan : = Rp 11,982,425.00

3. 1 m3 Pasang kusen pintu & jendela kayu borneo ( Kruwing , kempas , Meranti batu )
Total upah+bahan : = Rp 9,402,425.00

PEKERJAAN PINTU
4 1 m2 Pasang pintu klamp kayu kamper
Total upah+bahan : = Rp 478,860.00

6. 1 m2 Pasang pintu klamp kayu borneo


Total upah+bahan : = Rp 368,860.00

7. 1 m2 Pasang pintu panil kayu jati


Total upah+bahan : = Rp 1,092,837.50

8. 1 m2 Pasang pintu panil kayu kamper


Total upah+bahan : = Rp 778,837.50

9. 1 m2 Pasang pintu & jendela kaca kayu jati


Total upah+bahan : = Rp 742,620.00

10. 1 m2 Pasang pintu & jendela kaca kayu kamper


Total upah+bahan : = Rp 643,870.00

11. 1 m2 Pasang pintu & jendela kaca kayu borneo


Total upah+bahan : = Rp 568,620.00

12. 1 m2 Pasang pintu & jendela jalusi kayu jati


Total upah+bahan : = Rp 1,476,837.50

13. 1 m2 Pasang pintu & jendela jalusi kayu kamper


Total upah+bahan : = Rp 974,437.50

14. 1 m2 Pasang pintu plywood rangkap, rangka kayu jati


Total upah+bahan : = Rp 796,631.25

15. 1 m2 Pasang pintu plywood rangkap, rangka kayu kamper


Total upah+bahan : = Rp 503,396.25

Halaman : 12
JALUSI / KREPYAK MATI.
16. 1 m2 Pasang jalusi mati kusen kayu jati
Total upah+bahan : = Rp 1,252,256.25

17. 1 m2 Pasang jalusi mati kusen kayu kamper


Total upah+bahan : = Rp 781,256.25

18. 1 m2 Pasang pintu plywood rangkap,rangka kayu borneo


Total upah+bahan : = Rp 448,907.50

19. 1 m2 Pasang pintu teakwood rangkap, rangka kayu jati


Total upah+bahan : = Rp 648,687.50

20. 1 m2 Pasang pintu teakwood rangkap, rangka kayu kamper


Total upah+bahan : = Rp 494,827.50

21. 1 m2 Pasang pintu plywood & formika, rangka kayu jati


Total upah+bahan : = Rp 865,398.75

22. 1 m2 Pasang pintu plywood & formika, rangka kayu kamper


Total upah+bahan : = Rp 669,148.75

23. 1 m2 Pasang pintu teakwood & formika, rangka kayu jati


Total upah+bahan : = Rp 865,398.75

24. 1 m2 Pasang pintu teakwood & formika, rangka kayu kamper ( dipolitur )
Total upah+bahan : = Rp 673,116.25

25. 1 m2 Pasang pintu formika double, rangka kayu jati


Total upah+bahan : = Rp 957,053.75

26. 1 m2 Pasang pintu formika double, rangka kayu kamper


Total upah+bahan : = Rp 716,793.75

KUDA KUDA
27. 1 m3 Pasang konstruksi kuda-kuda kayu jati
Total upah+bahan : = Rp 19,594,125.00

28. 1 m3 Pasang konstruksi kuda-kuda kayu kamper


Total upah+bahan : = Rp 10,519,125.00

29 1 m3 Pasang konstruksi kuda-kuda kayu kruing / bengkirai / kempas.


Total upah+bahan : = Rp 8,154,125.00

30 1 m3 Pasang konstruksi kuda-kuda kayu meranti.


Total upah+bahan : = Rp 6,614,125.00

PASANG USUK.
31. 1 m2 Pasang kaso + reng genteng kodok kayu kamper
Total upah+bahan : = Rp 107,919.39

Halaman : 13
32. 1 m2 Pasang kaso + reng genteng kodok kayu kruwing / bengkirai / kempas.
Total upah+bahan : = Rp 84,871.75

33 1 m2 Pasang kaso + reng genteng kodok kayu meranti.


Total upah+bahan : = Rp 76,401.75

34 1 m2 Pasang kaso + reng genteng munier kayu jati


Total upah+bahan : = Rp 322,868.75

35 1 m2 Pasang kaso + reng genteng munier kayu kamper


Total upah+bahan : = Rp 130,363.75

36 1 m2 Pasang kaso + reng genteng beton kayu kruwing / bengkirai / kempas.


Total upah+bahan : = Rp 113,423.75

37 1 m2 Pasang kaso + reng genteng beton kayu meranti.


Total upah+bahan : = Rp 107,828.75

38 1 m2 Pasang kaso + reng atap sirap kayu kamper


Total upah+bahan : = Rp 1,297,118.50
39 1 m2 Pasang kaso + reng atap sirap kayu kruwing / bengkirai / kempas.
Total upah+bahan : = Rp 934,118.50
RANGKA PLAVON / LANGIT2.
40 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu jati
Total upah+bahan : = Rp 237,518.75

41 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kamper pamjamg 4 m.


Total upah+bahan : = Rp 142,718.75

42 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kamper potongan 5/7 2 meter.
Total upah+bahan : = Rp 97,718.75

43 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kruwing / bengkirai / kempas.


Total upah+bahan : = Rp 116,318.75

44 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu MERANTI 5/7 panjang 4 m.


Total upah+bahan : = Rp 103,118.75

45 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu meranti potongan 5/7 - 2 meter.
Total upah+bahan : = Rp 86,318.75

46 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu jati


Total upah+bahan : = Rp 412,402.50

47 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper panjang 4mtr.- 5/7


Total upah+bahan : = Rp 230,702.50

48 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper potongan panjang 2 mtr.- 5/7
Total upah+bahan : = Rp 144,452.50

49 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kruwing , bemgkirai / kempas.


Total upah+bahan : = Rp 180,102.50

Halaman : 14
50 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu Meranti panjang 4 meter - 5/7.
Total upah+bahan : = Rp 154,802.50

51 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu Meranti potongan panjang 2 meter - 5/7.
Total upah+bahan : = Rp 122,602.50

52 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu jati


Total upah+bahan : = Rp 485,426.88

53 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper panjang 4 mtr Uk.5/7


Total upah+bahan : = Rp 272,126.88

54 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper potongan panjang 2 mtr Uk.5/7
Total upah+bahan : = Rp 170,876.88

55 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu bengkirai / kruwing / kempas. 5/7


Total upah+bahan : = Rp 212,726.88

PASANG LISPLANG
56 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu jati
Total upah+bahan : = Rp 205,853.75

57 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu kamper


Total upah+bahan : = Rp 121,073.75

58 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu meranti.


Total upah+bahan : = Rp 87,053.75

59 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu jati


Total upah+bahan : = Rp 228,543.75

60 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu kamper


Total upah+bahan : = Rp 142,193.75

61 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu meranti.


Total upah+bahan : = Rp 107,543.75

62 1 m' Pasang lisplang ukuran 2 x ( 3 x 20 ) cm, kayu kamper


Total upah+bahan : = Rp 167,933.75

63 1 m' Pasang lisplang ukuran 2 x ( 3 x 20 ) cm, kayu meranti.


Total upah+bahan : = Rp 122,258.75

64 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu kamper


Total upah+bahan : = Rp 95,672.50

65 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu meranti.


Total upah+bahan : = Rp 68,582.50

66 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu kruwing / bengkirai / kempas.


Total upah+bahan : = Rp 78,382.50
Halaman : 15
DINDING PEMISAH KAYU / TRIPLEKS
67 1 m2 Pasang rangka dan dinding pemisah kayu kamper
Total upah+bahan : = Rp 282,103.75

68 1 m2 Pasang rangka dan dinding pemisah kayu kruwing / bengkirai / kempas.


Total upah+bahan : = Rp 225,128.75

67 1 m2 Pasang rangka dan dinding pemisah kayu meranti.


Total upah+bahan : = Rp 190,828.75

68 1 m2 Pasang dinding pemisah tripleks 4mm rangkap, rangka kayu kamper


Total upah+bahan : = Rp 185,567.50

68 1 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper


Total upah+bahan : = Rp 184,062.50

69 1 m2 Pasang dinding pemisah plywood / formica rangkap, rangka kayu kamper


Total upah+bahan : = Rp 184,707.50

PASANG DINDING LAMBRESIRING

70 1 m2 Pasang dinding lambriziring dari papan jati


Total upah+bahan : = Rp 377,602.50

71 1 m' Pasang list plafond, kayu profil


Total upah+bahan : = Rp 13,602.00

72 1 m' Pasang list plafond, kayu kamper 1/5.


Total upah+bahan : = Rp 10,452.00

Halaman : 16
PEKERJAAN PENUTUP PLAVON

1. 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 6 mm


Total upah+bahan : = Rp 33,638.50

2. 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 5 mm


Total upah+bahan : = Rp 26,853.50

3 1 m2 Pasang langit-langit calsibord ( 1.00 x 1.00 ) m, tebal 5 mm


Total upah+bahan : = Rp 36,478.50

4 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 4 mm


Total upah+bahan : = Rp 43,078.50

5 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 3.5 mm


Total upah+bahan : = Rp 41,428.50

6. 1 m2 Pasang langit-langit akustik ( 30 x 60 ) cm


Total upah+bahan : = Rp 83,348.75

7. 1 m2 Pasang langit-langit akustik ( 60 x 120 ) cm


Total upah+bahan : = Rp 80,248.75

8. 1 m2 Pasang langit-langit plywood ( 30 x 60 ) cm, tebal 4 mm


Total upah+bahan : = Rp 50,021.63

9. 1 m2 Pasang langit-langit plywood ( 30 x 60 ) cm, tebal 4 mm


Total upah+bahan : = Rp 243,125.63

10. 1 m2 Pasang langit-langit plywood ( 60 x 120 ) cm, tebal 4 mm


Total upah+bahan : = Rp 252,500.63

11 1 m2 Pasang langit-langit tripleks ( 60 x 120 ) cm, tebal 6 mm


Total upah+bahan : = Rp 55,250.63

12 1 m2 Pasang langit-langit lat kayu jati


Total upah+bahan : = Rp 472,207.50

13 1 m2 Pasang langit-langit Lat kayu ramin


Total upah+bahan : = Rp 244,207.50

14 1 m2 Pasang langit-langit lat kayu kamper


Total upah+bahan : = Rp 283,807.50

15 1 m2 Pasang langit-langit soft board


Total upah+bahan : = Rp 319,381.25

16 1 m2 Pasang langit-langit akustik 60 x 120 cm + rangka alluminium


Total upah+bahan : = Rp 178,820.63

17 1 m' Pasang list langit-langit kayu profil


Total upah+bahan : = Rp 20,018.75

18 1 m2 Pasang langit-langit gypsum board, tebal 9 mm


Total upah+bahan : = Rp 58,336.25
Halaman : 17
PEKERJAAN PENUTUP ATAP

1. 1 m2 Pasang atap genteng plenthong kecil (lokal)


Total upah+bahan : = Rp 71,084.00

2. 1 m2 Pasang atap genteng kodok/glazzur


Total upah+bahan : = Rp 74,834.00

3. 1 m2 Pasang atap genteng plenthong super/besar ex kanmuri


Total upah+bahan : = Rp 64,080.00

4 1 m2 Pasang atap genteng Glazur Kanmuri / KIA.


Total upah+bahan : = Rp 175,080.00

5 1 m2 Pasang atap genteng bambe / good year / Jatiwangi type Alto.Kw 1.


Total upah+bahan : = Rp 106,980.00

6 1 m2 Pasang atap genteng model Kaang pilang .Kw 1.


Total upah+bahan : = Rp 75,080.00

7 1 m2 Pasang atap genteng Nglayur .Kw 1.


Total upah+bahan : = Rp 63,830.00

8 1 m' Pasang genteng bubung plenthong kecil


Total upah+bahan : = Rp 89,277.50

9 1 m' Pasang genteng bubung kodok glazzur


Total upah+bahan : = Rp 106,777.50
10 1 m' Pasang genteng bubung plenthong besar
Total upah+bahan : = Rp 104,777.50

11 1 m2 Pasang genteng bubungan bambe / good year / Jatiwangi type Alto.Kw 1.


Total upah+bahan : = Rp 114,277.50

12 1 m2 Pasang genteng bubungan Galazur ex Kanmuri / KIA.


Total upah+bahan : = Rp 135,027.50

13 1 m2 Pasang atap genteng beton


Total upah+bahan : = Rp 108,735.00

14 1 m' Pasang nok genteng beton


Total upah+bahan : = Rp 107,330.00

15 1 m2 Pasang atap asbes gelombang besar.


Total upah+bahan : = Rp 69,414.00

16 1 m2 Pasang atap asbes gelombang kecil.


Total upah+bahan : = Rp 54,054.00

17 1 m1 Pasang BUBUNGAN asbes gelombang besar


Total upah+bahan : = Rp 94,052.25

Halaman : 18
18 1 m1 Pasang BUBUNGAN asbes gelombang kecil..
Total upah+bahan : = Rp 76,002.25

19 1 m2 Pasang atap seng Galvalum type DJLS 45 Warna


Total upah+bahan : = Rp 246,798.00

20 1 m2 Pasang atap seng Galvalum type DJLS 45 Warna


Total upah+bahan : = Rp 260,498.00

21 1 m2 Pasang atap POLYCARBONAT.


Total upah+bahan : = Rp 122,148.00

22 1 m2 Pasang atap sirap


Total upah+bahan : = Rp 4,545,820.00

23 1 m' Pasang nok sirap


Total upah+bahan : = Rp 95,827.50

24 1 m2 Pasang atap seng gelombang BJLS 28


Total upah+bahan : = Rp 83,700.50

25 1 m2 Pasang atap nok seng BJLS 28


Total upah+bahan : = Rp 49,446.50

26 1 m2 Pasang atap seng gelombang BJLS 30


Total upah+bahan : = Rp 87,564.50

27 1 m2 Pasang atap nok seng BJLS 30


Total upah+bahan : = Rp 53,654.50

PEKERJAAN BESI

1. 1 Kg Pasang rangka atap baja


Total upah+bahan : = Rp 23,124.38

2. 1 m2 Pasang pintu besi baja


Total upah+bahan : = Rp 696,072.50

3. 1 m2 Pasang jendela besi


Total upah+bahan : = Rp 468,273.44

4 1 m2 Pasang teraliS besi


Total upah+bahan : = Rp 412,686.25

5 1 m2 Pasang kawat harmonika


Total upah+bahan : = Rp 51,563.98

6 1 m2 Pasang kawat nyamuk


Total upah+bahan : = Rp 49,363.98

7 1 m2 Pasang kawat kassa / kawat burung.


Total upah+bahan : = Rp 46,063.98
Halaman : 19
8 1 m2 Pas pagar kawat dari besi siku tinggi 1,5 m dan panjang 3m tdk termasuk pondasi setempat.
Total upah+bahan : = Rp 285,166.67

Harga per M2 pagar kawat := 285,166.67 : 5 63,370.37

9 1 m2 Pasang pagar besi tralis dengan besi beton diameter 16 mm.


Total upah+bahan : = Rp 376,666.67

11 1 m2 Pintu Rolling bahan dari Aluminium.


Total upah+bahan : = Rp 345,750.00

12 1 m2 Pintu Rolling bahan dari plat besi / steel.


Total upah+bahan : = Rp 568,487.50

13 1 m2 Pintu Besi B.R.C.


Total upah+bahan : = Rp 472,000.00

14 1 m2 Pagar Besi B.R.C.


Total upah+bahan : = Rp 517,000.00

Halaman : 20
PEKERJAAN KUSEN ALUMINIUM.

15 1 M' Pasang kusen aluminium 3" putih. (Silver)


Total upah+bahan : = Rp 118,067.44

16 1 M' Pasang kusen aluminium 4" putih. (Silver)


Total upah+bahan : = Rp 135,667.44

17 1 M' Pasang kusen aluminium 3" coklat. (Brown)


Total upah+bahan : = Rp 124,667.44

18 1 M' Pasang kusen aluminium 4" coklat. (Brown)


Total upah+bahan : = Rp 131,267.44

19 1 Bh. Pasang pintu aluminium 2,75" putih ( Silver) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Total upah+bahan : = Rp 1,236,094.93

20 1 Bh. Pasang pintu aluminium 2,75" coklat ( Brown) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Total upah+bahan : = Rp 1,518,874.93

21 1M2 Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 797,688.00

22 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.60 Mtr.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 488,955.50

23 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.50 Mtr.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 464,305.50

24 1M2 Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 940,900.50

25 1Bh Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 60 Cm.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 554,089.25

26 1Bh. Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 50 Cm.
( Jendela isian kaca 5mm).
Total upah+bahan : = Rp 523,439.25

Halaman : 21
PEKERJAAN TALANG SENG ; KARET & PVC.

9 1 m' Pasang talang datar, seng bjls 28


Total upah+bahan : = Rp 82,493.75

10 Analog - talang karet per m' + papan= 70 % talang seng = Rp : 57,745.63

11 1 m' Pasang talang miring / jurai seng bjls 28


Total upah+bahan : = Rp 183,060.94

12 1 m' Pasang talang 1/2 lingkaran ø 10 cm, seng bjls 28


Total upah+bahan : = Rp 74,568.44

13 1 m' Pasang talang dari PVC diameter 3".


Total upah+bahan : = Rp 37,375.00

14 1 m' Pasang talang dari PVC diameter 4".


Total upah+bahan : = Rp 37,375.00

Halaman : 22
PEKERJAAN PRNGECATAN
Pemersihan Cat
1. 1 m2 Mengikis/mengerok permukaan cat tembok lama
Total upah+bahan : = Rp 11,896.88

2. 1 m2 Mencuci bidang permukaan tembok yang pernah dicat


Total upah+bahan : = Rp 11,709.38

3. 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual


Total upah+bahan : = Rp 11,709.38

4. 1 m2 Menyabun permukaan tembok lama


Total upah+bahan : = Rp 11,709.38

5. 1 m2 Mengerok karat atau cat lama permukaan baja dengan pancar pasir ( sanblasting )
dengan tingkat kebersihan Sa 2.5%
Untuk 10 M2 Total upah+bahan : = Rp 683,575.00

Untuk 1 M2 = Rp 68,357.50

6. 1 m2 Mendempul dan menggosok kayu


Total upah+bahan : = Rp 11,258.88

Cat KAYU
7. 1 m2 Pengecatan bidang kayu lama
Total upah+bahan : = Rp 32,876.88

8. 1 m2 Pengecatan bidang kayu baru ( 1x plamir , 1x cat dasar, 2x cat penutup )


Total upah+bahan : = Rp 36,336.88

9. 1 m2 Pengecatan bidang kayu baru ( 1x plamir , 1x cat dasar, 3x cat penutup )


Total upah+bahan : = Rp 42,456.88

POLITUR , TEAK OIL , PENGETIRAN


10. 1 m2 Pelaburan bidang kayu dengan teak oil
Total upah+bahan : = Rp 32,629.88

11. 1 m2 Pelaburan bidang kayu dengan politur ( TAK MENGKILAP)


Total upah+bahan : = Rp 29,254.88

12 10 m2 Pemelituran dengan serlag. ( SAMPAI MENGKILAP)


Untuk 10 M2 Total upah+bahan : = Rp 784,770.00
Untuk 1 M2 Total upah+bahan : = Rp 78,477.00

13 1 m2 Pelaburan bidang kayu dengan cat residu dan ter


Total upah+bahan : = Rp 11,827.50

14 1 m2 Pelaburan bidang kayu dengan vernis


Total upah+bahan : = Rp 31,824.88

Halaman : 23
Cat TEMBOK
Cat BARU.
14. 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penuCat Paragon /Decolith
Total upah+bahan : = Rp 22,086.28

15 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penuCat I.C.I. Catilac
Total upah+bahan : = Rp 28,386.28

16 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penuCat I.C.I. Watershild
Total upah+bahan : = Rp 37,386.28

Cat LAMA.
17 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat pen Cat Paragon /Decolith
Total upah+bahan : = Rp 17,408.14

18 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat pen Cat I.C.I. Catilac
Total upah+bahan : = Rp 23,183.14

19 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat pen Cat I.C.I. Watershild
Total upah+bahan : = Rp 31,433.14

20 1 m2 Melabur tembok dengan kapur sirih


Total upah+bahan : = Rp 12,615.68

21 1 m2 Melabur tembok lama dengan kapur sirih ( untuk pemeliharaan )


Total upah+bahan : = Rp 5,215.88

22 1 m2 Pemasangan wallpaper
Total upah+bahan : = Rp 79,687.88

23 1 m2 Pengecatan permukaan baja dengan meni besi


Total upah+bahan : = Rp 28,927.50

24 1 m2 Pengecatan permukaan baja dengan meni besi dan perancah


Total upah+bahan : = Rp 41,086.25

25 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual


sistem 4 lapis cat konvensional dengan tebal 200 um
Total upah+bahan : = Rp 71,813.75

26 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual


sistem 1 lapis cat mutakhir dengan tebal 200 um
Total upah+bahan : = Rp 43,152.88

27 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual


sistem 3 lapis cat konvensional dengan tebal 200 um
Total upah+bahan : = Rp 63,490.75

28 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara semprot ( airless spray )
sistem 1 lapis cat mutakhir dengan tebal 200 um
Total upah+bahan : = Rp 48,847.50
Halaman : 24
PEKERJAAN PENUTUP LANTAI
1 1 m2 Pasang lantai ubin warna akuran 40 x 40 cm
Total upah+bahan : = Rp 1,142,752.38

2 1 m2 Pasang lantai ubin warna akuran 30 x 30 cm


Total upah+bahan : = Rp 129,549.38

3 1 m2 Pasang lantai ubin teraso akuran 40 x 40 cm


Total upah+bahan : = Rp 102,932.88

5 1 m2 Pasang lantai ubin teraso akuran 30 x 30 cm


Total upah+bahan : = Rp 143,838.13

6 1 m2 Pasang lantai ubin granito akuran 40 x 40 cm


Total upah+bahan : = Rp 194,432.88

7 1 m2 Pasang lantai keramic Exensa 40 x 40 cm


Total upah+bahan : = Rp 160,532.13

8 1 m2 Pasang lantai marmer akuran 60 x 60 cm


Total upah+bahan : = Rp 201,740.13

9 1 m2 Pasang teraso cor ditempat nat kaca 4Cm x 5 mm


Total upah+bahan : = Rp 130,587.82

10 1 m2 Pasang grani cor ditempat nat kuningan


Total upah+bahan : = Rp 142,838.30

11 1 m1 Pasang lantai keramik artistik 5 x 20 cm / Lis / Ban


Total upah+bahan : = Rp 74,709.50

12 1 m1 Pasang lantai keramik artistik 7,5 x 25 cm / Lis / Ban


Total upah+bahan : = Rp 70,915.44

13 1 m2 Pasang lantai keramik 20 x 20 cm


Total upah+bahan : = Rp 112,857.82

14 1 m2 Pasang lantai keramik 30 x 30 cm


Total upah+bahan : = Rp 119,477.82

14 1 m2 Pasang lantai keramik 40 x 40 cm


Total upah+bahan : = Rp 114,912.82

15 1 m1 Pasang lantai keramik 30 x 30 cm anti slip / Rock tile


Total upah+bahan : = Rp 128,507.82

16 1 m2 Pasang lantai mosaik 30 x 30 cm.


Total upah+bahan : = Rp 129,032.82

17 1 m2 Pasang lantai karper 100% wool


Total upah+bahan : = Rp 251,267.88
Halaman : 25
18 1 m2 Pasang lantai karper 80% wool, 20% nylon
Total upah+bahan : = Rp 209,267.88

19 1 m2 Pasang lantai parquet jati


Total upah+bahan : = Rp 317,626.88

20 1 m2 Pasang dinding porselin 11 x 11 cm, putih


Total upah+bahan : = Rp 96,989.09

21 1 m2 Pasang dinding porselin 11 x 11 cm, warna


Total upah+bahan : = Rp 98,649.09

22 1 m2 Pasang dinding keramik 20 x 25 cm


Total upah+bahan : = Rp 115,672.21

23 1 m2 Pasang dinding keramik 20 x 35 cm


Total upah+bahan : = Rp 122,452.21

24 1 m2 Pasang dinding marmer


Total upah+bahan : = Rp 310,534.75

25 1 m2 Pasang dinding bata pelapis 7 x 3 x 24 cm


Total upah+bahan : = Rp 148,869.75
26 1 m2 Pasang dinding bata klinker 5 x 5 x 24 cm
Total upah+bahan : = Rp 146,508.00

27 1 m2 Pasang dinding batu paros


Total upah+bahan : = Rp 113,605.75

28 1 m2 Pasang dinding batu tempel hitam


Total upah+bahan : = Rp 89,455.75

29 1 m2 Pasang lantai vinyl oscar / xsintetis 30 x 30 cm KL 1


Total upah+bahan : = Rp 99,548.13

30 1 m2 Pasang lantai vinyl karet 30 x 30 cm


Total upah+bahan : = Rp 107,548.13

78. 1 m2 Pasang lantai vinyl motif kembang 30 x 30 cm


Total upah+bahan : = Rp 103,348.13

Halaman : 26
PEKERJAAN PAVING STONE

1 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm.
Total upah+bahan : = Rp 93,776.97

2 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm.
Total upah+bahan : = Rp 127,220.97

3 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm
Total upah+bahan : = Rp 106,736.97

4 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 123,296.97

5 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Total upah+bahan : = Rp 92,426.97

6 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 112,971.97

7 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Total upah+bahan : = Rp 105,726.97

8 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 120,076.97

9 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 6 Cm
Total upah+bahan : = Rp 103,136.97

10 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 138,556.97

11 1 m2 Pasang PAVING STONE warna merah TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 153,836.97

12 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 6 Cm
Total upah+bahan : = Rp 90,308.97

13 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 8 Cm
Total upah+bahan : = Rp 119,376.97

PEKERJAAN KANSTIN / SKERB.

1 1 m1 Pasang KANSTIN / SKERB Model lengkung Uk. 50 x 18 x 30 Cm.


Total upah+bahan : = Rp 108,077.50

1 1 m1 Pasang KANSTIN / SKERB Model lurus Uk. 8 x 40 x 20 Cm.


Total upah+bahan : = Rp 105,607.50

Halaman : 27
PEKERJAAN GEBALAN RUMPUT

1 1 m2 Penanaman Rumput LAMUR.


Total upah+bahan : = Rp 21,578.75

2 1 m2 Penanaman Rumput GAJAH.


Total upah+bahan : = Rp 23,078.75

3 1 m2 Penanaman Rumput JEPANG.


Total upah+bahan : = Rp 27,078.75

Halaman : 28
PEKERJAAN KUNCI DAN KACA

1. 1 buah pasang kunci tanam antik


Total upah+bahan : = Rp 199,373.75

2. 1 buah pasang kunci tanam biasa 2 X PUTAR.


Total upah+bahan : = Rp 171,873.75

3. 1 buah pasang kunci tanam KM/WC


Total upah+bahan : = Rp 130,811.88

4. 1 buah pasang kunci silinder


Total upah+bahan : = Rp

5. 1 buah pasang engsel pintu


Total upah+bahan : = Rp 37,914.06
6. 1 buah pasang engsel jendela kupu-kupu
Total upah+bahan : = Rp 26,609.38

7. 1 buah pasang engsel angin


Total upah+bahan : = Rp 22,109.38

8 1 buah pasang kait angin sikutan YANG BAIK


Total upah+bahan : = Rp 45,914.06

9 1 buah pasang door closer


Total upah+bahan : = Rp 299,796.88

10 1 buah pasang kunci selot kuningan panjang 25 Cm


Total upah+bahan : = Rp 94,968.75

11 1 buah pasang kunci selot kuningan panjang 15 Cm


Total upah+bahan : = Rp 59,318.75

12 1 buah pasang kunci selot hitam panjang 25 Cm


Total upah+bahan : = Rp 45,218.75

13 1 buah pasang kunci selot hitam panjang 15 Cm


Total upah+bahan : = Rp 38,918.75

14 1 buah pasang pegangan pintu/door holder


Total upah+bahan : = Rp 437,046.88

15 1 buah pasang door stop


Total upah+bahan : = Rp 33,859.38

16 1 buah pasang rel pintu dorong


Total upah+bahan : = Rp 276,656.25

17 1 buah pasang kunci lemari


Total upah+bahan : = Rp 41,323.44
Halaman : 29
18 1 m2 pasang kaca, tebal 3 mm
Total upah+bahan : = Rp 73,364.06

19 1 m2 pasang kaca, tebal 5 mm


Total upah+bahan : = Rp 99,214.06

20 1 m2 pasang kaca, rayben 5 mm


Total upah+bahan : = Rp 106,914.06

21 1 m2 pasang kaca buram, tebal 5 mm


Total upah+bahan : = Rp 104,123.44

22 1 m2 pasang kaca cermin, tebal 5 mm


Total upah+bahan : = Rp 172,914.06
23 1 m2 pasang kaca cermin, tebal 6 mm
Total upah+bahan : = Rp 425,914.06

24 1 m2 pasang kaca painting / gambar, tebal 5 mm


Total upah+bahan : = Rp 304,914.06

25 1 m2 pasang kaca patri, tebal 5 mm


Total upah+bahan : = Rp 431,414.06

Halaman : 30
PEKERJAAN SANITAIR

1. Memasang 1 buah kloset duduk/monoblok


Total upah+bahan : = Rp 1,336,983.00

2. Memasang 1 buah kloset jongkok porselen


Total upah+bahan : = Rp 430,375.00

3. Memasang 1 buah kloset jongkok teraso


Total upah+bahan : = Rp 444,637.50

4. Memasang 1 buah urinoir


Total upah+bahan : = Rp 475,175.00

5. Memasang 1 buah wastafel


Total upah+bahan : = Rp 809,857.50

6. Memasang 1 buah bak mandi teraso volume 0.3 m3


Total upah+bahan : = Rp 516,610.00

7. Memasang 1 buah bak mandi fiberglass volume 0.3 m3


Total upah+bahan : = Rp 665,957.50

8. Memasang 1 buah bak mandi batu bata volume 0.3 m3


Total upah+bahan : = Rp 1,618,475.00

9. Memasang 1 buah badtub porselen KIA ; INA ; Toto


Total upah+bahan : = Rp 1,616,231.25

9. Memasang 1 buah badtub fiber glass.


Total upah+bahan : = Rp 806,231.25

10. Membuat 1 buah bak beton volume 1 m3 air


Total upah+bahan : = Rp 4,144,950.00

11. Memasang 1 buah bak mandi fiberglass volume 1 m3 air


Total upah+bahan : = Rp 918,716.00

14. Memasang 1 m' pipa beton, Ø 15 - 20 cm


Total upah+bahan : = Rp 79,441.25
15. Memasang 1 m' pipa beton, Ø 30 - 100 cm
Total upah+bahan : = Rp 130,773.25

16. Memasang 1 buah bak kontrol pas. batu bata ( 30x30 ) cm, tinggi 35 cm
Total upah+bahan : = Rp 244,033.25

17. Memasang 1 buah bak kontrol pas. batu bata ( 45x45 ) cm, tinggi 50 cm
Total upah+bahan : = Rp 358,744.75

18. Memasang 1 buah bak kontrol pas. batu bata ( 60x60 ) cm, tinggi 65 cm
Total upah+bahan : = Rp 556,359.50
Halaman : 31
19. Memasang 1 m' pipa galvanis ø 1/2"
Total upah+bahan : = Rp 63,335.75

20. Memasang 1 m' pipa galvanis ø 3/4"


Total upah+bahan : = Rp 72,635.75

21. Memasang 1 m' pipa galvanis ø 1"


Total upah+bahan : = Rp 144,710.75

22. Memasang 1 m' pipa galvanis ø 1,25"


Total upah+bahan : = Rp 272,123.75

23. Memasang 1 m' pipa galvanis ø 2"


Total upah+bahan : = Rp 349,623.75

24. Memasang 1 m' pipa galvanis ø 3"


Total upah+bahan : = Rp 370,675.75

25. Memasang 1 m' pipa PVC tipe AW ø 1/2"


Total upah+bahan : = Rp 18,581.25

26. Memasang 1 m' pipa PVC tipe AW ø 3/4"


Total upah+bahan : = Rp 20,053.75

27. Memasang 1 m' pipa PVC tipe AW ø 1"


Total upah+bahan : = Rp 22,475.63

28 Memasang 1 m' pipa PVC tipe D ø 2"


Total upah+bahan : = Rp 32,880.00

29 Memasang 1 m' pipa PVC tipe D ø 3"


Total upah+bahan : = Rp 50,666.25

30 Memasang 1 m' pipa PVC tipe D ø 4"


Total upah+bahan : = Rp 86,007.63

31 Memasang 1 buah bak cuci piring stainless steel


Total upah+bahan : = Rp 377,828.13
32 Memasang 1 buah bak cuci piring teraso
Total upah+bahan : = Rp 409,592.93

33 Memasang 1 buah kran ø 3/4" atau 1/2"


Total upah+bahan : = Rp 48,161.25

34 Memasang 1 buah floor drain


Total upah+bahan : = Rp 28,098.75

Halaman : 32
PEMBUATAN SEPTIKTANK UNTUK KAPASITAS 15 ORANG.
( Ukuran 1.5 X 2.5 X dalam 1.75 & resapan diameter 1.5 m dalam 2m )

Volume Uraian pekerjaan Harga satuan. Jumlah harga

13 M3 Galian tanah @ Rp. 72,393.75 = Rp 941,118.75


4 M3Urug kembali tanah (1/4 galian) @ Rp. 16,466.25 = Rp 65,865.00
3 M3 Pasang batu bata 1:2 @ Rp. 819,115.38 = Rp 2,457,346.15
29 M2 Plesteran 1:2 @ Rp. 49,763.00 = Rp 1,443,127.00
1 Beton tumbuk 1:2 @ Rp. 776,192.50 = Rp 543,334.75
0 M3 Beton bertulang 123 @ Rp. 4,173,824.39 = Rp 834,764.88
2 Kerikil keringan @ Rp. 181,000.00 = Rp 271,500.00
2 M3 Pasir saringa @ Rp. 175,000.00 = Rp 350,000.00
1 M' Pasang pipa besi O 2" @ Rp. 35,000.00 = Rp 35,000.00
5 M' Pasang pipa PVC O 15 Cm @ Rp. 86,007.63 = Rp 430,038.13
20 Kg Ijuk Saringan @ Rp. 12,900.00 = Rp 258,000.00
1 Alat - alat bantu @ Rp. 35,000.00 = Rp 35,000.00
Jumlah = Rp 7,665,094.66

Sidoarjo, Januari 2014

DELTA TIRTA KABUPATEN SIDOARJO


DIREKTUR UTAMA

H.DJAJADI,SH,MM

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 33
ANALISA HARGA metode S.N.I. 03-2835-2002

PEKERJAAN PEMBORONGAN
PEREODE Bulan JANUARI 2014( Semester Pertama )

PEKERJAAN PERSIAPAN
1. 1 m2 Pembersihan Lapangan dan Peralatan
Upah An. SNI ( Revisi ) 6.8.1
0.100 O/hr Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.050 O/hr Mandor @ Rp. 108,750.00 = Rp 5,437.50
= Rp 12,937.50
Harga 1 m2 = Rp 12,937.50

2. 1 m' Pengukuran dan Pasang Papan Bowplank


Bahan An. SNI ( Revisi ) 6.4.1
0.012 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 52,800.00
0.020 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 280.00
0.007 m3 Kayu Papan meranti 3/20 @ Rp. 5,000,000.00 = Rp 35,000.00
Sub total : = Rp 88,080.00
Upah An. SNI ( Revisi ) 6.4.2
0.100 Oh Tukang Kayu @ Rp. 107,250.00 = Rp 10,725.00
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.010 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total Upah dan Bahan = Rp 107,928.75

3. 1 m' Pagar sementara dari kayu tinggi 2 m


Bahan An. SNI ( Revisi ) 6.1.1
1.250 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 67,500.00
5.500 kg Semen Portland @ Rp. 1,525.00 = Rp 8,387.50
0.005 m3 Pasir beton @ Rp. 198,000.00 = Rp 990.00
0.009 m3 Koral beton @ Rp. 181,000.00 = Rp 1,629.00
0.072 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 316,800.00
0.060 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 840.00
0.400 Lt Residu @ Rp. 10,500.00 = Rp 4,200.00
Sub total : = Rp 400,346.50
Upah An. SNI ( Revisi ) 6.1.2
0.200 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 21,600.00
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.020 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 2,160.00
0.020 Oh Mandor @ Rp. 108,750.00 = Rp 2,175.00
Sub total : = Rp 55,935.00
Total Upah dan Bahan = Rp 456,281.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 1
4 1 m' Pagar sementara dari kawat duri tinggi 1.8 m
Bahan An. SNI ( Revisi ) 6.3.1
1.250 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 67,500.00
2.000 kg Semen Portland @ Rp. 1,525.00 = Rp 3,050.00
25.000 kg Kawat duri @ Rp. 18,300.00 = Rp 457,500.00
0.005 m3 Pasir beton @ Rp. 198,000.00 = Rp 990.00
0.009 m3 Koral beton @ Rp. 181,000.00 = Rp 1,629.00
0.060 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 531,509.00
Upah An. SNI ( Revisi ) 6.3.2
0.200 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 21,600.00
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.020 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 2,160.00
0.020 Oh Mandor @ Rp. 108,750.00 = Rp 2,175.00
Sub total : = Rp 48,435.00
Total Upah dan Bahan = Rp 579,944.00

5 1 m2 Pembuatan kantor sementara, dengan lantai plesteran (Direksi keet)


Bahan An. SNI ( Revisi ) 6.5.1
1.250 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 67,500.00
0.180 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 792,000.00
0.850 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 11,900.00
1.100 kg Besi strip @ Rp. 11,825.00 = Rp 13,007.50
35.000 kg Semen Portland @ Rp. 1,525.00 = Rp 53,375.00
0.150 m3 Pasir pasang @ Rp. 175,000.00 = Rp 26,250.00
0.100 m3 Pasir beton @ Rp. 198,000.00 = Rp 19,800.00
0.150 m3 Koral beton @ Rp. 181,000.00 = Rp 27,150.00
30.000 Bh Bata merah @ Rp. 400.00 = Rp 12,000.00
0.250 Lbr Seng plat @ Rp. 74,000.00 = Rp 18,500.00
2.000 m2 Jendela nako @ Rp. 32,500.00 = Rp 65,000.00
0.080 m2 Kaca polos @ Rp. 73,000.00 = Rp 5,840.00
0.150 Bh Kunci tanam @ Rp. 96,000.00 = Rp 14,400.00
0.060 Lbr Playwood 4mm @ Rp. 77,500.00 = Rp 4,650.00
Sub total : = Rp 1,131,372.50
Upah An. SNI ( Revisi ) 6.5.2
2.000 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 216,000.00
1.000 Oh Tukang batu @ Rp. 107,250.00 = Rp 107,250.00
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.300 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 32,400.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 436,087.50
Total Upah dan Bahan = Rp 1,567,460.00

6 1 m2 Pembuatan gudang semen dan alat-alat


Bahan An. SNI ( Revisi ) 6.6.1
1.700 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 91,800.00
0.210 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 924,000.00
0.300 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 4,200.00
10.500 kg Semen Portland @ Rp. 61,000.00 = Rp 640,500.00
0.030 m3 Pasir beton @ Rp. 198,000.00 = Rp 5,940.00
0.050 m3 Koral beton @ Rp. 181,000.00 = Rp 9,050.00
1.500 Lbr Seng gelombang bljs 32 @ Rp. 81,400.00 = Rp 122,100.00
Sub total : = Rp 1,797,590.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 2
Upah An. SNI ( Revisi ) 6.6.2
2.000 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 216,000.00
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.200 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 21,600.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 318,037.50
Total Upah dan Bahan = Rp 2,115,627.50

7 1 m2 Pembuatan rumah jaga/konstruksi kayu


Bahan An. SNI ( Revisi ) 6.7.1
3.000 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 162,000.00
0.276 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 1,214,400.00
0.700 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 9,800.00
1.500 Lbr Seng gelombang bljs 32 @ Rp. 81,400.00 = Rp 122,100.00
Sub total : = Rp 1,508,300.00

Upah An. SNI ( Revisi ) 6.7.2


1.500 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 162,000.00
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.150 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 16,200.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 258,637.50
Total Upah dan Bahan = Rp 1,766,937.50

8 1 m2 Pembuatan bedeng buruh


Bahan An. SNI ( Revisi ) 6.9.1
1.250 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 67,500.00
0.186 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 818,400.00
0.300 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 4,200.00
18.000 kg Semen Portland @ Rp. 61,000.00 = Rp 1,098,000.00
0.030 m3 Pasir beton @ Rp. 198,000.00 = Rp 5,940.00
0.050 m3 Koral beton @ Rp. 181,000.00 = Rp 9,050.00
1.500 Lbr Seng gelombang bljs 32 @ Rp. 81,400.00 = Rp 122,100.00
1.350 Lbr Playwood 4mm @ Rp. 77,500.00 = Rp 104,625.00
Sub total : = Rp 2,229,815.00
Upah An. SNI ( Revisi ) 6.9.2
2.000 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 216,000.00
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.200 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 21,600.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 318,037.50
Total Upah dan Bahan = Rp 2,547,852.50

9 1 m2 Pembuatan bak adukan ukuran ( 40 x 50 x 25 ) cm


Bahan An. SNI ( Revisi ) 6.10.1
0.036 m3 Kayu Terentang / meranti @ Rp. 5,000,000.00 = Rp 180,000.00
0.080 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 1,120.00
1.000 Btg Kaso meranti 5/7 @ Rp. 54,000.00 = Rp 54,000.00
Sub total : = Rp 235,120.00
Upah An. SNI ( Revisi ) 6.10.2
0.300 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 32,400.00
0.0015 Oh Mandor @ Rp. 108,750.00 = Rp 163.13
Sub total : = Rp 32,400.00

Total Upah dan Bahan = Rp 267,520.00


D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 3
10 1 m2 Pembuatan stegger dari bambu
Bahan An. SNI ( Revisi ) 6.11.1
1.000 Btg Bambu Ø 6 - 10 / 600 cm @ Rp. 20,000.00 = Rp 20,000.00
0.250 Kg Tali ijuk @ Rp. 12,900.00 = Rp 3,225.00
Sub total : = Rp 23,225.00

Upah An. SNI ( Revisi ) 6.11.2


0.250 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 27,000.00
0.002 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 216.00
0.017 Oh Pekerja @ Rp. 75,000.00 = Rp 1,275.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 29,904.75
Total Upah dan Bahan = Rp 53,129.75
11 1 m2 Pembuatan jalan sementara
Bahan An. SNI ( Revisi ) 6.12.1
0.150 m3 Batu belah 15/20 @ Rp. 121,000.00 = Rp 18,150.00
0.090 m3 Batu pecah 5/7 @ Rp. 210,000.00 = Rp 18,900.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,750.00
Sub total : = Rp 38,800.00
Upah An. SNI ( Revisi ) 6.12.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 80,437.50
Total Upah dan Bahan = Rp 119,237.50

12 1 m3 Bongkaran beton bertulang


Upah An. SNI ( Revisi ) 6.13.1
6.667 Oh Pekerja @ Rp. 75,000.00 = Rp 500,025.00
0.333 Oh Mandor @ Rp. 108,750.00 = Rp 36,213.75
Sub total : = Rp 536,238.75
Total Upah = Rp 536,238.75

13 1 m3 Bongkaran dinding tembok bata merah

Upah An. SNI ( Revisi ) 6.14.1+ membuat


6.667 Oh Pekerja @ Rp. 75,000.00 = Rp 500,025.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 503,613.75
Total Upah = Rp 503,613.75

14 1 m' Pagar sementara dari seng gelombang tinggi 2 m


Bahan An. SNI ( Revisi ) 6.2.1
1.250 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. 54,000.00 = Rp 67,500.00
2.500 kg Semen Portland @ Rp. 1,525.00 = Rp 3,812.50
1.200 Lbr Seng gelombang 3" - 5" @ Rp. 81,400.00 = Rp 97,680.00
0.005 m3 Pasir beton @ Rp. 198,000.00 = Rp 990.00
0.009 m3 Koral beton @ Rp. 181,000.00 = Rp 1,629.00
0.072 m3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 316,800.00
0.060 kg Paku biasa 2" - 5 " @ Rp. 14,000.00 = Rp 840.00
0.450 kg Meni besi @ Rp. 24,500.00 = Rp 11,025.00
Sub total : = Rp 500,276.50
Upah An. SNI ( Revisi ) 6.2.2
0.200 Oh Tukang Kayu @ Rp. 108,000.00 = Rp 21,600.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 4
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.020 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 2,160.00
0.020 Oh Mandor @ Rp. 108,750.00 = Rp 2,175.00
Sub total : = Rp 55,935.00
Total Upah dan Bahan = Rp 556,211.50

15. 1 m' Pasang pagar kawat jaring galvanis(Harmonikaq), tinggi 1 meter.


Bahan An. SNI ( Revisi ) 6.15.1
0.434 Lbr Pagar kawat jaring @ Rp. 20,000.00 = Rp 8,680.00
Sub total : = Rp 8,680.00
Upah An. SNI ( Revisi ) 6.15.2
0.042 Oh Pekerja @ Rp. 75,000.00 = Rp 3,150.00
0.004 Oh Kepala Tukang @ Rp. 108,000.00 = Rp 432.00
0.042 Oh Tukang @ Rp. 108,000.00 = Rp 4,536.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 8,335.50
Total Upah dan Bahan = Rp 17,015.50

16. 1 m' Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm tinggi 1 meter


Bahan An. SNI ( Revisi ) 6.16.1
0.986 Lbr Panel beton pracetak @ Rp. 197,025.00 = Rp 194,266.65
0.525 Btg Kolom beton pracetak @ Rp. 127,650.00 = Rp 67,016.25
0.074 m3 Pasir beton @ Rp. 198,000.00 = Rp 14,652.00
0.146 m3 Koral 2/3 @ Rp. 181,000.00 = Rp 26,426.00
45.000 Kg Semen abu-abu @ Rp. 1,525.00 = Rp 68,625.00
Sub total : = Rp 370,985.90
Upah An. SNI ( Revisi ) 6.16.2
0.125 Oh Tukang batu @ Rp. 107,250.00 = Rp 13,406.25
0.375 Oh Pekerja @ Rp. 75,000.00 = Rp 28,125.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.019 Oh Mandor @ Rp. 108,750.00 = Rp 2,066.25
Sub total : = Rp 44,893.50
Total Upah dan Bahan = Rp 415,879.40

jika menggunakan konstruksi cerucuk<majka untuk 1 m panjang cerucuk/ bambu diameter 8-10 cm

harga Rp 8993

17 3 m panjang cerucuk kayu/ bambu diameter 8-10 cm


Bahan An. SNI ( Revisi ) 6.16.1
3.000 m Kayu/ bambu dia 8-10 cm @ Rp. 3,333.33 = Rp 10,000.00
0.020 m2 laburan meni dan ter @ Rp. 5,400.00 = Rp 108.00
0.010 sewa/hari alat pancang manual @ Rp. 120,000.00 = Rp 1,200.00
tripod tinggi 5 m dan berat penumbuk 5 kg
Sub total : = Rp 11,308.00
Upah An. SNI ( Revisi ) 6.16.2
0.010 Oh Tukang batu @ Rp. 107,250.00 = Rp 1,072.50
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 3,971.25
Total Upah dan Bahan = Rp 15,279.25

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 5
PEKERJAAN TANAH

1. 1 m3 Galian Untuk Tanah Biasa sedalam 1 m


Upah An. SNI ( Revisi ) 6.1.1
0.750 Oh Pekerja @ Rp. 75,000.00 = Rp. 56,250.00
0.025 Oh Mandor @ Rp. 108,750.00 = Rp. 2,718.75
= Rp. 58,968.75
Total Upah = Rp 58,968.75

2. 1 m3 Galian Untuk Tanah Biasa sedalam 2 m


Upah An. SNI ( Revisi ) 6.2.1
0.900 Oh Pekerja @ Rp. 75,000.00 = Rp. 67,500.00
0.045 Oh Mandor @ Rp. 108,750.00 = Rp. 4,893.75
= Rp. 72,393.75
Total Upah = Rp 72,393.75

3. 1 m3 Galian Untuk Tanah Biasa sedalam 3 m


Upah An. SNI ( Revisi ) 6.3.1
1.050 Oh Pekerja @ Rp. 75,000.00 = Rp. 78,750.00
0.067 Oh Mandor @ Rp. 108,750.00 = Rp. 7,286.25
= Rp. 86,036.25
Total Upah = Rp 86,036.25

4. 1 m3 Galian Untuk Tanah keras sedalam 1 m


Upah An. SNI ( Revisi ) 6.4.1
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp. 75,000.00
0.032 Oh Mandor @ Rp. 108,750.00 = Rp. 3,480.00
= Rp. 78,480.00
Total Upah = Rp 78,480.00

5. 1 m3 Galian Untuk Tanah cadas sedalam 1 m


Upah An. SNI ( Revisi ) 6.5.1
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp. 112,500.00
0.060 Oh Mandor @ Rp. 108,750.00 = Rp. 6,525.00
= Rp. 119,025.00
Total Upah = Rp 119,025.00

6. 1 m3 Galian Untuk Tanah lumpur sedalam 1 m


Upah An. SNI ( Revisi ) 6.6.1
1.200 Oh Pekerja @ Rp. 75,000.00 = Rp. 90,000.00
0.045 Oh Mandor @ Rp. 108,750.00 = Rp. 4,893.75
= Rp. 94,893.75
Total Upah = Rp 94,893.75

7. 1 m2 Pekerjaan stripping tebig setinggi 1 m


Upah An. SNI ( Revisi ) 6.7.1
0.050 Oh Pekerja @ Rp. 75,000.00 = Rp. 3,750.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp. 543.75
Sub total : = Rp. 4,293.75
Total Upah = Rp 4,293.75

8. 1 m3 Pembuangan tanah per M3 sejauh 30 m


Upah An. SNI ( Revisi ) 6.8.1
0.330 Oh Pekerja @ Rp. 75,000.00 = Rp. 24,750.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 6

0.010 Oh Mandor @ Rp. 108,750.00 = Rp. 1,087.50


Sub total : = Rp. 25,837.50
Total Upah = Rp 25,837.50

9. 1 m3 Urugan tanah kembali


Upah An. SNI ( Revisi ) 6.9.1
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp. 14,400.00
0.019 Oh Mandor @ Rp. 108,750.00 = Rp. 2,066.25
Sub total : = Rp. 16,466.25
Total Upah = Rp 16,466.25

10. 1 m3 Pemadatan tanah konvensional.


Upah An. SNI ( Revisi ) 6.10.1
0.500 Oh Pekerja @ Rp. 75,000.00 = Rp. 37,500.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp. 5,437.50
Sub total : = Rp. 42,937.50
Total Upah = Rp 42,937.50

11. 1 m3 Urugan pasir dengan pasir urug.


Bahan An. SNI ( Revisi ) 6.11.1
1.200 m3 Pasir urug @ Rp. 100,000.00 = Rp. 120,000.00
Sub total : = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.11.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp. 22,500.00
0.0100 Oh Mandor @ Rp. 108,750.00 = Rp. 1,087.50
Sub total : = Rp. 23,587.50
Total Upah + bahan = Rp 143,587.50

12. 1 m3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 Tnh liat.


Bahan An. SNI ( Revisi ) 6.12.1
0.400 m3 Pasir urug @ Rp. 100,000.00 = Rp. 40,000.00
0.135 m3 Kapur padam @ Rp. 88,000.00 = Rp. 11,880.00
0.948 m3 tanah urug / tanah liat @ Rp. 62,700.00 = Rp. 59,439.60
Sub total : = Rp. 111,319.60
Upah An. SNI ( Revisi ) 6.12.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp. 60,000.00
0.400 Oh Tukang batu @ Rp. 107,250.00 = Rp. 42,900.00
0.040 Oh Kepala tukang @ Rp. 108,000.00 = Rp. 4,320.00
0.0800 Oh Mandor @ Rp. 108,750.00 = Rp. 8,700.00
Sub total : = Rp. 115,920.00
Total Upah + bahan = Rp 227,239.60

13. 1 m3 Lapisan pudel campuran 1 Kp : 5 Tnh liat


Bahan An. SNI ( Revisi ) 6.13.1
0.248 m3 Kapur padam @ Rp. 88,000.00 = Rp. 21,824.00
1.240 m3 tanah urug / tanah liat @ Rp. 62,700.00 = Rp. 77,748.00
Sub total : = Rp. 99,572.00
Upah An. SNI ( Revisi ) 6.13.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp. 60,000.00
0.400 Oh Tukang batu @ Rp. 107,250.00 = Rp. 42,900.00
0.040 Oh Kepala tukang @ Rp. 108,000.00 = Rp. 4,320.00
0.0800 Oh Mandor @ Rp. 108,750.00 = Rp. 8,700.00
Sub total : = Rp. 115,920.00
Total Upah + bahan = Rp 215,492.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 7
14. 1 m3 Pemasangan 1M2 lapisan ijuk tebal 10 Cm.
Bahan An. SNI ( Revisi ) 6.14.1
6.000 Kg Ijuk @ Rp. 12,900.00 = Rp. 77,400.00
Sub total : = Rp. 77,400.00

Upah An. SNI ( Revisi ) 6.14.2


0.150 Oh Pekerja @ Rp. 75,000.00 = Rp. 11,250.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp. 1,631.25
Sub total : = Rp. 12,881.25
Total Upah + bahan = Rp 90,281.25

15. 1 m2 Pembuatan jalan sementara, tebal 25 cm


Bahan An. SNI ( Revisi ) 6.17.1
0.250 m3 Batu belah @ Rp. 121,000.00 = Rp. 30,250.00
0.030 m3 Kerikil @ Rp. 200,000.00 = Rp. 6,000.00
0.050 m3 Pasir pasang @ Rp. 175,000.00 = Rp. 8,750.00
Sub total : = Rp. 45,000.00
Upah An. SNI ( Revisi ) 6.17.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp. 75,000.00
0.100 Oh Mandor @ Rp. 108,750.00 = Rp. 10,875.00
Sub total : = Rp. 85,875.00
Total Upah + bahan = Rp 130,875.00

MENGURUG DENGAN SIRTU


TANPA PEMADATAN DAN CUKUP DIGELAR / DIRATAKAN DENGAN TENAGA MANUSIA.

16 1 m3 Urugan sirtu
Bahan An. SNI ( Revisi ) 6.15.1
1.200 m3 Sirtu @ Rp. 100,000.00 = Rp. 120,000.00
Sub total : = Rp. 120,000.00

Upah An. SNI ( Revisi ) 6.15.2


0.300 Oh Pekerja @ Rp. 75,000.00 = Rp. 22,500.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp. 1,087.50
Sub total : = Rp. 23,587.50
Total Upah + bahan = Rp 143,587.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 8
MENGURUG DENGAN SIRTU UNTUK PARTAI BESAR ( DIATAS 200 m3 )
DENGAN ARMADA TRUK TRONTON + PEMADATAN DENGAN DOSER..

1 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 10 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
1 Biaya transportasi. 1,500.00 = Rp. 1,500.00
Total Biaya / M3 = Rp 145,087.50

2 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 20 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
2 Biaya transportasi. 1,750.00 = Rp. 3,062.50
Total Biaya / M3 = Rp 146,650.00

3 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 30 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
3 Biaya transportasi. 1,500.00 = Rp. 3,750.00
Total Biaya / M3 = Rp 147,337.50

4 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 40 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
3 Biaya transportasi. 1,500.00 = Rp. 4,875.00
Total Biaya / M3 = Rp 148,462.50

5 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 50 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
4 Biaya transportasi. 1,750.00 = Rp. 7,000.00
Total Biaya / M3 = Rp 150,587.50

6 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 60 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
5 Biaya transportasi. 1,750.00 = Rp. 8,312.50
Total Biaya / M3 = Rp 151,900.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 9
MENGURUG DENGAN SIRTU UNTUK PARTAI KECIL ( KURANG DARI 200 m3 )
DENGAN ANGKUTAN TRUK DISEL 3/4. TANPA PEMADATAN (Cukup digelar dan diratakan)

1 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 10 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
1 Biaya transportasi. 1,500.00 = Rp. 2,013.00
Total Biaya / M3 = Rp 145,600.50

2 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 20 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
3 Biaya transportasi. 1,750.00 = Rp. 4,637.50
Total Biaya / M3 = Rp 148,225.00

3 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 30 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
4 Biaya transportasi. 1,500.00 = Rp. 5,325.00
Total Biaya / M3 = Rp 148,912.50

4 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 40 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
4 Biaya transportasi. 1,500.00 = Rp. 6,675.00
Total Biaya / M3 = Rp 150,262.50

5 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 50 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
5 Biaya transportasi. 1,750.00 = Rp. 9,362.50
Total Biaya / M3 = Rp 152,950.00

6 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)


(Jarak dengan penggambilan sirtu +/- 60 Km)
Bahan An. SNI ( Revisi ) 6.15.1 = Rp. 120,000.00
Upah An. SNI ( Revisi ) 6.15.2 = Rp. 23,587.50
Sub total : = Rp. 143,587.50
6 Biaya transportasi. 1,750.00 = Rp. 10,937.50
Total Biaya / M3 = Rp 154,525.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 10
PEKERJAAN PONDASI
1. 1 m3 Pasang pondasi batu kosong (Aanstamping)
Bahan An. SNI ( Revisi ) 6.14.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
0.432 m3 Pasir urug @ Rp. 100,000.00 = Rp 43,200.00
Sub total : = Rp 188,400.00
Upah An. SNI ( Revisi ) 6.14.2
0.780 Oh Pekerja @ Rp. 75,000.00 = Rp 58,500.00
0.390 Oh Tukang batu @ Rp. 107,250.00 = Rp 41,827.50
0.039 Oh Kepala tukang @ Rp. 108,000.00 = Rp 4,212.00
0.039 Oh Mandor @ Rp. 108,750.00 = Rp 4,241.25
Sub total : = Rp 108,780.75
Total upah+bahan : = Rp 297,180.75

2. 1 m3 Pasang pondasi batu kali 1 Pc : 1 Ps


Bahan An. SNI ( Revisi ) 6.1.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
267.000 Kg Semen porland @ Rp. 1,525.00 = Rp 407,175.00
0.314 m3 Pasir pasang @ Rp. 175,000.00 = Rp 54,950.00
Sub total : = Rp 607,325.00
Upah An. SNI ( Revisi ) 6.1.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 798,811.25

3. 1 m3 Pasang pondasi batu kali 1 Pc : 2 Ps


Bahan An. SNI ( Revisi ) 6.2.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
234.500 Kg Semen porland @ Rp. 1,525.00 = Rp 357,612.50
0.427 m3 Pasir pasang @ Rp. 175,000.00 = Rp 74,725.00
Sub total : = Rp 577,537.50
Upah An. SNI ( Revisi ) 6.2.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 769,023.75

4. 1 m3 Pasang pondasi batu kali 1 Pc : 2.5 Ps


Bahan An. SNI ( Revisi ) 6.3.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
215.000 Kg Semen porland @ Rp. 1,525.00 = Rp 327,875.00
0.400 m3 Pasir pasang @ Rp. 175,000.00 = Rp 69,912.50
Sub total : = Rp 542,987.50
Upah An. SNI ( Revisi ) 6.3.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 734,473.75
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 11
5. 1 m3 Pasang pondasi batu kali 1 Pc : 3 Ps
Bahan An. SNI ( Revisi ) 6.4.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
202.000 Kg Semen porland @ Rp. 1,525.00 = Rp 308,050.00
0.485 m3 Pasir pasang @ Rp. 175,000.00 = Rp 84,875.00
Sub total : = Rp 538,125.00
Upah An. SNI ( Revisi ) 6.4.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 729,611.25

6. 1 m3 Pasang pondasi batu kali 1 Pc : 4 Ps


Bahan An. SNI ( Revisi ) 6.5.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
163.000 Kg Semen porland @ Rp. 1,525.00 = Rp 248,575.00
0.520 m3 Pasir pasang @ Rp. 175,000.00 = Rp 91,000.00
Sub total : = Rp 484,775.00
Upah An. SNI ( Revisi ) 6.5.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 676,261.25

7. 1 m3 Pasang pondasi batu kali 1 Pc : 5 Ps


Bahan An. SNI ( Revisi ) 6.6.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
136.000 Kg Semen porland @ Rp. 1,525.00 = Rp 207,400.00
0.544 m3 Pasir pasang @ Rp. 175,000.00 = Rp 95,200.00
Sub total : = Rp 447,800.00
Upah An. SNI ( Revisi ) 6.6.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 639,286.25

8. 1 m3 Pasang pondasi batu kali 1 Pc : 6 Ps


Bahan An. SNI ( Revisi ) 6.7.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
117.000 Kg Semen porland @ Rp. 1,525.00 = Rp 178,425.00
0.561 m3 Pasir pasang @ Rp. 175,000.00 = Rp 98,175.00
Sub total : = Rp 421,800.00
Upah An. SNI ( Revisi ) 6.7.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 613,286.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 12
9. 1 m3 Pasang pondasi batu kali 1 Pc : 8 Ps
Bahan An. SNI ( Revisi ) 6.8.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
91.000 Kg Semen porland @ Rp. 1,525.00 = Rp 138,775.00
0.561 m3 Pasir pasang @ Rp. 175,000.00 = Rp 98,175.00
Sub total : = Rp 382,150.00
Upah An. SNI ( Revisi ) 6.8.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.600 Oh Tukang batu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 191,486.25
Total upah+bahan : = Rp 573,636.25

10. 1 m3 Pasang pondasi batu kali 1 Kp : 1 Sm : 1 Ps


Bahan An. SNI ( Revisi ) 6.9.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
0.170 m3 Kapur pasang @ Rp. 88,000.00 = Rp 14,960.00
0.170 m3 Semen merah @ Rp. 175,000.00 = Rp 29,750.00
0.340 m3 Pasir pasang @ Rp. 175,000.00 = Rp 59,500.00
Sub total : = Rp 249,410.00
Upah An. SNI ( Revisi ) 6.9.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 80,437.50
0.075 Oh Kepala tukang @ Rp. 108,000.00 = Rp 8,100.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 209,193.75
Total upah+bahan : = Rp 458,603.75

11. 1 m3 Pasang pondasi batu kali 1 Kp : 1 Sm : 2 Ps


Bahan An. SNI ( Revisi ) 6.10.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
0.170 m3 Kapur pasang @ Rp. 88,000.00 = Rp 14,960.00
0.170 m3 Semen merah @ Rp. 175,000.00 = Rp 29,750.00
0.340 m3 Pasir pasang @ Rp. 175,000.00 = Rp 59,500.00
Sub total : = Rp 249,410.00
Upah An. SNI ( Revisi ) 6.10.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 52,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 81,562.50
0.075 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,625.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 144,843.75
Total upah+bahan : = Rp 394,253.75

12. 1 m3 Pasang pondasi batu kali 1 Pc : 1/4 Kp : 4 Ps


Bahan An. SNI ( Revisi ) 6.11.1
1.100 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 133,100.00
156.000 Kg Semen portland @ Rp. 1,525.00 = Rp 237,900.00
0.032 m3 Kapur pasang @ Rp. 88,000.00 = Rp 2,816.00
0.584 m3 Pasir pasang @ Rp. 175,000.00 = Rp 102,200.00
Sub total : = Rp 476,016.00
Upah An. SNI ( Revisi ) 6.11.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 52,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 81,562.50
0.075 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,625.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 13
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 144,843.75
Total upah+bahan : = Rp 620,859.75

13. 1 m3 Pasang pondasi batu kali 1 Pc : 3 Kp : 10 Ps


Bahan An. SNI ( Revisi ) 6.12.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
61.000 Kg Semen portland @ Rp. 1,525.00 = Rp 93,025.00
0.147 m3 Kapur pasang @ Rp. 88,000.00 = Rp 12,936.00
0.492 m3 Pasir pasang @ Rp. 175,000.00 = Rp 86,100.00
Sub total : = Rp 337,261.00
Upah An. SNI ( Revisi ) 6.12.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 52,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 81,562.50
0.075 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,625.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 144,843.75
Total upah+bahan : = Rp 482,104.75

14. 1 m3 Pasang pondasi batu kali 1/4 Pc : 1 Kp : 4 Ps


Bahan An. SNI ( Revisi ) 6.13.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 145,200.00
41.000 Kg Semen portland @ Rp. 1,525.00 = Rp 62,525.00
0.131 m3 Kapur pasang @ Rp. 88,000.00 = Rp 11,528.00
0.523 m3 Pasir pasang @ Rp. 175,000.00 = Rp 91,525.00
Sub total : = Rp 310,778.00
Upah An. SNI ( Revisi ) 6.13.2
1.500 Oh Pekerja @ Rp. 75,000.00 = Rp 112,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 80,437.50
0.075 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,625.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 203,718.75
Total upah+bahan : = Rp 514,496.75

15. 1 m3 Pasang pondasi siklop 60 % BETON Camp. 1 PCX:2Psr:3Krl. dan 40 % batu kali
Bahan An. SNI ( Revisi ) 6.15.1
126.000 Kg Besi beton @ Rp. 10,500.00 = Rp 1,323,000.00
194.000 Kg Semen portland @ Rp. 1,525.00 = Rp 295,850.00
0.320 m3 Pasir beton @ Rp. 198,000.00 = Rp 63,360.00
0.490 m3 Koral beton @ Rp. 181,000.00 = Rp 88,690.00
0.800 Kg Kawat beton @ Rp. 14,700.00 = Rp 11,760.00
Sub total : = Rp 1,782,660.00
Upah An. SNI ( Revisi ) 6.15.2
3.000 Oh Pekerja @ Rp. 75,000.00 = Rp 225,000.00
0.850 Oh Tukang batu @ Rp. 107,250.00 = Rp 91,162.50
0.085 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,975.00
0.150 Oh Mandor @ Rp. 108,750.00 = Rp 16,312.50
Sub total : = Rp 335,450.00
Total upah+bahan : = Rp 2,118,110.00

16. 1 m3 Pasang pondasi sumuran Ø 100 cm


Bahan An. SNI ( Revisi ) 6.16.1
0.450 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 54,450.00
194.000 Kg Semen portland @ Rp. 1,525.00 = Rp 295,850.00
0.312 m3 Pasir beton @ Rp. 198,000.00 = Rp 61,776.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 14
0.468 m3 Koral beton @ Rp. 181,000.00 = Rp 84,708.00
Sub total : = Rp 496,784.00
Upah An. SNI ( Revisi ) 6.16.2
2.400 Oh Pekerja @ Rp. 75,000.00 = Rp 180,000.00
0.800 Oh Tukang batu @ Rp. 107,250.00 = Rp 85,800.00
0.080 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,800.00
0.119 Oh Mandor @ Rp. 108,750.00 = Rp 12,941.25
Sub total : = Rp 281,541.25
Total upah+bahan : = Rp 778,325.25

17. 1 m' Pembuatan tiang pancang ( 40 x 40 ) cm, beton bertulang


Bahan An. SNI ( Revisi ) 6.17.1
0.019 m3 Pasir urug darat @ Rp. 100,000.00 = Rp 1,900.00
0.094 m3 Pasir beton @ Rp. 198,000.00 = Rp 18,612.00
0.150 m3 Koral beton @ Rp. 181,000.00 = Rp 27,150.00
60.500 Kg Semen portland @ Rp. 1,525.00 = Rp 92,262.50
45.000 Kg Besi beton @ Rp. 10,500.00 = Rp 472,500.00
0.900 Kg Kawat beton @ Rp. 14,700.00 = Rp 13,230.00
0.032 m3 Kayu meranti 5/7 @ Rp. 5,000,000.00 = Rp 160,000.00
0.120 Kg Paku @ Rp. 14,000.00 = Rp 1,680.00
0.090 Lt Minyak bekisting @ Rp. 10,500.00 = Rp 945.00
0.240 Kg Plamuur tembok @ Rp. 15,500.00 = Rp 3,720.00
Sub total : = Rp 791,999.50
Upah An. SNI ( Revisi ) 6.17.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
0.670 Oh Tukang batu @ Rp. 107,250.00 = Rp 71,857.50
0.067 Oh Kepala tukang @ Rp. 35,000.00 = Rp 2,345.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 154,640.00
Total upah+bahan : = Rp 946,639.50
Jadi harga 1 Meter Tiang pancang ukuran 40 x 40 Cm2 = Rp 946,639.50

18. 1 m' Pembuatan tiang pancang ( 35 x 35 ) cm, beton bertulang


Bahan An. SNI ( Revisi ) 6.18.1
0.016 m3 Pasir urug darat @ Rp. 100,000.00 = Rp 1,600.00
0.080 m3 Pasir beton @ Rp. 100,000.00 = Rp 8,000.00
0.125 m3 Koral beton @ Rp. 181,000.00 = Rp 22,625.00
49.000 Kg Semen portland @ Rp. 1,525.00 = Rp 74,725.00
34.500 Kg Besi beton @ Rp. 10,500.00 = Rp 362,250.00
0.700 Kg Kawat beton @ Rp. 14,700.00 = Rp 10,290.00
0.027 m3 Kayu meranti 5/7 @ Rp. 5,000,000.00 = Rp 135,000.00
0.120 Kg Paku @ Rp. 14,000.00 = Rp 1,680.00
0.090 Lt Minyak bekisting @ Rp. 10,500.00 = Rp 945.00
0.200 Kg Plamuur tembok @ Rp. 15,500.00 = Rp 3,100.00
Sub total : = Rp 620,215.00
Upah An. SNI ( Revisi ) 6.18.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp 60,000.00
0.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 53,625.00
0.050 Oh Kepala tukang @ Rp. 35,000.00 = Rp 1,750.00
0.040 Oh Mandor @ Rp. 108,750.00 = Rp 4,350.00
Sub total : = Rp 119,725.00
Total upah+bahan : = Rp 739,940.00
Jadi harga 1 Meter Tiang pancang ukuran 35 x 35 Cm2 = Rp 739,940.00
PEKERJAAN BETON TUMBUK & BETON BERTULANG

BETON TUMBUK.
1. 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
Bahan An. SNI ( Revisi ) 6.1.1
218.000 Kg Semen portland @ Rp. 1,525.00 = Rp 332,450.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.870 m3 Koral beton @ Rp. 181,000.00 = Rp 157,470.00
Sub total : = Rp 592,880.00
Upah An. SNI ( Revisi ) 6.1.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 754,842.50

2. 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr


Bahan An. SNI ( Revisi ) 6.2.1
197.000 Kg Semen portland @ Rp. 1,525.00 = Rp 300,425.00
0.470 m3 Pasir beton @ Rp. 198,000.00 = Rp 93,060.00
0.940 m3 Koral beton @ Rp. 181,000.00 = Rp 170,140.00
Sub total : = Rp 563,625.00
Upah An. SNI ( Revisi ) 6.2.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 725,587.50

3. 1 m3 Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr


Bahan An. SNI ( Revisi ) 6.3.1
173.000 Kg Semen portland @ Rp. 1,525.00 = Rp 263,825.00
0.570 m3 Pasir beton @ Rp. 198,000.00 = Rp 112,860.00
0.870 m3 Koral beton @ Rp. 181,000.00 = Rp 157,470.00
Sub total : = Rp 534,155.00
Upah An. SNI ( Revisi ) 6.3.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 696,117.50

4. 1 m2 Membuat lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr tebal 5 Cm


Bahan An. SNI ( Revisi ) 6.4.1
10.900 Kg Semen portland @ Rp. 1,525.00 = Rp 16,622.50
0.026 m3 Pasir beton @ Rp. 198,000.00 = Rp 5,148.00
0.044 m3 Koral beton @ Rp. 181,000.00 = Rp 7,873.50
Sub total : = Rp 29,644.00
Upah An. SNI ( Revisi ) 6.4.2
0.08250 Oh Pekerja @ Rp. 75,000.00 = Rp 6,187.50
0.01250 Oh Tukang batu @ Rp. 107,250.00 = Rp 1,340.63
0.00125 Oh Kepala tukang @ Rp. 108,000.00 = Rp 135.00

0.00400 Oh Mandor @ Rp. 108,750.00 = Rp 435.00


Sub total : = Rp 8,098.13
Total upah+bahan : = Rp 37,742.13
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 32
BETON BERTULANG.
5. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
Bahan An. SNI ( Revisi ) 6.5.1
232.000 Kg Semen portland @ Rp. 1,525.00 = Rp 353,800.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.870 m3 Koral beton @ Rp. 181,000.00 = Rp 157,470.00
Sub total : = Rp 614,230.00
Upah An. SNI ( Revisi ) 6.5.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 776,192.50

6. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr


Bahan An. SNI ( Revisi ) 6.6.1
280.000 Kg Semen portland @ Rp. 1,525.00 = Rp 427,000.00
0.450 m3 Pasir beton @ Rp. 198,000.00 = Rp 89,100.00
0.900 m3 Koral beton @ Rp. 181,000.00 = Rp 162,900.00
Sub total : = Rp 679,000.00
Upah An. SNI ( Revisi ) 6.6.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 840,962.50

7. 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 2.5 Kr


Bahan An. SNI ( Revisi ) 6.7.1
352.000 Kg Semen portland @ Rp. 1,525.00 = Rp 536,800.00
0.560 m3 Pasir beton @ Rp. 198,000.00 = Rp 110,880.00
0.700 m3 Koral beton @ Rp. 181,000.00 = Rp 126,700.00
Sub total : = Rp 774,380.00
Upah An. SNI ( Revisi ) 6.7.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 1,002,925.00

8. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1.5 Ps : 3 Kr


Bahan An. SNI ( Revisi ) 6.8.1
357.000 Kg Semen portland @ Rp. 1,525.00 = Rp 544,425.00
0.420 m3 Pasir beton @ Rp. 198,000.00 = Rp 83,160.00
0.840 m3 Koral beton @ Rp. 181,000.00 = Rp 152,040.00
Sub total : = Rp 779,625.00

Upah An. SNI ( Revisi ) 6.8.2


1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 941,587.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 33
9. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1.5 Ps : 2.5 Kr
Bahan An. SNI ( Revisi ) 6.9.1
386.000 Kg Semen portland @ Rp. 1,525.00 = Rp 588,650.00
0.470 m3 Pasir beton @ Rp. 198,000.00 = Rp 93,060.00
0.700 m3 Koral beton @ Rp. 181,000.00 = Rp 126,700.00
Sub total : = Rp 808,410.00
Upah An. SNI ( Revisi ) 6.9.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 970,372.50

10. 1 m3 Membuat campuran beton bertulang, 1 Pc : 1 Ps : 2 Kr


Bahan An. SNI ( Revisi ) 6.10.1
479.000 Kg Semen portland @ Rp. 1,525.00 = Rp 730,475.00
0.370 m3 Pasir beton @ Rp. 198,000.00 = Rp 73,260.00
0.740 m3 Koral beton @ Rp. 181,000.00 = Rp 133,940.00
Sub total : = Rp 937,675.00
Upah An. SNI ( Revisi ) 6.10.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 1,099,637.50

11. 1 m3 Membuat beton tiang pancang prestressed beton


Bahan An. SNI ( Revisi ) 6.11.1
440.000 Kg Semen portland @ Rp. 1,525.00 = Rp 671,000.00
0.500 m3 Pasir beton @ Rp. 198,000.00 = Rp 99,000.00
0.800 m3 Koral beton @ Rp. 181,000.00 = Rp 144,800.00
2.460 Gln Repidrant @ Rp. 41,250.00 = Rp 101,475.00
Sub total : = Rp 1,016,275.00
Upah An. SNI ( Revisi ) 6.11.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 1,178,237.50

12. 1 m3 Membuat beton dengan puzzdith - 100 XR


Bahan An. SNI ( Revisi ) 6.12.1
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
1.000 Ltr Puzzdith - 100 XR @ Rp. 42,500.00 = Rp 42,500.00
Sub total : = Rp 808,430.00
Upah An. SNI ( Revisi ) 6.12.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.080 Oh Mandor @ Rp. 108,750.00 = Rp 8,700.00
Sub total : = Rp 161,962.50
Total upah+bahan : = Rp 970,392.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 34
13. 1 m3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr
Bahan An. SNI ( Revisi ) 6.17.1
615.000 Kg Semen portland @ Rp. 1,525.00 = Rp 937,875.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.520 m3 Koral beton @ Rp. 181,000.00 = Rp 94,120.00
Sub total : = Rp 1,134,955.00
Upah An. SNI ( Revisi ) 6.17.2
2.000 Oh Pekerja @ Rp. 75,000.00 = Rp 150,000.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
1.000 Oh Mandor @ Rp. 108,750.00 = Rp 108,750.00
Sub total : = Rp 300,067.50
Total upah+bahan : = Rp 1,435,022.50

14. 1 m3 Membuat beton kedap air dengan storox - 100


Bahan An. SNI ( Revisi ) 6.18.1
400.000 Kg Semen portland @ Rp. 1,525.00 = Rp 610,000.00
0.480 m3 Pasir beton @ Rp. 198,000.00 = Rp 95,040.00
0.800 m3 Koral beton 2/3 @ Rp. 181,000.00 = Rp 144,800.00
1.200 Kg Storox - 100 @ Rp. 65,000.00 = Rp 78,000.00
Sub total : = Rp 927,840.00
Upah An. SNI ( Revisi ) 6.18.2
2.000 Oh Pekerja @ Rp. 75,000.00 = Rp 150,000.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
1.000 Oh Mandor @ Rp. 108,750.00 = Rp 108,750.00
Sub total : = Rp 300,067.50
Total upah+bahan : = Rp 1,227,907.50
BETON SESUAI KARAKTERISTIK ( f 'c ). DENGAN UKURAN BERAT.
1 Membuat 1 M3 beton mutu f'c=7,4 Mpa (K100), slump 2 cm / W/c = 0,87.

Bahan An. SNI ( Revisi ) 6.18.1


247.000 Kg PC @ Rp. 1,525.00 = Rp 376,675.00
869.000 Kg Pasir Cor @ Rp. 198.00 = Rp 172,062.00
999.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 82,190.45
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 631,464.95
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 796,758.95

2 Membuat 1 M3 beton mutu f'c=9,8 Mpa (K125), slump 2 cm / W/c = 0,78.

Bahan An. SNI ( Revisi ) 6.18.1


276.000 Kg PC @ Rp. 1,525.00 = Rp 420,900.00
828.000 Kg Pasir Cor @ Rp. 198.00 = Rp 163,944.00
1012.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 83,260.00
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 668,641.50
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 833,935.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 34
3 Membuat 1 M3 beton mutu f'c=12,2 Mpa (K150), slump 2 cm / W/c = 0,72.

Bahan An. SNI ( Revisi ) 6.18.1


299.000 Kg PC @ Rp. 1,525.00 = Rp 455,975.00
799.000 Kg Pasir Cor @ Rp. 198.00 = Rp 158,202.00
1017.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 83,671.36
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 698,385.86
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 863,679.86
4 Membuat 1 M3 LANTAI KERJA beton mutu f'c=7,4 Mpa (K100), slump 3-6 cm / W/c = 0,87.

Bahan An. SNI ( Revisi ) 6.18.1


230.000 Kg PC @ Rp. 1,525.00 = Rp 350,750.00
893.000 Kg Pasir Cor @ Rp. 198.00 = Rp 176,814.00
1027.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 84,494.09
200.000 Ltr Air. @ Rp. 2.50 = Rp 500.00
Sub total : = Rp 612,558.09
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 777,852.09
5 Membuat 1 M3 beton mutu f'c=14,5 Mpa (K175), slump 2 cm / W/c = 0,66.

Bahan An. SNI ( Revisi ) 6.18.1


326.000 Kg PC @ Rp. 1,525.00 = Rp 497,150.00
760.000 Kg Pasir Cor @ Rp. 198.00 = Rp 150,480.00
1029.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 84,658.64
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 732,826.14
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 898,120.14
6 Membuat 1 M3 beton mutu f'c=16,9 Mpa (K200), slump 2 cm / W/c = 0,61.

Bahan An. SNI ( Revisi ) 6.18.1


352.000 Kg PC @ Rp. 1,525.00 = Rp 536,800.00
731.000 Kg Pasir Cor @ Rp. 198.00 = Rp 144,738.00
1031.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 84,823.18
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 766,898.68
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 932,192.68
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 35
7 Membuat 1 M3 beton mutu f'c=19,3 Mpa (K225), slump 2 cm / W/c = 0,58.

Bahan An. SNI ( Revisi ) 6.18.1


371.000 Kg PC @ Rp. 1,525.00 = Rp 565,775.00
698.000 Kg Pasir Cor @ Rp. 198.00 = Rp 138,204.00
1047.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 86,139.55
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 790,656.05
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 955,950.05
8 Membuat 1 M3 beton mutu f'c=21,7 Mpa (K250), slump 2 cm / W/c = 0,56.

Bahan An. SNI ( Revisi ) 6.18.1


384.000 Kg PC @ Rp. 1,525.00 = Rp 585,600.00
692.000 Kg Pasir Cor @ Rp. 198.00 = Rp 137,016.00
1039.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 85,481.36
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 808,634.86
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 973,928.86
9 Membuat 1 M3 beton mutu f'c=24,0 Mpa (K275), slump 2 cm / W/c = 0,53.

Bahan An. SNI ( Revisi ) 6.18.1


406.000 Kg PC @ Rp. 1,525.00 = Rp 619,150.00
684.000 Kg Pasir Cor @ Rp. 198.00 = Rp 135,432.00
1026.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 84,411.82
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 839,531.32
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 1,004,825.32
10 Membuat 1 M3 beton mutu f'c=26,4 Mpa (K300), slump 2 cm / W/c = 0,52.

Bahan An. SNI ( Revisi ) 6.18.1


413.000 Kg PC @ Rp. 1,525.00 = Rp 629,825.00
681.000 m3 Pasir Cor @ Rp. 198.00 = Rp 134,838.00
1021.000 m3 Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 84,000.45
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 849,200.95
Upah An. SNI ( Revisi ) 6.18.2
1.650 Oh Pekerja @ Rp. 75,000.00 = Rp 123,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
0.028 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,024.00
0.083 Oh Mandor @ Rp. 108,750.00 = Rp 9,026.25
Sub total : = Rp 165,294.00
Total upah+bahan : = Rp 1,014,494.95
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 36
11 Membuat 1 M3 beton mutu f'c=28,8 Mpa (K325), slump 2 cm / W/c = 0,49.

Bahan An. SNI ( Revisi ) 6.18.1


439.000 Kg PC @ Rp. 1,525.00 = Rp 669,475.00
670.000 Kg Pasir Cor @ Rp. 198.00 = Rp 132,660.00
1006.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 82,766.36
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 885,438.86
Upah An. SNI ( Revisi ) 6.18.2
2.100 Oh Pekerja @ Rp. 75,000.00 = Rp 157,500.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.105 Oh Mandor @ Rp. 108,750.00 = Rp 11,418.75
Sub total : = Rp 210,236.25
Total upah+bahan : = Rp 1,095,675.11
12 Membuat 1 M3 beton mutu f'c=31,2 Mpa (K350), slump 2 cm / W/c = 0,48.

Bahan An. SNI ( Revisi ) 6.18.1


448.000 Kg PC @ Rp. 1,525.00 = Rp 683,200.00
667.000 Kg Pasir Cor @ Rp. 198.00 = Rp 132,066.00
1000.000 Kg Krikil (maksimum 30 mm) @ Rp. 82.27 = Rp 82,272.73
215.000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp 898,076.23
Upah An. SNI ( Revisi ) 6.18.2
2.100 Oh Pekerja @ Rp. 75,000.00 = Rp 157,500.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.105 Oh Mandor @ Rp. 108,750.00 = Rp 11,418.75
Sub total : = Rp 210,236.25
Total upah+bahan : = Rp 1,108,312.48

13 Membuat 1 M3 beton kedap air dengan strorox - 100.

Bahan An. SNI ( Revisi ) 6.18.1


400.000 Kg PC @ Rp. 1,525.00 = Rp 610,000.00
0.480 m3 Pasir Cor @ Rp. 198,000.00 = Rp 95,040.00
0.800 m3 KR (kerikil 2cm / 3cm) @ Rp. 82.27 = Rp 65.82
1.200 Kg Strorox - 100 @ Rp. 65,000.00 = Rp 78,000.00
Sub total : = Rp 783,105.82
Upah An. SNI ( Revisi ) 6.18.2
2.100 Oh Pekerja @ Rp. 75,000.00 = Rp 157,500.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.105 Oh Mandor @ Rp. 108,750.00 = Rp 11,418.75
Sub total : = Rp 210,236.25
Total upah+bahan : = Rp 993,342.07
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 37

PEMBESIAN.
15 1 Kg Pembesian dengan besi polos
Bahan An. SNI ( Revisi ) 6.25.1
1.050 Kg Besi beton ( polos ) @ Rp. 11,825.00 = Rp 12,416.25
0.015 Kg Kawat beton @ Rp. 14,700.00 = Rp 220.50
Sub total : = Rp 12,636.75
Upah An. SNI ( Revisi ) 6.25.2
0.007 Oh Pekerja @ Rp. 75,000.00 = Rp 525.00
0.007 Oh Tukang besi @ Rp. 107,250.00 = Rp 750.75
0.0007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 75.60
0.0003 Oh Mandor @ Rp. 108,750.00 = Rp 32.63
Sub total : = Rp 1,383.98
Total upah+bahan : = Rp 14,020.73

15.a1 Kg Pembesian dengan besi ulir


Bahan An. SNI ( Revisi ) 6.25.1
1.050 Kg Besi beton ( ulir ) @ Rp. 11,825.00 = Rp 12,416.25
0.015 Kg Kawat beton @ Rp. 14,700.00 = Rp 220.50
Sub total : = Rp 12,636.75
Upah An. SNI ( Revisi ) 6.25.2
0.007 Oh Pekerja @ Rp. 75,000.00 = Rp 525.00
0.007 Oh Tukang besi @ Rp. 107,250.00 = Rp 750.75
0.0007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 75.60
0.0003 Oh Mandor @ Rp. 108,750.00 = Rp 32.63
Sub total : = Rp 1,383.98
Total upah+bahan : = Rp 14,020.73

16 1 Kg Kabel presstessed polos/strands


Bahan An. SNI ( Revisi ) 6.26.1
1.050 Kg Besi presstessed polos @ Rp. 10,750.00 = Rp 11,287.50
0.010 Kg Kawat beton @ Rp. 14,700.00 = Rp 147.00
Sub total : = Rp 11,434.50
Upah An. SNI ( Revisi ) 6.26.2
0.005 Oh Pekerja @ Rp. 75,000.00 = Rp 375.00
0.005 Oh Tukang besi @ Rp. 107,250.00 = Rp 536.25
0.0005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 54.00
0.0003 Oh Mandor @ Rp. 108,750.00 = Rp 32.63
Sub total : = Rp 997.88
Total upah+bahan : = Rp 12,432.38
17 1 Kg Jaring kawat baja
Bahan An. SNI ( Revisi ) 6.27.1
1.020 Kg Besi jaring kawat baja @ Rp. 8,750.00 = Rp 8,925.00
0.805 Kg Kawat beton @ Rp. 14,700.00 = Rp 11,833.50
Sub total : = Rp 20,758.50
Upah An. SNI ( Revisi ) 6.27.2
0.025 Oh Pekerja @ Rp. 75,000.00 = Rp 1,875.00
0.025 Oh Tukang besi @ Rp. 107,250.00 = Rp 2,681.25
0.0025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 270.00
0.0015 Oh Mandor @ Rp. 108,750.00 = Rp 163.13
Sub total : = Rp 4,989.38
Total upah+bahan : = Rp 25,747.88

BEGESTING.
18 1 m2 Pasang bekisting untuk pondasi
Bahan An. SNI ( Revisi ) 6.28.1
0.040 m3 Kayu terentang/Meranti @ Rp. 3,025,000.00 = Rp 121,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 4,200.00
0.100 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 1,050.00
Sub total : = Rp 126,250.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 38
Upah An. SNI ( Revisi ) 6.28.2
0.520 Oh Pekerja @ Rp. 75,000.00 = Rp 39,000.00
0.260 Oh Tukang kayu @ Rp. 107,250.00 = Rp 27,885.00
0.026 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,808.00
0.026 Oh Mandor @ Rp. 108,750.00 = Rp 2,827.50
Sub total : = Rp 72,520.50
Total upah+bahan : = Rp 198,770.50
19 1 m2 Pasang bekisting untuk sloof
Bahan An. SNI ( Revisi ) 6.29.1
0.045 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 136,125.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 4,200.00
0.100 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 1,050.00
Sub total : = Rp 141,375.00
Upah An. SNI ( Revisi ) 6.29.2
0.520 Oh Pekerja @ Rp. 75,000.00 = Rp 39,000.00
0.260 Oh Tukang kayu @ Rp. 107,250.00 = Rp 27,885.00
0.026 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,808.00
0.026 Oh Mandor @ Rp. 108,750.00 = Rp 2,827.50
Sub total : = Rp 72,520.50
Total upah+bahan : = Rp 213,895.50
20 1 m2 Pasang bekisting untuk kolom
Bahan An. SNI ( Revisi ) 6.30.1
0.040 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 121,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 5,600.00
0.200 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,100.00
0.015 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 63,000.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
2.000 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 108,000.00
Sub total : = Rp 338,200.00
Upah An. SNI ( Revisi ) 6.30.2
0.660 Oh Pekerja @ Rp. 75,000.00 = Rp 49,500.00
0.330 Oh Tukang kayu @ Rp. 107,250.00 = Rp 35,392.50
0.033 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,564.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 92,045.25
Total upah+bahan : = Rp 430,245.25
21 1 m2 Pasang bekisting untuk balok
Bahan An. SNI ( Revisi ) 6.31.1
0.040 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 121,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 5,600.00
0.200 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,100.00
0.018 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 75,600.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
2.000 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 108,000.00
Sub total : = Rp 350,800.00
Upah An. SNI ( Revisi ) 6.31.2
0.660 Oh Pekerja @ Rp. 75,000.00 = Rp 49,500.00
0.330 Oh Tukang kayu @ Rp. 107,250.00 = Rp 35,392.50
0.033 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,564.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 92,045.25
Total upah+bahan : = Rp 442,845.25
22 1 m2 Pasang bekisting untuk lantai
Bahan An. SNI ( Revisi ) 6.32.1
0.040 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 121,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 5,600.00
0.200 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,100.00
0.015 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 63,000.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 39
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
6.000 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 324,000.00
Sub total : = Rp 425,500.00
Upah An. SNI ( Revisi ) 6.32.2
0.660 Oh Pekerja @ Rp. 75,000.00 = Rp 49,500.00
0.330 Oh Tukang kayu @ Rp. 107,250.00 = Rp 35,392.50
0.033 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,564.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 92,045.25
Total upah+bahan : = Rp 517,545.25
23 1 m2 Pasang bekisting untuk dinding ( shear wall )
Bahan An. SNI ( Revisi ) 6.33.1
0.030 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 90,750.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 5,600.00
0.200 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,100.00
0.020 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 84,000.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.000 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 162,000.00
4.000 Bh Formtie/penjaga jarak bkstng @ Rp. 35,000.00 = Rp 140,000.00
Sub total : = Rp 340,500.00
Upah An. SNI ( Revisi ) 6.33.2
0.660 Oh Pekerja @ Rp. 75,000.00 = Rp 49,500.00
0.330 Oh Tukang kayu @ Rp. 107,250.00 = Rp 35,392.50
0.033 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,564.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 92,045.25
Total upah+bahan : = Rp 432,545.25
24 1 m2 Pasang bekisting untuk tangga
Bahan An. SNI ( Revisi ) 6.34.1
0.030 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 90,750.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 5,600.00
0.150 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 1,575.00
0.015 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 63,000.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
2.000 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 108,000.00
Sub total : = Rp 307,425.00
Upah An. SNI ( Revisi ) 6.34.2
0.660 Oh Pekerja @ Rp. 75,000.00 = Rp 49,500.00
0.330 Oh Tukang kayu @ Rp. 107,250.00 = Rp 35,392.50
0.033 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,564.00
0.033 Oh Mandor @ Rp. 108,750.00 = Rp 3,588.75
Sub total : = Rp 92,045.25
Total upah+bahan : = Rp 399,470.25
25 1 m2 Membuat begesting jembatan cor
Bahan An. SNI ( Revisi ) 6.37.1
0.0264 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 79,860.00
0.600 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 8,400.00
0.500 Btg Dolken kayu galam Ø 8-10 / 4 @ Rp. 54,000.00 = Rp 27,000.00
Sub total : = Rp 115,260.00
Upah An. SNI ( Revisi ) 6.37.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.050 Oh Tukang batu @ Rp. 107,250.00 = Rp 5,362.50
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 18,022.50
Total upah+bahan : = Rp 133,282.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 40
PONDASI BETON
30 1 m3 Membuat pondasi beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.38.1
0.200 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 605,000.00
1.500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 21,000.00
0.400 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 4,200.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
2.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 33,075.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
Sub total : = Rp 3,291,642.50
Upah An. SNI ( Revisi ) 6.38.2
5.300 Oh Pekerja @ Rp. 75,000.00 = Rp 397,500.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 139,425.00
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.262 Oh Kepala tukang @ Rp. 108,000.00 = Rp 28,296.00
0.265 Oh Mandor @ Rp. 108,750.00 = Rp 28,818.75
Sub total : = Rp 736,146.00
Total upah+bahan : = Rp 4,027,788.50

Sloof
31 1 m3 Membuat sloof beton bertulang ( 200 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.39.1
0.270 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 816,750.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
Sub total : = Rp 3,523,517.50
Upah An. SNI ( Revisi ) 6.39.2
5.650 Oh Pekerja @ Rp. 75,000.00 = Rp 423,750.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.400 Oh Tukang besi @ Rp. 107,250.00 = Rp 150,150.00
0.323 Oh Kepala tukang @ Rp. 108,000.00 = Rp 34,884.00
0.283 Oh Mandor @ Rp. 108,750.00 = Rp 30,776.25
Sub total : = Rp 836,364.00
Total upah+bahan : = Rp 4,359,881.50
32 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 5 dia 19 mm + beugel dia 8 mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.270 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 816,750.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
179.859 Kg Besi beton polos dia 16 mm @ Rp. 11,825.00 = Rp 2,126,832.68
262 81.656 Kg Besi begel polos dia 6 mm @ Rp. 11,825.00 = Rp 965,585.98
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 4,724,283.66
Upah An. SNI ( Revisi ) 6.39.2
4.850 Oh Pekerja @ Rp. 75,000.00 = Rp 363,750.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.350 Oh Tukang besi @ Rp. 107,250.00 = Rp 144,787.50
0.331 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,748.00
0.170 Oh Mandor @ Rp. 108,750.00 = Rp 18,487.50
Sub total : = Rp 767,620.50
Total upah+bahan : = Rp 5,491,904.16
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 41
33 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 4 dia 16 mm + beugel dia 6 mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.270 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 816,750.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
114.419 Kg Besi beton polos dia 16 mm @ Rp. 11,825.00 = Rp 1,353,002.31
45.745 Kg Besi begel polos dia 6 mm @ Rp. 11,825.00 = Rp 540,930.37
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 3,525,797.68
Upah An. SNI ( Revisi ) 6.39.2
4.850 Oh Pekerja @ Rp. 75,000.00 = Rp 363,750.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.350 Oh Tukang besi @ Rp. 107,250.00 = Rp 144,787.50
0.331 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,748.00
0.170 Oh Mandor @ Rp. 108,750.00 = Rp 18,487.50
Sub total : = Rp 767,620.50
Total upah+bahan : = Rp 4,293,418.18

33 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 4 dia 12 mm + beugel dia 6 mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.270 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 816,750.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
82.167 Kg Besi beton polos dia 12 mm @ Rp. 11,825.00 = Rp 971,620.83
6.715 Kg Besi begel polos dia 6 mm @ Rp. 11,825.00 = Rp 79,404.88
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 2,682,890.71
Upah An. SNI ( Revisi ) 6.39.2
4.850 Oh Pekerja @ Rp. 75,000.00 = Rp 363,750.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.350 Oh Tukang besi @ Rp. 107,250.00 = Rp 144,787.50
0.331 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,748.00
0.170 Oh Mandor @ Rp. 108,750.00 = Rp 18,487.50
Sub total : = Rp 767,620.50
Total upah+bahan : = Rp 3,450,511.21

34 1 m3 Membuat sloof beton bertulang ukuran 15 x 20 Cm dengan besi 4 dia 12 mm + beugel dia 6mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.270 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 816,750.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
114.419 Kg Besi beton polos dia 12 mm @ Rp. 11,825.00 = Rp 1,353,002.31
35.631 Kg Besi begel polos dia 6 mm @ Rp. 11,825.00 = Rp 421,336.58
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 3,406,203.89
Upah An. SNI ( Revisi ) 6.39.2
4.850 Oh Pekerja @ Rp. 75,000.00 = Rp 363,750.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 42
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.350 Oh Tukang besi @ Rp. 107,250.00 = Rp 144,787.50
0.331 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,748.00
0.170 Oh Mandor @ Rp. 108,750.00 = Rp 18,487.50
Sub total : = Rp 767,620.50
Total upah+bahan : = Rp 4,173,824.39

35 1 m3 Membuat sloof beton bertulang ukuran 15 x 20 Cm dengan besi 4 dia 10 mm + kegesting .


Bahan An. SNI ( Revisi ) 6.39.1
0.135 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 408,375.00
2.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 28,000.00
0.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 6,300.00
60.633 Kg Besi beton polos dia 10 mm @ Rp. 11,825.00 = Rp 716,989.17
6.715 Kg Besi begel polos dia 6 mm @ Rp. 11,825.00 = Rp 79,404.88
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 2,019,884.04
Upah An. SNI ( Revisi ) 6.39.2
4.850 Oh Pekerja @ Rp. 75,000.00 = Rp 363,750.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
1.560 Oh Tukang kayu @ Rp. 107,250.00 = Rp 167,310.00
1.300 Oh Tukang besi @ Rp. 107,250.00 = Rp 139,425.00
0.331 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,748.00
0.170 Oh Mandor @ Rp. 108,750.00 = Rp 18,487.50
Sub total : = Rp 762,258.00
Total upah+bahan : = Rp 2,782,142.04

Kolom
36 1 m3 Membuat kolom beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.40.1
0.400 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 0.00
4.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 56,000.00
2.000 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 21,000.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
4.500 Kg Kawat beton @ Rp. 14,700.00 = Rp 66,150.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.150 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 630,000.00
3.500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 385,000.00
20.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 0.00
Sub total : = Rp 3,786,517.50
Upah An. SNI ( Revisi ) 6.40.2
7.050 Oh Pekerja @ Rp. 75,000.00 = Rp 528,750.00
0.270 Oh Tukang batu @ Rp. 107,250.00 = Rp 28,957.50
1.650 Oh Tukang kayu @ Rp. 107,250.00 = Rp 176,962.50
2.100 Oh Tukang besi @ Rp. 107,250.00 = Rp 225,225.00
0.403 Oh Kepala tukang @ Rp. 108,000.00 = Rp 43,524.00
0.353 Oh Mandor @ Rp. 108,750.00 = Rp 38,388.75
Sub total : = Rp 1,041,807.75
Total upah+bahan : = Rp 4,828,325.25

36 1 m3 Membuat kolom beton bertulang ( 150 Kg besi + bekisting ) ---- dia. 10 mm - begel 6 mm
Bahan An. SNI ( Revisi ) 6.40.1
0.400 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 0.00
4.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 56,000.00
2.000 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 21,000.00
64.402 Kg Besi beton polos @ Rp. 11,825.00 = Rp 761,549.71
4.500 Kg Kawat beton @ Rp. 14,700.00 = Rp 66,150.00
0.2000 200.000 Kg Semen portland @ Rp. 1,525.00 = Rp 305,000.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 43
1.5500 0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.150 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 630,000.00
3.500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 385,000.00
20.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 0.00
Sub total : = Rp 2,478,229.71
Upah An. SNI ( Revisi ) 6.40.2
7.050 Oh Pekerja @ Rp. 75,000.00 = Rp 528,750.00
0.270 Oh Tukang batu @ Rp. 107,250.00 = Rp 28,957.50
1.650 Oh Tukang kayu @ Rp. 107,250.00 = Rp 176,962.50
2.100 Oh Tukang besi @ Rp. 107,250.00 = Rp 225,225.00
0.403 Oh Kepala tukang @ Rp. 108,000.00 = Rp 43,524.00
0.353 Oh Mandor @ Rp. 108,750.00 = Rp 38,388.75
Sub total : = Rp 1,041,807.75
Total upah+bahan : = Rp 3,520,037.46
37 1 m' Membuat kolom penguat ( kolom praktis ) beton bertulang ( 11 x 11 ) cm
Catatan : besi memakai diameter 12 mm beugel diameter 5 mm.
Bahan An. SNI ( Revisi ) 6.45.1
0.002 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 6,050.00
0.010 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 140.00
3.000 Kg Besi beton polos dia. 10 mm @ Rp. 11,825.00 = Rp 35,475.00
0.280 Kg Besi begel polos dia. 6 mm @ Rp. 11,825.00 = Rp 3,311.00
0.125 Kg Kawat beton @ Rp. 14,700.00 = Rp 1,837.50
4.000 Kg Semen portland @ Rp. 1,525.00 = Rp 6,100.00
0.006 m3 Pasir beton @ Rp. 198,000.00 = Rp 1,188.00
0.009 m3 Koral beton @ Rp. 181,000.00 = Rp 1,629.00
Sub total : = Rp 55,730.50
Upah An. SNI ( Revisi ) 6.45.2
0.180 Oh Pekerja @ Rp. 75,000.00 = Rp 13,500.00
0.020 Oh Tukang batu @ Rp. 107,250.00 = Rp 2,145.00
0.020 Oh Tukang kayu @ Rp. 107,250.00 = Rp 2,145.00
0.020 Oh Tukang besi @ Rp. 107,250.00 = Rp 2,160.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.009 Oh Mandor @ Rp. 108,750.00 = Rp 978.75
Sub total : = Rp 21,576.75
Total upah+bahan : = Rp 77,307.25
Biaya kolom praktis dengan besi polos 4 diameter 12 mm = Rp 77,307.25
Analog biaya / M3. = 77,307.25 x 60.61 = Rp 4,685,592.42

38 1 m' Membuat kolom penguat ( kolom praktis ) beton bertulang ( 11 x 11 ) cm


Catatan : besi memakai diameter 10 mm beugel diameter 5 mm.
Bahan An. SNI ( Revisi ) 6.45.1
0.002 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 6,050.00
0.010 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 140.00
2.300 Kg Besi beton polos dia. 10 mm @ Rp. 11,825.00 = Rp 27,197.50
0.280 Kg Besi begel polos dia. 6 mm @ Rp. 11,825.00 = Rp 3,311.00
0.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 3,675.00
4.000 Kg Semen portland @ Rp. 1,525.00 = Rp 6,100.00
0.006 m3 Pasir beton @ Rp. 198,000.00 = Rp 1,188.00
0.009 m3 Koral beton @ Rp. 181,000.00 = Rp 1,629.00
Sub total : = Rp 49,290.50
Upah An. SNI ( Revisi ) 6.45.2
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.020 Oh Tukang batu @ Rp. 107,250.00 = Rp 2,145.00
0.020 Oh Tukang kayu @ Rp. 107,250.00 = Rp 2,145.00
0.020 Oh Tukang besi @ Rp. 107,250.00 = Rp 2,145.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.003 Oh Mandor @ Rp. 108,750.00 = Rp 326.25
Sub total : = Rp 11,909.25
Total upah+bahan : = Rp 61,199.75
Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 61,199.75
Analog biaya / M3. = 61,199.75 x 60.61 = Rp 3,709,316.85
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 44
Balok
39 1 m3 Membuat balok beton bertulang ( 200 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.41.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 0.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 44,800.00
1.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 16,800.00
180.000 Kg Besi beton polos @ Rp. 11,825.00 = Rp 2,128,500.00
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.140 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 588,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
16.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 432,000.00
Sub total : = Rp 4,328,130.00
Upah An. SNI ( Revisi ) 6.41.2
6.350 Oh Pekerja @ Rp. 75,000.00 = Rp 476,250.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.650 Oh Tukang kayu @ Rp. 107,250.00 = Rp 176,962.50
1.400 Oh Tukang besi @ Rp. 107,250.00 = Rp 150,150.00
0.333 Oh Kepala tukang @ Rp. 108,000.00 = Rp 35,964.00
0.318 Oh Mandor @ Rp. 108,750.00 = Rp 34,582.50
Sub total : = Rp 903,402.75
Total upah+bahan : = Rp 5,231,532.75

40 1 m3 Membuat balok beton bertulang ( 150 Kg besi + bekisting )


Bahan An. SNI ( Revisi ) 6.42.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 968,000.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 44,800.00
1.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 16,800.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
2.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 33,075.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.120 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 504,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
32.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 1,728,000.00
Sub total : = Rp 6,231,042.50
Upah An. SNI ( Revisi ) 6.42.2
5.300 Oh Pekerja @ Rp. 75,000.00 = Rp 397,500.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 139,425.00
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.265 Oh Kepala tukang @ Rp. 108,000.00 = Rp 28,620.00
0.265 Oh Mandor @ Rp. 108,750.00 = Rp 28,818.75
Sub total : = Rp 736,470.00
Total upah+bahan : = Rp 6,967,512.50

41 1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm


Catatan : besi memakai diameter 12 mm beugel diameter 5 mm.
Bahan An. SNI ( Revisi ) 6.46.1
0.003 m3 Kayu terentang/Meranti (MC) @ Rp. 14,000.00 = Rp 42.00
0.020 Kg Paku biasa 2" - 5" @ Rp. 11,825.00 = Rp 236.50
3.600 Kg Besi beton polos dia 12 mm @ Rp. 11,825.00 = Rp 42,570.00
0.250 Kg Besi begel polos dia. 6 mm @ Rp. 11,825.00 = Rp 2,956.25
0.050 Kg Kawat beton @ Rp. 14,700.00 = Rp 735.00
5.500 Kg Semen portland @ Rp. 1,525.00 = Rp 8,387.50
0.009 m3 Pasir beton @ Rp. 198,000.00 = Rp 1,782.00
0.015 m3 Koral beton @ Rp. 181,000.00 = Rp 2,715.00
Sub total : = Rp 59,424.25
Upah An. SNI ( Revisi ) 6.46.2
0.297 Oh Pekerja @ Rp. 107,250.00 = Rp 31,853.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 45
0.033 Oh Tukang batu @ Rp. 107,250.00= Rp 3,539.25
0.033 Oh Tukang kayu @ Rp. 107,250.00= Rp 3,539.25
0.033 Oh Tukang besi @ Rp. 108,000.00= Rp 3,564.00
0.010 Oh Kepala tukang @ Rp. 108,750.00= Rp 1,087.50
0.015 Oh Mandor @ Rp. 0.00= Rp 0.00
Sub total : = Rp 43,583.25
Total upah+bahan : = Rp 103,007.50
Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 103,007.50
Analog biaya / M3. = 103,007.50 x 60.61 = Rp 6,243,284.58

42 1 m' Membuat ring balok beton bertulang ( 10 x 15 ) cm


Catatan : besi memakai diameter 10 mm beugel diameter 5 mm.
Bahan An. SNI ( Revisi ) 6.46.1
0.003 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 9,075.00
0.020 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 280.00
2.384 Kg Besi beton polos dia 10 mm @ Rp. 11,825.00 = Rp 28,190.80
0.280 Kg Besi begel polos dia. 6 mm @ Rp. 11,825.00 = Rp 3,311.00
0.050 Kg Kawat beton @ Rp. 14,700.00 = Rp 735.00
5.500 Kg Semen portland @ Rp. 1,525.00 = Rp 8,387.50
0.009 m3 Pasir beton @ Rp. 198,000.00 = Rp 1,782.00
0.015 m3 Koral beton @ Rp. 181,000.00 = Rp 2,715.00
Sub total : = Rp 54,476.30
Upah An. SNI ( Revisi ) 6.46.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.033 Oh Tukang batu @ Rp. 107,250.00 = Rp 3,539.25
0.033 Oh Tukang kayu @ Rp. 107,250.00 = Rp 3,539.25
0.033 Oh Tukang besi @ Rp. 107,250.00 = Rp 3,539.25
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,741.50
Total upah+bahan : = Rp 74,217.80
Biaya kolom praktis dengan besi polos 4 diameter 10 mm = Rp 74,217.80
Analog biaya / M3. = 74,217.80 x 60.61 = Rp 4,498,340.86

43 1 m3 Membuat dinding beton bertulang ( 150 Kg besi + bekisting )


Bahan An. SNI ( Revisi ) 6.43.1
0.240 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 726,000.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 44,800.00
1.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 16,800.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
2.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 33,075.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.160 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 672,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
14.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 756,000.00
Sub total : = Rp 5,185,042.50
Upah An. SNI ( Revisi ) 6.43.2
5.300 Oh Pekerja @ Rp. 75,000.00 = Rp 397,500.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 139,425.00
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.262 Oh Kepala tukang @ Rp. 108,000.00 = Rp 28,296.00
0.265 Oh Mandor @ Rp. 108,750.00 = Rp 28,818.75
Sub total : = Rp 736,146.00
Total upah+bahan : = Rp 5,921,188.50

44 1 m3 Membuat tangga beton bertulang ( 200 Kg besi + bekisting )


Bahan An. SNI ( Revisi ) 6.44.1
0.250 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 756,250.00
3.000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 42,000.00
1.200 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 12,600.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 46
200.000 Kg Besi beton polos @ Rp. 11,825.00 = Rp 2,365,000.00
3.000 Kg Kawat beton @ Rp. 14,700.00 = Rp 44,100.00
323.000 Kg Semen portland @ Rp. 1,525.00 = Rp 492,575.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
0.105 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 441,000.00
2.500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 275,000.00
14.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 54,000.00 = Rp 756,000.00
Sub total : = Rp 5,428,665.00
Upah An. SNI ( Revisi ) 6.44.2
5.600 Oh Pekerja @ Rp. 75,000.00 = Rp 420,000.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
2.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 246,675.00
1.400 Oh Tukang besi @ Rp. 107,250.00 = Rp 150,150.00
0.405 Oh Kepala tukang @ Rp. 108,000.00 = Rp 43,740.00
0.202 Oh Mandor @ Rp. 108,750.00 = Rp 21,967.50
Sub total : = Rp 920,070.00
Total upah+bahan : = Rp 6,348,735.00
Plat Lantai
45 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm , pembagi 8 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 116,160.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
0.192 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,016.00
5.690 Kg Besi beton polos 10 mm & 8 mm @ Rp. 11,825.00 = Rp 67,284.25
0.225 Kg Kawat beton @ Rp. 14,700.00 = Rp 3,307.50
38.760 Kg Semen portland @ Rp. 1,525.00 = Rp 59,109.00
0.062 m3 Pasir beton @ Rp. 198,000.00 = Rp 12,355.20
0.094 m3 Koral beton @ Rp. 181,000.00 = Rp 16,941.60
0.014 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 60,480.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.500 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 75,000.00 = Rp 262,500.00
Sub total : = Rp 642,153.55
Upah An. SNI ( Revisi ) 6.42.2
0.696 Oh Pekerja @ Rp. 75,000.00 = Rp 52,200.00
0.042 Oh Tukang batu @ Rp. 107,250.00 = Rp 4,504.50
0.336 Oh Tukang kayu @ Rp. 107,250.00 = Rp 36,036.00
0.126 Oh Tukang besi @ Rp. 107,250.00 = Rp 13,513.50
0.050 Oh Kepala tukang @ Rp. 107,250.00 = Rp 5,405.40
0.022 Oh Mandor @ Rp. 108,750.00 = Rp 2,414.25
Sub total : = Rp 114,073.65
Total upah+bahan : = Rp 756,227.20
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 10 - 12
dan besi polos dia 8 - 15 = Rp 756,227.20
Analog biaya / M3. = 756,227.20 x 8.33 = Rp 6,299,372.58

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 47
46 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 12 mm , pembagi 12 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 0.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 0.00
0.192 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 0.00
19.400 Kg Besi beton polos 12 mm & 12 mm @ Rp. 11,825.00 = Rp 229,405.00
0.225 Kg Kawat beton @ Rp. 14,700.00 = Rp 3,307.50
38.760 Kg Semen portland @ Rp. 1,525.00 = Rp 59,109.00
0.062 m3 Pasir beton @ Rp. 198,000.00 = Rp 12,355.20
0.094 m3 Koral beton @ Rp. 181,000.00 = Rp 16,941.60
0.014 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp
3.500 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 75,000.00 = Rp
Sub total : = Rp 321,118.30
Upah An. SNI ( Revisi ) 6.42.2
0.696 Oh Pekerja @ Rp. 75,000.00 = Rp 52,200.00
0.042 Oh Tukang batu @ Rp. 107,250.00 = Rp 4,504.50
0.336 Oh Tukang kayu @ Rp. 107,250.00 = Rp 36,036.00
0.126 Oh Tukang besi @ Rp. 107,250.00 = Rp 13,513.50
0.050 Oh Kepala tukang @ Rp. 107,250.00 = Rp 5,405.40
0.022 Oh Mandor @ Rp. 108,750.00 = Rp 2,414.25
Sub total : = Rp 114,073.65
Total upah+bahan : = Rp 435,191.95
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 12 - 15
dan besi polos dia 10 - 15 = Rp 435,191.95
Analog biaya / M3. = 435,191.95 x 8.33 = Rp 3,625,148.94

47 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm jarak 15 , pembagi 10 mm.
arak 15 rangkap atas bawah ( doble wappening)
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 116,160.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
0.192 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 2,016.00
15.893 Kg Besi beton polos 10 mm @ Rp. 11,825.00 = Rp 187,934.73
0.225 Kg Kawat beton @ Rp. 14,700.00 = Rp 3,307.50
38.760 Kg Semen portland @ Rp. 1,525.00 = Rp 59,109.00
0.062 m3 Pasir beton @ Rp. 198,000.00 = Rp 12,355.20
0.094 m3 Koral beton @ Rp. 181,000.00 = Rp 16,941.60
0.014 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 60,480.00
0.350 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.500 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 75,000.00 = Rp 262,500.00
Sub total : = Rp 762,804.03
Upah An. SNI ( Revisi ) 6.42.2
0.696 Oh Pekerja @ Rp. 75,000.00 = Rp 52,200.00
0.042 Oh Tukang batu @ Rp. 107,250.00 = Rp 4,504.50
0.336 Oh Tukang kayu @ Rp. 107,250.00 = Rp 36,036.00
0.126 Oh Tukang besi @ Rp. 107,250.00 = Rp 13,513.50
0.050 Oh Kepala tukang @ Rp. 107,250.00 = Rp 5,405.40
0.022 Oh Mandor @ Rp. 108,750.00 = Rp 2,414.25
Sub total : = Rp 114,073.65
Total upah+bahan : = Rp 876,877.68

Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm penulangan rangkap dengan besi dia 10 - 15
dan besi polos dia 8 - 15 (doble wappening) atas bawah. = Rp 876,877.68
Analog biaya / M3. = 876,877.68 x 8.33 = Rp 7,304,391.03
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. "Halaman : 48

Plat Lantai
45 1 m3 Membuat plat lantai bawah
Bahan An. SNI ( Revisi ) 6.42.1
0.2000 m3 Kayu terentang/Meranti (MC) @ Rp. 0.00 = Rp 0.00
1.5000 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 21,000.00
0.400 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 4,200.00
157.000 Kg Besi beton ulir @ Rp. 11,825.00 = Rp 1,856,525.00
2.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 33,075.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.520 m3 Pasir beton @ Rp. 198,000.00 = Rp 102,960.00
0.780 m3 Koral beton @ Rp. 181,000.00 = Rp 141,180.00
Sub total : = Rp 2,671,340.00
Upah An. SNI ( Revisi ) 6.42.2
3.390 Oh Pekerja @ Rp. 75,000.00 = Rp 254,250.00
0.350 Oh Tukang batu @ Rp. 107,250.00 = Rp 37,537.50
1.040 Oh Tukang kayu @ Rp. 107,250.00 = Rp 111,540.00
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.245 Oh Kepala tukang @ Rp. 107,250.00 = Rp 26,276.25
0.165 Oh Mandor @ Rp. 108,750.00 = Rp 17,943.75
Sub total : = Rp 560,160.00
Total upah+bahan : = Rp 3,231,500.00

45 1 m2 Membuat plat lantai tebal 10 Cm dengan besi polos diameter 10 mm , pembagi 8 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0100 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 30,250.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
0.192 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 0.00
5.123 Kg Besi beton polos 10 mm & 8 mm @ Rp. 11,825.00 = Rp 60,579.48
0.225 Kg Kawat beton @ Rp. 14,700.00 = Rp 3,307.50
22.000 Kg Semen portland @ Rp. 1,525.00 = Rp 33,550.00
0.052 m3 Pasir beton @ Rp. 198,000.00 = Rp 10,296.00
0.026 m3 Koral beton @ Rp. 181,000.00 = Rp 4,706.00
0.001 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 2,100.00
0.300 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 33,000.00
2.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 75,000.00 = Rp 150,000.00
Sub total : = Rp 331,288.98
Upah An. SNI ( Revisi ) 6.42.2
0.557 Oh Pekerja @ Rp. 75,000.00 = Rp 41,760.00
0.336 Oh Tukang batu @ Rp. 107,250.00 = Rp 36,036.00
0.269 Oh Tukang kayu @ Rp. 107,250.00 = Rp 28,828.80
0.101 Oh Tukang besi @ Rp. 107,250.00 = Rp 10,810.80
0.040 Oh Kepala tukang @ Rp. 107,250.00 = Rp 4,290.00
0.176 Oh Mandor @ Rp. 108,750.00 = Rp 19,140.00
Sub total : = Rp 140,865.60
Total upah+bahan : = Rp 472,154.58
Biaya pembuatan plat lantai per 1 M2 tebal 10 Cm dengan besi dia 10
dan besi polos dia 8 - 15 = Rp 472,154.58
Analog biaya / M3. = 472,154.58 x 10.00 = Rp 4,721,545.75

43 1 m3 Membuat dinding beton bertulang ( 150 Kg besi + bekisting )


Bahan An. SNI ( Revisi ) 6.43.1
0.240 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 0.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 44,800.00
1.600 Ltr Minyak bekisting @ Rp. 10,500.00 = Rp 16,800.00
157.500 Kg Besi beton polos @ Rp. 11,825.00 = Rp 1,862,437.50
2.250 Kg Kawat beton @ Rp. 14,700.00 = Rp 33,075.00
336.000 Kg Semen portland @ Rp. 1,525.00 = Rp 512,400.00
0.540 m3 Pasir beton @ Rp. 198,000.00 = Rp 106,920.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 44
0.810 m3 Koral beton @ Rp. 181,000.00 = Rp 146,610.00
0.160 m3 Balok kayu borneo @ Rp. 4,200,000.00 = Rp 672,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
24.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 24,000.00 = Rp 0.00
Sub total : = Rp 3,703,042.50
Upah An. SNI ( Revisi ) 6.43.2
5.300 Oh Pekerja @ Rp. 75,000.00 = Rp 397,500.00
0.275 Oh Tukang batu @ Rp. 107,250.00 = Rp 29,493.75
1.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 139,425.00
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.262 Oh Kepala tukang @ Rp. 65,000.00 = Rp 17,030.00
0.265 Oh Mandor @ Rp. 70,000.00 = Rp 18,550.00
Sub total : = Rp 714,611.25
Total upah+bahan : = Rp 4,417,653.75

Kolom
36 1 m3 Membuat kolom beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.40.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 3,750,000.00 = Rp 1,200,000.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 11,300.00 = Rp 36,160.00
1.600 Ltr Minyak bekisting @ Rp. 6,000.00 = Rp 9,600.00
157.500 Kg Besi beton polos @ Rp. 11,000.00 = Rp 1,732,500.00
2.250 Kg Kawat beton @ Rp. 13,250.00 = Rp 29,812.50
336.000 Kg Semen portland @ Rp. 1,125.00 = Rp 378,000.00
0.540 m3 Pasir beton @ Rp. 130,000.00 = Rp 70,200.00
0.810 m3 Koral beton @ Rp. 162,000.00 = Rp 131,220.00
0.120 m3 Balok kayu borneo @ Rp. 3,850,000.00 = Rp 462,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 139,750.00 = Rp 391,300.00
32.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 24,000.00 = Rp 768,000.00
Sub total : = Rp 5,208,792.50
Upah An. SNI ( Revisi ) 6.40.2
5.300 Oh Pekerja @ Rp. 40,000.00 = Rp 212,000.00
0.275 Oh Tukang batu @ Rp. 60,000.00 = Rp 16,500.00
1.300 Oh Tukang kayu @ Rp. 60,000.00 = Rp 78,000.00
1.050 Oh Tukang besi @ Rp. 60,000.00 = Rp 63,000.00
0.265 Oh Kepala tukang @ Rp. 65,000.00 = Rp 17,225.00
0.265 Oh Mandor @ Rp. 70,000.00 = Rp 18,550.00
Sub total : = Rp 405,275.00
Total upah+bahan : = Rp 5,614,067.50

Balok
39 1 m3 Membuat balok beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.41.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 3,750,000.00 = Rp 1,200,000.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 11,300.00 = Rp 36,160.00
1.600 Ltr Minyak bekisting @ Rp. 6,000.00 = Rp 9,600.00
157.500 Kg Besi beton polos @ Rp. 11,000.00 = Rp 1,732,500.00
2.250 Kg Kawat beton @ Rp. 13,250.00 = Rp 29,812.50
336.000 Kg Semen portland @ Rp. 1,125.00 = Rp 378,000.00
0.540 m3 Pasir beton @ Rp. 130,000.00 = Rp 70,200.00
0.810 m3 Koral beton @ Rp. 162,000.00 = Rp 131,220.00
0.120 m3 Balok kayu borneo @ Rp. 3,850,000.00 = Rp 462,000.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 139,750.00 = Rp 391,300.00
32.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 24,000.00 = Rp 768,000.00
Sub total : = Rp 5,208,792.50
Upah An. SNI ( Revisi ) 6.41.2
5.800 Oh Pekerja @ Rp. 40,000.00 = Rp 232,000.00
0.350 Oh Tukang batu @ Rp. 60,000.00 = Rp 21,000.00
2.800 Oh Tukang kayu @ Rp. 60,000.00 = Rp 168,000.00
1.050 Oh Tukang besi @ Rp. 60,000.00 = Rp 63,000.00
0.420 Oh Kepala tukang @ Rp. 65,000.00 = Rp 27,300.00
0.185 Oh Mandor @ Rp. 70,000.00 = Rp 12,950.00
Sub total : = Rp 524,250.00
Total upah+bahan : = Rp 5,733,042.50
Strouss
36 1 m3 Membuat kolom beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.40.1
0.320 m3 Kayu terentang/Meranti (MC) @ Rp. 0.00 = Rp 0.00
3.200 Kg Paku biasa 2" - 5" @ Rp. 0.00 = Rp 0.00
1.600 Ltr Minyak bekisting @ Rp. 0.00 = Rp 0.00
157.500 Kg Besi beton polos @ Rp. 11,000.00 = Rp 1,732,500.00
2.250 Kg Kawat beton @ Rp. 0.00 = Rp 0.00
336.000 Kg Semen portland @ Rp. 1,125.00 = Rp 378,000.00
0.540 m3 Pasir beton @ Rp. 130,000.00 = Rp 70,200.00
0.810 m3 Koral beton @ Rp. 162,000.00 = Rp 131,220.00
0.120 m3 Balok kayu borneo @ Rp. 0.00 = Rp 0.00
2.800 Lbr Plywood tebal 9 mm @ Rp. 0.00 = Rp 0.00
32.000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 2,311,920.00
Upah An. SNI ( Revisi ) 6.40.2
5.300 Oh Pekerja @ Rp. 40,000.00 = Rp 212,000.00
0.275 Oh Tukang batu @ Rp. 60,000.00 = Rp 16,500.00
1.300 Oh Tukang kayu @ Rp. 60,000.00 = Rp 78,000.00
1.050 Oh Tukang besi @ Rp. 60,000.00 = Rp 63,000.00
0.265 Oh Kepala tukang @ Rp. 65,000.00 = Rp 17,225.00
0.265 Oh Mandor @ Rp. 70,000.00 = Rp 18,550.00
Sub total : = Rp 405,275.00
Total upah+bahan : = Rp 2,717,195.00
PEKERJAAN PASANGAN

1. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps


Bahan An. SNI ( Revisi ) 6.1.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
55.600 Kg Semen portland @ Rp. 1,525.00 = Rp 84,790.00
0.056 m3 Pasir pasang @ Rp. 175,000.00 = Rp 9,800.00
Sub total : = Rp 164,590.00
Upah An. SNI ( Revisi ) 6.1.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan /m2: = Rp 236,462.50
Total per : M3 = Rp 909,471.15

2. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps


Bahan An. SNI ( Revisi ) 6.2.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
43.500 Kg Semen portland @ Rp. 1,525.00 = Rp 66,337.50
0.080 m3 Pasir pasang @ Rp. 175,000.00 = Rp 14,000.00
Sub total : = Rp 150,337.50
Upah An. SNI ( Revisi ) 6.2.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 222,210.00
Total per : M3 = Rp 854,653.85

3. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps


Bahan An. SNI ( Revisi ) 6.3.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
32.900 Kg Semen portland @ Rp. 1,525.00 = Rp 50,172.50
0.091 m3 Pasir pasang @ Rp. 175,000.00 = Rp 15,925.00
Sub total : = Rp 136,097.50
Upah An. SNI ( Revisi ) 6.3.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 207,970.00
Total per : M3 = Rp 799,884.62

4. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps


Bahan An. SNI ( Revisi ) 6.4.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
26.550 Kg Semen portland @ Rp. 1,525.00 = Rp 40,488.75
0.093 m3 Pasir pasang @ Rp. 175,000.00 = Rp 16,275.00
Sub total : = Rp 126,763.75
Upah An. SNI ( Revisi ) 6.4.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 16
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 198,636.25
Total per : M3 = Rp 763,985.58

5. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps


Bahan An. SNI ( Revisi ) 6.5.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
22.200 Kg Semen portland @ Rp. 1,525.00 = Rp 33,855.00
0.102 m3 Pasir pasang @ Rp. 175,000.00 = Rp 17,850.00
Sub total : = Rp 121,705.00
Upah An. SNI ( Revisi ) 6.5.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 193,577.50
Total per : M3 = Rp 744,528.85

6. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps


Bahan An. SNI ( Revisi ) 6.6.1
140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
19.500 Kg Semen portland @ Rp. 1,525.00 = Rp 29,737.50
0.122 m3 Pasir pasang @ Rp. 175,000.00 = Rp 21,350.00
Sub total : = Rp 121,087.50
Upah An. SNI ( Revisi ) 6.6.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 192,960.00
Total per : M3 = Rp 742,153.85

7. 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps


Bahan An. SNI ( Revisi ) 6.7.1
140.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 70,000.00
10.0800 Kg Semen portland @ Rp. 1,525.00 = Rp 15,372.00
0.0925 m3 Pasir pasang @ Rp. 175,000.00 = Rp 16,187.50
0.0275 m3 Kapur pasang @ Rp. 88,000.00 = Rp 2,420.00
Sub total : = Rp 103,979.50
Upah An. SNI ( Revisi ) 6.7.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 71,872.50
Total upah+bahan : = Rp 175,852.00
Total per : M3 = Rp 676,353.85

8. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 1 Ps


Bahan An. SNI ( Revisi ) 6.8.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 17
27.800 Kg Semen portland @ Rp. 1,525.00 = Rp 42,395.00
0.030 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,162.50
Sub total : = Rp 82,557.50
Upah An. SNI ( Revisi ) 6.8.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 118,493.75
Total per : M3 = Rp 911,490.38

9. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps


Bahan An. SNI ( Revisi ) 6.9.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
18.950 Kg Semen portland @ Rp. 1,525.00 = Rp 28,898.75
0.038 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,650.00
Sub total : = Rp 70,548.75
Upah An. SNI ( Revisi ) 6.9.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 106,485.00
Total per : M3 = Rp 819,115.38

10. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps


Bahan An. SNI ( Revisi ) 6.10.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
14.370 Kg Semen portland @ Rp. 1,525.00 = Rp 21,914.25
0.040 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,000.00
Sub total : = Rp 63,914.25
Upah An. SNI ( Revisi ) 6.10.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 99,850.50
Total per : M3 = Rp 768,080.77

11. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps


Bahan An. SNI ( Revisi ) 6.4.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
11.500 Kg Semen portland @ Rp. 1,525.00 = Rp 17,537.50
0.043 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,525.00
Sub total : = Rp 60,062.50
Upah An. SNI ( Revisi ) 6.4.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 95,998.75
Total per : M3 = Rp 738,451.92
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 18
12. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps
Bahan An. SNI ( Revisi ) 6.12.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
9.680 Kg Semen portland @ Rp. 1,525.00 = Rp 14,762.00
0.045 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,875.00
Sub total : = Rp 57,637.00
Upah An. SNI ( Revisi ) 6.12.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 93,573.25
Total per : M3 = Rp 719,794.23

13. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps


Bahan An. SNI ( Revisi ) 6.13.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
8.320 Kg Semen portland @ Rp. 1,525.00 = Rp 12,688.00
0.0490 m3 Pasir pasang @ Rp. 175,000.00 = Rp 8,575.00
Sub total : = Rp 56,263.00
Upah An. SNI ( Revisi ) 6.13.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 92,199.25
Total per : M3 = Rp 709,225.00

14. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps


Bahan An. SNI ( Revisi ) 6.14.1
70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
6.500 Kg Semen portland @ Rp. 1,525.00 = Rp 9,912.50
0.050 m3 Pasir pasang @ Rp. 175,000.00 = Rp 8,750.00
Sub total : = Rp 53,662.50
Upah An. SNI ( Revisi ) 6.14.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 89,598.75
Total per : M3 = Rp 689,221.15

15. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 5 Ps


Bahan An. SNI ( Revisi ) 6.15.1
70.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
4.5000 Kg Semen portland @ Rp. 1,525.00 = Rp 6,862.50
0.0130 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,275.00
0.0137 m3 Kapur padam @ Rp. 88,000.00 = Rp 1,205.60
Sub total : = Rp 45,343.10
Upah An. SNI ( Revisi ) 6.15.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 19
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 81,279.35
Total per : M3 = Rp 625,225.77

16. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1 Ps


Bahan An. SNI ( Revisi ) 6.16.1
70.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
0.0180 Kg Semen merah / bata merah tumbuk @ Rp. 1,525.00 = Rp 27.45
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.0180 m3 Kapur padam @ Rp. 88,000.00 = Rp 1,584.00
Sub total : = Rp 39,761.45
Upah An. SNI ( Revisi ) 6.16.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 75,697.70
Total per : M3 = Rp 582,290.00

17. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Ps


Bahan An. SNI ( Revisi ) 6.17.1
70.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 500.00 = Rp 35,000.00
0.0140 Kg Semen merah / bata merah tumbuk @ Rp. 1,525.00 = Rp 21.35
0.0280 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,900.00
0.0140 m3 Kapur padam @ Rp. 88,000.00 = Rp 1,232.00
Sub total : = Rp 41,153.35
Upah An. SNI ( Revisi ) 6.17.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 77,089.60
Total per : M3 = Rp 592,996.92

18 1 m2 Pasangan dinding conblock ( CB. 20 ) campuran 1PC : 3Psr.


Bahan An. SNI ( Revisi ) 6.21.1
12.5000 Bh Concrete block ( CB. 20 ) @ Rp. 8,100.00 = Rp 101,250.00
30.3200 Kg Semen portland @ Rp. 1,525.00 = Rp 46,238.00
0.7280 m3 Pasir beton @ Rp. 198,000.00 = Rp 144,144.00
0.2800 m3 Pasir pasang @ Rp. 175,000.00 = Rp 49,000.00
0.2800 Kg Besi beton polos Ø 8 mm @ Rp. 10,500.00 = Rp 2,940.00
0.0060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 84.00
0.0010 m3 Kayu terentang @ Rp. 3,025,000.00 = Rp 3,025.00
0.0300 Kg Kawat beton @ Rp. 14,700.00 = Rp 441.00
0.0050 m3 Koral beton @ Rp. 181,000.00 = Rp 905.00
Sub total : = Rp 348,027.00
Upah An. SNI ( Revisi ) 6.21.2
0.3000 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.1500 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.0150 Oh Tukang besi @ Rp. 108,000.00 = Rp 1,620.00
0.0150 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 20
0.0185 Oh Mandor @ Rp. 108,750.00 = Rp 2,011.88
Sub total : = Rp 43,839.38
Total upah+bahan : = Rp 391,866.38

19 1 m2 Pasangan dinding roster/terawang ( 12 x 11 x 24 ) cm camp. 1PC : 4 Psr.


Bahan An. SNI ( Revisi ) 6.25.1
30.0000 Bh Roster/terawang @ Rp. 5,400.00 = Rp 162,000.00
11.0000 Kg Semen portland @ Rp. 1,525.00 = Rp 16,775.00
0.0350 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,125.00
Sub total : = Rp 184,900.00

Upah An. SNI ( Revisi ) 6.25.2


0.3000 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.1000 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.0100 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 220,836.25

20 1 m2 Pasangan bata berongga ( 5 x 11 x 24 ) cm Camp. 1PC : 3 Psr.


Bahan An. SNI ( Revisi ) 6.26.1
70.0000 Bh Bata berongga @ Rp. 3,600.00 = Rp 252,000.00
14.0000 Kg Semen portland @ Rp. 1,525.00 = Rp 21,350.00
0.0320 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 26,950.00
Upah An. SNI ( Revisi ) 6.26.2
0.3000 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.1500 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.0150 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 41,838.75
Total upah+bahan : = Rp 68,788.75
Total per : M3 = Rp 286,619.79

27. 1 m2 Pasangan dinding anyaman bambu, rangka kayu


Bahan An. SNI ( Revisi ) 6.27.1
1.5000 M2 Bilik bambu @ Rp. 17,000.00 = Rp 25,500.00
0.0140 M3 Kayu meranti 5/7 @ Rp. 4,400,000.00 = Rp 61,600.00
0.0120 Kg Paku @ Rp. 14,000.00 = Rp 168.00
0.0030 m3 List kayu 2/4 @ Rp. 6,000.00 = Rp 18.00
Sub total : = Rp 87,286.00
Upah An. SNI ( Revisi ) 6.27.2
0.1000 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.0500 Oh Tukang batu @ Rp. 107,250.00 = Rp 5,362.50
0.0050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.0020 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 13,620.00
Total upah+bahan : = Rp 100,906.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 21

19 1 m2 Pasangan dinding roster/terawang ( 12 x 11 x 24 ) cm camp. 1PC : 4 Psr.


Bahan An. SNI ( Revisi ) 6.25.1
1.100 m2 Batu garis Precast @ Rp. 120,000.00 = Rp 132,000.00
3.500 Kg Semen portland @ Rp. 1,525.00 = Rp 5,337.50
0.050 m3 Pasir pasang @ Rp. 175,000.00 = Rp 8,750.00
Sub total : = Rp 146,087.50
Upah An. SNI ( Revisi ) 6.25.2
0.3000 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.1000 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.0100 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 35,936.25
Total upah+bahan : = Rp 182,023.75
PEKERJAAN PLESTERAN

1. 1 m2 Plesteran, 1 Pc : 1 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.1.1
15.504 Kg Semen portland @ Rp. 1,525.00 = Rp 23,643.60
0.016 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,800.00
Sub total : = Rp 26,443.60
Upah An. SNI ( Revisi ) 6.1.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 60,238.60

2. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.2.1
8.520 Kg Semen portland @ Rp. 1,525.00 = Rp 12,993.00
0.017 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,975.00
Sub total : = Rp 15,968.00
Upah An. SNI ( Revisi ) 6.2.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 49,763.00

3. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.3.1
6.480 Kg Semen portland @ Rp. 1,525.00 = Rp 9,882.00
0.019 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,325.00
Sub total : = Rp 13,207.00
Upah An. SNI ( Revisi ) 6.3.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 47,002.00

4. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.4.1
5.200 Kg Semen portland @ Rp. 1,525.00 = Rp 7,930.00
0.020 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,500.00
Sub total : = Rp 11,430.00
Upah An. SNI ( Revisi ) 6.4.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 45,225.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 22
5. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.5.1
4.320 Kg Semen portland @ Rp. 1,525.00 = Rp 6,588.00
0.022 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,850.00
Sub total : = Rp 10,438.00
Upah An. SNI ( Revisi ) 6.5.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 44,233.00

6. 1 m2 Plesteran, 1 Pc : 6 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.6.1
3.680 Kg Semen portland @ Rp. 1,525.00 = Rp 5,612.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
Sub total : = Rp 9,637.00
Upah An. SNI ( Revisi ) 6.6.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 43,432.00

7. 1 m2 Plesteran, 1 Pc : 8 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.7.1
2.880 Kg Semen portland @ Rp. 1,525.00 = Rp 4,392.00
0.024 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,200.00
Sub total : = Rp 8,592.00
Upah An. SNI ( Revisi ) 6.7.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 42,387.00

8. 1 m2 Plesteran, 1 Pc : 0.5 Kp : 3 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.8.1
5.760 Kg Semen portland @ Rp. 1,525.00 = Rp 8,784.00
0.003 m3 Kapur Padam @ Rp. 88,000.00 = Rp 264.00
0.013 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,275.00
Sub total : = Rp 11,323.00
Upah An. SNI ( Revisi ) 6.8.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 45,118.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 23
9. 1 m2 Plesteran, 1 Pc : 3 Kp : 10 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.9.1
1.840 Kg Semen portland @ Rp. 1,525.00 = Rp 2,806.00
0.0035 m3 Kapur Padam @ Rp. 88,000.00 = Rp 308.00
0.014 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,450.00
Sub total : = Rp 5,564.00
Upah An. SNI ( Revisi ) 6.9.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 39,359.00

10 1 m2 Plesteran, 1 Pc : 3 Kp : 8 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.9.1
2.208 Kg Semen portland @ Rp. 1,525.00 = Rp 3,367.20
0.0042 m3 Kapur Padam @ Rp. 88,000.00 = Rp 369.60
0.011 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,925.00
Sub total : = Rp 5,661.80
Upah An. SNI ( Revisi ) 6.9.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 39,456.80

11 1 m2 Plesteran, 1 Pc : 3 Kp : 5 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.9.1
2.760 Kg Semen portland @ Rp. 1,525.00 = Rp 4,209.00
0.005 m3 Kapur Padam @ Rp. 88,000.00 = Rp 462.00
0.007 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,225.00
Sub total : = Rp 5,896.00
Upah An. SNI ( Revisi ) 6.9.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 39,691.00

12 1 m2 Plesteran, 0.5 Pc : 1 Kp : 4 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.10.1
1.925 Kg Semen portland @ Rp. 1,525.00 = Rp 2,935.63
0.0022 m3 Kapur Padam @ Rp. 88,000.00 = Rp 193.60
0.019 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,325.00
Sub total : = Rp 6,454.23
Upah An. SNI ( Revisi ) 6.10.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 40,249.23
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 24
11. 1 m2 Plesteran, 1 Kp : 1 Sm : 1 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.11.1
0.009 m3 Semen merah @ Rp. 175,000.00 = Rp 1,575.00
0.009 m3 Kapur Padam @ Rp. 88,000.00 = Rp 792.00
0.009 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,575.00
Sub total : = Rp 3,942.00
Upah An. SNI ( Revisi ) 6.11.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 37,737.00

12. 1 m2 Plesteran, 1 Kp : 1 Sm : 2 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.12.1
0.007 m3 Semen merah @ Rp. 175,000.00 = Rp 1,225.00
0.007 m3 Kapur Padam @ Rp. 88,000.00 = Rp 616.00
0.015 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,625.00
Sub total : = Rp 4,466.00
Upah An. SNI ( Revisi ) 6.12.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 38,261.00

13. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 20 mm


Bahan An. SNI ( Revisi ) 6.13.1
11.360 Kg Semen portland @ Rp. 1,525.00 = Rp 17,324.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,966.67
Sub total : = Rp 21,290.67
Upah An. SNI ( Revisi ) 6.13.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 43,991.25
Total upah+bahan : = Rp 65,281.92

14. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 20 mm


Bahan An. SNI ( Revisi ) 6.14.1
8.640 Kg Semen portland @ Rp. 1,525.00 = Rp 13,176.00
0.025 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,433.33
Sub total : = Rp 17,609.33
Upah An. SNI ( Revisi ) 6.14.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 43,719.38
Total upah+bahan : = Rp 61,328.71
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 25
15. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 20 mm
Bahan An. SNI ( Revisi ) 6.15.1
6.933 Kg Semen portland @ Rp. 1,525.00 = Rp 10,573.33
0.027 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,666.67
Sub total : = Rp 15,240.00
Upah An. SNI ( Revisi ) 6.15.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 43,719.38
Total upah+bahan : = Rp 58,959.38

16. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 20 mm


Bahan An. SNI ( Revisi ) 6.16.1
5.760 Kg Semen portland @ Rp. 1,525.00 = Rp 8,784.00
0.029 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,133.33
Sub total : = Rp 13,917.33
Upah An. SNI ( Revisi ) 6.16.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 43,719.38
Total upah+bahan : = Rp 57,636.71

17. 1 m2 Plesteran, 1 Pc : 6 Ps, tebal 20 mm


Bahan An. SNI ( Revisi ) 6.17.1
4.907 Kg Semen portland @ Rp. 1,525.00 = Rp 7,482.67
0.030 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,250.00
Sub total : = Rp 12,732.67
Upah An. SNI ( Revisi ) 6.17.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 43,719.38
Total upah+bahan : = Rp 56,452.04

18. 1 m2 Plesteran, 1 Kp : 1 Sm : 2 Ps, tebal 20 mm


Bahan An. SNI ( Revisi ) 6.18.1
0.009 m3 Semen merah @ Rp. 175,000.00 = Rp 1,575.00
0.009 m3 Pasir padam @ Rp. 88,000.00 = Rp 792.00
0.018 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
Sub total : = Rp 5,517.00
Upah An. SNI ( Revisi ) 6.18.2
0.2667 Oh Pekerja @ Rp. 75,000.00 = Rp 20,000.00
0.2000 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.0200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0133 Oh Mandor @ Rp. 108,750.00 = Rp 1,450.00
Sub total : = Rp 45,060.00
Total upah+bahan : = Rp 50,577.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 26
19. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 25 mm
Bahan An. SNI ( Revisi ) 6.19.1
14.200 Kg Semen portland @ Rp. 1,525.00 = Rp 21,655.00
0.028 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,958.33
Sub total : = Rp 26,613.33
Upah An. SNI ( Revisi ) 6.19.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 47,523.75
Total upah+bahan : = Rp 74,137.08

20. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 25 mm


Bahan An. SNI ( Revisi ) 6.20.1
10.800 Kg Semen portland @ Rp. 1,525.00 = Rp 16,470.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,541.67
Sub total : = Rp 22,011.67
Upah An. SNI ( Revisi ) 6.20.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 47,523.75
Total upah+bahan : = Rp 69,535.42

21. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 25 mm


Bahan An. SNI ( Revisi ) 6.21.1
8.667 Kg Semen portland @ Rp. 1,525.00 = Rp 13,216.67
0.033 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,833.33
Sub total : = Rp 19,050.00
Upah An. SNI ( Revisi ) 6.21.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 47,523.75
Total upah+bahan : = Rp 66,573.75

22. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 25 mm


Bahan An. SNI ( Revisi ) 6.22.1
7.200 Kg Semen portland @ Rp. 1,525.00 = Rp 10,980.00
0.037 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,416.67
Sub total : = Rp 17,396.67
Upah An. SNI ( Revisi ) 6.22.2
0.300 Oh Pekerja @ Rp. 75,000.00 = Rp 22,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 47,523.75
Total upah+bahan : = Rp 64,920.42

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 27

23. 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 30 mm


Bahan An. SNI ( Revisi ) 6.23.1
17.040 Kg Semen portland @ Rp. 1,525.00 = Rp 25,986.00
0.034 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,950.00
Sub total : = Rp 31,936.00
Upah An. SNI ( Revisi ) 6.23.2
0.320 Oh Pekerja @ Rp. 75,000.00 = Rp 24,000.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 55,143.75
Total upah+bahan : = Rp 87,079.75

24. 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 30 mm


Bahan An. SNI ( Revisi ) 6.24.1
12.960 Kg Semen portland @ Rp. 1,525.00 = Rp 19,764.00
0.038 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,650.00
Sub total : = Rp 26,414.00
Upah An. SNI ( Revisi ) 6.24.2
0.320 Oh Pekerja @ Rp. 75,000.00 = Rp 24,000.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 55,143.75
Total upah+bahan : = Rp 81,557.75

25. 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 30 mm


Bahan An. SNI ( Revisi ) 6.25.1
10.400 Kg Semen portland @ Rp. 1,525.00 = Rp 15,860.00
0.040 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,000.00
Sub total : = Rp 22,860.00
Upah An. SNI ( Revisi ) 6.25.2
0.320 Oh Pekerja @ Rp. 75,000.00 = Rp 24,000.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 55,143.75
Total upah+bahan : = Rp 78,003.75

26. 1 m2 Plesteran, 1 Pc : 5 Ps, tebal 30 mm


Bahan An. SNI ( Revisi ) 6.26.1
8.640 Kg Semen portland @ Rp. 1,525.00 = Rp 13,176.00
0.044 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,700.00
Sub total : = Rp 20,876.00
Upah An. SNI ( Revisi ) 6.26.2
0.320 Oh Pekerja @ Rp. 75,000.00 = Rp 24,000.00
0.250 Oh Tukang batu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.0150 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 55,143.75
Total upah+bahan : = Rp 76,019.75

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 28

27. 1 m2 Berapen, 1 Pc : 5 Ps, tebal 30 mm


Bahan An. SNI ( Revisi ) 6.27.1
7.070 Kg Semen portland @ Rp. 1,525.00 = Rp 10,781.75
0.021 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,675.00
Sub total : = Rp 14,456.75
1 m2 Berapen, 1 Pc : 5 Ps, tebal 30 mm
Upah An. SNI ( Revisi ) 6.27.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.070 Oh Tukang batu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0080 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 20,383.50
Total upah+bahan : = Rp 34,840.25

28. 1 m2 Berapen, 1 Pc : 5 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.28.1
5.670 Kg Semen portland @ Rp. 1,525.00 = Rp 8,646.75
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
Sub total : = Rp 12,671.75
Upah An. SNI ( Revisi ) 6.28.2 .
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.070 Oh Tukang batu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0080 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 20,383.50
Total upah+bahan : = Rp 33,055.25

29. 1 m2 Plesteran beton, 1 Pc : 2 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.29.1
9.300 Kg Semen portland @ Rp. 1,525.00 = Rp 14,182.50
0.017 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,975.00
Sub total : = Rp 17,157.50
Upah An. SNI ( Revisi ) 6.29.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 44,523.75
Total upah+bahan : = Rp 61,681.25

30. 1 m2 Plesteran beton, 1 Pc : 3 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.30.1
7.070 Kg Semen portland @ Rp. 1,525.00 = Rp 10,781.75
0.019 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,325.00
Sub total : = Rp 14,106.75
Upah An. SNI ( Revisi ) 6.30.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0130 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 44,523.75
Total upah+bahan : = Rp 58,630.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 29

31. 1 m2 Plesteran skoning, 1 Pc : 2 Ps


Bahan An. SNI ( Revisi ) 6.31.1
0.500 Kg Semen portland @ Rp. 1,525.00 = Rp 762.50
0.002 m3 Pasir pasang @ Rp. 175,000.00 = Rp 350.00
Sub total : = Rp 1,112.50
Upah An. SNI ( Revisi ) 6.31.2
0.057 Oh Pekerja @ Rp. 75,000.00 = Rp 4,275.00
0.038 Oh Tukang batu @ Rp. 107,250.00 = Rp 4,075.50
0.038 Oh Kepala tukang @ Rp. 108,000.00 = Rp 4,104.00
0.0020 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 12,672.00
Total upah+bahan : = Rp 13,784.50

32. 1 m2 Plesteran granito, 1 Pc warna : 2 Granito, tebal 10 mm


Bahan An. SNI ( Revisi ) 6.32.1
0.144 Kg Pc warna @ Rp. 9,500.00 = Rp 1,368.00
5.680 Kg Semen portland @ Rp. 1,525.00 = Rp 8,662.00
0.011 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,983.33
15.000 Kg Batu granito @ Rp. 272.63 = Rp 4,089.47
Sub total : = Rp 16,102.81
Upah An. SNI ( Revisi ) 6.32.2
0.450 Oh Pekerja @ Rp. 75,000.00 = Rp 33,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.002 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.025 Oh Mandor @ Rp. 108,750.00 = Rp 2,718.75
Sub total : = Rp 58,134.75
Total upah+bahan : = Rp 74,237.56

33. 1 m2 Plesteran Teraso, 1 Pc warna : 2 batu teraso, tebal 10 mm


Bahan An. SNI ( Revisi ) 6.33.1
0.144 Kg Pc warna @ Rp. 9,500.00 = Rp 1,368.00
5.680 Kg Semen portland @ Rp. 1,525.00 = Rp 8,662.00
0.011 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,983.33
11.500 Kg Batu teraso @ Rp. 53.26 = Rp 612.53
Sub total : = Rp 12,625.86
Upah An. SNI ( Revisi ) 6.33.2
0.450 Oh Pekerja @ Rp. 75,000.00 = Rp 33,750.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.002 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.025 Oh Mandor @ Rp. 108,750.00 = Rp 2,718.75
Sub total : = Rp 58,134.75
Total upah+bahan : = Rp 70,760.61

34. 1 m2 Plesteran ciprat ,( kamprotan) 1 Pc : 2 Ps


Bahan An. SNI ( Revisi ) 6.34.1
4.320 Kg Semen portland @ Rp. 1,525.00 = Rp 6,588.00
0.016 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,800.00
Sub total : = Rp 9,388.00
Upah An. SNI ( Revisi ) 6.34.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.001 Oh Kepala tukang @ Rp. 108,000.00 = Rp 108.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 31,214.25
Total upah+bahan : = Rp 40,602.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 30
35. 1 m2 Plesteran siar / setrikan adukan, 1 Pc : 2 Ps
Bahan An. SNI ( Revisi ) 6.35.1
4.320 Kg Semen portland @ Rp. 1,525.00 = Rp 6,588.00
0.016 m3 Pasir pasang @ Rp. 175,000.00 = Rp 2,800.00
Sub total : = Rp 9,388.00
1 m2 Plesteran siar / setrikan adukan, 1 Pc : 2 Ps
Upah An. SNI ( Revisi ) 6.35.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.070 Oh Tukang batu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 20,383.50
Total upah+bahan : = Rp 29,771.50

36 1 m' Benangan
Bahan 2 Kg Semen portland @ Rp. 1,525.00 = Rp 3,431.25
Sub total : = Rp 3,431.25

Upah 0 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00


0 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 11,812.50
Total upah+bahan : = Rp 15,243.75

1. 1 m2 Plesteran, 1 Pc : 1 Ps, tebal 15 mm


Bahan An. SNI ( Revisi ) 6.1.1
6.480 Kg Semen portland @ Rp. 1,200.00 = Rp 7,776.00
0.016 m3 Pasir pasang @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 7,776.00
Upah An. SNI ( Revisi ) 6.1.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 33,795.00
Total upah+bahan : = Rp 41,571.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 31
PEKERJAAN KAYU
KUSEN PINTU + JENDELA
1. 1 m3 Pasang kusen pintu & jendela kayu jati ( kayu klas.I).
Bahan An. SNI ( Revisi ) 6.1.1
1.100 m3 Kayu jati, balok @ Rp. 16,000,000.00 = Rp 17,600,000.00
1.200 Kg Paku 10Cm @ Rp. 14,000.00 = Rp 16,800.00
1.000 Kg Lem kayu @ Rp. 36,500.00 = Rp 36,500.00
Sub total : = Rp 17,653,300.00
Upah An. SNI ( Revisi ) 6.1.2
6.000 Oh Pekerja @ Rp. 75,000.00 = Rp 450,000.00
20.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 2,145,000.00
2.000 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216,000.00
0.300 Oh Mandor @ Rp. 108,750.00 = Rp 32,625.00
Sub total : = Rp 2,843,625.00
Total upah+bahan : = Rp 20,496,925.00

2. 1 m3 Pasang kusen pintu & jendela kayu kamper (Kayu klas II )


Bahan An. SNI ( Revisi ) 6.2.1
1.200 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 9,300,000.00
1.200 Kg Paku 10Cm @ Rp. 14,000.00 = Rp 16,800.00
1.000 Kg Lem kayu @ Rp. 36,500.00 = Rp 36,500.00
Sub total : = Rp 9,353,300.00
Upah An. SNI ( Revisi ) 6.2.2
6.000 Oh Pekerja @ Rp. 75,000.00 = Rp 450,000.00
18.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,930,500.00
2.000 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216,000.00
0.300 Oh Mandor @ Rp. 108,750.00 = Rp 32,625.00
Sub total : = Rp 2,629,125.00
Total upah+bahan : = Rp 11,982,425.00

3. 1 m3 Pasang kusen pintu & jendela kayu borneo ( Kruwing , kempas , Meranti batu )
Bahan An. SNI ( Revisi ) 6.3.1
1.200 m3 Kayu borneo, balok @ Rp. 5,600,000.00 = Rp 6,720,000.00
1.200 Kg Paku 10Cm @ Rp. 14,000.00 = Rp 16,800.00
1.000 Kg Lem kayu @ Rp. 36,500.00 = Rp 36,500.00
Sub total : = Rp 6,773,300.00
Upah An. SNI ( Revisi ) 6.3.2
6.000 Oh Pekerja @ Rp. 75,000.00 = Rp 450,000.00
18.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,930,500.00
2.000 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216,000.00
0.300 Oh Mandor @ Rp. 108,750.00 = Rp 32,625.00
Sub total : = Rp 2,629,125.00
Total upah+bahan : = Rp 9,402,425.00

PEKERJAAN PINTU
4 1 m2 Pasang pintu klamp kayu kamper
Bahan An. SNI ( Revisi ) 6.5.1
0.040 m3 Kayu kamper papan @ Rp. 8,150,000.00 = Rp 326,000.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
Sub total : = Rp 326,700.00
Upah An. SNI ( Revisi ) 6.5.2
0.350 Oh Pekerja @ Rp. 75,000.00 = Rp 26,250.00
1.050 Oh Tukang kayu @ Rp. 107,250.00 = Rp 112,612.50
0.105 Oh Kepala tukang @ Rp. 108,000.00 = Rp 11,340.00
0.018 Oh Mandor @ Rp. 108,750.00 = Rp 1,957.50
Sub total : = Rp 152,160.00
Total upah+bahan : = Rp 478,860.00
6. 1 m2 Pasang pintu klamp kayu borneo
Bahan An. SNI ( Revisi ) 6.6.1
0.036 m3 Kayu borneo papan @ Rp. 6,000,000.00 = Rp 216,000.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 48
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
Sub total : = Rp 216,700.00
Upah An. SNI ( Revisi ) 6.6.2
0.350 Oh Pekerja @ Rp. 75,000.00 = Rp 26,250.00
1.050 Oh Tukang kayu @ Rp. 107,250.00 = Rp 112,612.50
0.105 Oh Kepala tukang @ Rp. 108,000.00 = Rp 11,340.00
0.018 Oh Mandor @ Rp. 108,750.00 = Rp 1,957.50
Sub total : = Rp 152,160.00
Total upah+bahan : = Rp 368,860.00

7. 1 m2 Pasang pintu panil kayu jati


Bahan An. SNI ( Revisi ) 6.7.1
0.040 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 640,000.00
0.500 kg Lem kayu @ Rp. 36,500.00 = Rp 18,250.00
Sub total : = Rp 658,250.00
Upah An. SNI ( Revisi ) 6.7.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
3.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 321,750.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 434,587.50
Total upah+bahan : = Rp 1,092,837.50

8. 1 m2 Pasang pintu panil kayu kamper


Bahan An. SNI ( Revisi ) 6.8.1
0.040 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 326,000.00
0.500 kg Lem kayu @ Rp. 36,500.00 = Rp 18,250.00
Sub total : = Rp 344,250.00
Upah An. SNI ( Revisi ) 6.8.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
3.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 321,750.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 434,587.50
Total upah+bahan : = Rp 778,837.50

9. 1 m2 Pasang pintu & jendela kaca kayu jati


Bahan An. SNI ( Revisi ) 6.9.1
0.024 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 384,000.00
0.300 kg Lem kayu @ Rp. 36,500.00 = Rp 10,950.00
Sub total : = Rp 394,950.00
Upah An. SNI ( Revisi ) 6.9.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp 60,000.00
2.400 Oh Tukang kayu @ Rp. 107,250.00 = Rp 257,400.00
0.240 Oh Kepala tukang @ Rp. 108,000.00 = Rp 25,920.00
0.040 Oh Mandor @ Rp. 108,750.00 = Rp 4,350.00
Sub total : = Rp 347,670.00
Total upah+bahan : = Rp 742,620.00

10. 1 m2 Pasang pintu & jendela kaca kayu kamper


Bahan An. SNI ( Revisi ) 6.10.1
0.035 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 285,250.00
0.300 kg Lem kayu @ Rp. 36,500.00 = Rp 10,950.00
Sub total : = Rp 296,200.00
Upah An. SNI ( Revisi ) 6.10.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp 60,000.00
2.400 Oh Tukang kayu @ Rp. 107,250.00 = Rp 257,400.00
0.240 Oh Kepala tukang @ Rp. 108,000.00 = Rp 25,920.00
0.040 Oh Mandor @ Rp. 108,750.00 = Rp 4,350.00
Sub total : = Rp 347,670.00
Total upah+bahan : = Rp 643,870.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 49
11. 1 m2 Pasang pintu & jendela kaca kayu borneo
Bahan An. SNI ( Revisi ) 6.11.1
0.035 m3 Kayu borneo, papan @ Rp. 6,000,000.00 = Rp 210,000.00
0.300 kg Lem kayu @ Rp. 36,500.00 = Rp 10,950.00
Sub total : = Rp 220,950.00
Upah An. SNI ( Revisi ) 6.11.2
0.800 Oh Pekerja @ Rp. 75,000.00 = Rp 60,000.00
2.400 Oh Tukang kayu @ Rp. 107,250.00 = Rp 257,400.00
0.240 Oh Kepala tukang @ Rp. 108,000.00 = Rp 25,920.00
0.040 Oh Mandor @ Rp. 108,750.00 = Rp 4,350.00
Sub total : = Rp 347,670.00
Total upah+bahan : = Rp 568,620.00

12. 1 m2 Pasang pintu & jendela jalusi kayu jati


Bahan An. SNI ( Revisi ) 6.12.1
0.064 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 1,024,000.00
0.500 kg Lem kayu @ Rp. 36,500.00 = Rp 18,250.00
Sub total : = Rp 1,042,250.00
Upah An. SNI ( Revisi ) 6.12.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
3.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 321,750.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 434,587.50
Total upah+bahan : = Rp 1,476,837.50

13. 1 m2 Pasang pintu & jendela jalusi kayu kamper


Bahan An. SNI ( Revisi ) 6.13.1
0.064 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 521,600.00
0.500 kg Lem kayu @ Rp. 36,500.00 = Rp 18,250.00
Sub total : = Rp 539,850.00
Upah An. SNI ( Revisi ) 6.13.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
3.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 321,750.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 434,587.50
Total upah+bahan : = Rp 974,437.50

14. 1 m2 Pasang pintu plywood rangkap, rangka kayu jati


Bahan An. SNI ( Revisi ) 6.14.1
0.0250 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 400,000.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
0.500 kg Lem kayu @ Rp. 10,500.00 = Rp 5,250.00
1.000 Lbr Plywood (90x 220 cm)x 4 @ Rp. 86,750.00 = Rp 86,750.00
Sub total : = Rp 492,420.00
Upah An. SNI ( Revisi ) 6.14.2
0.700 Oh Pekerja @ Rp. 75,000.00 = Rp 52,500.00
2.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 225,225.00
0.210 Oh Kepala tukang @ Rp. 108,000.00 = Rp 22,680.00
0.035 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 304,211.25
Total upah+bahan : = Rp 796,631.25

15. 1 m2 Pasang pintu plywood rangkap, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.15.1
0.0196 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 159,740.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 50
0.300 Lt Lem kayu @ Rp. 10,500.00 = Rp 3,150.00
1.000 Lbr Plywood 4' x 3' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
Sub total : = Rp 206,685.00
Upah An. SNI ( Revisi ) 6.15.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
2.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 225,225.00
0.210 Oh Kepala tukang @ Rp. 108,000.00 = Rp 22,680.00
0.035 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 296,711.25
Total upah+bahan : = Rp 503,396.25

JALUSI / KREPYAK MATI.


16. 1 m2 Pasang jalusi mati kusen kayu jati
Bahan An. SNI ( Revisi ) 6.16.1
0.060 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 960,000.00
0.150 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 962,100.00
Upah An. SNI ( Revisi ) 6.16.2
0.670 Oh Pekerja @ Rp. 75,000.00 = Rp 50,250.00
2.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 214,500.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.035 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 290,156.25
Total upah+bahan : = Rp 1,252,256.25

17. 1 m2 Pasang jalusi mati kusen kayu kamper


Bahan An. SNI ( Revisi ) 6.17.1
0.060 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 489,000.00
0.150 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 491,100.00
Upah An. SNI ( Revisi ) 6.17.2
0.670 Oh Pekerja @ Rp. 75,000.00 = Rp 50,250.00
2.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 214,500.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.035 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 290,156.25
Total upah+bahan : = Rp 781,256.25

18. 1 m2 Pasang pintu plywood rangkap,rangka kayu borneo


Bahan An. SNI ( Revisi ) 6.18.1
0.0196 m3 Kayu borneo, papan @ Rp. 6,000,000.00 = Rp 117,600.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
0.300 Lt Lem kayu @ Rp. 10,500.00 = Rp 3,150.00
1.000 Lbr Plywood 4' x 3' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
Sub total : = Rp 164,545.00
Upah An. SNI ( Revisi ) 6.18.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
2.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 214,500.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 284,362.50
Total upah+bahan : = Rp 448,907.50

19. 1 m2 Pasang pintu teakwood rangkap, rangka kayu jati


Bahan An. SNI ( Revisi ) 6.19.1
0.0196 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 313,600.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 51
0.300 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 4,200.00
0.300 Lt Lem kayu @ Rp. 10,500.00 = Rp 3,150.00
1.000 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
Sub total : = Rp 364,325.00
Upah An. SNI ( Revisi ) 6.19.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
2.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 214,500.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 284,362.50
Total upah+bahan : = Rp 648,687.50

20. 1 m2 Pasang pintu teakwood rangkap, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.20.1
0.0196 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 159,740.00
0.300 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 4,200.00
0.300 Lt Lem kayu @ Rp. 10,500.00 = Rp 3,150.00
1.000 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
Sub total : = Rp 210,465.00
Upah An. SNI ( Revisi ) 6.20.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
2.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 214,500.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 284,362.50
Total upah+bahan : = Rp 494,827.50

21. 1 m2 Pasang pintu plywood & formika, rangka kayu jati


Bahan An. SNI ( Revisi ) 6.21.1
0.0250 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 400,000.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
0.800 Kg Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
1.000 Lbr Plywood 90cmx220cm x 4 @ Rp. 43,375.00 = Rp 43,375.00
0.500 Lbr Formica @ Rp. 87,500.00 = Rp 43,750.00
Sub total : = Rp 495,945.00
Upah An. SNI ( Revisi ) 6.21.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 865,398.75

22. 1 m2 Pasang pintu plywood & formika, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.22.1
0.0250 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 203,750.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
0.800 kg Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
1.000 Lbr Plywood 4' x 8' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
0.500 Lbr Formica 4' x 3' @ Rp. 87,500.00 = Rp 43,750.00
Sub total : = Rp 299,695.00
Upah An. SNI ( Revisi ) 6.21.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 52
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 669,148.75

23. 1 m2 Pasang pintu teakwood & formika, rangka kayu jati


Bahan An. SNI ( Revisi ) 6.23.1
0.0250 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 400,000.00
0.030 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 420.00
0.800 g Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
1.000 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 43,375.00 = Rp 43,375.00
0.500 Lbr Formica 4' x 8' @ Rp. 87,500.00 = Rp 43,750.00
Sub total : = Rp 495,945.00
Upah An. SNI ( Revisi ) 6.21.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 865,398.75

24. 1 m2 Pasang pintu teakwood & formika, rangka kayu kamper ( dipolitur )
Bahan An. SNI ( Revisi ) 6.24.1
0.0250 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 203,750.00
0.300 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 4,200.00
0.800 Lt Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
0.500 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 43,375.00 = Rp 21,687.50
0.500 Lt Politur @ Rp. 43,750.00 = Rp 21,875.00
0.500 Lbr Formica 4' x 8' @ Rp. 87,500.00 = Rp 43,750.00
Sub total : = Rp 303,662.50
Upah An. SNI ( Revisi ) 6.24.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 673,116.25

25. 1 m2 Pasang pintu formika double, rangka kayu jati


Bahan An. SNI ( Revisi ) 6.25.1
0.0250 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 400,000.00
0.300 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 4,200.00
0.800 Kg Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
2.000 Lbr Formica 4' x 8' @ Rp. 87,500.00 = Rp 175,000.00
Sub total : = Rp 587,600.00
Upah An. SNI ( Revisi ) 6.25.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 957,053.75

26. 1 m2 Pasang pintu formika double, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.26.1
0.0196 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 159,740.00
0.300 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 4,200.00
0.800 Kg Lem kayu @ Rp. 10,500.00 = Rp 8,400.00
2.000 Lbr Plywood 4' x 8' x 4 mm @ Rp. 87,500.00 = Rp 175,000.00
Sub total : = Rp 347,340.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 53
Upah An. SNI ( Revisi ) 6.26.2
0.850 Oh Pekerja @ Rp. 75,000.00 = Rp 63,750.00
2.550 Oh Tukang kayu @ Rp. 107,250.00 = Rp 273,487.50
0.255 Oh Kepala tukang @ Rp. 108,000.00 = Rp 27,540.00
0.043 Oh Mandor @ Rp. 108,750.00 = Rp 4,676.25
Sub total : = Rp 369,453.75
Total upah+bahan : = Rp 716,793.75

KUDA KUDA
27. 1 m3 Pasang konstruksi kuda-kuda kayu jati
Bahan An. SNI ( Revisi ) 6.27.1
1.100 m3 Kayu jati, balok @ Rp. 16,000,000.00 = Rp 17,600,000.00
15.000 Kg Besi strip @ Rp. 11,825.00 = Rp 177,375.00
5.600 Kg Paku biasa 12 Cm. @ Rp. 14,000.00 = Rp 78,400.00
Sub total : = Rp 17,855,775.00
Upah An. SNI ( Revisi ) 6.27.2
4.000 Oh Pekerja @ Rp. 75,000.00 = Rp 300,000.00
12.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,287,000.00
1.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 129,600.00
0.200 Oh Mandor @ Rp. 108,750.00 = Rp 21,750.00
Sub total : = Rp 1,738,350.00
Total upah+bahan : = Rp 19,594,125.00

28. 1 m3 Pasang konstruksi kuda-kuda kayu kamper


Bahan An. SNI ( Revisi ) 6.28.1
1.100 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 8,525,000.00
15.000 Kg Besi strip @ Rp. 11,825.00 = Rp 177,375.00
5.600 Kg Paku biasa 12 Cm. @ Rp. 14,000.00 = Rp 78,400.00
Sub total : = Rp 8,780,775.00
Upah An. SNI ( Revisi ) 6.28.2
4.000 Oh Pekerja @ Rp. 75,000.00 = Rp 300,000.00
12.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,287,000.00
1.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 129,600.00
0.200 Oh Mandor @ Rp. 108,750.00 = Rp 21,750.00
Sub total : = Rp 1,738,350.00
Total upah+bahan : = Rp 10,519,125.00

29 1 m3 Pasang konstruksi kuda-kuda kayu kruing / bengkirai / kempas.


Bahan An. SNI ( Revisi ) 6.30.1
1.100 m3 Kayu kruing, balok @ Rp. 5,600,000.00 = Rp 6,160,000.00
15.000 Kg Besi strip @ Rp. 11,825.00 = Rp 177,375.00
5.600 Kg Paku biasa 12 Cm. @ Rp. 14,000.00 = Rp 78,400.00
Sub total : = Rp 6,415,775.00
Upah An. SNI ( Revisi ) 6.30.2
4.000 Oh Pekerja @ Rp. 75,000.00 = Rp 300,000.00
12.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,287,000.00
1.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 129,600.00
0.200 Oh Mandor @ Rp. 108,750.00 = Rp 21,750.00
Sub total : = Rp 1,738,350.00
Total upah+bahan : = Rp 8,154,125.00

30 1 m3 Pasang konstruksi kuda-kuda kayu meranti.


Bahan An. SNI ( Revisi ) 6.28.1
1.100 m3 Kayu kamper, balok @ Rp. 4,200,000.00 = Rp 4,620,000.00
15.000 Kg Besi strip @ Rp. 11,825.00 = Rp 177,375.00
5.600 Kg Paku biasa 12 Cm. @ Rp. 14,000.00 = Rp 78,400.00
Sub total : = Rp 4,875,775.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 54
Upah An. SNI ( Revisi ) 6.28.2
4.000 Oh Pekerja @ Rp. 75,000.00 = Rp 300,000.00
12.000 Oh Tukang kayu @ Rp. 107,250.00 = Rp 1,287,000.00
1.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 129,600.00
0.200 Oh Mandor @ Rp. 108,750.00 = Rp 21,750.00
Sub total : = Rp 1,738,350.00
Total upah+bahan : = Rp 6,614,125.00

PASANG USUK.
31. 1 m2 Pasang kaso + reng genteng kodok kayu kamper
Bahan An. SNI ( Revisi ) 6.31.1
0.0077 m3 Kayu kamper, usuk 5/7. @ Rp. 7,700,000.00 = Rp 59,290.00
0.0046 m3 Reng 2/3 cm kayu kamper @ Rp. 5,472,000.00 = Rp 25,280.64
0.2500 Kg Paku biasa 5 Cm dan 10 @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 88,070.64
Upah An. SNI ( Revisi ) 6.31.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 107,919.39

32. 1 m2 Pasang kaso + reng genteng kodok kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.32.1
0.0077 m3 Ky. kruw/beng/kempas, us @ Rp. 5,500,000.00 = Rp 42,350.00
0.0046 m3 Reng 2/3 cm kayu kruwing@ Rp. 4,150,000.00 = Rp 19,173.00
0.2500 Kg Paku biasa 5 Cm dan 10 @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 65,023.00
Upah An. SNI ( Revisi ) 6.32.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 84,871.75

33 1 m2 Pasang kaso + reng genteng kodok kayu meranti.


Bahan An. SNI ( Revisi ) 6.32.1
0.0077 m3 Kayu meranti, usuk @ Rp. 4,400,000.00 = Rp 33,880.00
0.0046 m3 Reng 2/3 cm kayu kruwing@ Rp. 4,150,000.00 = Rp 19,173.00
0.2500 Kg Paku biasa 5 Cm dan 10 @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 56,553.00
Upah An. SNI ( Revisi ) 6.32.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 76,401.75

34 1 m2 Pasang kaso + reng genteng munier kayu jati


Bahan An. SNI ( Revisi ) 6.33.1
0.0077 m3 Kayu jati, balok / usuk. @ Rp. 15,600,000.00 = Rp 120,120.00
0.0115 m3 Reng 3/5 cm kayu jati @ Rp. 15,600,000.00 = Rp 179,400.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 303,020.00
Upah An. SNI ( Revisi ) 6.33.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 55
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 322,868.75

35 1 m2 Pasang kaso + reng genteng munier kayu kamper


Bahan An. SNI ( Revisi ) 6.34.1
0.0077 m3 Kayu kamper, usuk 5/7. @ Rp. 7,700,000.00 = Rp 59,290.00
0.0115 m3 Reng 3/5 cm kayu kruwing@ Rp. 4,150,000.00 = Rp 47,725.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 110,515.00
Upah An. SNI ( Revisi ) 6.34.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 130,363.75

36 1 m2 Pasang kaso + reng genteng beton kayu kruwing / bengkirai / kempas.


Bahan An. SNI ( Revisi ) 6.35.1
0.0077 m3 Ky. kruw/beng/kempas, us @ Rp. 5,500,000.00 = Rp 42,350.00
0.0115 m3 Reng 3/5 cm kayu kruwing@ Rp. 4,150,000.00 = Rp 47,725.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 93,575.00
Upah An. SNI ( Revisi ) 6.35.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 113,423.75

37 1 m2 Pasang kaso + reng genteng beton kayu meranti.


Bahan An. SNI ( Revisi ) 6.35.1
0.0077 m3 Kayu meranti, usuk @ Rp. 4,400,000.00 = Rp 33,880.00
0.0115 m3 Reng 3/5 cm kayu meranti @ Rp. 4,400,000.00 = Rp 50,600.00
0.2500 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 87,980.00
Upah An. SNI ( Revisi ) 6.35.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 107,828.75

38 1 m2 Pasang kaso + reng atap sirap kayu kamper


Bahan An. SNI ( Revisi ) 6.36.1
0.165 m3 Kayu kamper, usuk 5/7. @ Rp. 7,700,000.00 = Rp 1,270,500.00
0.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 1,273,300.00
Upah An. SNI ( Revisi ) 6.36.2
0.120 Oh Pekerja @ Rp. 75,000.00 = Rp 9,000.00
0.120 Oh Tukang kayu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 23,818.50
Total upah+bahan : = Rp 1,297,118.50
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 56
39 1 m2 Pasang kaso + reng atap sirap kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.37.1
0.165 m3 Ky. kruw/beng/kempas, us @ Rp. 5,500,000.00 = Rp 907,500.00
0.200 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 910,300.00
Upah An. SNI ( Revisi ) 6.37.2
0.120 Oh Pekerja @ Rp. 75,000.00 = Rp 9,000.00
0.120 Oh Tukang kayu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 23,818.50
Total upah+bahan : = Rp 934,118.50

RANGKA PLAVON / LANGIT2.


40 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu jati
Bahan An. SNI ( Revisi ) 6.38.1
0.012 m3 Kayu jati, usuk 5/7 & 4/6. @ Rp. 15,600,000.00 = Rp 187,200.00
0.100 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 188,600.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 237,518.75

41 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kamper pamjamg 4 m.


Bahan An. SNI ( Revisi ) 6.39.1
0.012 m3 Kayu kamper 5/7 - 4 mtr. @ Rp. 7,700,000.00 = Rp 92,400.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 93,800.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 142,718.75

42 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kamper potongan 5/7 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.012 m3 Kayu kamper 5/7 - 2 mtr. @ Rp. 3,950,000.00 = Rp 47,400.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 48,800.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 97,718.75
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 57
43 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.40.1
0.012 m3 Ky. kruw/beng/kempas, us @ Rp. 5,500,000.00 = Rp 66,000.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 67,400.00
Upah An. SNI ( Revisi ) 6.40.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 116,318.75

44 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu MERANTI 5/7 panjang 4 m.


Bahan An. SNI ( Revisi ) 6.39.1
0.012 m3 Kayu meranti 5/7 - 4 mtr. @ Rp. 4,400,000.00 = Rp 52,800.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 54,200.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 103,118.75

45 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu meranti potongan 5/7 - 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.012 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. 3,000,000.00 = Rp 36,000.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 37,400.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 86,318.75

46 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu jati


Bahan An. SNI ( Revisi ) 6.38.1
0.0154 m3 Kayu jati, usuk 5/7 & 4/6. @ Rp. 15,600,000.00 = Rp 240,240.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 243,040.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 297,861.25
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 58
47 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu kamper pamjamg 4 m.
Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu kamper 5/7 - 4 mtr. @ Rp. 7,700,000.00 = Rp 118,580.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 121,380.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 176,201.25

48 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu kamper potongan 5/7 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu kamper 5/7 - 2 mtr. @ Rp. 3,950,000.00 = Rp 60,830.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 63,630.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 118,451.25

49 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu kruwing / bengkirai / kempas.


Bahan An. SNI ( Revisi ) 6.40.1
0.0154 m3 Kayu meranti 5/7 - 4 mtr. @ Rp. 5,500,000.00 = Rp 84,700.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 87,500.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 142,321.25

50 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu MERANTI 5/7 panjang 4 m.


Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu meranti 5/7 - 4 mtr. @ Rp. 4,400,000.00 = Rp 67,760.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 70,560.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 125,381.25
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 59
51 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu meranti potongan 5/7 - 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. 3,000,000.00 = Rp 46,200.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 49,000.00
Upah An. SNI ( Revisi ) 6.38.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 54,821.25
Total upah+bahan : = Rp 103,821.25

52 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu jati


Bahan An. SNI ( Revisi ) 6.41.1
0.0163 m3 Kayu jati, usuk 5/7. @ Rp. 15,600,000.00 = Rp 254,280.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 257,780.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 309,282.50

53 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu kamper panjang 4mtr.- 5/7


Bahan An. SNI ( Revisi ) 6.42.1
0.0163 m3 Kayu kamper, usuk 5/7 @ Rp. 7,700,000.00 = Rp 125,510.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 129,010.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 180,512.50

54 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu kamper potongan panjang 2 mtr.- 5/7
Bahan An. SNI ( Revisi ) 6.42.1
0.0163 m3 Kayu kamper, potongan 2 @ Rp. 3,950,000.00 = Rp 64,385.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 67,885.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 119,387.50
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 60
55 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu kruwing , bemgkirai / kempas.
Bahan An. SNI ( Revisi ) 6.43.1
0.0163 m3 0 @ Rp. 5,500,000.00 = Rp 89,650.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 93,150.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 144,652.50

56 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu Meranti panjang 4 meter - 5/7.


Bahan An. SNI ( Revisi ) 6.43.1
0.0163 m3 0 @ Rp. 4,400,000.00 = Rp 71,720.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 75,220.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 126,722.50

57 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu Meranti potongan panjang 2 meter - 5/7.
Bahan An. SNI ( Revisi ) 6.43.1
0.0163 m3 Paku biasa 2" - 5" @ Rp. 3,000,000.00 = Rp 48,900.00
0.250 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 3,500.00
Sub total : = Rp 52,400.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 103,902.50

58 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu jati


Bahan An. SNI ( Revisi ) 6.41.1
0.023 m3 Kayu jati, usuk 5/7. @ Rp. 15,600,000.00 = Rp 358,800.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 360,900.00
Upah An. SNI ( Revisi ) 6.41.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 412,402.50
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 61
59 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper panjang 4mtr.- 5/7
Bahan An. SNI ( Revisi ) 6.42.1
0.023 m3 Kayu kamper, usuk 5/7 @ Rp. 7,700,000.00 = Rp 177,100.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 179,200.00
Upah An. SNI ( Revisi ) 6.42.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 230,702.50

60 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper potongan panjang 2 mtr.- 5/7
Bahan An. SNI ( Revisi ) 6.42.1
0.023 m3 Kayu kamper, potongan 2 @ Rp. 3,950,000.00 = Rp 90,850.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 92,950.00
Upah An. SNI ( Revisi ) 6.42.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 144,452.50

61 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kruwing , bemgkirai / kempas.


Bahan An. SNI ( Revisi ) 6.43.1
0.023 m3 Ky. kruw/beng/kempas, us @ Rp. 5,500,000.00 = Rp 126,500.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 128,600.00
Upah An. SNI ( Revisi ) 6.43.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 180,102.50

62 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu Meranti panjang 4 meter - 5/7.


Bahan An. SNI ( Revisi ) 6.43.1
0.023 m3 Kayu meranti 5/7 - 4 mtr. @ Rp. 4,400,000.00 = Rp 101,200.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 103,300.00
Upah An. SNI ( Revisi ) 6.43.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 154,802.50
63 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu Meranti potongan panjang 2 meter - 5/7.
Bahan An. SNI ( Revisi ) 6.43.1
0.023 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. 3,000,000.00 = Rp 69,000.00
0.150 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,100.00
Sub total : = Rp 71,100.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 62
Upah An. SNI ( Revisi ) 6.43.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.300 Oh Tukang kayu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 51,502.50
Total upah+bahan : = Rp 122,602.50

64 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu jati


Bahan An. SNI ( Revisi ) 6.44.1
0.027 m3 Kayu jati, balok @ Rp. 15,600,000.00 = Rp 421,200.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 424,000.00
Upah An. SNI ( Revisi ) 6.44.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.350 Oh Tukang kayu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 61,426.88
Total upah+bahan : = Rp 485,426.88

65 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper panjang 4 mtr Uk.5/7


Bahan An. SNI ( Revisi ) 6.45.1
0.027 m3 Kayu kamper, usuk 5/7 @ Rp. 7,700,000.00 = Rp 207,900.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 210,700.00
Upah An. SNI ( Revisi ) 6.45.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.350 Oh Tukang kayu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 61,426.88
Total upah+bahan : = Rp 272,126.88

66 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper potongan panjang 2 mtr Uk.5/7
Bahan An. SNI ( Revisi ) 6.45.1
0.027 m3 Kayu kamper, usuk 5/7 @ Rp. 3,950,000.00 = Rp 106,650.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 109,450.00
Upah An. SNI ( Revisi ) 6.45.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.350 Oh Tukang kayu @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 61,426.88
Total upah+bahan : = Rp 170,876.88

67 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu bengkirai / kruwing / kempas. 5/7


Bahan An. SNI ( Revisi ) 6.46.1
0.027 m3 Kayu borneo, usuk. @ Rp. 5,500,000.00 = Rp 148,500.00
0.200 Kg Paku biasa 7 - 10 cm @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 151,300.00
Upah An. SNI ( Revisi ) 6.46.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.350 Oh Tukang kayu @ Rp. 107,250.00 = Rp 37,537.50
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 63
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 61,426.88
Total upah+bahan : = Rp 212,726.88

PASANG LISPLANG
68 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu jati
Bahan An. SNI ( Revisi ) 6.47.1
0.0108 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 172,800.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 174,200.00
Upah An. SNI ( Revisi ) 6.47.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0050 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 31,653.75
Total upah+bahan : = Rp 205,853.75

69 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu kamper


Bahan An. SNI ( Revisi ) 6.48.1
0.0108 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 88,020.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 89,420.00
Upah An. SNI ( Revisi ) 6.47.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0050 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 31,653.75
Total upah+bahan : = Rp 121,073.75
70 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu meranti.
Bahan An. SNI ( Revisi ) 6.48.1
0.0108 m3 Kayu meranti, papan @ Rp. 5,000,000.00 = Rp 54,000.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 55,400.00
Upah An. SNI ( Revisi ) 6.47.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0050 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 31,653.75
Total upah+bahan : = Rp 87,053.75

71 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu jati


Bahan An. SNI ( Revisi ) 6.49.1
0.0110 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 176,000.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
Sub total : = Rp 176,700.00
Upah An. SNI ( Revisi ) 6.49.2
0.110 Oh Pekerja @ Rp. 75,000.00 = Rp 8,250.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 51,843.75
Total upah+bahan : = Rp 228,543.75
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 64
72 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu kamper
Bahan An. SNI ( Revisi ) 6.50.1
0.0110 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 89,650.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
Sub total : = Rp 90,350.00
Upah An. SNI ( Revisi ) 6.49.2
0.110 Oh Pekerja @ Rp. 75,000.00 = Rp 8,250.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 51,843.75
Total upah+bahan : = Rp 142,193.75

73 1 m' Pasang lisplang ukuran ( 3 x 30 ) cm, kayu meranti.


Bahan An. SNI ( Revisi ) 6.50.1
0.0110 m3 Kayu kamper, meranti. @ Rp. 5,000,000.00 = Rp 55,000.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
Sub total : = Rp 55,700.00
Upah An. SNI ( Revisi ) 6.49.2
0.110 Oh Pekerja @ Rp. 75,000.00 = Rp 8,250.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 21,600.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 51,843.75
Total upah+bahan : = Rp 107,543.75

74 1 m' Pasang lisplang ukuran 2 x ( 3 x 20 ) cm, kayu kamper


Bahan An. SNI ( Revisi ) 6.51.1
0.0145 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 118,175.00
0.060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 119,015.00
Upah An. SNI ( Revisi ) 6.51.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 167,933.75

75 1 m' Pasang lisplang ukuran 2 x ( 3 x 20 ) cm, kayu meranti.


Bahan An. SNI ( Revisi ) 6.51.1
0.0145 m3 Kayu kamper, papan @ Rp. 5,000,000.00 = Rp 72,500.00
0.060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 73,340.00
Upah An. SNI ( Revisi ) 6.51.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 48,918.75
Total upah+bahan : = Rp 122,258.75

76 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu kamper


Bahan An. SNI ( Revisi ) 6.52.1
0.0086 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 70,090.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 65
0.060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 70,930.00
Upah An. SNI ( Revisi ) 6.52.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 24,742.50
Total upah+bahan : = Rp 95,672.50

77 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu meranti.


Bahan An. SNI ( Revisi ) 6.52.1
0.0086 m3 Kayu kamper, papan @ Rp. 5,000,000.00 = Rp 43,000.00
0.060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 43,840.00
Upah An. SNI ( Revisi ) 6.52.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 24,742.50
Total upah+bahan : = Rp 68,582.50

79 1 m' Pasang lisplang ukuran 2 x ( 2 x 20 ) cm, kayu kruwing / bengkirai / kempas.


Bahan An. SNI ( Revisi ) 6.53.1
0.0088 m3 Kayu borneo, papan @ Rp. 6,000,000.00 = Rp 52,800.00
0.060 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 840.00
Sub total : = Rp 53,640.00
Upah An. SNI ( Revisi ) 6.53.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.050 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 24,742.50
Total upah+bahan : = Rp 78,382.50

DINDING PEMISAH KAYU / TRIPLEKS


79 1 m2 Pasang rangka dan dinding pemisah (60 x 120 ) Cm kayu kamper
Bahan An. SNI ( Revisi ) 6.54.1
0.0195 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 151,125.00
0.007 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 57,050.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 209,575.00
Upah An. SNI ( Revisi ) 6.54.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.450 Oh Tukang kayu @ Rp. 107,250.00 = Rp 48,262.50
0.045 Oh Kepala tukang @ Rp. 108,000.00 = Rp 4,860.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 72,528.75
Total upah+bahan : = Rp 282,103.75

80 1 m2 Pasang rangka dan dinding pemisah (60 x 120) Cm kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.55.1
0.0195 m3 Kayu , balok @ Rp. 5,600,000.00 = Rp 109,200.00
0.007 m3 Kayu , papan @ Rp. 6,000,000.00 = Rp 42,000.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 66
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 152,600.00
Upah An. SNI ( Revisi ) 6.55.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.450 Oh Tukang kayu @ Rp. 107,250.00 = Rp 48,262.50
0.045 Oh Kepala tukang @ Rp. 108,000.00 = Rp 4,860.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 72,528.75
Total upah+bahan : = Rp 225,128.75

81 1 m2 Pasang rangka dan dinding pemisah ( 60 x 120) kayu meranti.


Bahan An. SNI ( Revisi ) 6.54.1
0.0195 m3 Kayu meranti, balok @ Rp. 4,200,000.00 = Rp 81,900.00
0.007 m3 Kayu meranti, papan @ Rp. 5,000,000.00 = Rp 35,000.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
Sub total : = Rp 118,300.00
Upah An. SNI ( Revisi ) 6.54.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.450 Oh Tukang kayu @ Rp. 107,250.00 = Rp 48,262.50
0.045 Oh Kepala tukang @ Rp. 108,000.00 = Rp 4,860.00
0.075 Oh Mandor @ Rp. 108,750.00 = Rp 8,156.25
Sub total : = Rp 72,528.75
Total upah+bahan : = Rp 190,828.75

82 1 m2 Pasang dinding pemisah tripleks 4mm rangkap, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.56.1
0.0280 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 217,000.00
0.150 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 2,100.00
0.560 Lt Lem kayu @ Rp. 36,500.00 = Rp 20,440.00
0.860 Lbr Tripleks 120 x 240 Cm x @ Rp. 88,500.00 = Rp 76,110.00
Sub total : = Rp 98,650.00
Upah An. SNI ( Revisi ) 6.56.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 185,567.50

83 1 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper


Bahan An. SNI ( Revisi ) 6.56.1
0.0280 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 217,000.00
0.150 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 2,100.00
0.560 Lt Lem kayu @ Rp. 36,500.00 = Rp 20,440.00
0.860 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 86,750.00 = Rp 74,605.00
Sub total : = Rp 97,145.00
Upah An. SNI ( Revisi ) 6.56.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 184,062.50
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 67
84 1 m2 Pasang dinding pemisah plywood / formica rangkap, rangka kayu kamper
Bahan An. SNI ( Revisi ) 6.57.1
0.0280 m3 Kayu kamper, balok @ Rp. 7,750,000.00 = Rp 217,000.00
0.150 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 2,100.00
0.560 Lt Lem kayu @ Rp. 36,500.00 = Rp 20,440.00
0.860 Lbr Plywood / formika. @ Rp. 87,500.00 = Rp 75,250.00
Sub total : = Rp 97,790.00
Upah An. SNI ( Revisi ) 6.57.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 184,707.50

PASANG DINDING LAMBRESIRING


85 1 m2 Pasang dinding lambriziring dari papan jati
Bahan An. SNI ( Revisi ) 6.58.1
0.0070 m3 Kayu jati, balok @ Rp. 16,000,000.00 = Rp 112,000.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 1,400.00
0.150 Kg Paku skrup 3,5" @ Rp. 23,000.00 = Rp 3,450.00
Sub total : = Rp 116,850.00
Upah An. SNI ( Revisi ) 6.58.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
1.800 Oh Tukang kayu @ Rp. 107,250.00 = Rp 193,050.00
0.180 Oh Kepala tukang @ Rp. 108,000.00 = Rp 19,440.00
0.030 Oh Mandor @ Rp. 108,750.00 = Rp 3,262.50
Sub total : = Rp 260,752.50
Total upah+bahan : = Rp 377,602.50

86 1 m' Pasang list plafond, kayu profil


Bahan An. SNI ( Revisi ) 6.60.1
1.050 m' Kayu profil @ Rp. 9,000.00 = Rp 9,450.00
Sub total : = Rp 9,450.00
Upah An. SNI ( Revisi ) 6.60.2
0.021 Oh Pekerja @ Rp. 75,000.00 = Rp 1,575.00
0.021 Oh Tukang kayu @ Rp. 107,250.00 = Rp 2,252.25
0.002 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 4,152.00
Total upah+bahan : = Rp 13,602.00

87 1 m' Pasang list plafond, kayu kamper 1/5.


Bahan An. SNI ( Revisi ) 6.60.1
1.050 m' Kayu profil @ Rp. 6,000.00 = Rp 6,300.00
Sub total : = Rp 6,300.00
Upah An. SNI ( Revisi ) 6.60.2
0.021 Oh Pekerja @ Rp. 75,000.00 = Rp 1,575.00
0.021 Oh Tukang kayu @ Rp. 107,250.00 = Rp 2,252.25
0.002 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 4,152.00
Total upah+bahan : = Rp 10,452.00

D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007.. Halaman : 68
PEKERJAAN PENUTUP PLAVON
1. 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 6 mm
Bahan An. SNI ( Revisi ) 6.1.1
1.100 Lbr Asbes langit-langit tbl 6 mm @ Rp. 20,500.00 = Rp 22,550.00
0.010 Kg Paku @ Rp. 14,000.00 = Rp 140.00
Sub total : = Rp 22,690.00
Upah An. SNI ( Revisi ) 6.1.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.070 Oh Tukang kayu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0040 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
Sub total : = Rp 10,948.50
Total upah+bahan : = Rp 33,638.50

2. 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.2.1
1.100 Lbr Asbes langit-langit tbl 5 mm @ Rp. 14,250.00 = Rp 15,675.00
0.010 Kg Paku @ Rp. 23,000.00 = Rp 230.00
Sub total : = Rp 15,905.00
Upah An. SNI ( Revisi ) 6.2.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.070 Oh Tukang kayu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0040 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
Sub total : = Rp 10,948.50
Total upah+bahan : = Rp 26,853.50

3 1 m2 Pasang langit-langit calsibord ( 1.00 x 1.00 ) m, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.2.1
1.100 Lbr Asbes langit-langit tbl 5 mm @ Rp. 23,000.00 = Rp 25,300.00
0.010 Kg Paku @ Rp. 23,000.00 = Rp 230.00
Sub total : = Rp 25,530.00
Upah An. SNI ( Revisi ) 6.2.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.070 Oh Tukang kayu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0040 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
Sub total : = Rp 10,948.50
Total upah+bahan : = Rp 36,478.50

4 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 4 mm


Bahan An. SNI ( Revisi ) 6.3.1
1.100 Lbr Asbes langit-langit tbl 4 mm @ Rp. 29,000.00 = Rp 31,900.00
0.010 Kg Paku @ Rp. 23,000.00 = Rp 230.00
Sub total : = Rp 32,130.00
Upah An. SNI ( Revisi ) 6.3.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.070 Oh Tukang kayu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0040 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
Sub total : = Rp 10,948.50
Total upah+bahan : = Rp 43,078.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 66
5 1 m2 Pasang langit-langit asbes ( 1.00 x 1.00 ) m, tebal 3.5 mm
Bahan An. SNI ( Revisi ) 6.4.1
1.100 Lbr Asbes langit-langit tbl 3.5 mm @ Rp. 27,500.00 = Rp 30,250.00
0.010 Kg Paku @ Rp. 23,000.00 = Rp 230.00
Sub total : = Rp 30,480.00
Upah An. SNI ( Revisi ) 6.4.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.070 Oh Tukang kayu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.0040 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
Sub total : = Rp 10,948.50
Total upah+bahan : = Rp 41,428.50
6. 1 m2 Pasang langit-langit akustik ( 30 x 60 ) cm
Bahan An. SNI ( Revisi ) 6.6.1
5.800 Lbr Akustik ukuran 30 x 60 cm @ Rp. 10,750.00 = Rp 62,350.00
0.050 Kg Paku @ Rp. 23,000.00 = Rp 1,150.00
Sub total : = Rp 63,500.00
Upah An. SNI ( Revisi ) 6.6.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 83,348.75

7. 1 m2 Pasang langit-langit akustik ( 60 x 120 ) cm


Bahan An. SNI ( Revisi ) 6.7.1
1.500 Lbr Akustik arm strong 60 x 120 cm @ Rp. 39,500.00 = Rp 59,250.00
0.050 Kg Paku @ Rp. 23,000.00 = Rp 1,150.00
Sub total : = Rp 60,400.00
Upah An. SNI ( Revisi ) 6.7.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 19,848.75
Total upah+bahan : = Rp 80,248.75

8. 1 m2 Pasang langit-langit plywood ( 30 x 60 ) cm, tebal 4 mm


Bahan An. SNI ( Revisi ) 6.8.1
0.360 Lbr Plywood 4' x 8' x 4 mm @ Rp. 88,600.00 = Rp 31,896.00
0.030 Kg Paku @ Rp. 23,000.00 = Rp 690.00
Sub total : = Rp 32,586.00
Upah An. SNI ( Revisi ) 6.8.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0035 Oh Mandor @ Rp. 108,750.00 = Rp 380.63
Sub total : = Rp 17,435.63
Total upah+bahan : = Rp 50,021.63

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 67
9. 1 m2 Pasang langit-langit plywood ( 30 x 60 ) cm, tebal 4 mm
Bahan An. SNI ( Revisi ) 6.9.1
0.360 Lbr Plywood 4' x 8' x 6 mm @ Rp. 625,000.00 = Rp 225,000.00
0.030 Kg Paku @ Rp. 23,000.00 = Rp 690.00
Sub total : = Rp 225,690.00
Upah An. SNI ( Revisi ) 6.9.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0035 Oh Mandor @ Rp. 108,750.00 = Rp 380.63
Sub total : = Rp 17,435.63
Total upah+bahan : = Rp 243,125.63

10. 1 m2 Pasang langit-langit plywood ( 60 x 120 ) cm, tebal 4 mm


Bahan An. SNI ( Revisi ) 6.10.1
0.375 Lbr Plywood 4' x 8' x 4 mm @ Rp. 625,000.00 = Rp 234,375.00
0.030 Kg Paku @ Rp. 23,000.00 = Rp 690.00
Sub total : = Rp 235,065.00
Upah An. SNI ( Revisi ) 6.10.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0035 Oh Mandor @ Rp. 108,750.00 = Rp 380.63
Sub total : = Rp 17,435.63
Total upah+bahan : = Rp 252,500.63
11 1 m2 Pasang langit-langit tripleks ( 60 x 120 ) cm, tebal 6 mm
Bahan An. SNI ( Revisi ) 6.13.1
0.375 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 99,000.00 = Rp 37,125.00
0.030 Kg Paku @ Rp. 23,000.00 = Rp 690.00
Sub total : = Rp 37,815.00
Upah An. SNI ( Revisi ) 6.13.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0035 Oh Mandor @ Rp. 108,750.00 = Rp 380.63
Sub total : = Rp 17,435.63
Total upah+bahan : = Rp 55,250.63

12 1 m2 Pasang langit-langit lat kayu jati


Bahan An. SNI ( Revisi ) 6.14.1
0.024 m3 Kayu jati, papan @ Rp. 16,000,000.00 = Rp 384,000.00
0.010 Kg Paku @ Rp. 14,000.00 = Rp 140.00
0.050 Kg Paku sekrup @ Rp. 23,000.00 = Rp 1,150.00
Sub total : = Rp 385,290.00
Upah An. SNI ( Revisi ) 6.14.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 472,207.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 68
13 1 m2 Pasang langit-langit Lat kayu ramin
Bahan An. SNI ( Revisi ) 6.15.1
0.024 m3 Kayu ramin @ Rp. 6,500,000.00 = Rp 156,000.00
0.010 Kg Paku @ Rp. 14,000.00 = Rp 140.00
0.050 Kg Paku sekrup @ Rp. 23,000.00 = Rp 1,150.00
Sub total : = Rp 157,290.00
Upah An. SNI ( Revisi ) 6.15.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 244,207.50

14 1 m2 Pasang langit-langit lat kayu kamper


Bahan An. SNI ( Revisi ) 6.16.1
0.024 m3 Kayu kamper, papan @ Rp. 8,150,000.00 = Rp 195,600.00
0.010 Kg Paku @ Rp. 14,000.00 = Rp 140.00
0.050 Kg Paku sekrup @ Rp. 23,000.00 = Rp 1,150.00
Sub total : = Rp 196,890.00
Upah An. SNI ( Revisi ) 6.16.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 86,917.50
Total upah+bahan : = Rp 283,807.50

15 1 m2 Pasang langit-langit soft board


Bahan An. SNI ( Revisi ) 6.17.1
0.350 Lbr Soft board 4' x 8' x 4mm @ Rp. 35,000.00 = Rp 12,250.00
10.000 Bh Paku @ Rp. 25,000.00 = Rp 250,000.00
Sub total : = Rp 262,250.00
Upah An. SNI ( Revisi ) 6.17.2
0.600 Oh Pekerja @ Rp. 75,000.00 = Rp 45,000.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.003 Oh Mandor @ Rp. 108,750.00 = Rp 326.25
Sub total : = Rp 57,131.25
Total upah+bahan : = Rp 319,381.25
16 1 m2 Pasang langit-langit akustik 60 x 120 cm + rangka alluminium
Bahan An. SNI ( Revisi ) 6.18.1
3.600 m' Profil alluminium T @ Rp. 12,500.00 = Rp 45,000.00
0.150 Kg Kawat seng polos @ Rp. 18,200.00 = Rp 2,730.00
1.000 Bh Ramset/dinabolt @ Rp. 750.00 = Rp 750.00
1.500 Lbr Akustik arm strong 60x120 cm @ Rp. 39,500.00 = Rp 59,250.00
Sub total : = Rp 107,730.00
Upah An. SNI ( Revisi ) 6.18.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 53,625.00
0.050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,400.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 71,090.63
Total upah+bahan : = Rp 178,820.63
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 69
17 1 m' Pasang list langit-langit kayu profil
Bahan An. SNI ( Revisi ) 6.19.1
1.100 m' List kayu profil @ Rp. 9,000.00 = Rp 9,900.00
0.010 Kg Paku @ Rp. 14,000.00 = Rp 140.00
Sub total : = Rp 10,040.00
Upah An. SNI ( Revisi ) 6.19.2
0.050 Oh Pekerja @ Rp. 75,000.00 = Rp 3,750.00
0.050 Oh Tukang kayu @ Rp. 107,250.00 = Rp 5,362.50
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.003 Oh Mandor @ Rp. 108,750.00 = Rp 326.25
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 20,018.75

18 1 m2 Pasang langit-langit gypsum board, tebal 9 mm


Bahan An. SNI ( Revisi ) 6.24.1
0.364 Lbr Gypsum board ( 120x240x9 mm ) @ Rp. 115,000.00 = Rp 41,860.00
0.110 Kg Paku sekrup @ Rp. 23,000.00 = Rp 2,530.00
Sub total : = Rp 44,390.00
Upah An. SNI ( Revisi ) 6.24.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.050 Oh Tukang kayu @ Rp. 107,250.00 = Rp 5,362.50
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.0050 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 13,946.25
Total upah+bahan : = Rp 58,336.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 70
PEKERJAAN PENUTUP ATAP
1. 1 m2 Pasang atap genteng plenthong kecil (lokal)
Bahan An. SNI ( Revisi ) 6.1.1
25.000 Bh Genteng plenthong @ Rp. 2,000.00 = Rp 50,000.00
Sub total : = Rp 50,000.00
Upah An. SNI ( Revisi ) 6.1.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.075 Oh Tukang kayu @ Rp. 108,000.00 = Rp 8,100.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 21,084.00
Total upah+bahan : = Rp 71,084.00

2. 1 m2 Pasang atap genteng kodok/glazzur


Bahan An. SNI ( Revisi ) 6.2.1
25.000 Bh Genteng kodok @ Rp. 2,150.00 = Rp 53,750.00
Sub total : = Rp 53,750.00
Upah An. SNI ( Revisi ) 6.2.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.075 Oh Tukang kayu @ Rp. 108,000.00 = Rp 8,100.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 21,084.00
Total upah+bahan : = Rp 74,834.00

3. 1 m2 Pasang atap genteng plenthong super/besar ex kanmuri


Bahan An. SNI ( Revisi ) 6.3.1
12.000 Bh Genteng plenthong super @ Rp. 3,250.00 = Rp 39,000.00
Sub total : = Rp 39,000.00
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 25,080.00
Total upah+bahan : = Rp 64,080.00

4 1 m2 Pasang atap genteng Glazur Kanmuri / KIA.


Bahan An. SNI ( Revisi ) 6.3.1
12.000 Bh Genteng plenthong super @ Rp. 12,500.00 = Rp 150,000.00
Sub total : = Rp 150,000.00
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 25,080.00
Total upah+bahan : = Rp 175,080.00

5 1 m2 Pasang atap genteng bambe / good year / Jatiwangi type Alto.Kw 1.


Bahan An. SNI ( Revisi ) 6.3.1
21.000 Bh Genteng plenthong super @ Rp. 3,900.00 = Rp 81,900.00
Sub total : = Rp 81,900.00
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 71
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 25,080.00
Total upah+bahan : = Rp 106,980.00

6 1 m2 Pasang atap genteng model Kaang pilang .Kw 1.


Bahan An. SNI ( Revisi ) 6.3.1
25.000 Bh Genteng model krg.pilang @ Rp. 2,000.00 = Rp 50,000.00
Sub total : = Rp 50,000.00
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 25,080.00
Total upah+bahan : = Rp 75,080.00

7 1 m2 Pasang atap genteng Nglayur .Kw 1.


Bahan An. SNI ( Revisi ) 6.3.1
25.000 Bh Genteng nglayur. @ Rp. 1,550.00 = Rp 38,750.00
Sub total : = Rp 38,750.00
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 25,080.00
Total upah+bahan : = Rp 63,830.00

8 1 m' Pasang genteng bubung plenthong kecil


Bahan An. SNI ( Revisi ) 6.4.1
5.000 Bh Genteng bubung plenthong kecil @ Rp. 3,500.00 = Rp 17,500.00
8.000 Kg Semen portland @ Rp. 1,525.00 = Rp 12,200.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 35,300.00
Upah An. SNI ( Revisi ) 6.4.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 53,977.50
Total upah+bahan : = Rp 89,277.50

9 1 m' Pasang genteng bubung kodok glazzur


Bahan An. SNI ( Revisi ) 6.5.1
5.000 Bh Genteng bubung kodok @ Rp. 7,000.00 = Rp 35,000.00
8.000 Kg Semen portland @ Rp. 1,525.00 = Rp 12,200.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 52,800.00
Upah An. SNI ( Revisi ) 6.5.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 53,977.50
Total upah+bahan : = Rp 106,777.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 72
10 1 m' Pasang genteng bubung plenthong besar
Bahan An. SNI ( Revisi ) 6.6.1
4.000 Bh Genteng bubung plenthong besar @ Rp. 8,250.00 = Rp 33,000.00
8.000 Kg Semen portland @ Rp. 1,525.00 = Rp 12,200.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 50,800.00
Upah An. SNI ( Revisi ) 6.6.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 53,977.50
Total upah+bahan : = Rp 104,777.50

11 1 m2 Pasang genteng bubungan bambe / good year / Jatiwangi type Alto.Kw 1.


Bahan An. SNI ( Revisi ) 6.4.1
5.000 Bh Genteng bubung good year. @ Rp. 8,500.00 = Rp 42,500.00
8.000 Kg Semen portland @ Rp. 1,525.00 = Rp 12,200.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 60,300.00
Upah An. SNI ( Revisi ) 6.4.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 53,977.50
Total upah+bahan : = Rp 114,277.50

12 1 m2 Pasang genteng bubungan Galazur ex Kanmuri / KIA.


Bahan An. SNI ( Revisi ) 6.4.1
5.000 Bh Genteng bubung good year. @ Rp. 12,650.00 = Rp 63,250.00
8.000 Kg Semen portland @ Rp. 1,525.00 = Rp 12,200.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
Sub total : = Rp 81,050.00
Upah An. SNI ( Revisi ) 6.4.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.002 Oh Mandor @ Rp. 108,750.00 = Rp 217.50
Sub total : = Rp 53,977.50
Total upah+bahan : = Rp 135,027.50

13 1 m2 Pasang atap genteng beton


Bahan An. SNI ( Revisi ) 6.30.1
11.000 Bh Genteng beton @ Rp. 7,400.00 = Rp 81,400.00
0.030 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 420.00
Sub total : = Rp 81,820.00
Upah An. SNI ( Revisi ) 6.30.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.100 Oh Tukang kayu @ Rp. 108,000.00 = Rp 10,800.00
0.010 Oh Kepala tukang @ Rp. 108,750.00 = Rp 1,087.50
0.010 Oh Mandor @ Rp. 2,750.00 = Rp 27.50
Sub total : = Rp 26,915.00
Total upah+bahan : = Rp 108,735.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 73
14 1 m' Pasang nok genteng beton
Bahan An. SNI ( Revisi ) 6.34.1
3.500 Bh Nok genteng beton @ Rp. 7,500.00 = Rp 26,250.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
10.800 Kg Semen abu-abu @ Rp. 1,525.00 = Rp 16,470.00
0.032 m3 Pasir pasang @ Rp. 175,000.00 = Rp 5,600.00
0.250 Kg Semen warna @ Rp. 9,500.00 = Rp 2,375.00
Sub total : = Rp 51,395.00
Upah An. SNI ( Revisi ) 6.34.2
0.400 Oh Pekerja @ Rp. 75,000.00 = Rp 30,000.00
0.200 Oh Tukang kayu @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.020 Oh Mandor @ Rp. 108,750.00 = Rp 2,175.00
Sub total : = Rp 55,935.00
Total upah+bahan : = Rp 107,330.00

15 1 m2 Pasang atap asbes gelombang besar.


Bahan An. SNI ( Revisi ) 6.8.1
1.200 M2 Asbes glmbg @ Rp. 38,600.00 = Rp 46,320.00
0.120 Kg Paku pancing 60 x 230 @ Rp. 23,000.00 = Rp 2,760.00
Sub total : = Rp 49,080.00
Upah An. SNI ( Revisi ) 6.8.2
0.140 Oh Pekerja @ Rp. 75,000.00 = Rp 10,500.00
0.075 Oh Tukang kayu @ Rp. 108,000.00 = Rp 8,100.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 20,334.00
Total upah+bahan : = Rp 69,414.00

16 1 m2 Pasang atap asbes gelombang kecil.


Bahan An. SNI ( Revisi ) 6.9.1
1.200 M2 Asbes glmbg @ Rp. 25,800.00 = Rp 30,960.00
0.120 Kg Paku pancing 60 x 230 @ Rp. 23,000.00 = Rp 2,760.00
Sub total : = Rp 33,720.00
Upah An. SNI ( Revisi ) 6.9.2
0.140 Oh Pekerja @ Rp. 75,000.00 = Rp 10,500.00
0.075 Oh Tukang kayu @ Rp. 108,000.00 = Rp 8,100.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 20,334.00
Total upah+bahan : = Rp 54,054.00

17 1 m1 Pasang BUBUNGAN asbes gelombang besar


Bahan An. SNI ( Revisi ) 6.9.1
1.000 Bh Nok asbes gel.besar @ Rp. 79,750.00 = Rp 79,750.00
4.000 Bh skrup kayu/paku payung @ Rp. 50.00 = Rp 200.00
Sub total : = Rp 79,950.00
Upah An. SNI ( Revisi ) 6.9.2
0 Oh Pekerja @ Rp. 75,000.00 = Rp 375.00
0 Oh Tukang kayu @ Rp. 108,000.00 = Rp 11,880.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 14,102.25
Total upah+bahan : = Rp 94,052.25

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 74
18 1 m1 Pasang BUBUNGAN asbes gelombang kecil..
Bahan An. SNI ( Revisi ) 6.9.1
1.000 Bh Nok asbes gel.besar @ Rp. 61,700.00 = Rp 61,700.00
4.000 Bh skrup kayu/paku payung @ Rp. 50.00 = Rp 200.00
Sub total : = Rp 61,900.00
Upah An. SNI ( Revisi ) 6.9.2
0 Oh Pekerja @ Rp. 75,000.00 = Rp 375.00
0 Oh Tukang kayu @ Rp. 108,000.00 = Rp 11,880.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
Sub total : = Rp 14,102.25
Total upah+bahan : = Rp 76,002.25

19 1 m2 Pasang atap seng Galvalum type DJLS 45 Warna


Bahan An. SNI
1 M2 1 M! SENG GALVALUM warna.
( Lebar efektif 73 Cm.) @ Rp. 175,000.00 = Rp 239,750.00
4.000 Bh Paku rifet @ Rp. 300.00 = Rp 1,200.00
Sub total : = Rp 240,950.00
Upah An. SNI
0 Oh Pekerja @ Rp. 75,000.00 = Rp 1,575.00
0 Oh Tukang kayu @ Rp. 108,000.00 = Rp 1,188.00
0 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
1 Ls Biaya mekanik/peralatan @ Rp. 2,650.00 Rp 2,650.00
Sub total : = Rp 5,848.00
Total upah+bahan : = Rp 246,798.00

20 1 m2 Pasang atap seng Galvalum type DJLS 45 Warna


Bahan An. SNI
1 M2 1 M! SENG GALVALUM warna.
( Lebar efektif 73 Cm.) @ Rp. 185,000.00 = Rp 253,450.00
4.000 Bh Paku rifet @ Rp. 300.00 = Rp 1,200.00
Sub total : = Rp 254,650.00
Upah An. SNI
0 Oh Pekerja @ Rp. 75,000.00 = Rp 1,575.00
0 Oh Tukang kayu @ Rp. 108,000.00 = Rp 1,188.00
0 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
1 Ls Biaya mekanik/peralatan @ Rp. 2,650.00 Rp 2,650.00
Sub total : = Rp 5,848.00
Total upah+bahan : = Rp 260,498.00

21 1 m2 Pasang atap POLYCARBONAT.


Bahan An. SNI
1 m2 Polycarbonat warna. @ Rp. 100,000.00 Rp 115,000.00
4.000 Bh Paku rifet @ Rp. 300.00 = Rp 1,200.00
Sub total : = Rp 116,200.00
Upah An. SNI
0 Oh Pekerja @ Rp. 75,000.00 = Rp 1,575.00
0 Oh Tukang PASANG @ Rp. 108,000.00 = Rp 1,188.00
0 Oh Mandor @ Rp. 108,750.00 = Rp 435.00
1 Ls Biaya mekanik/peralatan @ Rp. 2,750.00 Rp 2,750.00
Sub total : = Rp 5,948.00
Total upah+bahan : = Rp 122,148.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 75
22 1 m2 Pasang atap sirap
Bahan An. SNI ( Revisi ) 6.33.1
60.000 Bh Genteng sirap @ Rp. 75,000.00 = Rp 4,500,000.00
0.200 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 2,800.00
Sub total : = Rp 4,502,800.00
Upah An. SNI ( Revisi ) 6.33.2
0.166 Oh Pekerja @ Rp. 75,000.00 = Rp 12,450.00
0.250 Oh Tukang kayu @ Rp. 108,000.00 = Rp 27,000.00
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 43,020.00
Total upah+bahan : = Rp 4,545,820.00

23 1 m' Pasang nok sirap


Bahan An. SNI ( Revisi ) 6.37.1
0.400 Lbr Seng plat 3" x 6" bjls 28 @ Rp. 76,400.00 = Rp 30,560.00
0.060 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 840.00
0.050 Kg Paku biasa 2" - 5" @ Rp. 14,000.00 = Rp 700.00
0.004 m3 Kayu borneo, papan tebal 3 cm @ Rp. 6,000,000.00 = Rp 24,000.00
Sub total : = Rp 56,100.00
Upah An. SNI ( Revisi ) 6.37.2
0.125 Oh Pekerja @ Rp. 75,000.00 = Rp 9,375.00
0.250 Oh Tukang kayu @ Rp. 108,000.00 = Rp 27,000.00
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 39,727.50
Total upah+bahan : = Rp 95,827.50

24 1 m2 Pasang atap seng gelombang BJLS 28


Bahan An. SNI ( Revisi ) 6.38.1
0.700 Lbr Seng glmbg 3" x 6" bjls 28 @ Rp. 95,200.00 = Rp 66,640.00
0.020 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 280.00
Sub total : = Rp 66,920.00
Upah An. SNI ( Revisi ) 6.38.2
0.120 Oh Pekerja @ Rp. 75,000.00 = Rp 9,000.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 16,780.50
Total upah+bahan : = Rp 83,700.50

25 1 m2 Pasang atap nok seng BJLS 28


Bahan An. SNI ( Revisi ) 6.39.1
0.300 Lbr Seng plat 3" x 6" bjls 28 @ Rp. 95,200.00 = Rp 28,560.00
0.040 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 560.00
Sub total : = Rp 29,120.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.070 Oh Tukang kayu @ Rp. 108,000.00 = Rp 7,560.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 20,326.50
Total upah+bahan : = Rp 49,446.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 76

26 1 m2 Pasang atap seng gelombang BJLS 30


Bahan An. SNI ( Revisi ) 6.38.1
0.700 Lbr Seng glmbg 3" x 6" bjls 28 @ Rp. 98,400.00 = Rp 68,880.00
0.020 Kg Paku biasa 1/2" - 1" @ Rp. 95,200.00 = Rp 1,904.00
Sub total : = Rp 70,784.00
Upah An. SNI ( Revisi ) 6.38.2
0.120 Oh Pekerja @ Rp. 75,000.00 = Rp 9,000.00
0.060 Oh Tukang kayu @ Rp. 108,000.00 = Rp 6,480.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 16,780.50
Total upah+bahan : = Rp 87,564.50

27 1 m2 Pasang atap nok seng BJLS 30


Bahan An. SNI ( Revisi ) 6.39.1
0.300 Lbr Seng plat 3" x 6" bjls 28 @ Rp. 98,400.00 = Rp 29,520.00
0.040 Kg Paku biasa 1/2" - 1" @ Rp. 95,200.00 = Rp 3,808.00
Sub total : = Rp 33,328.00
Upah An. SNI ( Revisi ) 6.39.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.070 Oh Tukang kayu @ Rp. 108,000.00 = Rp 7,560.00
0.008 Oh Kepala tukang @ Rp. 108,000.00 = Rp 864.00
0.006 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
Sub total : = Rp 20,326.50
Total upah+bahan : = Rp 53,654.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 77
PEKERJAAN BESI & ALUMINIUM
1. 1 Kg Pasang rangka atap baja
Bahan An. SNI ( Revisi ) 6.1.1
1.150 Kg Besi profil WF @ Rp. 11,825.00 = Rp 13,598.75
0.080 Kg Meni besi @ Rp. 24,500.00 = Rp 1,960.00
Sub total : = Rp 15,558.75
Upah An. SNI ( Revisi ) 6.1.2
1 0.006 Oh Pekerja @ Rp. 75,000.00 = Rp 450.00
6 0.060 Oh Tukang besi @ Rp. 107,250.00 = Rp 6,435.00
1 0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0 0.0003 Oh Mandor @ Rp. 108,750.00 = Rp 32.63
Sub total : = Rp 7,565.63
Total upah+bahan : = Rp 23,124.38

2. 1 m2 Pasang pintu besi plat baja tabal 2mm rangkap, rangka baja siku 30.30.3.
Bahan An. SNI ( Revisi ) 6.2.1
15.000 Kg Besi siku 30.30.3 @ Rp. 11,825.00 = Rp 177,375.00
32.800 Kg Besi plat baja tebal 2mm. @ Rp. 11,825.00 = Rp 387,860.00
0.050 Kg Kawat las. @ Rp. 37,500.00 = Rp 1,875.00
Sub total : = Rp 567,110.00
Upah An. SNI ( Revisi ) 6.2.2
0.650 Oh Tukang besi @ Rp. 107,250.00 = Rp 69,712.50
0.650 Oh Pekerja @ Rp. 75,000.00 = Rp 48,750.00
0.065 Oh Kepala tukang @ Rp. 108,000.00 = Rp 7,020.00
0.032 Oh Mandor @ Rp. 108,750.00 = Rp 3,480.00
Sub total : = Rp 128,962.50
Total upah+bahan : = Rp 696,072.50

3. 1 m2 Pasang jendela besi


Bahan An. SNI ( Revisi ) 6.3.1
1.000 m2 Jendela besi @ Rp. 265,000.00 = Rp 265,000.00
Sub total : = Rp 265,000.00
Upah An. SNI ( Revisi ) 6.3.2
1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00
0.105 Oh Kepala tukang @ Rp. 108,000.00 = Rp 11,340.00
0.00525 Oh Mandor @ Rp. 108,750.00 = Rp 570.94
Sub total : = Rp 203,273.44
Total upah+bahan : = Rp 468,273.44

4 1 m2 Pasang teraliS besi


Bahan An. SNI ( Revisi ) 6.12.1
11.500 m' Besi strip 2 x 3 @ Rp. 16,750.00 = Rp 192,625.00
Sub total : = Rp 192,625.00
Upah An. SNI ( Revisi ) 6.12.2
1.200 Oh Tukang las @ Rp. 107,250.00 = Rp 128,700.00
1.200 Oh Pekerja @ Rp. 75,000.00 = Rp 90,000.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0006 Oh Mandor @ Rp. 108,750.00 = Rp 65.25
Sub total : = Rp 220,061.25
Total upah+bahan : = Rp 412,686.25

5 1 m2 Pasang kawat harmonika


Bahan An. SNI ( Revisi ) 6.13.1
1.100 m2 Kawat harmonika @ Rp. 20,000.00 = Rp 22,000.00
0.020 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 280.00
0.0018 m3 Kayu kamper, reng @ Rp. 5,472,000.00 = Rp 9,849.60
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 78
Sub total : = Rp 32,129.60
Upah An. SNI ( Revisi ) 6.13.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 108,000.00 = Rp 10,800.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0005 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 19,434.38
Total upah+bahan : = Rp 51,563.98

6 1 m2 Pasang kawat nyamuk


Bahan An. SNI ( Revisi ) 6.14.1
1.100 m2 Kawat nyamuk @ Rp. 18,000.00 = Rp 19,800.00
0.020 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 280.00
0.0018 m3 Kayu kamper, reng @ Rp. 5,472,000.00 = Rp 9,849.60
Sub total : = Rp 29,929.60
Upah An. SNI ( Revisi ) 6.14.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 108,000.00 = Rp 10,800.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0005 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 19,434.38
Total upah+bahan : = Rp 49,363.98

7 1 m2 Pasang kawat kassa / kawat burung.


Bahan An. SNI ( Revisi ) 6.15.1
1.100 m2 Kawat kassa @ Rp. 15,000.00 = Rp 16,500.00
0.020 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 280.00
0.0018 m3 Kayu kamper, reng @ Rp. 5,472,000.00 = Rp 9,849.60
Sub total : = Rp 26,629.60
Upah An. SNI ( Revisi ) 6.15.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.100 Oh Tukang kayu @ Rp. 108,000.00 = Rp 10,800.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0005 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 19,434.38
Total upah+bahan : = Rp 46,063.98

8 1 m2 Pasang pagar kawat dari besi siku tinggi 1,5 m dan panjang 3m tidak termasuk pondasi setempat.
Bahan
12 m1 m' besi L 40 . 40 . 5 @ Rp. 18,333.33 = Rp 212,666.67
34 m1 m'kawat duri @ Rp. 18,300.00 = Rp 622,200.00
Sub total : = Rp 834,866.67

Upah Pekerjaan mengelas diperhitungkan. Rp 27,500.00


Ongkos kerja diperhitungkan = Rp 45,000.00
Sub total : = Rp 72,500.00
Total upah+bahan : = Rp 285,166.67

Harga per M2 pagar kawat := 285,166.67 : 5 63,370.37

9 1 m2 Pasang pagar besi tralis dengan besi beton diameter 16 mm.


Bahan
11 m1 btg.besi beton panjang 1 m @ Rp. 13,333.33 = Rp 146,666.67
Plat pengikat diperhitungkan 70,000.00
Baja Cor / mainan diperhitungkan Rp 95,000.00
Sub total : = Rp 311,666.67
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 79
Upah Pekerjaan mengelas diperhitungkan. Rp 85,000.00
Ongkos kerja diperhitungkan = Rp 65,000.00
Sub total : = Rp 65,000.00
Total upah+bahan : = Rp 376,666.67

11 1 m2 Pintu Rolling bahan dari Aluminium.


Bahan
1 M2 Pintu dari aluminium @ Rp. 255,000.00 = Rp 293,250.00
Sub total : = Rp 293,250.00
Upah Biaya pasang / Upah diperhitungkan. Rp 52,500.00
Sub total : = Rp 52,500.00
Total upah+bahan : = Rp 345,750.00

12 1 m2 Pintu Rolling bahan dari plat besi / steel.


Bahan
1 M2 Pintu dari aluminium @ Rp. 370,000.00 = Rp 370,000.00
Sub total : = Rp 370,000.00
Upah An. SNI ( Revisi ) 6.15.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
1.000 Oh Tukang besi @ Rp. 107,250.00 = Rp 107,250.00
0.100 Oh Kepala tukang besi. @ Rp. 108,000.00 = Rp 10,800.00
0.0500 Oh Mandor @ Rp. 108,750.00 = Rp 5,437.50
Sub total : = Rp 198,487.50
Total upah+bahan : = Rp 568,487.50

13 1 m2 Pintu Besi B.R.C.


Bahan 1 M2 pagar besi BRC. @ Rp. 370,000.00 = Rp 407,000.00
Sub total : = Rp 407,000.00
Upah Biaya pasang / Upah diperhitungkan. = Rp 60,000.00
Biaya transfotasi (relatif) jarak
jauh dekatnya. = Rp 5,000.00
Sub total : = Rp 65,000.00
Total upah+bahan : = Rp 472,000.00

14 1 m2 Pagar Besi B.R.C.

Bahan 1 M2 pagar besi BRC. @ Rp. 370,000.00 = Rp 407,000.00


1 M2 Rangka besi besi pintu diameter 2 incs. 45,000.00
Sub total : = Rp 452,000.00
Upah Biaya pasang / Upah diperhitungkan. = Rp 60,000.00
Biaya transfotasi (relatif) jarak
jauh dekatnya. = Rp 5,000.00
Sub total : = Rp 65,000.00
Total upah+bahan : = Rp 517,000.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 80
PEKERJAAN KUSEN ALUMINIUM.

15 1 M' Pasang kusen aluminium 3" putih. (Silver)


Bahan An. SNI ( Revisi ) 6.12.1
1.1 M1 Aluminium putih 3". @ Rp. 90,000.00 = Rp 99,000.00
Sub total : = Rp 99,000.00
Upah 0.104 Oh Pekerja @ Rp. 75,000.00 = Rp 7,800.00
0.104 Oh Tukang besi @ Rp. 107,250.00 = Rp 11,154.00
0.001 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Mandor @ Rp. 108,750.00 = Rp 5.44
Sub total : = Rp 19,067.44
Total upah+bahan : = Rp 118,067.44

16 1 M' Pasang kusen aluminium 4" putih. (Silver)


Bahan An. SNI ( Revisi ) 6.12.1
1.1 M1 Aluminium putih 4". @ Rp. 96,000.00 = Rp 105,600.00
1.1 M1 Coating biru @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 105,600.00

Upah 0.104 Oh Pekerja @ Rp. 75,000.00 = Rp 7,800.00


0.104 Oh Tukang besi @ Rp. 107,250.00 = Rp 11,154.00
0.001 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Mandor @ Rp. 108,750.00 = Rp 5.44
Sub total : = Rp 19,067.44
Total upah+bahan : = Rp 124,667.44

16 1 M' Pasang kusen aluminium 4" putih. (Silver)


Bahan An. SNI ( Revisi ) 6.12.1
1.1 M1 Aluminium putih 4". @ Rp. 96,000.00 = Rp 105,600.00
1.1 M1 Coating biru @ Rp. 10,000.00 = Rp 11,000.00
Sub total : = Rp 116,600.00

Upah 0.104 Oh Pekerja @ Rp. 75,000.00 = Rp 7,800.00


0.104 Oh Tukang besi @ Rp. 107,250.00 = Rp 11,154.00
0.001 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Mandor @ Rp. 108,750.00 = Rp 5.44
Sub total : = Rp 19,067.44
Total upah+bahan : = Rp 135,667.44

17 1 M' Pasang kusen aluminium 3" coklat. (Brown)


Bahan An. SNI ( Revisi ) 6.12.1
1.1 M1 Aluminium coklat/ brown 3". @ Rp. 96,000.00 = Rp 105,600.00
Sub total : = Rp 105,600.00

Upah 0.104 Oh Pekerja @ Rp. 75,000.00 = Rp 7,800.00


0.104 Oh Tukang besi @ Rp. 107,250.00 = Rp 11,154.00
0.001 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Mandor @ Rp. 108,750.00 = Rp 5.44
Sub total : = Rp 19,067.44
Total upah+bahan : = Rp 124,667.44

18 1 M' Pasang kusen aluminium 4" coklat. (Brown)


Bahan An. SNI ( Revisi ) 6.12.1
1.1 M1 Aluminium coklat/ brown 3". @ Rp. 102,000.00 = Rp 112,200.00
Sub total : = Rp 112,200.00

Upah 0.104 Oh Pekerja @ Rp. 75,000.00 = Rp 7,800.00


0.104 Oh Tukang besi @ Rp. 107,250.00 = Rp 11,154.00
0.001 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Mandor @ Rp. 108,750.00 = Rp 5.44
Sub total : = Rp 19,067.44
Total upah+bahan : = Rp 131,267.44
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 81

19 1 Bh. Pasang pintu aluminium 2,75" putih ( Silver) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Bahan An. SNI ( Revisi ) 6.9.1
6 M1 Slimar Aluminium putih 2.75" @ Rp. 90,000.00 = Rp 562,500.00
15 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 112,500.00
1 set Engsel. @ Rp. 19,000.00 Rp 19,000.00
1 Bh Kunci @ Rp. 76,000.00 Rp 76,000.00
1 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 46,720.00
1 M2 Multipleks 9 mm @ Rp. 110,000.00 Rp 136,400.00
1 Ls Paku Skrup @ Rp. 7,500.00 Rp 7,500.00
Sub total : = Rp 960,620.00
koefisen tenaga ditambah 35 % dari anlisa untuk 1 M2 pembuatan pintu aluminium.
Upah 1.418 Oh Pekerja @ Rp. 75,000.00 = Rp 106,312.50
1.418 Oh Tukang besi @ Rp. 108,000.00 = Rp 153,090.00
0.142 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 15,309.00
0.0070 Oh Mandor @ Rp. 108,750.00 = Rp 763.43
Sub total : = Rp 275,474.93
Total upah+bahan : = Rp 1,236,094.93

20 1 Bh. Pasang pintu aluminium 2,75" coklat ( Brown) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Bahan An. SNI ( Revisi ) 6.9.1
6 M1 Slimar Aluminium coklat 2.75" @ Rp. 120,000.00 = Rp 750,000.00
15 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 112,500.00
1 set Engsel. @ Rp. 15,000.00 Rp 15,000.00
1 Bh Kunci @ Rp. 76,000.00 Rp 76,000.00
2 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 146,000.00
1 M2 Multipleks 9 mm @ Rp. 110,000.00 Rp 136,400.00
1 Ls Paku Skrup @ Rp. 7,500.00 Rp 7,500.00
Sub total : = Rp 1,243,400.00
koefisen tenaga ditambah 30 % dari anlisa untuk 1 M2 pembuatan pintu aluminium karena
pintu ini ukuran 80 x 200 Cm.dan ada ambang tengah.
Upah 1.418 Oh Pekerja @ Rp. 75,000.00 = Rp 106,312.50
1.418 Oh Tukang besi @ Rp. 108,000.00 = Rp 153,090.00
0.142 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 15,309.00
0.0070 Oh Mandor @ Rp. 108,750.00 = Rp 763.43
Sub total : = Rp 275,474.93
Total upah+bahan : = Rp 1,518,874.93

21 1M2 Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
5 M1 Slimar Aluminium putih 2" @ Rp. 90,000.00 = Rp 432,000.00
9 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 63,750.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
1 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 65,882.50
Sub total : = Rp 593,632.50

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 108,000.00 = Rp 113,400.00
0.105 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 11,340.00
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 204,055.50
Total upah+bahan : = Rp 797,688.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 82
22 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.60 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2 M1 Slimar Aluminium putih 2" @ Rp. 90,000.00 = Rp 198,000.00
4 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 33,000.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
0 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 21,900.00
Sub total : = Rp 284,900.00

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 108,000.00 = Rp 113,400.00
0.105 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 11,340.00
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 204,055.50
Total upah+bahan : = Rp 488,955.50

23 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.50 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2 M1 Slimar Aluminium putih 2" @ Rp. 90,000.00 = Rp 180,000.00
4 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 30,000.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
0 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 18,250.00
Sub total : = Rp 260,250.00

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 108,000.00 = Rp 113,400.00
0.105 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 11,340.00
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 204,055.50
Total upah+bahan : = Rp 464,305.50

24 1M2 Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
5 M1 Slimar Aluminium coklat 2" @ Rp. 120,000.00 = Rp 576,000.00
9 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 63,750.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
1 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 65,882.50
Sub total : = Rp 737,632.50

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.105 Oh Kepala tukang besi @ Rp. 108,000.00 = Rp 11,340.00
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 203,268.00
Total upah+bahan : = Rp 940,900.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 83

25 1Bh Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 60 Cm.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2 M1 Slimar Aluminium coklat 2" @ Rp. 120,000.00 = Rp 264,000.00
4 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 33,000.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
0 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 21,900.00
Sub total : = Rp 350,900.00

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.105 Oh Kepala tukang besi @ Rp. 107,250.00 = Rp 11,261.25
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 203,189.25
Total upah+bahan : = Rp 554,089.25

26 1Bh. Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 50 Cm.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2 M1 Slimar Aluminium coklat 2" @ Rp. 120,000.00 = Rp 240,000.00
4 M1 Karet penjepit kaca/ tripleks. @ Rp. 7,500.00 Rp 30,000.00
1 set Engsel jendela. @ Rp. 14,000.00 Rp 14,000.00
1 Bh Hak window . @ Rp. 18,000.00 Rp 18,000.00
0 M2 Kaca bening 5 mm @ Rp. 73,000.00 Rp 18,250.00
Sub total : = Rp 320,250.00

Upah 1.050 Oh Pekerja @ Rp. 75,000.00 = Rp 78,750.00


1.050 Oh Tukang besi @ Rp. 107,250.00 = Rp 112,612.50
0.105 Oh Kepala tukang besi @ Rp. 107,250.00 = Rp 11,261.25
0.0052 Oh Mandor @ Rp. 108,750.00 = Rp 565.50
Sub total : = Rp 203,189.25
Total upah+bahan : = Rp 523,439.25

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 84

PEKERJAAN TALANG SENG ; KARET & PVC.

19 1 m' Pasang talang datar, seng bjls 28 lebar 90Cm.


Bahan An. SNI ( Revisi ) 6.18.1
1.050 Lbr Seng plat 3' x 6' bjls 28 @ Rp. 11,500.00 = Rp 12,075.00
0.015 Kg Paku biasa 1/2" - 1" @ Rp. 14,000.00 = Rp 210.00
0.0019 m3 Kayu borneo, papan @ Rp. 5,000,000.00 = Rp 9,500.00
Sub total : = Rp 21,785.00
Upah An. SNI ( Revisi ) 6.18.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.400 Oh Tukang kayu @ Rp. 107,250.00 = Rp 42,900.00
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 60,708.75
Total upah+bahan : = Rp 82,493.75

20 Analog - talang karet per m' + papan= 70 % talang seng = Rp : 57,745.63

21 1 m' Pasang talang miring / jurai seng bjls 28


Bahan An. SNI ( Revisi ) 6.19.1
0.500 Lbr Seng plat 3' x 6' bjls 28 @ Rp. 76,400.00 = Rp 38,200.00
0.015 Kg Paku biasa 1/2" - 1" @ Rp. 75,000.00 = Rp 1,125.00
0.019 m3 Kayu borneo, papan @ Rp. 5,000,000.00 = Rp 95,000.00
Sub total : = Rp 134,325.00
Upah An. SNI ( Revisi ) 6.19.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.400 Oh Tukang kayu @ Rp. 107,250.00 = Rp 42,900.00
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.00125 Oh Mandor @ Rp. 108,750.00 = Rp 135.94
Sub total : = Rp 48,735.94
Total upah+bahan : = Rp 183,060.94

22 1 m' Pasang talang 1/2 lingkaran ø 10 cm, seng bjls 28


Bahan An. SNI ( Revisi ) 6.20.1
0.300 Lbr Seng plat 3' x 6' bjls 28 @ Rp. 76,400.00 = Rp 22,920.00
0.100 Kg Paku biasa 1/2" - 1" @ Rp. 75,000.00 = Rp 7,500.00
0.500 Kg Besi strip @ Rp. 6,500.00 = Rp 3,250.00
Sub total : = Rp 33,670.00
Upah An. SNI ( Revisi ) 6.20.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.00125 Oh Mandor @ Rp. 108,750.00 = Rp 135.94
Sub total : = Rp 40,898.44
Total upah+bahan : = Rp 74,568.44

13 1 m' Pasang talang dari PVC diameter 3".


Bahan 0 Ljr lonjor PVC diameter 3" @ Rp. 105,000.00 = Rp 26,250.00
1 Bh Knie 3" @ Rp. 6,500.00 = Rp 3,250.00
0 Bh tube lem pvc @ Rp. 3,750.00 = Rp 1,312.50
1 Bh buah klem + 2 paku beton @ Rp. 2,750.00 = Rp 2,062.50
Sub total : = Rp 32,875.00
Upah LUMSUM Rp 4,500.00
Total upah+bahan : = Rp 37,375.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 85
14 1 m' Pasang talang dari PVC diameter 4".
Bahan 0 Ljr lonjor PVC diameter 3" @ Rp. 105,000.00 = Rp 26,250.00
1 Bh Knie 3" @ Rp. 6,500.00 = Rp 3,250.00
0 Bh tube lem pvc @ Rp. 3,750.00 = Rp 1,312.50
1 Bh buah klem + 2 paku beton @ Rp. 2,750.00 = Rp 2,062.50
Sub total : = Rp 32,875.00
Upah LUMSUM Rp 4,500.00
Total upah+bahan : = Rp 37,375.00

PEKERJAAN PENGECATAN
Pemersihan Cat
1. 1 m2 Mengikis/mengerok permukaan cat tembok lama
Bahan An. SNI ( Revisi ) 6.1.1
0.050 Kg Soda api @ Rp. 7,500.00 = Rp 375.00
Sub total : = Rp 375.00
Upah An. SNI ( Revisi ) 6.1.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0 Oh Tukang cat @ Rp. 108,000.00 = Rp 0.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 11,521.88
Total upah+bahan : = Rp 11,896.88

2. 1 m2 Mencuci bidang permukaan tembok yang pernah dicat


Bahan An. SNI ( Revisi ) 6.2.1
0.050 Kg S a b u n @ Rp. 3,750.00 = Rp 187.50
Sub total : = Rp 187.50
Upah An. SNI ( Revisi ) 6.2.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0 Oh Tukang cat @ Rp. 108,000.00 = Rp 0.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 11,521.88
Total upah+bahan : = Rp 11,709.38

3. 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual


Bahan An. SNI ( Revisi ) 6.3.1
0.050 Kg S a b u n @ Rp. 3,750.00 = Rp 187.50
Sub total : = Rp 187.50
Upah An. SNI ( Revisi ) 6.3.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0 Oh Tukang cat @ Rp. 108,000.00 = Rp 0.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 11,521.88
Total upah+bahan : = Rp 11,709.38

4. 1 m2 Menyabun permukaan tembok lama


Bahan An. SNI ( Revisi ) 6.4.1
0.050 Kg S a b u n @ Rp. 3,750.00 = Rp 187.50
Sub total : = Rp 187.50
Upah An. SNI ( Revisi ) 6.4.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 86
0 Oh Tukang cat @ Rp. 108,000.00 = Rp 0.00
0 Oh Kepala tukang @ Rp. 108,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 11,521.88
Total upah+bahan : = Rp 11,709.38

5. 1 m2 Mengerok karat atau cat lama permukaan baja dengan pancar pasir ( sanblasting )
dengan tingkat kebersihan Sa 2.5%
Bahan UNTUK 10 m2 'An. SNI ( Revisi ) 6.5.1
40.000 Kg Pasir silika @ Rp. 25.00 = Rp 1,000.00
10.000 Ltr B B M @ Rp. 3,250.00 = Rp 32,500.00
Sub total : = Rp 33,500.00
Alat An. SNI ( Revisi ) 6.5.2 PER 10 M2.
Sewa / hari Kompressor, blasting pot, @ Rp. 250,000.00 = Rp 250,000.00
selang dan nozle
Sub total : = Rp 250,000.00
Upah An. SNI ( Revisi ) 6.5.3
1.600 Oh Pekerja @ Rp. 75,000.00 = Rp 120,000.00
1.600 Oh Tukang cat @ Rp. 108,000.00 = Rp 172,800.00
0.800 Oh Kepala tukang @ Rp. 108,000.00 = Rp 86,400.00
0.500 Oh Mandor @ Rp. 108,750.00 = Rp 54,375.00
Sub total : = Rp 433,575.00
Untuk 10 M2 Total upah+bahan : = Rp 683,575.00

Untuk 1 M2 = Rp 68,357.50

6. 1 m2 Mendempul dan menggosok kayu


Bahan An. SNI ( Revisi ) 6.6.1 Per 10M2
0.080 Kg Dempul jati @ Rp. 37,500.00 = Rp 3,000.00
0.020 Lt Minyak cat @ Rp. 10,500.00 = Rp 210.00
0.010 Kg Batu apung @ Rp. 2,500.00 = Rp 25.00
Sub total : = Rp 3,235.00
Upah An. SNI ( Revisi ) 6.6.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.040 Oh Tukang cat @ Rp. 108,000.00 = Rp 4,320.00
0.004 Oh Kepala tukang @ Rp. 108,000.00 = Rp 432.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 8,023.88
Total upah+bahan : = Rp 11,258.88

Cat KAYU

7. 1 m2 Pengecatan bidang kayu lama


Bahan An. SNI ( Revisi ) 6.7.1
0.150 Kg Plamir @ Rp. 17,000.00 = Rp 2,550.00
0.170 Kg Cat dasar @ Rp. 28,500.00 = Rp 4,845.00
0.170 Kg Cat penutup @ Rp. 65,000.00 = Rp 11,050.00
Sub total : = Rp 18,445.00
Upah An. SNI ( Revisi ) 6.7.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.075 Oh Tukang cat @ Rp. 108,000.00 = Rp 8,100.00
0.0075 Oh Kepala tukang @ Rp. 108,000.00 = Rp 810.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 14,431.88
Total upah+bahan : = Rp 32,876.88
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 87
8. 1 m2 Pengecatan bidang kayu baru ( 1x plamir , 1x cat dasar, 2x cat penutup )
Bahan An. SNI ( Revisi ) 6.8.1
0.200 Kg Cat meni @ Rp. 24,500.00 = Rp 4,900.00
0.150 Kg Plamir @ Rp. 17,000.00 = Rp 2,550.00
0.170 Kg Cat dasar @ Rp. 28,500.00 = Rp 4,845.00
0.260 Kg Cat penutup 2x @ Rp. 65,000.00 = Rp 16,900.00
Sub total : = Rp 29,195.00
Upah An. SNI ( Revisi ) 6.8.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.009 Oh Tukang cat @ Rp. 108,000.00 = Rp 972.00
0.0060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 7,141.88
Total upah+bahan : = Rp 36,336.88

9. 1 m2 Pengecatan bidang kayu baru ( 1x plamir , 1x cat dasar, 3x cat penutup )


Bahan An. SNI ( Revisi ) 6.9.1
0.200 Kg Cat meni @ Rp. 24,500.00 = Rp 4,900.00
0.150 Kg Plamir @ Rp. 17,000.00 = Rp 2,550.00
0.170 Kg Cat dasar @ Rp. 28,500.00 = Rp 4,845.00
0.350 Kg Cat penutup 3 x @ Rp. 65,000.00 = Rp 22,750.00
Sub total : = Rp 35,045.00
Upah An. SNI ( Revisi ) 6.9.2
0.070 Oh Pekerja @ Rp. 75,000.00 = Rp 5,250.00
0.014 Oh Tukang cat @ Rp. 108,000.00 = Rp 1,458.00
0.0040 Oh Kepala tukang @ Rp. 108,000.00 = Rp 432.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 7,411.88
Total upah+bahan : = Rp 42,456.88

POLITUR , TEAK OIL , PENGETIRAN

10. 1 m2 Pelaburan bidang kayu dengan teak oil


Bahan An. SNI ( Revisi ) 6.10.1
0.360 Ltr Teak oil @ Rp. 43,750.00 = Rp 15,750.00
Sub total : = Rp 15,750.00
Upah An. SNI ( Revisi ) 6.10.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.063 Oh Tukang cat @ Rp. 108,000.00 = Rp 6,804.00
0.0630 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,804.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 16,879.88
Total upah+bahan : = Rp 32,629.88

11. 1 m2 Pelaburan bidang kayu dengan politur ( TAK MENGKILAP)


Bahan An. SNI ( Revisi ) 6.11.1
0.150 Ltr Politur @ Rp. 43,750.00 = Rp 6,562.50
0.372 Ltr Politur jadi @ Rp. 43,750.00 = Rp 16,275.00
2.000 Lbr Ampelas @ Rp. 2,250.00 = Rp 4,500.00
Sub total : = Rp 20,775.00
Upah An. SNI ( Revisi ) 6.11.2
0.000 Oh Pekerja @ Rp. 75,000.00 = Rp 0.00
0.060 Oh Tukang cat @ Rp. 108,000.00 = Rp 6,480.00
0.0160 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,728.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 88
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 8,479.88
Total upah+bahan : = Rp 29,254.88

12 10 m2 Pemelituran dengan serlag. ( SAMPAI MENGKILAP)


Bahan Politur dengan serlag mencampur sendiri.
2 Kg Serlag @ Rp. 58,000.00 = Rp 116,000.00
1 Ltr Spirtus. @ Rp. 14,300.00 = Rp 14,300.00
1 Kg Dempul @ Rp. 37,500.00 = Rp 30,000.00
2 Kg Batu kambang @ Rp. 2,500.00 = Rp 3,750.00
2 Lbr Kertas gosok. @ Rp. 5,000.00 = Rp 10,000.00
2 Lbr Kain pop @ Rp. 750.00 = Rp 1,500.00
Sub total : A = Rp 175,550.00
Upah Menggosok dan mendempul
0 Oh Tukang politur @ Rp. 43,750.00 = Rp 17,500.00
0 Oh Kepala tukangTukang cat @ Rp. 108,000.00 = Rp 4,320.00
Sub total : B = Rp 21,820.00

Upah Memlitur sampai mengkilap.


2.500 Oh Pekerja @ Rp. 75,000.00 = Rp 187,500.00
3.000 Oh Tukang politur @ Rp. 108,000.00 = Rp 324,000.00
0.300 Oh Kepala tukangTukang cat @ Rp. 108,000.00 = Rp 32,400.00
0.400 Oh Mandor @ Rp. 108,750.00 = Rp 43,500.00
Sub total : C = Rp 587,400.00
Untuk 10 M2 Total upah+bahan : = Rp 784,770.00
Untuk 1 M2 Total upah+bahan : = Rp 78,477.00
13 1 m2 Pelaburan bidang kayu dengan cat residu dan ter
Bahan An. SNI ( Revisi ) 6.12.1
0.350 Ltr Residu atau ter @ Rp. 10,500.00 = Rp 3,675.00
Sub total : = Rp 3,675.00
Upah An. SNI ( Revisi ) 6.12.2
0.100 Oh Pekerja @ Rp. 75,000.00 = Rp 7,500.00
0.000 Oh Tukang cat @ Rp. 108,000.00 = Rp 0.00
0.0000 Oh Kepala tukang @ Rp. 108,000.00 = Rp 0.00
0.0060 Oh Mandor @ Rp. 108,750.00 = Rp 652.50
. Sub total : = Rp 8,152.50
Total upah+bahan : = Rp 11,827.50

14 1 m2 Pelaburan bidang kayu dengan vernis


Bahan An. SNI ( Revisi ) 6.13.1
0.150 Ltr Vernis @ Rp. 54,800.00 = Rp 8,220.00
0.050 Kg Dempul @ Rp. 37,500.00 = Rp 1,875.00
0.100 Lbr Ampelas @ Rp. 5,000.00 = Rp 500.00
0.010 Bh Kuas @ Rp. 4,500.00 = Rp 45.00
Sub total : = Rp 545.00
Upah An. SNI ( Revisi ) 6.13.2
0.160 Oh Pekerja @ Rp. 75,000.00 = Rp 12,000.00
0.160 Oh Tukang cat @ Rp. 108,000.00 = Rp 17,280.00
0.0160 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,728.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 31,279.88
Total upah+bahan : = Rp 31,824.88

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 89
Cat TEMBOK
Cat BARU.
14. 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Cat Paragon /Decolith
Bahan An. SNI ( Revisi ) 6.14.1
0.100 Kg Plamir @ Rp. 15,500.00 = Rp 1,550.00
0.250 Lbr Ampelas @ Rp. 5,000.00 = Rp 1,250.00
0.020 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 130.00
0.100 Kg Cat dasar @ Rp. 27,500.00 = Rp 2,750.00
0.260 Kg Cat penutup 2x @ Rp. 27,500.00 = Rp 7,150.00
Sub total : = Rp 12,830.00
Upah An. SNI ( Revisi ) 6.14.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.063 Oh Tukang cat @ Rp. 108,000.00 = Rp 6,804.00
0.0063 Oh Kepala tukang @ Rp. 108,000.00 = Rp 680.40
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 9,256.28
Total upah+bahan : = Rp 22,086.28

15 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Cat I.C.I. Catilac
Bahan An. SNI ( Revisi ) 6.14.1
0.100 Kg Plamir @ Rp. 15,500.00 = Rp 1,550.00
0.250 Lbr Ampelas @ Rp. 5,000.00 = Rp 1,250.00
0.020 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 130.00
0.100 Kg Cat dasar @ Rp. 45,000.00 = Rp 4,500.00
0.260 Kg Cat penutup 2x @ Rp. 45,000.00 = Rp 11,700.00
Sub total : = Rp 19,130.00
Upah An. SNI ( Revisi ) 6.14.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.063 Oh Tukang cat @ Rp. 108,000.00 = Rp 6,804.00
0.0063 Oh Kepala tukang @ Rp. 108,000.00 = Rp 680.40
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 9,256.28
Total upah+bahan : = Rp 28,386.28

16 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Watershild


Bahan An. SNI ( Revisi ) 6.14.1
0.100 Kg Plamir @ Rp. 15,500.00 = Rp 1,550.00
0.250 Lbr Ampelas @ Rp. 5,000.00 = Rp 1,250.00
0.020 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 130.00
0.100 Kg Cat dasar @ Rp. 70,000.00 = Rp 7,000.00
0.260 Kg Cat penutup 2x @ Rp. 70,000.00 = Rp 18,200.00
Sub total : = Rp 28,130.00
Upah An. SNI ( Revisi ) 6.14.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.063 Oh Tukang cat @ Rp. 108,000.00 = Rp 6,804.00
0.0063 Oh Kepala tukang @ Rp. 108,000.00 = Rp 680.40
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 9,256.28
Total upah+bahan : = Rp 37,386.28

Cat LAMA.
17 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat penutup ) Cat Paragon /Decolith
Bahan An. SNI ( Revisi ) 6.14.1
0.010 Kg Plamir @ Rp. 15,500.00 = Rp 155.00
0.120 Lbr Ampelas @ Rp. 5,000.00 = Rp 600.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 90
0.033 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 216.67
0.110 Kg Cat dasar @ Rp. 27,500.00 = Rp 3,025.00
0.220 Kg Cat penutup 2x @ Rp. 27,500.00 = Rp 6,050.00
Sub total : = Rp 10,046.67
Upah An. SNI ( Revisi ) 6.14.2
0.028 Oh Pekerja @ Rp. 75,000.00 = Rp 2,100.00
0.042 Oh Tukang cat @ Rp. 108,000.00 = Rp 4,536.00
0.0042 Oh Kepala tukang @ Rp. 108,000.00 = Rp 453.60
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 7,361.48
Total upah+bahan : = Rp 17,408.14

18 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat penutup ) Cat I.C.I. Catilac
Bahan An. SNI ( Revisi ) 6.14.1
0.010 Kg Plamir @ Rp. 15,500.00 = Rp 155.00
0.120 Lbr Ampelas @ Rp. 5,000.00 = Rp 600.00
0.033 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 216.67
0.110 Kg Cat dasar @ Rp. 45,000.00 = Rp 4,950.00
0.220 Kg Cat penutup 2x @ Rp. 45,000.00 = Rp 9,900.00
Sub total : = Rp 15,821.67
Upah An. SNI ( Revisi ) 6.14.2
0.028 Oh Pekerja @ Rp. 75,000.00 = Rp 2,100.00
0.042 Oh Tukang cat @ Rp. 108,000.00 = Rp 4,536.00
0.0042 Oh Kepala tukang @ Rp. 108,000.00 = Rp 453.60
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 7,361.48
Total upah+bahan : = Rp 23,183.14

19 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat penutup ) Watershild


Bahan An. SNI ( Revisi ) 6.14.1
0.010 Kg Plamir @ Rp. 15,500.00 = Rp 155.00
0.120 Lbr Ampelas @ Rp. 5,000.00 = Rp 600.00
0.033 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 216.67
0.110 Kg Cat dasar @ Rp. 70,000.00 = Rp 7,700.00
0.220 Kg Cat penutup 2x @ Rp. 70,000.00 = Rp 15,400.00
Sub total : = Rp 24,071.67
Upah An. SNI ( Revisi ) 6.14.2
0.028 Oh Pekerja @ Rp. 75,000.00 = Rp 2,100.00
0.042 Oh Tukang cat @ Rp. 108,000.00 = Rp 4,536.00
0.0042 Oh Kepala tukang @ Rp. 108,000.00 = Rp 453.60
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 7,361.48
Total upah+bahan : = Rp 31,433.14

20 1 m2 Melabur tembok dengan kapur sirih


Bahan An. SNI ( Revisi ) 6.17.1
0.100 Lbr Ampelas @ Rp. 5,000.00 = Rp 500.00
0.250 Ikt Alang-alang @ Rp. 750.00 = Rp 187.50
0.002 Bh Andang andang @ Rp. 300,000.00 = Rp 600.00
0.150 Kg Kapur sirih @ Rp. 2,500.00 = Rp 375.00
Sub total : = Rp 975.00
Upah An. SNI ( Revisi ) 6.17.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.001 Oh Tukang cat @ Rp. 108,000.00 = Rp 108.00
0.0001 Oh Kepala tukang @ Rp. 108,000.00 = Rp 10.80
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 91
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 11,640.68
Total upah+bahan : = Rp 12,615.68

21 1 m2 Melabur tembok lama dengan kapur sirih ( untuk pemeliharaan )


Bahan An. SNI ( Revisi ) 6.18.1
0.002 m3 Andang andang @ Rp. 300,000.00 = Rp 600.00
0.300 Kg Kapur sirih @ Rp. 2,500.00 = Rp 750.00
Sub total : = Rp 1,350.00
Upah An. SNI ( Revisi ) 6.18.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.005 Oh Tukang cat @ Rp. 108,000.00 = Rp 540.00
0.0005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 54.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 3,865.88
Total upah+bahan : = Rp 5,215.88

22 1 m2 Pemasangan wallpaper
Bahan An. SNI ( Revisi ) 6.19.1
1.200 m2 Wall paper @ Rp. 45,000.00 = Rp 54,000.00
0.200 Kg Perekat @ Rp. 10,500.00 = Rp 2,100.00
Sub total : = Rp 56,100.00
Upah An. SNI ( Revisi ) 6.19.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang cat @ Rp. 108,000.00 = Rp 21,600.00
0.0020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 23,587.88
Total upah+bahan : = Rp 79,687.88

23 1 m2 Pengecatan permukaan baja dengan meni besi


Bahan An. SNI ( Revisi ) 6.20.1
0.100 Kg Meni besi @ Rp. 24,500.00 = Rp 2,450.00
0.020 Bh Kuas @ Rp. 6,500.00 = Rp 130.00
Sub total : = Rp 2,580.00
Upah An. SNI ( Revisi ) 6.20.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang cat @ Rp. 108,000.00 = Rp 21,600.00
0.0200 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.0100 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
. Sub total : = Rp 26,347.50
Total upah+bahan : = Rp 28,927.50

24 1 m2 Pengecatan permukaan baja dengan meni besi dan perancah


Bahan An. SNI ( Revisi ) 6.21.1
0.100 Kg Meni besi @ Rp. 24,500.00 = Rp 2,450.00
0.010 Bh Kuas @ Rp. 6,500.00 = Rp 65.00
0.002 m3 Perancah kayu @ Rp. 750,000.00 = Rp 1,500.00
Sub total : = Rp 1,565.00
Upah An. SNI ( Revisi ) 6.21.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.300 Oh Tukang cat @ Rp. 108,000.00 = Rp 32,400.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.015 Oh Mandor @ Rp. 108,750.00 = Rp 1,631.25
. Sub total : = Rp 39,521.25
Total upah+bahan : = Rp 41,086.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 92
25 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual
sistem 4 lapis cat konvensional dengan tebal 200 um
Bahan An. SNI ( Revisi ) 6.22.1
0.100 Kg Meni ( read lead ) A @ Rp. 24,500.00 = Rp 2,450.00
0.100 Kg Meni ( read lead ) B @ Rp. 15,250.00 = Rp 1,525.00
0.010 Bh Kuas @ Rp. 6,500.00 = Rp 65.00
0.040 Kg Alluminium C @ Rp. 22,500.00 = Rp 900.00
0.040 Kg Alluminium B @ Rp. 26,250.00 = Rp 1,050.00
0.010 Ltr Pengencer @ Rp. 10,500.00 = Rp 105.00
0.002 m3 Andang andang @ Rp. 300,000.00 = Rp 600.00
Sub total : = Rp 6,695.00
Upah An. SNI ( Revisi ) 6.22.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.500 Oh Tukang cat @ Rp. 108,000.00 = Rp 54,000.00
0.050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,400.00
0.025 Oh Mandor @ Rp. 108,750.00 = Rp 2,718.75
. Sub total : = Rp 65,118.75
Total upah+bahan : = Rp 71,813.75

26 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual


sistem 1 lapis cat mutakhir dengan tebal 200 um
Bahan An. SNI ( Revisi ) 6.23.1
0.300 Kg C a t @ Rp. 65,000.00 = Rp 19,500.00
0.010 Bh Kuas @ Rp. 6,500.00 = Rp 65.00
Sub total : = Rp 19,565.00
Upah An. SNI ( Revisi ) 6.23.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang cat @ Rp. 108,000.00 = Rp 21,600.00
0.002 Oh Kepala tukang @ Rp. 108,000.00 = Rp 216.00
0.003 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
. Sub total : = Rp 23,587.88
Total upah+bahan : = Rp 43,152.88

27 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara manual


sistem 3 lapis cat konvensional dengan tebal 200 um
Bahan An. SNI ( Revisi ) 6.24.1
0.110 Kg Cat dasar @ Rp. 65,000.00 = Rp 7,150.00
0.170 Kg Cat antara @ Rp. 65,000.00 = Rp 11,050.00
0.010 Bh Kuas @ Rp. 6,500.00 = Rp 65.00
0.080 Kg Cat penutup @ Rp. 65,000.00 = Rp 5,200.00
Sub total : = Rp 16,315.00
Upah An. SNI ( Revisi ) 6.24.2
0.040 Oh Pekerja @ Rp. 75,000.00 = Rp 3,000.00
0.400 Oh Tukang cat @ Rp. 108,000.00 = Rp 43,200.00
0.004 Oh Kepala tukang @ Rp. 108,000.00 = Rp 432.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
. Sub total : = Rp 47,175.75
Total upah+bahan : = Rp 63,490.75

28 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara semprot ( airless spray )
sistem 1 lapis cat mutakhir dengan tebal 200 um
Bahan An. SNI ( Revisi ) 6.25.1
0.300 Kg Cat dasar @ Rp. 65,000.00 = Rp 19,500.00
Peralatan Lumsum = Rp 3,000.00
Sub total : = Rp 22,500.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 93
Upah An. SNI ( Revisi ) 6.25.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang cat @ Rp. 108,000.00 = Rp 21,600.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
. Sub total : = Rp 26,347.50
Total upah+bahan : = Rp 48,847.50
PEKERJAAN PENUTUP LANTAI
1 1 m2 Pasang lantai ubin warna akuran 40 x 40 cm
Bahan An. SNI ( Revisi ) 6.4.1
6.630 Bh Ubin warna 40 x 40 cm @ Rp. 163,900.00 = Rp 1,086,657.00
9.800 Kg Semen portland @ Rp. 1,525.00 = Rp 14,945.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 1,108,477.00
Upah An. SNI ( Revisi ) 6.4.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 1,142,752.38

2 1 m2 Pasang lantai ubin warna akuran 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.5.1
11.200 Bh Ubin warna 30 x 30 cm @ Rp. 6,500.00 = Rp 72,800.00
8.360 Kg Semen portland @ Rp. 1,525.00 = Rp 12,749.00
0.023 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,025.00
0.600 Kg Semen warna @ Rp. 9,500.00 = Rp 5,700.00
Sub total : = Rp 95,274.00
Upah An. SNI ( Revisi ) 6.5.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 129,549.38

3 1 m2 Pasang lantai ubin teraso akuran 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.7.1
6.250 Bh Ubin teraso 40 x 40 cm @ Rp. 7,500.00 = Rp 46,875.00
8.800 Kg Semen portland @ Rp. 1,525.00 = Rp 13,420.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 66,907.50
Upah An. SNI ( Revisi ) 6.7.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 102,932.88

4 1 m2 Pasang lantai ubin teraso akuran 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.8.1
11.200 Bh Ubin teraso 30 x 30 cm @ Rp. 7,300.00 = Rp 81,760.00
10.000 Kg Semen portland @ Rp. 1,525.00 = Rp 15,250.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.600 Kg Semen warna @ Rp. 9,500.00 = Rp 5,700.00
Sub total : = Rp 106,472.50
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 95
Upah An. SNI ( Revisi ) 6.8.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.125 Oh Tukang batu @ Rp. 107,250.00 = Rp 13,406.25
0.013 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,350.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 37,365.63
Total upah+bahan : = Rp 143,838.13

5 1 m2 Pasang lantai ubin granito akuran 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.9.1
6.250 Bh Ubin granito 40 x 40 cm @ Rp. 22,176.00 = Rp 138,600.00
9.800 Kg Semen portland @ Rp. 1,525.00 = Rp 14,945.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 160,157.50
Upah An. SNI ( Revisi ) 6.9.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 194,432.88

6 1 m2 Pasang lantai keramic Exensa 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.10.1
6.250 Bh Keramic esensas 30 x 30 cm @ Rp. 16,480.00 = Rp 103,000.00
10.000 Kg Semen portland @ Rp. 1,525.00 = Rp 15,250.00
0.0215 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,762.50
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 124,862.50
Upah An. SNI ( Revisi ) 6.10.2
0.260 Oh Pekerja @ Rp. 75,000.00 = Rp 19,500.00
0.125 Oh Tukang batu @ Rp. 107,250.00 = Rp 13,406.25
0.0130 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,404.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 35,669.63
Total upah+bahan : = Rp 160,532.13

7 1 m2 Pasang lantai marmer akuran 60 x 60 cm


Bahan An. SNI ( Revisi ) 6.13.1
2.940 Bh Ubin teralux marmer 60 x 60 @ Rp. 48,469.39 = Rp 142,500.00
8.190 Kg Semen portland @ Rp. 1,525.00 = Rp 12,489.75
0.045 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,875.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 165,714.75
Upah An. SNI ( Revisi ) 6.13.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 201,740.13
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 96
8 1 m2 Pasang lantai marmer akuran 100 x 100 cm
Bahan An. SNI ( Revisi ) 6.13.1
1.060 M2 Ubin teralux marmer 1 x 1 m2 @ Rp. 142,500.00 = Rp 151,050.00
8.190 Kg Semen portland @ Rp. 1,525.00 = Rp 12,489.75
0.045 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,875.00
0.250 Kg Semen warna @ Rp. 9,500.00 = Rp 2,375.00
Sub total : = Rp 173,789.75
Upah An. SNI ( Revisi ) 6.13.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.0125 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Biaya poles. @ Rp. = Rp 1,750.00
Sub total : = Rp 36,025.38
Total upah+bahan : = Rp 209,815.13

9 1 m2 Pasang teraso cor ditempat nat kaca 4Cm x 5 mm


Bahan An. SNI ( Revisi ) 6.31.1
0.0036 m3 Bahan teraso cor @ Rp. 101,200.00 = Rp 364.32
12.285 Kg Semen portland @ Rp. 1,525.00 = Rp 18,734.63
0.095 m3 Pasir pasang @ Rp. 175,000.00 = Rp 16,625.00
2.000 m1 nat kaca @ Rp. 2,250.00 = Rp 4,500.00
1.000 Kg Semen warna @ Rp. 9,500.00 = Rp 9,500.00
Sub total : = Rp 49,723.95

Upah An. SNI ( Revisi ) 6.31.2


0.900 Oh Pekerja @ Rp. 75,000.00 = Rp 67,500.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Biaya poles. Lumsum = Rp 2,250.00
Sub total : = Rp 80,863.88
Total upah+bahan : = Rp 130,587.82

10 1 m2 Pasang TRASO cor ditempat nat kuningan


Bahan An. SNI ( Revisi ) 6.31.1
0.0036 m3 Bahan teraso cor @ Rp. 518,000.00 = Rp 1,864.80
12.285 Kg Semen portland @ Rp. 1,525.00 = Rp 18,734.63
0.095 m3 Pasir pasang 0.00 175,000.00 = Rp 16,625.00
2.000 m1 nat kaca @ Rp. 7,500.00 = Rp 15,000.00
1.000 Kg Semen warna @ Rp. 9,500.00 = Rp 9,500.00
Sub total : = Rp 61,724.43
Upah An. SNI ( Revisi ) 6.31.2
0.900 Oh Pekerja @ Rp. 75,000.00 = Rp 67,500.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Biaya poles. Sub total : = Rp 2,500.00
Sub total : = Rp 81,113.88
Total upah+bahan : = Rp 142,838.30
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 97
11 1 m1 Pasang lantai keramik artistik 5 x 20 cm / Lis / Ban
Bahan An. SNI ( Revisi ) 6.36.1
5.000 Bh Ubin keramik artistik 5x20 cm @ Rp. 10,000.00 = Rp 50,000.00
0.850 Kg Semen portland @ Rp. 1,525.00 = Rp 1,296.25
0.0022 m3 Pasir pasang @ Rp. 175,000.00 = Rp 385.00
0.080 Kg Semen warna @ Rp. 9,500.00 = Rp 760.00
Sub total : = Rp 52,441.25
Upah An. SNI ( Revisi ) 6.36.2
0.090 Oh Pekerja @ Rp. 75,000.00 = Rp 6,750.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0450 Oh Mandor @ Rp. 108,750.00 = Rp 4,893.75
Sub total : = Rp 22,268.25
Total upah+bahan : = Rp 74,709.50

12 1 m1 Pasang lantai keramik artistik 7,5 x 25 cm / Lis / Ban


Bahan An. SNI ( Revisi ) 6.37.1
5.000 Bh Plint keramik artistik 10x20 cm @ Rp. 13000 = Rp 50,000.00
1.063 Kg Semen portland @ Rp. 1,525.00 = Rp 1,620.31
0.003 m3 Pasir pasang @ Rp. 175,000.00 = Rp 481.25
0.100 Kg Semen warna @ Rp. 9,500.00 = Rp 950.00
Sub total : = Rp 53,051.56
Upah An. SNI ( Revisi ) 6.37.2
0.090 Oh Pekerja @ Rp. 75,000.00 = Rp 6,750.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.0045 Oh Mandor @ Rp. 108,750.00 = Rp 489.38
Sub total : = Rp 17,863.88
Total upah+bahan : = Rp 70,915.44

13 1 m2 Pasang lantai keramik 20 x 20 cm


Bahan An. SNI ( Revisi ) 6.42.1
1.050 m2 Ubin keramik 10x20 cm @ Rp. 44,500.00 = Rp 46,725.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.350 Kg Semen warna @ Rp. 9,500.00 = Rp 3,325.00
Sub total : = Rp 78,582.45
Upah An. SNI ( Revisi ) 6.42.2
0.250 Oh Pekerja @ Rp. 75,000.00 = Rp 18,750.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 34,275.38
Total upah+bahan : = Rp 112,857.82

14 1 m2 Pasang lantai keramik 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 30 x 30 Cm @ Rp. 53,400.00 = Rp 56,070.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 87,452.45
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 119,477.82
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 98
15 1 m2 Pasang lantai keramik 40 x 40 cm (Motif)
Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 40 x 40 Cm @ Rp. 60,000.00 = Rp 63,000.00
7.454 Kg Semen portland @ Rp. 1,140.00 = Rp 8,497.45
3.926 Kg Kapur bubuk @ Rp. 2,375.00 = Rp 9,324.49
0.0420 m3 Pasir pasang @ Rp. 150,000.00 = Rp 6,300.00
0.200 Kg Semen warna @ Rp. 7,125.00 = Rp 1,425.00
Sub total : = Rp 88,546.93
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 57,333.33 = Rp 12,613.33
0.100 Oh Tukang batu @ Rp. 81,986.67 = Rp 8,198.67
0.012 Oh Kepala tukang @ Rp. 82,560.00 = Rp 990.72
0.013 Oh Mandor @ Rp. 83,133.33 = Rp 1,080.73
Sub total : = Rp 22,883.45
Total upah+bahan : = Rp 111,430.39

16 1 m2 Pasang lantai keramik 40 x 40 cm


Bahan An. SNI ( Revisi ) 6.47.1
1.050 M2 Ubin keramik 40 x 40 Cm @ Rp. 52,000.00 = Rp 54,600.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.200 Kg Semen warna @ Rp. 9,500.00 = Rp 1,900.00
Sub total : = Rp 85,032.45
Upah An. SNI ( Revisi ) 6.47.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 29,880.38
Total upah+bahan : = Rp 114,912.82

17 1 m1 Pasang lantai keramik 30 x 30 cm anti slip / Rock tile


Bahan An. SNI ( Revisi ) 6.48.1
1.050 M2 Ubin keramik 30x30 anti slip @ Rp. 62,000.00 = Rp 65,100.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.0420 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 96,482.45
Upah An. SNI ( Revisi ) 6.48.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 128,507.82

18 1 m2 Pasang lantai mosaik 30 x 30 cm.


Bahan An. SNI ( Revisi ) 6.51.1
1.050 m2 Mosaik 30x30cm @ Rp. 62,500.00 = Rp 65,625.00
7.454 Kg Semen portland @ Rp. 1,525.00 = Rp 11,367.20
3.926 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 9,815.25
0.042 m3 Pasir pasang @ Rp. 175,000.00 = Rp 7,350.00
0.300 Kg Semen warna @ Rp. 9,500.00 = Rp 2,850.00
Sub total : = Rp 97,007.45
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 99
Upah An. SNI ( Revisi ) 6.51.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.120 Oh Tukang batu @ Rp. 107,250.00 = Rp 12,870.00
0.012 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,296.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 32,025.38
Total upah+bahan : = Rp 129,032.82

19 1 m2 Pasang lantai karpet 100% wool


Bahan An. SNI ( Revisi ) 6.52.1
1.050 m2 Feltex carpet 100% T-21 @ Rp. 195,000.00 = Rp 204,750.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 217,525.00
Upah An. SNI ( Revisi ) 6.52.2
0.170 Oh Pekerja @ Rp. 75,000.00 = Rp 12,750.00
0.170 Oh Tukang @ Rp. 107,250.00 = Rp 18,232.50
0.017 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,836.00
0.0085 Oh Mandor @ Rp. 108,750.00 = Rp 924.38
Sub total : = Rp 33,742.88
Total upah+bahan : = Rp 251,267.88

20 1 m2 Pasang lantai karpet 80% wool, 20% nylon


Bahan An. SNI ( Revisi ) 6.53.1
1.050 m2 Carpet 80% wool, 20% nylon @ Rp. 155,000.00 = Rp 162,750.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 175,525.00
Upah An. SNI ( Revisi ) 6.53.2
0.170 Oh Pekerja @ Rp. 75,000.00 = Rp 12,750.00
0.170 Oh Tukang @ Rp. 107,250.00 = Rp 18,232.50
0.017 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,836.00
0.0085 Oh Mandor @ Rp. 108,750.00 = Rp 924.38
Sub total : = Rp 33,742.88
Total upah+bahan : = Rp 209,267.88

e:\ANALISA-2009\SNI.12-A.wk4\2012. Halaman : 100


21 1 m2 Pasang lantai parquet jati
Bahan An. SNI ( Revisi ) 6.56.1
1.050 m2 Parquet jati @ Rp. 192,500.00 = Rp 202,125.00
0.600 Kg Lem vinyl @ Rp. 36,500.00 = Rp 21,900.00
Sub total : = Rp 224,025.00
Upah An. SNI ( Revisi ) 6.56.2
0.650 Oh Pekerja @ Rp. 75,000.00 = Rp 48,750.00
0.350 Oh Tukang @ Rp. 107,250.00 = Rp 37,537.50
0.035 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,780.00
0.0325 Oh Mandor @ Rp. 108,750.00 = Rp 3,534.38
Sub total : = Rp 93,601.88
Total upah+bahan : = Rp 317,626.88

22 1 m2 Pasang dinding porselin 11 x 11 cm, putih


Bahan An. SNI ( Revisi ) 6.58.1
83.000 Bh Porselin 11x11 cm @ Rp. 375.00 = Rp 31,125.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.500 Kg Semen warna @ Rp. 9,500.00 = Rp 4,750.00
Sub total : = Rp 55,519.71
Upah An. SNI ( Revisi ) 6.58.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 41,469.38
Total upah+bahan : = Rp 96,989.09

23 1 m2 Pasang dinding porselin 11 x 11 cm, warna


Bahan An. SNI ( Revisi ) 6.59.1
83.000 Bh Porselin 11x11 cm, warna @ Rp. 395.00 = Rp 32,785.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.500 Kg Semen warna @ Rp. 9,500.00 = Rp 4,750.00
Sub total : = Rp 57,179.71
Upah An. SNI ( Revisi ) 6.59.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,359.38
Sub total : = Rp 41,469.38
Total upah+bahan : = Rp 98,649.09

24 1 m2 Pasang dinding keramik 20 x 25 cm


Bahan An. SNI ( Revisi ) 6.69.1
1.050 M2 Keramik 20 x 25 cm @ Rp. 46,600.00 = Rp 48,930.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.400 Kg Semen warna @ Rp. 9,500.00 = Rp 3,800.00
Sub total : = Rp 72,374.71

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 101


Upah An. SNI ( Revisi ) 6.69.2
0.248 Oh Pekerja @ Rp. 75,000.00 = Rp 18,600.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 43,297.50
Total upah+bahan : = Rp 115,672.21

25 1 m2 Pasang dinding keramik 20 x 35 cm


Bahan An. SNI ( Revisi ) 6.69.1
1.050 M2 Keramik 20 x 35 cm @ Rp. 55,700.00 = Rp 58,485.00
6.929 Kg Semen portland @ Rp. 1,525.00 = Rp 10,565.96
2.372 Kg Kapur bubuk @ Rp. 2,500.00 = Rp 5,928.75
0.0180 m3 Pasir pasang @ Rp. 175,000.00 = Rp 3,150.00
0.250 Kg Semen warna @ Rp. 9,500.00 = Rp 2,375.00
Sub total : = Rp 80,504.71
Upah An. SNI ( Revisi ) 6.69.2
0.230 Oh Pekerja @ Rp. 75,000.00 = Rp 17,250.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.010 Oh Mandor @ Rp. 108,750.00 = Rp 1,087.50
Sub total : = Rp 41,947.50
Total upah+bahan : = Rp 122,452.21

26 1 m2 Pasang dinding marmer


Bahan An. SNI ( Revisi ) 6.70.1
1.020 m2 Marmer @ Rp. 142,500.00 = Rp 145,350.00
2.000 Bh Paku pancing 60x230 @ Rp. 1,750.00 = Rp 3,500.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
0.400 Kg Semen warna @ Rp. 9,500.00 = Rp 3,800.00
Sub total : = Rp 175,996.00
Upah An. SNI ( Revisi ) 6.70.2
0.720 Oh Pekerja @ Rp. 75,000.00 = Rp 54,000.00
0.650 Oh Tukang batu @ Rp. 107,250.00 = Rp 69,712.50
0.065 Oh Kepala tukang @ Rp. 108,000.00 = Rp 7,020.00
0.0350 Oh Mandor @ Rp. 108,750.00 = Rp 3,806.25
Sub total : = Rp 134,538.75
Total upah+bahan : = Rp 310,534.75

27 1 m2 Pasang dinding bata pelapis 7 x 3 x 24 cm


Bahan An. SNI ( Revisi ) 6.71.1
1.050 M2 Bata pelapis dinding @ Rp. 80,000.00 = Rp 84,000.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
Sub total : = Rp 107,346.00
Upah An. SNI ( Revisi ) 6.71.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.200 Oh Tukang batu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.013 Oh Mandor @ Rp. 108,750.00 = Rp 1,413.75
Sub total : = Rp 41,523.75
Total upah+bahan : = Rp 148,869.75
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 102
28 1 m2 Pasang dinding bata klinker 5 x 5 x 24 cm
Bahan An. SNI ( Revisi ) 6.72.1
1.050 M2 Bata pelapis klinker @ Rp. 80,000.00 = Rp 84,000.00
12.440 Kg Semen portland @ Rp. 1,525.00 = Rp 18,971.00
0.0250 m3 Pasir pasang @ Rp. 175,000.00 = Rp 4,375.00
Sub total : = Rp 107,346.00
Upah An. SNI ( Revisi ) 6.72.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 146,508.00

29 1 m2 Pasang dinding batu paros


Bahan An. SNI ( Revisi ) 6.73.1
1.050 m2 Batu paros @ Rp. 48,000.00 = Rp 50,400.00
11.750 Kg Semen portland @ Rp. 1,525.00 = Rp 17,918.75
0.0350 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,125.00
Sub total : = Rp 74,443.75
Upah An. SNI ( Revisi ) 6.73.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 113,605.75

30 1 m2 Pasang dinding batu tempel hitam


Bahan An. SNI ( Revisi ) 6.74.1
1.050 m2 Batu tempel hitam @ Rp. 25,000.00 = Rp 26,250.00
11.750 Kg Semen portland @ Rp. 1,525.00 = Rp 17,918.75
0.0350 m3 Pasir pasang @ Rp. 175,000.00 = Rp 6,125.00
Sub total : = Rp 50,293.75
Upah An. SNI ( Revisi ) 6.74.2
0.220 Oh Pekerja @ Rp. 75,000.00 = Rp 16,500.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.012 Oh Mandor @ Rp. 108,750.00 = Rp 1,305.00
Sub total : = Rp 39,162.00
Total upah+bahan : = Rp 89,455.75

31 1 m2 Pasang lantai vinyl oscar / xsintetis 30 x 30 cm KL 1


Bahan An. SNI ( Revisi ) 6.75.1
11.050 Bh Vinyl oscar/sintetist 30x30 cm @ Rp. 5,158.37 = Rp 57,000.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 69,775.00
Upah An. SNI ( Revisi ) 6.75.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 99,548.13

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 103


32 1 m2 Pasang lantai vinyl karet 30 x 30 cm
Bahan An. SNI ( Revisi ) 6.76.1
11.050 Bh Vinyl karet 30x30 cm @ Rp. 5,882.35 = Rp 65,000.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 77,775.00
Upah An. SNI ( Revisi ) 6.76.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 107,548.13

33 1 m2 Pasang lantai vinyl motif kembang 30 x 30 cm


Bahan An. SNI ( Revisi ) 6.78.1
11.050 Bh Vinyl mtf kembang 30x30 cm e @ Rp. 5,502.26 = Rp 60,800.00
0.350 Kg Lem vinyl @ Rp. 36,500.00 = Rp 12,775.00
Sub total : = Rp 73,575.00
Upah An. SNI ( Revisi ) 6.78.2
0.150 Oh Pekerja @ Rp. 75,000.00 = Rp 11,250.00
0.150 Oh Tukang @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0075 Oh Mandor @ Rp. 108,750.00 = Rp 815.63
Sub total : = Rp 29,773.13
Total upah+bahan : = Rp 103,348.13

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 104


PEKERJAAN PAVING STONE

1 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm.
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 1350.000 = Rp 48,600.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 60,600.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 93,776.97

2 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm.
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 2279.000 = Rp 82,044.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 94,044.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 127,220.97

3 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 1710.000 = Rp 61,560.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 73,560.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 106,736.97

4 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
36 Bj Paving type "S" @ Rp. 2170.000 = Rp 78,120.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 90,120.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 123,296.97

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 105


5 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1350.000 = Rp 47,250.00
0.12 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 59,250.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 92,426.97

6 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1937.000 = Rp 67,795.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 79,795.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 112,971.97

7 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 1730.000 = Rp 60,550.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 72,550.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 105,726.97

8 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35 Bj Paving type "Tiga berlian" @ Rp. 2140.000 = Rp 74,900.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 86,900.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 120,076.97

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 106


9 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
46 Bj Paving type "Segi empat" @ Rp. 1260.000 = Rp 57,960.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 69,960.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 103,136.97

10 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46 Bj Paving type "Ssgi empat" @ Rp. 2,030.00 = Rp 93,380.00
0.120 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,000.00
Sub total : = Rp 105,380.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 138,556.97

11 1 m2 Pasang PAVING STONE warna merah TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46 Bj Paving type "Ssgi empat" @ Rp. 2360.000 = Rp 108,560.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,100.00
Sub total : = Rp 120,660.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 153,836.97

12 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
26 Bj Paving type "Ssgi ENAM" @ Rp. 1732.000 = Rp 45,032.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,100.00
Sub total : = Rp 57,132.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 90,308.97

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 107


13 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
26 Bj Paving type "Ssgi ENAM" @ Rp. 2850.000 = Rp 74,100.00
0.121 m3 Pasir urug 10 Cm. @ Rp. 100,000.00 = Rp 12,100.00
Sub total : = Rp 86,200.00
Upah An. SNI ( Revisi )
0.192 Oh Pekerja @ Rp. 75,000.00 = Rp 14,415.00
0.151 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,245.16
0.016 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,674.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 842.81
Sub total : = Rp 33,176.97
Total upah+bahan : = Rp 119,376.97

PEKERJAAN KANSTIN / SKERB.

1 1 m1 Pasang KANSTIN / SKERB Model lengkung Uk. 18 x 50 x 30 Cm.


Bahan An. SNI ( Revisi )
2 Bj Skreb lengkung @ Rp. 35,000.00 = Rp 70,000.00
0.050 m3 Pasir pasang @ Rp. 61,000.00 = Rp 3,050.00
1.000 Ls Spesi utk sambungan @ Rp. 1,450.00 = Rp 1,450.00
Sub total : = Rp 74,500.00
Upah An. SNI ( Revisi )
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 33,577.50
Total upah+bahan : = Rp 108,077.50

1 1 m1 Pasang KANSTIN / SKERB Model lurus Uk. 10 x 40 x 20 Cm.


Bahan An. SNI ( Revisi )
3 Bj skerb" @ Rp. 27,500.00 = Rp 68,750.00
0.030 m3 Pasir pasang @ Rp. 61,000.00 = Rp 1,830.00
1.000 Ls Spesi utk sambungan @ Rp. 1,450.00 = Rp 1,450.00
Sub total : = Rp 72,030.00
Upah An. SNI ( Revisi )
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
0.150 Oh Tukang batu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 33,577.50
Total upah+bahan : = Rp 105,607.50

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 108


PEKERJAAN GEBALAN RUMPUT

1 1 m2 Penanaman Rumput LAMUR.


Bahan An. SNI ( Revisi )
1 m2 Rumput lamur @ Rp. 12,500.00 = Rp 12,500.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 14,600.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.015 Oh Tukang batu @ Rp. 107,250.00 = Rp 1,608.75
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 6,978.75
Total upah+bahan : = Rp 21,578.75

2 1 m2 Penanaman Rumput GAJAH.


Bahan An. SNI ( Revisi )
1 m2 Rumput gajah. @ Rp. 14,000.00 = Rp 14,000.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 16,100.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.015 Oh Tukang batu @ Rp. 107,250.00 = Rp 1,608.75
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 6,978.75
Total upah+bahan : = Rp 23,078.75

3 1 m2 Penanaman Rumput JEPANG.


Bahan An. SNI ( Revisi )
1 m2 Rumput jepang. @ Rp. 18,000.00 = Rp 18,000.00
0.030 m3 Tnh humus + pupuk kandang @ Rp. 70,000.00 = Rp 2,100.00
Sub total : = Rp 20,100.00
Upah An. SNI ( Revisi )
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.015 Oh Tukang batu @ Rp. 107,250.00 = Rp 1,608.75
0.008 Oh Mandor @ Rp. 108,750.00 = Rp 870.00
Sub total : = Rp 6,978.75
Total upah+bahan : = Rp 27,078.75

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 109


PEKERJAAN KUNCI DAN KACA
1. 1 buah pasang kunci tanam antik
Bahan An. SNI ( Revisi ) 6.1.1
1.000 Bh Kunci tanam antik @ Rp. 123,500.00 = Rp 123,500.00
Sub total : = Rp 123,500.00
Upah An. SNI ( Revisi ) 6.1.2
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 75,873.75
Total upah+bahan : = Rp 199,373.75

2. 1 buah pasang kunci tanam biasa 2 X PUTAR.


Bahan An. SNI ( Revisi ) 6.2.1
1.000 Bh Kunci tanam biasa @ Rp. 96,000.00 = Rp 96,000.00
Sub total : = Rp 96,000.00
Upah An. SNI ( Revisi ) 6.2.2
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 75,873.75
Total upah+bahan : = Rp 171,873.75

3. 1 buah pasang kunci tanam KM/WC


Bahan An. SNI ( Revisi ) 6.3.1
1.000 Bh Kunci tanam KM/WC @ Rp. 76,000.00 = Rp 76,000.00
Sub total : = Rp 76,000.00
Upah An. SNI ( Revisi ) 6.3.2
0.005 Oh Pekerja @ Rp. 75,000.00 = Rp 375.00
0.500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 53,625.00
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 54,811.88
Total upah+bahan : = Rp 130,811.88

4. 1 buah pasang kunci silinder


Bahan An. SNI ( Revisi ) 6.4.1
1.000 Bh Kunci silinder @ Rp. 65,250.00 = Rp 65,250.00
Sub total : = Rp 65,250.00
Upah An. SNI ( Revisi ) 6.4.2
0.005 Oh Pekerja @ Rp. 75,000.00 = Rp 375.00
0.500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 53,625.00
0.005 Oh Kepala tukang @ Rp. 108,000.00 = Rp 540.00
0.00025 Oh Mandor @ Rp. 108,750.00 = Rp 27.19
Sub total : = Rp 54,567.19
Total upah+bahan : = Rp

5. 1 buah pasang engsel pintu


Bahan An. SNI ( Revisi ) 6.5.1
1.000 Bh Engsel pintu @ Rp. 19,000.00 = Rp 19,000.00
Sub total : = Rp 19,000.00
Upah An. SNI ( Revisi ) 6.5.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
D:\Bud D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007. Halaman : 108
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 37,914.06
6. 1 buah pasang engsel jendela kupu-kupu
Bahan An. SNI ( Revisi ) 6.6.1
1.000 Bh Engsel jendela @ Rp. 14,000.00 = Rp 14,000.00
Sub total : = Rp 14,000.00
Upah An. SNI ( Revisi ) 6.6.2
0.010 Oh Pekerja @ Rp. 75,000.00 = Rp 750.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0005 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 12,609.38
Total upah+bahan : = Rp 26,609.38

7. 1 buah pasang engsel angin


Bahan An. SNI ( Revisi ) 6.7.1
1.000 Bh Engsel angin @ Rp. 9,500.00 = Rp 9,500.00
Sub total : = Rp 9,500.00
Upah An. SNI ( Revisi ) 6.7.2
0.010 Oh Pekerja @ Rp. 75,000.00 = Rp 750.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 12,609.38
Total upah+bahan : = Rp 22,109.38

8 1 buah pasang kait angin sikutan YANG BAIK


Bahan An. SNI ( Revisi ) 6.9.1
1.000 Bh Kait angin @ Rp. 27,000.00 = Rp 27,000.00
Sub total : = Rp 27,000.00
Upah An. SNI ( Revisi ) 6.9.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 45,914.06

9 1 buah pasang door closer


Bahan An. SNI ( Revisi ) 6.10.1
1.000 Bh Door closer @ Rp. 236,750.00 = Rp 236,750.00
Sub total : = Rp 236,750.00
Upah An. SNI ( Revisi ) 6.10.2
0.050 Oh Pekerja @ Rp. 75,000.00 = Rp 3,750.00
0.500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 53,625.00
0.050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,400.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 63,046.88
Total upah+bahan : = Rp 299,796.88

10 1 buah pasang kunci selot kuningan panjang 25 Cm


Bahan An. SNI ( Revisi ) 6.11.1
1.000 Bh Kunci selot @ Rp. 69,750.00 = Rp 69,750.00
Sub total : = Rp 69,750.00
D:\Bud D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007. Halaman : 109
Upah An. SNI ( Revisi ) 6.11.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 25,218.75
Total upah+bahan : = Rp 94,968.75

11 1 buah pasang kunci selot kuningan panjang 15 Cm


Bahan An. SNI ( Revisi ) 6.11.1
1.000 Bh Kunci selot @ Rp. 34,100.00 = Rp 34,100.00
Sub total : = Rp 34,100.00
Upah An. SNI ( Revisi ) 6.11.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 25,218.75
Total upah+bahan : = Rp 59,318.75

12 1 buah pasang kunci selot hitam panjang 25 Cm


Bahan An. SNI ( Revisi ) 6.11.1
1.000 Bh Kunci selot @ Rp. 20,000.00 = Rp 20,000.00
Sub total : = Rp 20,000.00
Upah An. SNI ( Revisi ) 6.11.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 25,218.75
Total upah+bahan : = Rp 45,218.75

13 1 buah pasang kunci selot hitam panjang 15 Cm


Bahan An. SNI ( Revisi ) 6.11.1
1.000 Bh Kunci selot @ Rp. 13,700.00 = Rp 13,700.00
Sub total : = Rp 13,700.00
Upah An. SNI ( Revisi ) 6.11.2
0.020 Oh Pekerja @ Rp. 75,000.00 = Rp 1,500.00
0.200 Oh Tukang kayu @ Rp. 107,250.00 = Rp 21,450.00
0.020 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,160.00
0.001 Oh Mandor @ Rp. 108,750.00 = Rp 108.75
Sub total : = Rp 25,218.75
Total upah+bahan : = Rp 38,918.75

14 1 buah pasang pegangan pintu/door holder


Bahan An. SNI ( Revisi ) 6.12.1
1.000 Bh Door holder @ Rp. 374,000.00 = Rp 374,000.00
Sub total : = Rp 374,000.00
Upah An. SNI ( Revisi ) 6.12.2
0.050 Oh Pekerja @ Rp. 75,000.00 = Rp 3,750.00
0.500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 53,625.00
0.050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,400.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 63,046.88
Total upah+bahan : = Rp 437,046.88
D:\Bud D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007. Halaman : 110
15 1 buah pasang door stop
Bahan An. SNI ( Revisi ) 6.13.1
1.000 Bh Door stop @ Rp. 21,250.00 = Rp 21,250.00
Sub total : = Rp 21,250.00
Upah An. SNI ( Revisi ) 6.13.2
0.010 Oh Pekerja @ Rp. 75,000.00 = Rp 750.00
0.100 Oh Tukang kayu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.0005 Oh Mandor @ Rp. 108,750.00 = Rp 54.38
Sub total : = Rp 12,609.38
Total upah+bahan : = Rp 33,859.38

16 1 buah pasang rel pintu dorong


Bahan An. SNI ( Revisi ) 6.14.1
1.000 Bh Rel pintu dorong @ Rp. 201,000.00 = Rp 201,000.00
Sub total : = Rp 201,000.00
Upah An. SNI ( Revisi ) 6.14.2
0.060 Oh Pekerja @ Rp. 75,000.00 = Rp 4,500.00
0.600 Oh Tukang kayu @ Rp. 107,250.00 = Rp 64,350.00
0.060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 6,480.00
0.003 Oh Mandor @ Rp. 108,750.00 = Rp 326.25
Sub total : = Rp 75,656.25
Total upah+bahan : = Rp 276,656.25

17 1 buah pasang kunci lemari


Bahan An. SNI ( Revisi ) 6.15.1
1.000 Bh Kunci lemari @ Rp. 9,800.00 = Rp 9,800.00
Sub total : = Rp 9,800.00
Upah An. SNI ( Revisi ) 6.15.2
0.025 Oh Pekerja @ Rp. 75,000.00 = Rp 1,875.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.00125 Oh Mandor @ Rp. 108,750.00 = Rp 135.94
Sub total : = Rp 31,523.44
Total upah+bahan : = Rp 41,323.44

18 1 m2 pasang kaca, tebal 3 mm


Bahan An. SNI ( Revisi ) 6.16.1
1.100 m2 Kaca tebal 3 mm @ Rp. 49,500.00 = Rp 54,450.00
Sub total : = Rp 54,450.00
Upah An. SNI ( Revisi ) 6.16.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 73,364.06

19 1 m2 pasang kaca, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.17.1
1.100 m2 Kaca tebal 5 mm @ Rp. 73,000.00 = Rp 80,300.00
Sub total : = Rp 80,300.00
Upah An. SNI ( Revisi ) 6.17.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
D:\Bud D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007. Halaman : 111
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 99,214.06

20 1 m2 pasang kaca, rayben 5 mm


Bahan An. SNI ( Revisi ) 6.18.1
1.100 m2 Kaca tebal 8 mm @ Rp. 80,000.00 = Rp 88,000.00
Sub total : = Rp 88,000.00
Upah An. SNI ( Revisi ) 6.18.2
0.0150 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.1500 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.0150 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.0008 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 106,914.06

21 1 m2 pasang kaca buram, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.19.1
1.100 m2 Kaca buram @ Rp. 66,000.00 = Rp 72,600.00
Sub total : = Rp 72,600.00
Upah An. SNI ( Revisi ) 6.19.2
0.025 Oh Pekerja @ Rp. 75,000.00 = Rp 1,875.00
0.250 Oh Tukang kayu @ Rp. 107,250.00 = Rp 26,812.50
0.025 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,700.00
0.00125 Oh Mandor @ Rp. 108,750.00 = Rp 135.94
Sub total : = Rp 31,523.44
Total upah+bahan : = Rp 104,123.44

22 1 m2 pasang kaca cermin, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.20.1
1.100 m2 Kaca cermin @ Rp. 140,000.00 = Rp 154,000.00
Sub total : = Rp 154,000.00
Upah An. SNI ( Revisi ) 6.20.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 172,914.06

23 1 m2 pasang kaca cermin, tebal 6 mm


Bahan An. SNI ( Revisi ) 6.21.1
1.100 m2 Kaca cermin @ Rp. 370,000.00 = Rp 407,000.00
Sub total : = Rp 407,000.00
Upah An. SNI ( Revisi ) 6.21.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 425,914.06
D:\Bud D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\2007. Halaman : 112

24 1 m2 pasang kaca painting / gambar, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.23.1
1.100 m2 Kaca wireglass @ Rp. 260,000.00 = Rp 286,000.00
Sub total : = Rp 286,000.00
Upah An. SNI ( Revisi ) 6.23.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 304,914.06

25 1 m2 pasang kaca patri, tebal 5 mm


Bahan An. SNI ( Revisi ) 6.24.1
1.100 m2 Kaca patri @ Rp. 375,000.00 = Rp 412,500.00
Sub total : = Rp 412,500.00
Upah An. SNI ( Revisi ) 6.24.2
0.015 Oh Pekerja @ Rp. 75,000.00 = Rp 1,125.00
0.150 Oh Tukang kayu @ Rp. 107,250.00 = Rp 16,087.50
0.015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,620.00
0.00075 Oh Mandor @ Rp. 108,750.00 = Rp 81.56
Sub total : = Rp 18,914.06
Total upah+bahan : = Rp 431,414.06
PEKERJAAN SANITAIR

1. Memasang 1 buah kloset duduk/monoblok


Bahan An. SNI ( Revisi ) 6.1.1
1.000 Bh Kloset duduk/monoblok @ Rp. 900,000.00 = Rp 900,000.00
6.000 % Perlengkapan CLOSED = Rp 54,000.00
Sub total : = Rp 954,000.00
Upah An. SNI ( Revisi ) 6.1.2
3.300 Oh Pekerja @ Rp. 75,000.00 = Rp 247,500.00
1.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 117,975.00
0.001 Oh Kepala tukang @ Rp. 108,000.00 = Rp 108.00
0.1600 Oh Mandor @ Rp. 108,750.00 = Rp 17,400.00
Sub total : = Rp 382,983.00
Total upah+bahan : = Rp 1,336,983.00

2. Memasang 1 buah kloset jongkok porselen


Bahan An. SNI ( Revisi ) 6.2.1
1.000 Bh Kloset jongkok porselen @ Rp. 150,000.00 = Rp 150,000.00
6.000 Kg Semen portland @ Rp. 1,525.00 = Rp 9,150.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,750.00
Sub total : = Rp 160,900.00
Upah An. SNI ( Revisi ) 6.2.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
1.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 160,875.00
0.150 Oh Kepala tukang @ Rp. 108,000.00 = Rp 16,200.00
0.160 Oh Mandor @ Rp. 108,750.00 = Rp 17,400.00
Sub total : = Rp 269,475.00
Total upah+bahan : = Rp 430,375.00

3. Memasang 1 buah kloset jongkok teraso


Bahan An. SNI ( Revisi ) 6.3.1
1.000 Bh Kloset jongkok teraso @ Rp. 150,000.00 = Rp 150,000.00
7.000 Bh Bata merah 5 x 11 x 22 @ Rp. 500.00 = Rp 3,500.00
6.000 Kg Semen portland @ Rp. 1,525.00 = Rp 9,150.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 1,750.00
Sub total : = Rp 164,400.00
Upah An. SNI ( Revisi ) 6.3.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
1.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 160,875.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.110 Oh Mandor @ Rp. 108,750.00 = Rp 11,962.50
Sub total : = Rp 280,237.50
Total upah+bahan : = Rp 444,637.50

4. Memasang 1 buah urinoir


Bahan An. SNI ( Revisi ) 6.4.1
1.000 Bh Urinoir @ Rp. 67,000.00 = Rp 67,000.00
30.000 % Perlengkapan urinoir Rp 20,100.00
6.000 Kg Semen portland @ Rp. 1,525.00 = Rp 9,150.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 175,000.00
Sub total : = Rp 271,250.00
Upah An. SNI ( Revisi ) 6.4.2
1.000 Oh Pekerja @ Rp. 75,000.00 = Rp 75,000.00
1.000 Oh Tukang batu @ Rp. 107,250.00 = Rp 107,250.00
0.100 Oh Kepala tukang @ Rp. 108,000.00 = Rp 10,800.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 114
0.100 Oh Mandor @ Rp. 108,750.00 = Rp 10,875.00
Sub total : = Rp 203,925.00
Total upah+bahan : = Rp 475,175.00

5. Memasang 1 buah wastafel


Bahan An. SNI ( Revisi ) 6.5.1
1.000 Bh Wastafel @ Rp. 382,250.00 = Rp 382,250.00
12.000 % Perlengkapan washtafel = Rp 45,870.00
6.000 Kg Semen portland @ Rp. 1,525.00 = Rp 9,150.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 175,000.00
Sub total : = Rp 612,270.00
Upah An. SNI ( Revisi ) 6.5.2
0.200 Oh Pekerja @ Rp. 75,000.00 = Rp 15,000.00
1.450 Oh Tukang batu @ Rp. 107,250.00 = Rp 155,512.50
0.150 Oh Kepala tukang @ Rp. 108,000.00 = Rp 16,200.00
0.100 Oh Mandor @ Rp. 108,750.00 = Rp 10,875.00
Sub total : = Rp 197,587.50
Total upah+bahan : = Rp 809,857.50

6. Memasang 1 buah bak mandi teraso volume 0.3 m3


Bahan An. SNI ( Revisi ) 6.6.1
1.000 Bh Bak teraso @ Rp. 75,000.00 = Rp 75,000.00
6.000 Kg Semen portland @ Rp. 1,525.00 = Rp 9,150.00
0.010 m3 Pasir pasang @ Rp. 175,000.00 = Rp 175,000.00
Sub total : = Rp 259,150.00
Upah An. SNI ( Revisi ) 6.6.2
2.100 Oh Pekerja @ Rp. 75,000.00 = Rp 157,500.00
0.750 Oh Tukang batu @ Rp. 107,250.00 = Rp 80,437.50
0.070 Oh Kepala tukang @ Rp. 108,000.00 = Rp 7,560.00
0.110 Oh Mandor @ Rp. 108,750.00 = Rp 11,962.50
Sub total : = Rp 257,460.00
Total upah+bahan : = Rp 516,610.00

7. Memasang 1 buah bak mandi fiberglass volume 0.3 m3


Bahan An. SNI ( Revisi ) 6.7.1
1.000 Bh Bak fiberglass @ Rp. 145,000.00 = Rp 145,000.00
18.000 % Perlengkapan bak fiber = Rp 26,100.00
Sub total : = Rp 171,100.00
Upah An. SNI ( Revisi ) 6.7.2
1.800 Oh Pekerja @ Rp. 75,000.00 = Rp 135,000.00
2.700 Oh Tukang batu @ Rp. 107,250.00 = Rp 289,575.00
0.540 Oh Kepala tukang @ Rp. 108,000.00 = Rp 58,320.00
0.110 Oh Mandor @ Rp. 108,750.00 = Rp 11,962.50
Sub total : = Rp 494,857.50
Total upah+bahan : = Rp 665,957.50

8. Memasang 1 buah bak mandi batu bata volume 0.3 m3


Bahan An. SNI ( Revisi ) 6.8.1
0.400 m3 Batu bata @ Rp. 500.00 = Rp 200.00
120.000 Kg Semen portland @ Rp. 1,525.00 = Rp 183,000.00
0.300 m3 Pasir pasang @ Rp. 175,000.00 = Rp 52,500.00
360.000 Bh Porselen ( 11x11 ) cm @ Rp. 1,500.00 = Rp 540,000.00
6.000 Kg Semen nat @ Rp. 1,000.00 = Rp 6,000.00
Sub total : = Rp 781,700.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 115
Upah An. SNI ( Revisi ) 6.8.2
6.000 Oh Pekerja @ Rp. 75,000.00 = Rp 450,000.00
3.000 Oh Tukang batu @ Rp. 107,250.00 = Rp 321,750.00
0.300 Oh Kepala tukang @ Rp. 108,000.00 = Rp 32,400.00
0.300 Oh Mandor @ Rp. 108,750.00 = Rp 32,625.00
Sub total : = Rp 836,775.00
Total upah+bahan : = Rp 1,618,475.00

9. Memasang 1 buah badtub porselen KIA ; INA ; Toto


Bahan An. SNI ( Revisi ) 6.9.1
1.000 m3 Badkip @ Rp. 1,250,000.00 = Rp 1,250,000.00
20.000 % Perlengkapan badkip = Rp 250,000.00
Sub total : = Rp 1,500,000.00
Upah An. SNI ( Revisi ) 6.9.2
0.000 Oh Pekerja @ Rp. 75,000.00 = Rp 0.00
0.075 Oh Tukang batu @ Rp. 107,250.00 = Rp 8,043.75
0.750 Oh Kepala tukang @ Rp. 108,000.00 = Rp 81,000.00
0.250 Oh Mandor @ Rp. 108,750.00 = Rp 27,187.50
Sub total : = Rp 116,231.25
Total upah+bahan : = Rp 1,616,231.25

9. Memasang 1 buah badtub fiber glass.


Bahan An. SNI ( Revisi ) 6.9.1
1.000 m3 Badkip @ Rp. 575,000.00 = Rp 575,000.00
20.000 % Perlengkapan badkip = Rp 115,000.00
Sub total : = Rp 690,000.00
Upah An. SNI ( Revisi ) 6.9.2
0.000 Oh Pekerja @ Rp. 75,000.00 = Rp 0.00
0.075 Oh Tukang batu @ Rp. 107,250.00 = Rp 8,043.75
0.750 Oh Kepala tukang @ Rp. 108,000.00 = Rp 81,000.00
0.250 Oh Mandor @ Rp. 108,750.00 = Rp 27,187.50
Sub total : = Rp 116,231.25
Total upah+bahan : = Rp 806,231.25

10. Membuat 1 buah bak beton volume 1 m3 air


Bahan An. SNI ( Revisi ) 6.10.1
0.900 m3 Beton 1 : 1.5 : 2.5 @ Rp. 345,000.00 = Rp 310,500.00
180.000 Kg Besi beton @ Rp. 10,500.00 = Rp 1,890,000.00
0.250 m3 Kayu cetakan @ Rp. 3,025,000.00 = Rp 756,250.00
5.000 m2 Keramic 20 x 25 @ Rp. 46,600.00 = Rp 233,000.00
1.000 Ls Perlengkapan = Rp 15,000.00
Sub total : = Rp 3,204,750.00
Upah An. SNI ( Revisi ) 6.10.2
3.500 Oh Pekerja @ Rp. 75,000.00 = Rp 262,500.00
4.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 482,625.00
0.900 Oh Kepala tukang @ Rp. 108,000.00 = Rp 97,200.00
0.900 Oh Mandor @ Rp. 108,750.00 = Rp 97,875.00
Sub total : = Rp 940,200.00
Total upah+bahan : = Rp 4,144,950.00

11. Memasang 1 buah bak mandi fiberglass volume 1 m3 air


Bahan An. SNI ( Revisi ) 6.11.1
1.000 Bh Bak fiberglass @ Rp. 14,300.00 = Rp 14,300.00
12.000 % Perlengkapan bak fiber = Rp 1,716.00
Sub total : = Rp 16,016.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 116
Upah An. SNI ( Revisi ) 6.11.2
3.000 Oh Pekerja @ Rp. 75,000.00 = Rp 225,000.00
4.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 482,625.00
0.900 Oh Kepala tukang @ Rp. 108,000.00 = Rp 97,200.00
0.900 Oh Mandor @ Rp. 108,750.00 = Rp 97,875.00
Sub total : = Rp 902,700.00
Total upah+bahan : = Rp 918,716.00

14. Memasang 1 m' pipa beton, Ø 15 - 20 cm


Bahan An. SNI ( Revisi ) 6.14.1
1.100 Bh Pipa beton @ Rp. 36,500.00 = Rp 40,150.00
0.027 m3 Batu bata @ Rp. 500.00 = Rp 13.50
3.920 Kg Semen portland @ Rp. 1,525.00 = Rp 5,978.00
0.065 m3 Pasir pasang @ Rp. 175,000.00 = Rp 11,375.00
0 m3 Pasir urug @ Rp. 100,000.00 = Rp 2,400.00
Sub total : = Rp 59,916.50
Upah An. SNI ( Revisi ) 6.14.2
0.140 Oh Pekerja @ Rp. 75,000.00 = Rp 10,500.00
0.070 Oh Tukang batu @ Rp. 107,250.00 = Rp 7,507.50
0.007 Oh Kepala tukang @ Rp. 108,000.00 = Rp 756.00
0.007 Oh Mandor @ Rp. 108,750.00 = Rp 761.25
Sub total : = Rp 19,524.75
Total upah+bahan : = Rp 79,441.25

15. Memasang 1 m' pipa beton, Ø 30 - 100 cm


Bahan An. SNI ( Revisi ) 6.15.1
1.100 Bh Pipa beton @ Rp. 40,200.00 = Rp 44,220.00
0.550 m3 Batu bata @ Rp. 500.00 = Rp 275.00
10.300 Kg Semen portland @ Rp. 1,525.00 = Rp 15,707.50
0.061 m3 Pasir pasang @ Rp. 175,000.00 = Rp 10,675.00
0 m3 Pasir urug @ Rp. 100,000.00 = Rp 6,900.00
Sub total : = Rp 77,777.50
Upah An. SNI ( Revisi ) 6.15.2
0.380 Oh Pekerja @ Rp. 75,000.00 = Rp 28,500.00
0.190 Oh Tukang batu @ Rp. 107,250.00 = Rp 20,377.50
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.019 Oh Mandor @ Rp. 108,750.00 = Rp 2,066.25
Sub total : = Rp 52,995.75
Total upah+bahan : = Rp 130,773.25

16. Memasang 1 buah bak kontrol pas. batu bata ( 30x30 ) cm, tinggi 35 cm
Bahan An. SNI ( Revisi ) 6.16.1
0.145 m3 Batu bata @ Rp. 500.00 = Rp 72.50
44.000 Kg Semen portland @ Rp. 1,525.00 = Rp 67,100.00
0.070 m3 Pasir pasang @ Rp. 175,000.00 = Rp 12,250.00
0.070 m3 Batu kerikil @ Rp. 181,000.00 = Rp 12,670.00
1.600 Kg Besi beton @ Rp. 10,500.00 = Rp 16,800.00
0.060 m3 Pasir beton @ Rp. 198,000.00 = Rp 11,880.00
Sub total : = Rp 120,772.50
Upah An. SNI ( Revisi ) 6.16.2
0.167 Oh Pekerja @ Rp. 75,000.00 = Rp 12,500.00
1.015 Oh Tukang batu @ Rp. 107,250.00 = Rp 108,858.75
0.0015 Oh Kepala tukang @ Rp. 108,000.00 = Rp 162.00
0.016 Oh Mandor @ Rp. 108,750.00 = Rp 1,740.00
Sub total : = Rp 123,260.75
Total upah+bahan : = Rp 244,033.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 117
17. Memasang 1 buah bak kontrol pas. batu bata ( 45x45 ) cm, tinggi 50 cm
Bahan An. SNI ( Revisi ) 6.17.1
0.250 m3 Batu bata @ Rp. 500.00 = Rp 125.00
77.000 Kg Semen portland @ Rp. 1,525.00 = Rp 117,425.00
0.130 m3 Pasir pasang @ Rp. 175,000.00 = Rp 22,750.00
0.020 m3 Batu kerikil @ Rp. 181,000.00 = Rp 3,620.00
2.600 Kg Besi beton @ Rp. 10,500.00 = Rp 27,300.00
0.090 m3 Pasir beton @ Rp. 198,000.00 = Rp 17,820.00
Sub total : = Rp 189,040.00
Upah An. SNI ( Revisi ) 6.17.2
1.420 Oh Pekerja @ Rp. 75,000.00 = Rp 106,500.00
0.470 Oh Tukang batu @ Rp. 107,250.00 = Rp 50,407.50
0.047 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,076.00
0.071 Oh Mandor @ Rp. 108,750.00 = Rp 7,721.25
Sub total : = Rp 169,704.75
Total upah+bahan : = Rp 358,744.75

18. Memasang 1 buah bak kontrol pas. batu bata ( 60x60 ) cm, tinggi 65 cm
Bahan An. SNI ( Revisi ) 6.18.1
0.371 m3 Batu bata @ Rp. 500.00 = Rp 185.50
114.000 Kg Semen portland @ Rp. 1,525.00 = Rp 173,850.00
0.184 m3 Pasir pasang @ Rp. 175,000.00 = Rp 32,200.00
0.033 m3 Batu kerikil @ Rp. 181,000.00 = Rp 5,973.00
4.850 Kg Besi beton @ Rp. 10,500.00 = Rp 50,925.00
0.120 m3 Pasir beton @ Rp. 198,000.00 = Rp 23,760.00
Sub total : = Rp 286,893.50
Upah An. SNI ( Revisi ) 6.18.2
2.160 Oh Pekerja @ Rp. 75,000.00 = Rp 162,000.00
0.720 Oh Tukang batu @ Rp. 107,250.00 = Rp 77,220.00
0.072 Oh Kepala tukang @ Rp. 108,000.00 = Rp 7,776.00
0.108 Oh Mandor @ Rp. 108,750.00 = Rp 11,745.00
0.100 Oh Tukang gali @ Rp. 107,250.00 = Rp 10,725.00
Sub total : = Rp 269,466.00
Total upah+bahan : = Rp 556,359.50

19. Memasang 1 m' pipa galvanis ø 1/2"


Bahan An. SNI ( Revisi ) 6.19.1
1.200 m' Pipa galvanis @ Rp. 29,500.00 = Rp 35,400.00
35 % Perlengkapan = Rp 10,325.00
Sub total : = Rp 45,725.00
Upah An. SNI ( Revisi ) 6.19.2
0.054 Oh Pekerja @ Rp. 75,000.00 = Rp 4,050.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.027 Oh Mandor @ Rp. 108,750.00 = Rp 2,936.25
Sub total : = Rp 17,610.75
Total upah+bahan : = Rp 63,335.75

20. Memasang 1 m' pipa galvanis ø 3/4"


Bahan An. SNI ( Revisi ) 6.20.1
1.200 m' Pipa galvanis @ Rp. 35,500.00 = Rp 42,600.00
35 % Perlengkapan = Rp 12,425.00
Sub total : = Rp 55,025.00

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 118


Upah An. SNI ( Revisi ) 6.20.2
0.054 Oh Pekerja @ Rp. 75,000.00 = Rp 4,050.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.027 Oh Mandor @ Rp. 108,750.00 = Rp 2,936.25
Sub total : = Rp 17,610.75
Total upah+bahan : = Rp 72,635.75

21. Memasang 1 m' pipa galvanis ø 1"


Bahan An. SNI ( Revisi ) 6.21.1
1.200 m' Pipa galvanis @ Rp. 82,000.00 = Rp 98,400.00
35 % Perlengkapan = Rp 28,700.00
Sub total : = Rp 127,100.00
Upah An. SNI ( Revisi ) 6.21.2
0.054 Oh Pekerja @ Rp. 75,000.00 = Rp 4,050.00
0.090 Oh Tukang batu @ Rp. 107,250.00 = Rp 9,652.50
0.009 Oh Kepala tukang @ Rp. 108,000.00 = Rp 972.00
0.027 Oh Mandor @ Rp. 108,750.00 = Rp 2,936.25
Sub total : = Rp 17,610.75
Total upah+bahan : = Rp 144,710.75

22. Memasang 1 m' pipa galvanis ø 1,25"


Bahan An. SNI ( Revisi ) 6.22.1
1.200 m' Pipa galvanis @ Rp. 156,250.00 = Rp 187,500.00
35 % Perlengkapan = Rp 54,687.50
Sub total : = Rp 242,187.50
Upah An. SNI ( Revisi ) 6.22.2
0.108 Oh Pekerja @ Rp. 75,000.00 = Rp 8,100.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.018 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,944.00
0.0054 Oh Mandor @ Rp. 108,750.00 = Rp 587.25
Sub total : = Rp 29,936.25
Total upah+bahan : = Rp 272,123.75

23. Memasang 1 m' pipa galvanis ø 2"


Bahan An. SNI ( Revisi ) 6.23.1
1.200 m' Pipa galvanis @ Rp. 206,250.00 = Rp 247,500.00
35 % Perlengkapan = Rp 72,187.50
Sub total : = Rp 319,687.50
Upah An. SNI ( Revisi ) 6.23.2
0.108 Oh Pekerja @ Rp. 75,000.00 = Rp 8,100.00
0.180 Oh Tukang batu @ Rp. 107,250.00 = Rp 19,305.00
0.018 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,944.00
0.0054 Oh Mandor @ Rp. 108,750.00 = Rp 587.25
Sub total : = Rp 29,936.25
Total upah+bahan : = Rp 349,623.75

24. Memasang 1 m' pipa galvanis ø 3"


Bahan An. SNI ( Revisi ) 6.24.1
1.200 m' Pipa galvanis @ Rp. 215,000.00 = Rp 258,000.00
35 % Perlengkapan = Rp 75,250.00
Sub total : = Rp 333,250.00
Upah An. SNI ( Revisi ) 6.24.2
0.135 Oh Pekerja @ Rp. 75,000.00 = Rp 10,125.00
0.225 Oh Tukang batu @ Rp. 107,250.00 = Rp 24,131.25
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 119
0.0225 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,430.00
0.0068 Oh Mandor @ Rp. 108,750.00 = Rp 739.50
Sub total : = Rp 37,425.75
Total upah+bahan : = Rp 370,675.75

25. Memasang 1 m' pipa PVC tipe AW ø 1/2"


Bahan An. SNI ( Revisi ) 6.25.1
1.200 m' Pipa PVC @ Rp. 5,550.00 = Rp 6,660.00
35 % Perlengkapan = Rp 1,942.50
Sub total : = Rp 8,602.50
Upah An. SNI ( Revisi ) 6.25.2
0.036 Oh Pekerja @ Rp. 75,000.00 = Rp 2,700.00
0.060 Oh Tukang batu @ Rp. 107,250.00 = Rp 6,435.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0018 Oh Mandor @ Rp. 108,750.00 = Rp 195.75
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 18,581.25

26. Memasang 1 m' pipa PVC tipe AW ø 3/4"


Bahan An. SNI ( Revisi ) 6.26.1
1.200 m' Pipa PVC @ Rp. 6,500.00 = Rp 7,800.00
35 % Perlengkapan = Rp 2,275.00
Sub total : = Rp 10,075.00
Upah An. SNI ( Revisi ) 6.26.2
0.036 Oh Pekerja @ Rp. 75,000.00 = Rp 2,700.00
0.060 Oh Tukang batu @ Rp. 107,250.00 = Rp 6,435.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0018 Oh Mandor @ Rp. 108,750.00 = Rp 195.75
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 20,053.75

27. Memasang 1 m' pipa PVC tipe AW ø 1"


Bahan An. SNI ( Revisi ) 6.27.1
1.200 m' Pipa PVC @ Rp. 8,062.50 = Rp 9,675.00
35 % Perlengkapan = Rp 2,821.88
Sub total : = Rp 12,496.88
Upah An. SNI ( Revisi ) 6.27.2
0.036 Oh Pekerja @ Rp. 75,000.00 = Rp 2,700.00
0.060 Oh Tukang batu @ Rp. 107,250.00 = Rp 6,435.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0018 Oh Mandor @ Rp. 108,750.00 = Rp 195.75
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 22,475.63

28 Memasang 1 m' pipa PVC tipe D ø 2"


Bahan An. SNI ( Revisi ) 6.29.1
1.200 m' Pipa PVC @ Rp. 14,775.00 = Rp 17,730.00
35 % Perlengkapan = Rp 5,171.25
Sub total : = Rp 22,901.25
Upah An. SNI ( Revisi ) 6.29.2
0.036 Oh Pekerja @ Rp. 75,000.00 = Rp 2,700.00
0.060 Oh Tukang batu @ Rp. 107,250.00 = Rp 6,435.00
0.006 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0018 Oh Mandor @ Rp. 108,750.00 = Rp 195.75
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 32,880.00
D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 120
29 Memasang 1 m' pipa PVC tipe D ø 3"
Bahan An. SNI ( Revisi ) 6.30.1
1.200 m' Pipa PVC @ Rp. 26,250.00 = Rp 31,500.00
35 % Perlengkapan = Rp 9,187.50
Sub total : = Rp 40,687.50
Upah An. SNI ( Revisi ) 6.30.2
0.036 Oh Pekerja @ Rp. 75,000.00 = Rp 2,700.00
0.060 Oh Tukang batu @ Rp. 107,250.00 = Rp 6,435.00
0.0060 Oh Kepala tukang @ Rp. 108,000.00 = Rp 648.00
0.0018 Oh Mandor @ Rp. 108,750.00 = Rp 195.75
Sub total : = Rp 9,978.75
Total upah+bahan : = Rp 50,666.25

30 Memasang 1 m' pipa PVC tipe D ø 4"


Bahan An. SNI ( Revisi ) 6.31.1
1.200 m' Pipa PVC @ Rp. 41,000.00 = Rp 49,200.00
35 % Perlengkapan = Rp 14,350.00
Sub total : = Rp 63,550.00
Upah An. SNI ( Revisi ) 6.31.2
0.081 Oh Pekerja @ Rp. 75,000.00 = Rp 6,075.00
0.135 Oh Tukang batu @ Rp. 107,250.00 = Rp 14,478.75
0.0135 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,458.00
0.0041 Oh Mandor @ Rp. 108,750.00 = Rp 445.88
Sub total : = Rp 22,457.63
Total upah+bahan : = Rp 86,007.63

31 Memasang 1 buah bak cuci piring stainless steel


Bahan An. SNI ( Revisi ) 6.33.1
1.000 Bh Bak cuci stainless steel @ Rp. 265,000.00 = Rp 265,000.00
1.000 set Water drain + assesories @ Rp. 75,000.00 = Rp 75,000.00
Sub total : = Rp 340,000.00
Upah An. SNI ( Revisi ) 6.33.2
0.030 Oh Pekerja @ Rp. 75,000.00 = Rp 2,250.00
0.300 Oh Tukang batu @ Rp. 107,250.00 = Rp 32,175.00
0.030 Oh Kepala tukang @ Rp. 108,000.00 = Rp 3,240.00
0.0015 Oh Mandor @ Rp. 108,750.00 = Rp 163.13
Sub total : = Rp 37,828.13
Total upah+bahan : = Rp 377,828.13

32 Memasang 1 buah bak cuci piring teraso


Bahan An. SNI ( Revisi ) 6.34.1
1.000 Bh Bak cuci teraso @ Rp. 115,000.00 = Rp 115,000.00
1.000 set Water drain + assesories @ Rp. 55,000.00 = Rp 55,001.00
20.000 Kg Semen portland @ Rp. 1,525.00 = Rp 1,545.00
0.050 m3 Pasir pasang @ Rp. 175,000.00 = Rp 175,000.05
Sub total : = Rp 346,546.05
Upah An. SNI ( Revisi ) 6.34.2
0.050 Oh Pekerja @ Rp. 75,000.00 = Rp 3,750.00
0.500 Oh Tukang batu @ Rp. 107,250.00 = Rp 53,625.00
0.050 Oh Kepala tukang @ Rp. 108,000.00 = Rp 5,400.00
0.0025 Oh Mandor @ Rp. 108,750.00 = Rp 271.88
Sub total : = Rp 63,046.88
Total upah+bahan : = Rp 409,592.93

D:\Budi\DataBudi\ANALISA-2008\SNI.08-A.wk4\2008. Halaman : 121


33 Memasang 1 buah kran ø 3/4" atau 1/2"
Bahan An. SNI ( Revisi ) 6.35.1
1.000 Bh Kran air @ Rp. 35,000.00 = Rp 35,000.00
0.025 Bh Seal tape @ Rp. 2,500.00 = Rp 62.50
Sub total : = Rp 35,062.50
Upah An. SNI ( Revisi ) 6.35.2
0.010 Oh Pekerja @ Rp. 75,000.00 = Rp 750.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 13,098.75
Total upah+bahan : = Rp 48,161.25

34 Memasang 1 buah floor drain


Bahan An. SNI ( Revisi ) 6.36.1
1.000 Bh Floor drain @ Rp. 15,000.00 = Rp 15,000.00
Sub total : = Rp 15,000.00
Upah An. SNI ( Revisi ) 6.36.2
0.010 Oh Pekerja @ Rp. 75,000.00 = Rp 750.00
0.100 Oh Tukang batu @ Rp. 107,250.00 = Rp 10,725.00
0.010 Oh Kepala tukang @ Rp. 108,000.00 = Rp 1,080.00
0.005 Oh Mandor @ Rp. 108,750.00 = Rp 543.75
Sub total : = Rp 13,098.75
Total upah+bahan : = Rp 28,098.75

PEMBUATAN SEPTIKTANK UNTUK KAPASITAS 15 ORANG.


( Ukuran 1.5 X 2.5 X dalam 1.75 & resapan diameter 1.5 m dalam 2m )

Volume Uraian pekerjaan Harga satuan. Jumlah harga

13 M3 Galian tanah @ Rp. 72,393.75 = Rp 941,118.75


4 M3Urug kembali tanah (1/4 galian) @ Rp. 16,466.25 = Rp 65,865.00
3 M3 Pasang batu bata 1:2 @ Rp. 819,115.38 = Rp 2,457,346.15
29 M2 Plesteran 1:2 @ Rp. 49,763.00 = Rp 1,443,127.00
1 Beton tumbuk 1:2:3. @ Rp. 776,192.50 = Rp 543,334.75
0 M3 Beton bertulang 123 @ Rp. 4,173,824.39 = Rp 834,764.88
2 Kerikil keringan @ Rp. 181,000.00 = Rp 271,500.00
2 M3 Pasir saringan @ Rp. 175,000.00 = Rp 350,000.00
1 M' Pasang pipa besi O 2" @ Rp. 35,000.00 = Rp 35,000.00
5 M' Pasang pipa PVC O 15 Cm @ Rp. 86,007.63 = Rp 430,038.13
20 Kg Ijuk Saringan @ Rp. 12,900.00 = Rp 258,000.00
1 Alat - alat bantu @ Rp. 35,000.00 = Rp 35,000.00
Jumlah = Rp 7,665,094.66

15. Memasang 1 m' buis betonuk , Ø 30 - 100 cm


Bahan An. SNI ( Revisi ) 6.15.1
1.100 Bh Pipa beton @ Rp. 36,000.00 = Rp 39,600.00
0.550 m3 Batu bata @ Rp. 500.00 = Rp 275.00
10.300 Kg Semen portland @ Rp. 1,525.00 = Rp 15,707.50
0.061 m3 Pasir pasang @ Rp. 175,000.00 = Rp 10,675.00
0 m3 Pasir urug @ Rp. 100,000.00 = Rp 6,900.00
Sub total : = Rp 73,157.50
Upah An. SNI ( Revisi ) 6.15.2
0.380 Oh Pekerja @ Rp. 75,000.00 = Rp 28,500.00
0.190 Oh Tukang batu @ Rp. 107,250.00 = Rp 20,377.50
0.019 Oh Kepala tukang @ Rp. 108,000.00 = Rp 2,052.00
0.019 Oh Mandor @ Rp. 108,750.00 = Rp 2,066.25
Sub total : = Rp 52,995.75
Total upah+bahan : = Rp 126,153.25
Halaman : 6

ANALISA PERHITUNGAN HARGA PER M1 PEMBUATAN


PAGAR DEPAN

REKAPITULASI
RENCANA ANGGARAN BIAYA
PEMBANGUNAN PAGAR DEPAN BATU MERAH DAN BESI
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH TOTAL.


(Rp) (Rp).
1 2 3 4
A PAGAR DEPAN SEPANJANG 10 M'
I PEKERJAAN PERSIAPAN. Rp. 358,786.25
II PEK. TANAH DAN URUGAN Rp. 802,030.63
III PEK. PASANGAN Rp. ###
IV PEKERJAAN BETON Rp. ###
V PEKERJAAN PLESTERAN Rp. ###
VI PEKERJAAN BESI. Rp. ###
VII PEKERJAAN CAT - CATAN Rp. ###
VIII PEKERJAAN LAIN LAIN. Rp. 75,000.00
Jumlah : ###
Jumlah. Rp. ###
PPn 10 %. Rp. 1,496,428.16
Jumlah. Rp. ###
Dibulatkan. Rp. ###
Biaya perencanaan 7 %. Rp. 1,152,270.00
Jumlah. Rp. ###
Biaya pengawasan.4 %. Rp. 704,530.80
Jumlah. Rp. ###
Biaya PTP.1,3 %. Rp. 238,131.41
Jumlah total. Rp. ###
Dibulatkan. Rp. ###

Panjang pagar + pintu = 10 M1 Rp. ###


Jadi harga per M' Pagar depan tersebut ,
dengan tinggi pasangan 50Cm dan besi 100 Cm : = Rp. 1,855,600.00
D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 7

ANALISA PERHITUNGAN HARGA PER M1 PEMBUATAN


PAGAR DEPAN

RENCANA ANGGARAN BIAYA


PEMBANGUNAN PAGAR DEPAN BATU MERAH DAN BESI
DILOKASI KABUPATEN SIDOARJO.

VOLU- HARGA JUMLAH


NO JENIS PEKERJAAN ME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
A PAGAR DEPAN SEPANJANG 10 M'
I PEKERJAAN PERSIAPAN.
1 Pembersihan Lokasi 10.00 M2 3,500.00 35,000.00
2 Uiset bouwplank / uitset 3.00 M1 107,928.75 323,786.25
358,786.25
II PEK. TANAH DAN URUGAN
1 Galian tanah pondasi 7.68 M3 58,968.75 452,880.00
2 Urugan sirtu keliling pagar 10 Cm. 0.45 M3 148,225.00 66,701.25
3 Urugan sirtu bawah pondasi 1.85 M3 148,225.00 274,216.25
4 Urugan tanah kembali 0.50 M3 16,466.25 8,233.13
802,030.63
III PEK. PASANGAN
1 Aanstamping 1.52 M3 297,180.75 451,714.74
2 Pondasi batu kali 1 Pc : 3 Kp : 8 Ps 3.20 M3 482,104.75 1,542,735.20
3 Pas. dinding bata trasram 1Pc : 3 P 0.45 M3 768,080.77 345,636.35
4 Pasang dinding bata 1Pc : 3 Kp : 0.45 M3 625,225.77 281,351.60
2,621,437.88
IV PEKERJAAN BETON
1 Beton sloof praktis 15/20 K175 0.15 M3 ### 626,073.66
2 Beton kolom praktis 15/15 K175 0.19 M3 ### 704,770.20
3 Beton balok latai / ring balk K175 0.23 M3 ### 1,435,955.45
2,766,799.31
V PEKERJAAN PLESTERAN
1 Plesteran dinding trasram 1:3 12.00 M2 47,002.00 564,024.00
2 Plesteran beton 1:2 7.50 M2 49,763.00 373,222.50
3 Benangan air dan tali air 34.00 M1 15,243.75 518,287.50
1,455,534.00
VI PEKERJAAN BESI.
1 Pagar besi. 11.20 M2 376,666.67 4,218,666.67
2 Pasang pintu besi.lebar 2m 4.00 M2 385,000.00 1,540,000.00
3 Gembok. 1.00 Bh 50,000.00 50,000.00
5,808,666.67
VII PEKERJAAN CAT - CATAN
1 Cat dinding 19.50 M2 22,086.28 430,682.36
2 Cat besi. ( 3 x cat) 15.20 M2 42,456.88 645,344.50
1,076,026.86
VIII PEKERJAAN LAIN LAIN.
1 Pembersihan. 1.00 M1 75,000.00 75,000.00
75,000.00
D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 8

ANALISA PERHITUNGAN HARGA PER M1 PEMBUATAN


PAGAR SAMPING DAN BELAKANG

REKAPITULASI

RENCANA ANGGARAN BIAYA


PEMBANGUNAN PAGAR DEPAN BATU MERAH DAN BESI
PEMBANGUNAN PAGAR SAMPING BELAKANG DARI BATUMERAH.
DILOKASI KABUPATEN SIDOARJO.
1 2 3 4
B PAGAR SAMPING / BELAKANG TINGGI 2M SEPANJANG 10 M'
I PEKERJAAN PERSIAPAN. Rp. 574,643.75
II PEK. TANAH DAN URUGAN Rp. 872,618.75
III PEK. PASANGAN Rp. ###
IV PEKERJAAN BETON Rp. ###
V PEKERJAAN PLESTERAN Rp. ###
VI PEKERJAAN CAT - CATAN Rp. ###
VII PEKERJAAN LAIN LAIN. Rp. 50,000.00
Jumlah : ###

Jumlah. Rp. ###


PPn 10 %. Rp. 1,170,980.70
Jumlah. Rp. ###
Dibulatkan. Rp. ###
Biaya perencanaan 7 %. Rp. 901,670.00
Jumlah. Rp. ###
Biaya pengawasan.4 %. Rp. 551,306.80
Jumlah. Rp. ###
Biaya PTP.1,3 %. Rp. 186,341.70
Jumlah total. Rp. ###
Dibulatkan. Rp. ###

Panjang pagar + pintu = 10 M1 Rp. ###

Jadi harga per M' Pagar samping / belakang tersebut ,


dengan tinggi pasangan dinding 2 meter : = Rp. 1,452,000.00

D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 9

RENCANA ANGGARAN BIAYA


PEMBANGUNAN PAGAR DEPAN BATU MERAH DAN BESI
PEMBANGUNAN PAGAR SAMPING BELAKANG DARI BATU MERAH.
DILOKASI KABUPATEN SIDOARJO.
1 2 3 4 5 6
B PAGAR SAMPING / BELAKANG TINGGI 2M SEPANJANG 10 M'
I PEKERJAAN PERSIAPAN.
1 Pembersihan Lokasi 10.00 M2 3,500.00 35,000.00
2 Uiset bouwplank / uitset 5.00 M1 107,928.75 539,643.75
574,643.75

II PEK. TANAH DAN URUGAN


1 Galian tanah pondasi 8.50 M3 58,968.75 501,234.38
2 Urugan sirtu keliling pagar 10 Cm. 0.45 M3 148,225.00 66,701.25
3 Urugan sirtu bawah pondasi 2.00 M3 148,225.00 296,450.00
4 Urugan tanah kembali 0.50 M3 16,466.25 8,233.13
872,618.75

III PEK. PASANGAN


1 Aanstamping 1.85 M3 297,180.75 549,784.39
2 Pondasi batu kali 1 Pc : 3 Kp : 8 Ps 3.41 M3 482,104.75 1,643,977.20
3 Pas. dinding bata trasram 1Pc : 3 P 0.45 M3 768,080.77 345,636.35
4 Pasang dinding bata 1Pc : 3 Kp : 2.10 M3 625,225.77 1,312,974.12
3,852,372.05

IV PEKERJAAN BETON
1 Beton sloof praktis 15/20 K175 0.33 M3 ### 1,377,362.05
2 Beton kolom praktis 15/15 K175 0.16 M3 ### 593,490.70
3 Beton balok latai / ring balk K175 0.23 M3 ### 853,142.87
2,823,995.62

V PEKERJAAN PLESTERAN
1 Plesteran dinding trasram 1:3 6.00 M2 47,002.00 282,012.00
2 Plesteran beton 1:2 12.25 M2 49,763.00 609,596.75
3 Plesteran dinding biasa 1: 3: 8 28.00 M2 39,456.80 1,104,790.40
4 Benangan air dan tali air 34.00 M1 15,243.75 518,287.50
2,514,686.65

VI PEKERJAAN CAT - CATAN


1 Cat dinding 46.25 M2 22,086.28 1,021,490.22
1,021,490.22

VII PEKERJAAN LAIN LAIN.


1 Pembersihan. 1.00 Ls 50,000.00 50,000.00
50,000.00

D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 10
ANALISA PERHITUNGAN HARGA PER M2
BANGUNAN GEDUNG

REKAPITULASI
RENCANA ANGGARAN BIAYA
PEMBANGUNAN DUA RUANG KLAS UNTUK SMU
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH TOTAL.


(Rp) (Rp).
1 2 3 4

I PEKERJAAN PERSIAPAN. Rp. ###


II PEK. TANAH DAN URUGAN Rp. ###
III PEK. PASANGAN Rp. ###
IV PEKERJAAN PLESTERAN Rp. ###
V PEKERJAAN BETON Rp. ###
VI PEK. KUSEN, PINTU & JENDELA Rp. ###
VII PEK. KUDA - KUDA & RANGKA ATAP Rp. ###
VIII PEK. PENUTUP ATAP Rp. ###
IX PEK. LANGIT - LANGIT Rp. ###
X PEK. PENGGANTUNG & PENGUNCI Rp. ###
XI PEKERJAAN CAT - CATAN Rp. ###
XII PEKERJAAN LANTAI Rp. ###
XIII PEKERJAAN LISTRIK Rp. ###
XIV PEK. SALURAN Rp. ###

Jumlah. Rp. ###


PPn 10 %. Rp. ###
Jumlah. Rp. ###
Dibulatkan. Rp. ###
Biaya perencanaan 7 %. Rp. ###
Jumlah. Rp. ###
Biaya pengawasan.4 %. Rp. ###
Jumlah. Rp. ###
Biaya PTP.1,3 %. Rp. 6,906,953.75
Jumlah total. Rp. ###
Dibulatkan. Rp. ###

Luas lantai gedung 144 M2


s lantai teras separuh luas lantai gedung. 16 M2
jumlah luas lantai. 160 M2

Jadi harga per M2 bangunan gedung tsb. Rp.206.486.000 : 160 Rp. 3,363,818.75
Hd-AD-11+Taba\Analisa2\M2-sni05.Wk4\sheet Contoh RAB- 2005.

D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 11

ANALISA PERHITUNGAN HARGA PER M2


BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
PEMBANGUNAN DUA RUANG KLAS UNTUK SMU
DILOKASI KABUPATEN SIDOARJO.

HARGA JUMLAH
NO JENIS PEKERJAAN VOLUMESATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN.
1 Pembersihan Lokasi 240.00 M2 2,000.00 480,000.00
2 Uiset bouwplank / uitset 72.00 M1 107,928.75 7,770,870.00
8,250,870.00
II PEK. TANAH DAN URUGAN
1 Galian tanah pondasi 87.40 M3 58,968.75 5,153,868.75
2 Urugan sirtu keliling bangunan 74.50 M3 148,225.00 ###
3 Urugan sirtu bawah lantai 124.50 M3 148,225.00 ###
4 Urugan pasir bawah lantai 17.60 M3 143,587.50 2,527,140.00
5 Urugan tanah kembali 28.00 M3 16,466.25 461,055.00
###
III PEK. PASANGAN
1 Aanstamping 13.20 M3 297,180.75 3,922,785.90
2 Pondasi batu kali 1 Pc : 3 Kp : 8 Ps 32.94 M3 482,104.75 ###
3 Pasang rollag batu bata 1 Pc : 3 Ps 2.00 M2 768,080.77 1,536,161.54
3 Pas. dinding bata trasram 1Pc : 3 P 1.97 M3 768,080.77 1,513,119.12
4 Pasang dinding bata 1Pc : 3 Kp : 24.32 M3 625,225.77 ###
###
IV PEKERJAAN PLESTERAN
1 Plesteran dinding trasram 1:3 35.48 M2 47,002.00 1,667,630.96
2 Plesteran beton 1:3 95.79 M2 49,763.00 4,766,797.77
3 Plesteran dinding biasa 1: 3: 8 357.10 M2 39,456.80 ###
4 Benangan air dan tali air 357.00 M1 15,243.75 5,442,018.75
5 Kol-kolan keliling bangunan 82.00 M1 15,243.75 1,249,987.50
###
V PEKERJAAN BETON
1 Beton sloof praktis 15/15 K175 0.96 M3 ### 4,006,871.41
2 Beton sloof strutur 15 / 20 K175 2.70 M3 ### ###
3 Beton kolom praktis 15/15 K175 0.32 M3 ### 1,186,981.39
4 Beton kolom struktur 15 /30 K175 3.10 M3 ### ###
5 Beton balok latai / ring balk K175 2.32 M3 ### ###
6 Beton konsol K175 0.52 M3 ### 3,301,342.20
###
VI PEK. KUSEN, PINTU & JENDELA
1 Kusen kayu kamper 1.72 M3 ### ###
2 Daun pintu panil kamper. 6.89 M2 778,837.50 5,369,305.73
3 Konsol kayu bengkirai/kempas 0.59 M3 ### 4,810,933.75
4 Pasang kaca bening 5 mm ( jendela 14.18 M2 99,214.06 1,406,855.41
5 Jalusi kayu 1,5 x 15 cm 126.20 M' 17,500.00 2,208,500.00
6 daun pintu double teakwood rangk 1.76 M2 494,827.50 870,896.40
7 kadalan kayu kamper 2 x 4 cm 4.23 M' 15,000.00 63,450.00
8 lis kayu untuk pasang kaca mati 95.60 M' 5,750.00 549,700.00
9 angker / dook 76.00 Bh 20,000.00 1,520,000.00
###

D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-

Halaman : 12
1 2 3 4 5 6
VII PEK. KUDA - KUDA & RANGKA
1 Kuda - kuda kayu bengkirai / kruwi 1.85 M3 ### ###
2 Gording nok kayu / ikatan angin 1.96 M3 ### ###
3 Papan lisplank kayu kamper 3/30 68.12 M1 142,193.75 9,686,238.25
4 Papan lisplank kayu kamper 3/15 28.12 M1 71,096.88 1,999,244.13
5 Papan reuter kayu kruwing 20.00 M1 24,800.00 496,000.00
6 Psg usuk kayu kruwing 5/7 + rang ja281.20 M2 84,871.75 ###
###
VIII PEK. PENUTUP ATAP
1 Pasang atap genteng bambe Kw1 281.20 M2 106,980.00 ###
2 Pasang nok genteng bubungan 20.00 M1 114,277.50 2,285,550.00
###
IX PEK. LANGIT - LANGIT
1 Rka plafond ky meranti+ eternit 100248.30 M2 113,172.25 ###
2 Pasng list plafond kayu kamper 1/4 213.50 M1 7,500.00 1,601,250.00
###
X PEK. PENGGANTUNG & PENGUNCI
1 Pasang kunci tanam 3.00 Bh 171,873.75 515,621.25
2 Pasang engsel pintu 15.00 Bh 37,914.06 568,710.94
3 Pasang engsel jendela 32.00 Bh 26,609.38 851,500.00
4 Pasang hak angin jendela 32.00 Bh 22,109.38 707,500.00
5 Pasang handle jendela 16.00 Bh 8,000.00 128,000.00
6 Pasang grendel panjang 4.00 Bh 45,218.75 180,875.00
7 Pasang grendel biasa 16.00 Bh 59,318.75 949,100.00
8 Pasang grendel injak 4.00 Bh 15,000.00 60,000.00
9 Pasang beugel untuk kuda-kuda 16.00 Bh 12,000.00 192,000.00
10 Pasang angker baut 52.00 Bh 7,500.00 390,000.00
11 Pasang mur baut 152.00 Kg 7,000.00 1,064,000.00
5,607,307.19
XI PEKERJAAN CAT - CATAN
1 Cat dinding 395.37 M2 22,086.28 8,732,250.55
2 Cat Plafond 248.30 M2 22,086.28 5,484,022.08
3 Cata Kayu 190.00 M2 42,456.88 8,066,806.25
4 Plituran 18.60 M2 78,477.00 1,459,672.20
###
XII PEKERJAAN LANTAI
1 Pasang lantai keramic.30 x 30. 176.40 M2 119,477.82 ###
2 Lantai rabat keliling bangunan 63.60 M3 754,842.50 ###
###
XIII PEKERJAAN LISTRIK
1 Penyambungan inst. setempat. 1.00 Ls 150,000.00 150,000.00
2 Pasang Instalasi 18.00 ttk 213,500.00 3,843,000.00
3 Pasang stop kontak 2.00 Bh 22,500.00 45,000.00
4 Pasang lampu TL 2 x 20 watt 12.00 Bh 75,000.00 900,000.00
5 Pasang lampu pijar 25 watt 2.00 Bh 12,500.00 25,000.00
6 Pasang skalar ganda 3.00 Bh 25,000.00 75,000.00
7 Panel MCB 1.00 Unit 160,000.00 160,000.00
5,198,000.00
XIV PEK. SALURAN
1 Saluran buis beton terbuka dia 20 62.00 M1 37,500.00 2,325,000.00
2 Saluran buis beton tertutup dia 20 2.00 M1 45,000.00 90,000.00
3 Bak kontrol 6.00 Bh 244,033.25 1,464,199.50
3,879,199.50
D:\Budi\DataBudi\ANALISA-08A\SNI.08-A.wk4\sHEET RAB. -2008,-
ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

HARGA
NO JENIS PEKERJAAN VOLUME SATU- SATUAN
AN ( Rp )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00
2 Pek. Pembongkaran kap dan plafond 235.85 m2 3,000.00
3 Pek. Pembongkaran kusen lama. 1.00 Ls 500,000.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00
Jumlah :
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 2.59 M3 58,968.75
2 Pek. Urug tanah kembali 0.78 M3 16,466.25
3 Pek. Urugan sirtu bawah lantai / peninggian 25 Cm 59.96 M3 143,587.50
4 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 143,587.50
Jumlah :
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6). 80 Cm 6.36 M3 709,225.00
4 Pek. Pas bt. bata peninggian gewel ( 1 : 6) 70 Cm 5.78 M3 709,225.00
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00
7 Pek. Plesteran (1 : 3 : 5 ) 161.87 M2 39,691.00
8 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00
9 Pembongkaran dinding trasram lama.( 30 Cm ). 88.00 M1 12,500.00
10 Pasang trsram 30 Cm. 3.96 M3 799,884.62
11 Pek. Plesteran trasram (1 : 3) 52.80 M2 58,630.50
12 Pek. Plesteran beton (1 : 3) 57.60 M2 58,630.50
13 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75
14 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75
15 Pek. Tali air kusen 298.00 M' 15,243.75
Jumlah :
IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 0.91 M3 4,685,592.42
2 Pek. Cor Kolom utama 15/25 K 175 1.79 M3 4,685,592.42
3 Pek. Cor Kolom 15/15 peninggian bewel. K 175 0 M3 4,685,592.42
4 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50
5 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50
6 Pek. Cor Kolom sisi partisi 15/25 K 175 0.45 M3 3,625,148.94
7 Pek. Cor Ring balk gewel 15/20 K 175 1.95 M3 6,243,284.58
8 Pek. Cor Ring balk gedung 15/20 K 175 2.64 M3 6,243,284.58
Jumlah :
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kruwing 8/12 2 M3 8,154,125.00
2 Pasang gording kayu kruwing.8 / 12. 3 M3 8,154,125.00
3 Pasang usuk meranti 5/7 reng kamper 2/3 338 M2 107,919.39
4 Konsol meranti 2x6/12 + tiang teras. 1 M3 6,614,125.00
5 Pek. Papan reuter 2/20 meranti 28.50 M' 68,582.50
6 Pek. Lisplank 3/30 kamper 83.50 M' 142,193.75
7 Pek. Papan kompres 2/15 kamper 26.00 M' 95,672.50
8 Pek. Atap genteng Ex. Karangpilang 370.50 M2 75,080.00
9 Pek. Atap Bumbungan Ex. Karangpilang 28.50 M' 114,277.50
10 Pek. Rangka plafond kayu meranti. 304.50 M2 103,118.75
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB-SD. -2007,-

1 2 3 4 5

11 Pek. eternit Ex. Kerang Spesial 304.50 M2 33,638.50


12 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00
Jumlah :
VI PEK. KUSEN DAN PENGGANTUNG
1 Pek. Kusen kayu kamper 6/12 1.75 M3 11,982,425.00
2 Pek. jalusi kayu kamper 2.5/15 0.54 M3 11,982,425.00
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 265,000.00
7 Pek. Kaca 5 mm 20.50 M2 87,600.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00
9 Pek. Engsel jendela 21.00 Set 16,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00
12 Pas. Hak angin 21.00 Set 9,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00
Jumlah :
VII PEKERJAAN KERAMIK LANTAI
1 Pek. Keramik lantai 30/30 (putih polos) 235.85 m2 119,477.82
2 Pek. Keramik tegak stage20/30 (putih polos) 6.50 m2 119,477.82
Jumlah :
VIII PEKERJAAN INSTALASI LISTRIK .
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 8.00 bh 55,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00
Jumlah :
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 549.60 M2 28,386.28
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88
6 Pek. Pengecatan plafond 304.50 M2 28,386.28
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88
9 Pek. Cat Partisi 22.50 M2 36,336.88
Jumlah :
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

RANGKA ATAP KUDA2 KAYU.


REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,138,800.00

II PEKERJAAN TANAH Rp. 8,882,720.46

III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 39,220,370.98

IV PEKERJAAN BETON Rp. 48,995,903.28

V PEKERJAAN ATAP DAN PLAFOND Rp. 174,724,662.38

VI PEK. KUSEN DAN PENGGANTUNG Rp. 56,819,446.66

VII PEKERJAAN KERAMIK LANTAI Rp. 28,955,450.28

VIII PEKERJAAN INSTALASI LISTRIK . Rp. 2,508,500.00

IX PEKERJAAN PENGECATAN Rp. 34,840,550.23

Jumlah.
Jumlah. Rp.
PPn 10 %. Rp.
Jumlah. Rp.
Dibulatkan. Rp.
Biaya perencanaan 6 %. Rp.
Jumlah. Rp.
Biaya pengawasan.4 %. Rp.
Jumlah. Rp.
Biaya PTP.1,3 %. Rp.
Jumlah total. Rp.
Dibulatkan. Rp.

Luas lantai gedung 26,5 X 7 = 186 M2


luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp.
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .)

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2.
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar %
3 Harga per ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 1,889,575.92

Sidoarjo, Januari 2007.

Dihitung oleh:
Kasi Perencanaan Teknis
Subdin Tata Bangunan

Budi Utomo, ST. MM.


NIP. 110 022 647

3 RAUNG KLAS DAN KAMARMANDI/WC.


ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI GARI 3 RUANG KLAS DAN KAMAR MANDI / WC.(3 Km/Wc)
DILOKASI KABUPATEN SIDOARJO.

HARGA
NO JENIS PEKERJAAN VOLUME SATU- SATUAN
AN ( Rp )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00
2 Pek. Pembongkaran kap dan plafond 235.85 m2 3,000.00
3 Pek. Pembongkaran kusen lama. 1.00 Ls 500,000.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00
Jumlah :
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 2.59 M3 58,968.75
2 Pek. Urug tanah kembali 0.78 M3 16,466.25
3 Pek. Urugan sirtu bawah lantai / peninggian 25 Cm 59.96 M3 143,587.50
4 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 143,587.50
Jumlah :
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6). 80 Cm 6.36 M3 709,225.00
4 Pek. Pas bt. bata peninggian gewel ( 1 : 6) 70 Cm 5.78 M3 709,225.00
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00
7 Pek. Plesteran (1 : 3 : 5 ) 161.87 M2 39,691.00
8 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00
9 Pembongkaran dinding trasram lama.( 30 Cm ). 88.00 M1 12,500.00
10 Pasang trsram 30 Cm. 3.96 M3 768,080.77
11 Pek. Plesteran trasram (1 : 3) 52.80 M2 58,630.50
12 Pek. Plesteran beton (1 : 3) 57.60 M2 58,630.50
13 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75
14 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75
15 Pek. Tali air kusen 298.00 M' 15,243.75
Jumlah :
IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 0.91 M3 4,685,592.42
2 Pek. Cor Kolom utama 15/25 K 175 1.79 M3 4,685,592.42
3 Pek. Cor Kolom 15/15 peninggian bewel. K 175 0 M3 4,685,592.42
4 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50
5 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50
6 Pek. Cor Kolom sisi partisi 15/25 K 175 0.45 M3 3,625,148.94
7 Pek. Cor Ring balk gewel 15/20 K 175 1.95 M3 6,243,284.58
8 Pek. Cor Ring balk gedung 15/20 K 175 2.64 M3 6,243,284.58
Jumlah :
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kruwing 8/12 2 M3 8,154,125.00
2 Pasang gording kayu kruwing.8 / 12. 3 M3 8,154,125.00
3 Pasang usuk meranti 5/7 reng kamper 2/3 338 M2 107,919.39
4 Konsol meranti 2x6/12 + tiang teras. 1 M3 6,614,125.00
5 Pek. Papan reuter 2/20 meranti 28.50 M' 68,582.50
6 Pek. Lisplank 3/30 kamper 83.50 M' 142,193.75
7 Pek. Papan kompres 2/15 kamper 26.00 M' 95,672.50
8 Pek. Atap genteng Ex. Karangpilang 370.50 M2 75,080.00
9 Pek. Atap Bumbungan Ex. Karangpilang 28.50 M' 114,277.50

D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

1 2 3 4 5
10 Pek. Rangka plafond kayu meranti. 304.50 M2 103,118.75
11 Pek. eternit Ex. Kerang Spesial 304.50 M2 33,638.50
12 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00
Jumlah :
VI PEK. KUSEN DAN PENGGANTUNG
1 Pek. Kusen kayu kamper 6/12 1.75 M3 11,982,425.00
2 Pek. jalusi kayu kamper 2.5/15 0.54 M3 11,982,425.00
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 265,000.00
7 Pek. Kaca 5 mm 20.50 M2 87,600.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00
9 Pek. Engsel jendela 21.00 Set 16,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00
12 Pas. Hak angin 21.00 Set 9,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00
Jumlah :
VII PEKERJAAN KERAMIK LANTAI
1 Pek. Keramik lantai 30/30 (putih polos) 228.35 m2 119,477.82
2 Pek. Keramik tegak stage20/30 (putih polos) 6.50 m2 119,477.82
Jumlah :
VIII PEKERJAAN SANITASI. ( kAMAR MANDI / WC.
A PEKERJAAN ANITASI.
1 Pasang closed jomgkok. 3.00 bh 145,000.00
2 Pasang flour drain. 3.00 bh 35,000.00
3 Pasang bak mandi dari fiber glass 0,3 M3 3.00 bh 425,000.00
4 Pasang Kran air. 3.00 bh 25,000.00
5 Pasang pipa PVC 3/4 ". 18.00 M1 4,750.00
6 Pasang pipa PVC 4 " untuk avour Km & WC. 16.00 M1 27,500.00
7 Alat bantu ( lem, silotip dll) 1.00 Ls 85,000.00
Jumlah :
B PEKERJAAN PASANGAN + PLESTERAN.
1 Pasang batu merah trasram dudukan bak mandi
dudukan Closed jongkok. 1 : 3. 0.80 M3 768,080.77
2 Plesteran trasram. 18.00 M2 58,630.50
3 Benangan. 24.50 M1 15,243.75
4 Pembuatan septik tang. 1.00 Unit 7,665,094.66
5 Pasang pompa ex national / dab / simitzu. 1.00 Unit 475,000.00
Jumlah :
C PEKERJAAN PINTU + KERAMIC..
1 Pasang pintu Km dari PVC komplit kunci dan engsel. 3.00 Unit 575,000.00
2 Pasang keramic lantai kamar mandi / WC.(kasar) 7.50 M2 119,477.82
3 Pasang keramic dinding 20 x 25.tinggi 1,75 26.25 M2 119,477.82
Jumlah :
IX PEKERJAAN INSTALASI LISTRIK .
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 8.00 bh 55,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00
Jumlah :
X PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 579.60 M2 28,386.28
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88
6 Pek. Pengecatan plafond 304.50 M2 28,386.28
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88
9 Pek. Cat Partisi 22.50 M2 36,336.88
Jumlah :
3 RAUNG KLAS DAN KAMARMANDI/WC.
REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI GARI 3 RUANG KLAS DAN KAMAR MANDI / WC.(3 Km/Wc)
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,138,800.00

II PEKERJAAN TANAH Rp. 8,882,720.46

III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 39,094,427.75

IV PEKERJAAN BETON Rp. 48,995,903.28


V PEKERJAAN ATAP DAN PLAFOND Rp. 174,724,662.38

VI PEK. KUSEN DAN PENGGANTUNG Rp. 56,819,446.66

VII PEKERJAAN KERAMIK LANTAI Rp. 28,059,366.61

VIII PEKERJAAN SANITASI. ( kAMAR MANDI / WC.


A PEKERJAAN ANITASI. Rp. 2,500,500.00
B PEKERJAAN PASANGAN + PLESTERAN. Rp. 10,183,380.15
C PEKERJAAN PINTU + KERAMIC.. Rp. 5,757,376.51

IX PEKERJAAN INSTALASI LISTRIK . Rp. 2,508,500.00

X PEKERJAAN PENGECATAN Rp. 35,692,138.48

Jumlah.
Jumlah. Rp.
PPn 10 %. Rp.
Jumlah. Rp.
Dibulatkan. Rp.
Biaya perencanaan 6 %. Rp.
Jumlah. Rp.
Biaya pengawasan.4 %. Rp.
Jumlah. Rp.
Biaya PTP.1,3 %. Rp.
Jumlah total. Rp.
Dibulatkan. Rp.

Luas lantai gedung 26,5 X 7 = 186 M2


luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp.
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .)

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2.
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar %
3 Harga per ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 1,976,301.06

Untuk usulan rehabilitasi SD didaerah timur yang pasangan dindingnya sudah kropos sebaikmya diambil
ratan rata dari nilai per ruang :3 Rg. klas +kantor Kep. sekolah dengan 3 Rg. klas + Km / WC =

D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-


RANGKA ATAP GALVALUM.

RANGKA ATAP GALVALUM.


ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.
HARGA
NO JENIS PEKERJAAN VOLUME SATU- SATUAN
AN ( Rp )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00
2 Pek. Pembongkaran kap dan plafond 263.25 m2 3,000.00
3 Pek. Pembongkaran kusen 1.00 Ls 500,000.00
4 Pek. Pengupasan plesteran setinggi 2m 350.00 m2 3,500.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00
Jumlah :
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 41.75 M3 58,968.75
2 Pek. Urug tanah kembali 12.53 M3 16,466.25
3 Pek. Urugan sirtu bawah lantai / peninggian 25 Cm 59.38 M3 143,587.50
4 Pek. Urug pasir bawah pondasi dan lantai 5Cm 13.62 M3 143,587.50
Jumlah :
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 2.18 M3 297,180.75
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 1.09 M3 613,286.25
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6) 80 Cm 12.61 M3 709,225.00
4 Pek. Pas bt. bata gewel baru ( 1 : 6) 70 Cm 7.88 M3 709,225.00
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00
7 Pek. Pasangan batu bata atas kusen. 7.80 M3 709,225.00
8 Pek. Plesteran (1 : 3 : 5 ) 537.00 M2 39,691.00
9 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00
10 Pek. Plesteran trasram (1 : 3) 52.50 M2 58,630.50
11 Pek. Plesteran beton (1 : 3) 81.60 M2 58,630.50
12 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75
13 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75
14 Pek. Tali air kusen 298.00 M' 15,243.75
Jumlah :
IV PEKERJAAN BETON
1 Pek. Cor lantai kerja 0.63 M3 754,842.50
2 Pek. Cor kolom 20/20 selasar K 175 1.24 M3 4,685,592.42
3 Pek. Cor Kolom utama 15/25 dan 15/30 partisi K 175 2.40 M3 4,685,592.42
4 Pek. Cor balok latai 15/20 K 175 1.59 M3 6,243,284.58
5 Pek. Cor Kolom 15/15 peninggian &ring gewel K 175 1.43 M3 4,685,592.42
6 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50
7 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50
8 Pek. Cor plat setempat 60 x 60 tebal 20 cm K 175 1.78 M3 3,625,148.94
8 Pek. Cor Ring balk gedung + teras 15/20 K 175 2.25 M3 6,243,284.58
Jumlah :
V PEKERJAAN ATAP DAN PLAFOND
1 Pek. Atap Kuda - kuda Galvalum / Sincalum. 337.50 M2 170,000.00
2 Pek. Papan reuter 2/20 meranti 27.00 M' 68,582.50
3 Pek. Lisplank 3/30 kamper 77.00 M' 142,193.75
4 Pek. Papan kompres 2/15 kamper 25.00 M' 95,672.50
5 Pek. Atap genteng Ex. Karangpilang 337.50 M2 75,080.00
6 Pek. Atap Bumbungan Ex. Karangpilang 27.00 M' 114,277.50
7 Pek. Rangka plafond kayu meranti. 294.50 M2 103,118.75
8 Pek. eternit Ex. Kerang Spesial 294.50 M2 33,638.50
9 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00
Jumlah :

1 2 3 4 5

VI PEK. KUSEN DAN PENGGANTUNG


1 Pek. Kusen kayu kamper 6/15 2.19 M3 11,982,425.00

2 Pek. jalusi kayu kamper 2.5/15 0.54 M2 11,982,425.00


3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 Bh 778,837.50
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 503,396.25
7 Pek. Kaca 5 mm 20.50 M2 87,600.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00
9 Pek. Engsel jendela 21.00 Set 16,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00
12 Pas. Hak angin 21.00 Set 9,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00
Jumlah :
VII PEKERJAAN KERAMIK LANTAI
1 Pek. Keramik lantai 30/30 (putih polos) 237.50 m2 119,477.82
2 Pek. Keramik dinding luar 20/25 ( warna ) t :125 Cm 22.60 m2 119,477.82
3 Rabatan antara saluran dan lantai teras 7 Cm. 0.98 m3 754,842.50
4 Rabatan bawah lantai 5 Cm. camp. 1:3: 5. 11.88 m3 754,842.50
Jumlah :
VIII PEKERJAAN INSTALASI LISTRIK + SANITASI.
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 5.00 bh 55,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00
9 Pembuatan saluran terbuka dari bus beton U. 20. 40.00 M1 107,750.00
Jumlah :
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 622.60 M2 28,386.28
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88
6 Pek. Pengecatan plafond 294.50 M2 28,386.28
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88
9 Pek. Cat Partisi 22.50 M2 36,336.88
Jumlah :

D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

RANGKA ATAP GALVALUM.


REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 4,446,000.00

II PEKERJAAN TANAH Rp. 13,150,072.59

III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 63,332,620.80

IV PEKERJAAN BETON Rp. 59,675,091.24

V PEKERJAAN ATAP DAN PLAFOND Rp. 143,724,461.38

VI PEK. KUSEN DAN PENGGANTUNG Rp. 64,749,706.63

VII PEKERJAAN KERAMIK LANTAI Rp. 40,779,681.97

VIII PEKERJAAN INSTALASI LISTRIK + SANITASI. Rp. 6,653,500.00

IX PEKERJAAN PENGECATAN Rp. 36,628,885.55

Jumlah.
Jumlah. Rp.
PPn 10 %. Rp.
Jumlah. Rp.
Dibulatkan. Rp.
Biaya perencanaan 6 %. Rp.
Jumlah. Rp.
Biaya pengawasan.4 %. Rp.
Jumlah. Rp.
Biaya PTP.1,3 %. Rp.
Jumlah total. Rp.
Dibulatkan. Rp.

Luas lantai gedung 186 M2


luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp.
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .)

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2.
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 galvalum sebesar %
3 Harga per ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 2,055,963.09
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

KUDA2 BESI SIKU

RANGKA ATAP BAJA SIKU 50.50.5.

ANALISA PERHITUNGAN HARGA PER M2


REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

HARGA
NO JENIS PEKERJAAN VOLUME SATU- SATUAN
AN ( Rp )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00
2 Pek. Pembongkaran kap dan plafond 263.25 m2 3,000.00
3 Pek. Pembongkaran kusen 1.00 Ls 500,000.00
4 Pek. Pengupasan plesteran setinggi 2m 350.00 m2 3,500.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00
Jumlah :
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 41.75 M3 58,968.75
2 Pek. Urug tanah kembali 12.53 M3 16,466.25
3 Pek. Urugan sirtu bawah lantai / peninggian 25 Cm 59.38 M3 143,587.50
4 Pek. Urug pasir bawah pondasi dan lantai 5Cm 13.62 M3 143,587.50
Jumlah :
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 2.18 M3 297,180.75
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 1.09 M3 613,286.25
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6) 80 Cm 12.61 M3 709,225.00
4 Pek. Pas bt. bata gewel baru ( 1 : 6) 70 Cm 7.88 M3 709,225.00
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00
7 Pek. Pasangan batu bata atas kusen. 7.80 M3 709,225.00
8 Pek. Plesteran (1 : 3 : 5 ) 537.00 M2 39,691.00
9 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00
10 Pek. Plesteran trasram (1 : 3) 52.50 M2 58,630.50
11 Pek. Plesteran beton (1 : 3) 81.60 M2 58,630.50
12 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75
13 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75
14 Pek. Tali air kusen 298.00 M' 15,243.75
Jumlah :
IV PEKERJAAN BETON
1 Pek. Cor lantai kerja 0.63 M3 754,842.50
2 Pek. Cor kolom 20/20 selasar K 175 1.24 M3 4,685,592.42
3 Pek. Cor Kolom utama 15/25 dan 15/30 partisi K 175 2.40 M3 4,685,592.42
4 Pek. Cor balok latai 15/20 K 175 1.59 M3 6,243,284.58
5 Pek. Cor Kolom 15/15 peninggian &ring gewel K 175 1.43 M3 4,685,592.42
6 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50
7 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50
8 Pek. Cor plat setempat 60 x 60 tebal 20 cm K 175 1.78 M3 3,625,148.94
8 Pek. Cor Ring balk gedung + teras 15/20 K 175 2.25 M3 6,243,284.58
Jumlah :
V PEKERJAAN ATAP DAN PLAFOND
1 Pek. Kuda - kuda besi siku 50.50.5. 1,645.24 Kg 23,124.38
2 Besi siku konsol 45.45.5 334.08 Kg 23,124.38
3 Plat simpul +plat plendes. 395.86 Kg 23,124.38
4 Siku 60.60.6. penahan gording. 65.04 Kg 23,124.38
5 Fabrikasi / pengelasan. 2,375.18 Kg 2,250.00
6 Baut angker. 56.00 Bh 27,500.00
7 Biaya erections. 2,375.18 Kg 1,750.00
8 Pengecatan sincromate. 104.07 M2 41,086.25

1 2 3 4 5

9 Pasang gording kayu kruwing.8 / 12. 2.85 M3 8,154,125.00


10 Pasang usuk meranti 5/7 reng kamper 2/3 337.50 M2 84,871.75
11 Pek. Papan reuter 2/20 meranti 27.00 M' 68,582.50
12 Pek. Lisplank 3/30 kamper 77.00 M' 142,193.75
13 Pek. Papan kompres 2/15 kamper 25.00 M' 95,672.50
14 Pek. Atap genteng Ex. Karangpilang 337.50 M2 75,080.00
15 Pek. Atap Bumbungan Ex. Karangpilang 27.00 M' 114,277.50
16 Pek. Rangka plafond kayu meranti. 294.50 M2 103,118.75
17 Pek. eternit Ex. Kerang Spesial 294.50 M2 33,638.50
18 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00
Jumlah :

VI PEK. KUSEN DAN PENGGANTUNG


1 Pek. Kusen kayu kamper 6/15 2.19 M3 11,982,425.00
2 Pek. jalusi kayu kamper 2.5/15 0.54 M2 11,982,425.00
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 Bh 778,837.50
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 503,396.25
7 Pek. Kaca 5 mm 20.50 M2 87,600.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00
9 Pek. Engsel jendela 21.00 Set 16,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00
12 Pas. Hak angin 21.00 Set 9,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00
Jumlah :

VII PEKERJAAN KERAMIK LANTAI


1 Pek. Keramik lantai 30/30 (putih polos) 237.50 m2 119,477.82
2 Pek. Keramik dinding luar 20/25 ( warna ) t :125 Cm 22.60 m2 119,477.82
3 Rabatan antara saluran dan lantai teras 7 Cm. 0.98 m3 754,842.50
4 Rabatan bawah lantai 5 Cm. camp. 1:3: 5. 11.88 m3 754,842.50
Jumlah :

VIII PEKERJAAN INSTALASI LISTRIK + SANITASI.


1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 5.00 bh 55,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00
9 Pembuatan saluran terbuka dari bus beton U. 20. 40.00 M1 107,750.00
Jumlah :

IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 622.60 M2 28,386.28
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88
6 Pek. Pengecatan plafond 294.50 M2 28,386.28
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88
9 Pek. Cat Partisi 22.50 M2 36,336.88
Jumlah :

RANGKA ATAP BAJA SIKU 50.50.5.


REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 4,446,000.00

II PEKERJAAN TANAH Rp. 13,150,072.59

III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 63,332,620.80

IV PEKERJAAN BETON Rp. 59,675,091.24

V PEKERJAAN ATAP DAN PLAFOND Rp. 209,987,894.27

VI PEK. KUSEN DAN PENGGANTUNG Rp. 64,749,706.63

VII PEKERJAAN KERAMIK LANTAI Rp. 40,779,681.97

VIII PEKERJAAN INSTALASI LISTRIK + SANITASI. Rp. 6,653,500.00

IX PEKERJAAN PENGECATAN Rp. 36,628,885.55

Jumlah.
Jumlah. Rp.
PPn 10 %. Rp.
Jumlah. Rp.
Dibulatkan. Rp.
Biaya perencanaan 6 %. Rp.
Jumlah. Rp.
Biaya pengawasan.4 %. Rp.
Jumlah. Rp.
Biaya PTP.1,3 %. Rp.
Jumlah total. Rp.
Dibulatkan. Rp.

Luas lantai gedung 188 M2


luas lantai teras separuh luas lantai gedung. 13 M2
jumlah luas lantai. 200 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp.
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .)

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2.
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 galvalum sebesar %
3 Harga per ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 2,497,017.28
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-
RANGKA BESI WF

RANGKA ATAP BAJA W.F. 203. 133. 5,84. 7,82


ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

HARGA
NO JENIS PEKERJAAN VOLUME SATU- SATUAN
AN ( Rp )
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00
2 Pek. Pembongkaran kap dan plafond 263.25 m2 3,000.00
3 Pek. Pembongkaran kusen 1.00 Ls 500,000.00
4 Pek. Pengupasan plesteran setinggi 2m 350.00 m2 3,500.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00
Jumlah :
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat 41.75 M3 58,968.75
2 Pek. Urug tanah kembali 12.53 M3 16,466.25
3 Pek. Urugan sirtu bawah lantai / peninggian 25 Cm 59.38 M3 143,587.50
4 Pek. Urug pasir bawah pondasi dan lantai 5Cm 13.62 M3 143,587.50
Jumlah :
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 2.18 M3 297,180.75
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 1.09 M3 613,286.25
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6) 80 Cm 12.61 M3 709,225.00
4 Pek. Pas bt. bata gewel baru ( 1 : 6) 70 Cm 7.88 M3 709,225.00
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00
7 Pek. Pasangan batu bata atas kusen. 7.80 M3 709,225.00
8 Pek. Plesteran (1 : 3 : 5 ) 537.00 M2 39,691.00
9 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00
10 Pek. Plesteran trasram (1 : 3) 52.50 M2 58,630.50
11 Pek. Plesteran beton (1 : 3) 81.60 M2 58,630.50
12 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75
13 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75
14 Pek. Tali air kusen 298.00 M' 15,243.75
Jumlah :
IV PEKERJAAN BETON
1 Pek. Cor lantai kerja 0.63 M3 754,842.50
2 Pek. Cor kolom 20/20 selasar K 175 1.24 M3 4,685,592.42
3 Pek. Cor Kolom utama 15/25 dan 20/30 partisi K 175 3.15 M3 4,685,592.42
4 Pek. Cor balok latai 15/20 K 175 1.59 M3 6,243,284.58
5 Pek. Cor Kolom 15/15 peninggian &ring gewel K 175 1.43 M3 4,685,592.42
6 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50
7 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50
8 Pek. Cor plat setempat 60 x 60 tebal 20 cm K 175 1.78 M3 3,625,148.94
8 Pek. Cor Ring balk gedung + teras 15/20 K 175 2.25 M3 6,243,284.58
Jumlah :
V PEKERJAAN ATAP DAN PLAFOND
1 Pek. Kuda - kuda W.F. 203. 133. 5,84. 7,82. 1,675.37 Kg 23,124.38
2 Besi siku konsol 45.45.5 334.08 Kg 23,124.38
3 Plat simpul +plat plendes. 130.64 Kg 23,124.38
4 Siku 60.60.6. penahan gording. 65.04 Kg 23,124.38
5 Fabrikasi / pengelasan. 2,205.12 Kg 2,250.00
6 Baut angker. 56.00 Bh 27,500.00
7 Biaya erections. 2,205.12 Kg 1,750.00
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

1 2 3 4 5

8 Pengecatan sincromate. 75.18 M2 41,086.25


9 Pasang gording CANAL C.150. 50. 20. 3.2 555.93 Kg 23,124.38
10 Pasang usuk meranti 5/7 reng kamper 2/3 337.50 M2 107,919.39

11 Pek. Papan reuter 2/20 meranti 27.00 M' 68,582.50


12 Pek. Lisplank 3/30 kamper 77.00 M' 142,193.75

13 Pek. Papan kompres 2/15 kamper 25.00 M' 95,672.50


14 Pek. Atap genteng Ex. Karangpilang 337.50 M2 75,080.00
15 Pek. Atap Bumbungan Ex. Karangpilang 27.00 M' 114,277.50
16 Pek. Rangka plafond kayu meranti. 294.50 M2 103,118.75
17 Pek. eternit Ex. Kerang Spesial 294.50 M2 33,638.50
18 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00
Jumlah :
VI PEK. KUSEN DAN PENGGANTUNG
1 Pek. Kusen kayu kamper 6/15 2.19 M3 11,982,425.00
2 Pek. jalusi kayu kamper 2.5/15 0.54 M2 11,982,425.00
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 Bh 778,837.50
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 503,396.25
7 Pek. Kaca 5 mm 20.50 M2 87,600.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00
9 Pek. Engsel jendela 21.00 Set 16,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00
12 Pas. Hak angin 21.00 Set 9,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00
Jumlah :

VII PEKERJAAN KERAMIK LANTAI


1 Pek. Keramik lantai 30/30 (putih polos) 237.50 m2 119,477.82
2 Pek. Keramik dinding luar 20/25 ( warna ) t :125 Cm 22.60 m2 119,477.82
3 Rabatan antara saluran dan lantai teras 7 Cm. 0.98 m3 754,842.50
4 Rabatan bawah lantai 5 Cm. camp. 1:3: 5. 11.88 m3 754,842.50
Jumlah :
VIII PEKERJAAN INSTALASI LISTRIK + SANITASI.
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 5.00 bh 55,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00
9 Pembuatan saluran terbuka dari bus beton U. 20. 40.00 M1 107,750.00
Jumlah :
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 622.60 M2 28,386.28
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88
6 Pek. Pengecatan plafond 294.50 M2 28,386.28
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88
9 Pek. Cat Partisi 22.50 M2 36,336.88
Jumlah :
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

RANGKA ATAP BAJA W.F. 203. 133. 5,84. 7,82


REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
I UNIT TERDIRI 3 RUANG KLAS DAN SATU BUAH KANTOR.
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 4,446,000.00

II PEKERJAAN TANAH Rp. 13,150,072.59

III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 63,332,620.80

IV PEKERJAAN BETON Rp. 63,189,285.56

V PEKERJAAN ATAP DAN PLAFOND Rp. 200,069,161.38

VI PEK. KUSEN DAN PENGGANTUNG Rp. 64,749,706.63

VII PEKERJAAN KERAMIK LANTAI Rp. 40,779,681.97

VIII PEKERJAAN INSTALASI LISTRIK + SANITASI. Rp. 6,653,500.00

IX PEKERJAAN PENGECATAN Rp. 36,628,885.55

Jumlah.
Jumlah. Rp.
PPn 10 %. Rp.
Jumlah. Rp.
Dibulatkan. Rp.
Biaya perencanaan 6 %. Rp.
Jumlah. Rp.
Biaya pengawasan.4 %. Rp.
Jumlah. Rp.
Biaya PTP.1,3 %. Rp.
Jumlah total. Rp.
Dibulatkan. Rp.

Luas lantai gedung 188 M2


luas lantai teras separuh luas lantai gedung. 13 M2
jumlah luas lantai. 200 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp.
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .)

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2.
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 BESI.WF sebesar %
3 Harga per ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 2,464,994.59
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-

DAFTAR HARGA BAHAN BANGUNAN


DAN UPAH KERJA
DIWILAYAH KABUPATEN SIDOARJO

PERBANDINGAN HARGA PER RUANG.KLAS


ATAS DASAR PEMAKAIAN KONSTRUKSI ATAP / KUDA KUDA
SEBAGAI DASAR USULAN ANGGARAN TAHUN 2008

1 KUDA KUDA KAYU KRUWING HARGA PER RUIANG KLAS ( RP ) :


KUDA KUDA KAYU KRUWING HARGA PER M2 ( RP ) :

2 KUDA KUDA GALVALUM HARGA PER RUANG KLAS ( RP ) :


KUDA KUDA GALVALUM HARGA PER M2 ( RP ) :

3 KUDA KUDA SKU 50.50.5 HARGA PER RUANG KLAS ( RP ) :


KUDA KUDA SKU 50.50.5 HARGA PER M2 ( RP ) :

4 KUDA KUDA W.F. 203. 133. 5,84. 7,82. HARGA PER RANG KLAS ( RP ) :
KUDA KUDA W.F. 203. 133. 5,84. 7,82. HARGA PER M2 ( RP ) :

5 KUDA KUDA KAYU TAHUN DAN SEBAGIAN DIPAKAI KEMBALI EX. INPRES
HARGA PER RUANG KLAS (RP) :
KUDA KUDA KAYU TAHUN SEBAGIAN DIPAKAI ADA PENINGGIAN PER M2 ( RP ) :

6 KUDA KUDA KAYU JATI JAMAN BELANDA. KAYU LAMADIPAKAI KEMBALI


HARGA PER RUANG KLAS (RP) :
KUDA KUDA KAYU JATI TANPA PENINGGIAN PER M2 ( RP ) :

Sidoarjo, JANUARI 2008.


Dihitung oleh:
Kasi Perencanaan Teknis
Subdin Tata Bangunan

Budi Utomo, ST. MM.


NIP. 110 022 647
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\sHEET RAB. -2007,-
Halaman : 14

M2

SAR
ANTOR.

JUMLAH
HARGA
( Rp )
6

1,181,250.00
707,550.00
500,000.00
750,000.00
3,138,800.00

152,729.06
12,794.28
8,609,506.50
107,690.63
8,882,720.46

256,764.17
412,128.36
4,510,671.00
4,095,774.38
909,581.06
1,631,217.50
6,424,649.87
750,000.00
1,100,000.00
3,167,543.08
3,095,690.40
3,377,116.80
2,789,606.25
2,156,990.63
4,542,637.50
39,220,370.98

4,273,260.29
8,363,782.47
1,054,258.30
3,344,406.00
1,672,203.00
1,631,317.02
12,174,404.92
16,482,271.28
48,995,903.28

19,406,817.50
23,239,256.25
36,422,794.13
4,166,898.75
1,954,601.25
11,873,178.13
2,487,485.00
27,817,140.00
3,256,908.75
31,399,659.38

Halaman : 15
6

10,242,923.25
2,457,000.00
174,724,662.38

20,993,208.60
6,470,509.50
5,560,899.75
13,302,354.20
1,797,124.61
2,981,250.00
1,795,800.00
684,000.00
352,800.00
691,200.00
1,701,000.00
199,500.00
289,800.00
56,819,446.66

28,178,844.44
776,605.85
28,955,450.28

1,365,000.00
29,500.00
112,000.00
102,000.00
440,000.00
60,000.00
175,000.00
225,000.00
2,508,500.00

15,601,096.74
3,114,070.19
1,616,990.94
1,798,675.31
1,046,502.00
8,643,620.74
1,308,127.50
893,887.13
817,579.69
34,840,550.23
Halaman : 13

TOR.

JUMLAH HARGA
(Rp)

398,086,404.28
398,086,407.28
39,808,640.73
437,895,048.01
437,895,000.00
26,273,700.00
464,168,700.00
18,566,748.00
482,735,448.00
6,275,560.82
489,011,008.82
489,011,000.00
2,321,162.93
1,889,575.92

3,447,914.22
67.32

112,665,964.32

oarjo, Januari 2007.

Dihitung oleh:
si Perencanaan Teknis
Subdin Tata Bangunan

i Utomo, ST. MM.


NIP. 110 022 647

Halaman : 17

M2

SAR
C.(3 Km/Wc)

JUMLAH
HARGA
( Rp )
6

1,181,250.00
707,550.00
500,000.00
750,000.00
3,138,800.00

152,729.06
12,794.28
8,609,506.50
107,690.63
8,882,720.46
256,764.17
412,128.36
4,510,671.00
4,095,774.38
909,581.06
1,631,217.50
6,424,649.87
750,000.00
1,100,000.00
3,041,599.85
3,095,690.40
3,377,116.80
2,789,606.25
2,156,990.63
4,542,637.50
39,094,427.75

4,273,260.29
8,363,782.47
1,054,258.30
3,344,406.00
1,672,203.00
1,631,317.02
12,174,404.92
16,482,271.28
48,995,903.28

19,406,817.50
23,239,256.25
36,422,794.13
4,166,898.75
1,954,601.25
11,873,178.13
2,487,485.00
27,817,140.00
3,256,908.75

Halaman : 18
6
31,399,659.38
10,242,923.25
2,457,000.00
174,724,662.38

20,993,208.60
6,470,509.50
5,560,899.75
13,302,354.20
1,797,124.61
2,981,250.00
1,795,800.00
684,000.00
352,800.00
691,200.00
1,701,000.00
199,500.00
289,800.00
56,819,446.66

27,282,760.77
776,605.85
28,059,366.61

435,000.00
105,000.00
1,275,000.00
75,000.00
85,500.00
440,000.00
85,000.00
2,500,500.00

614,464.62
1,055,349.00
373,471.88
7,665,094.66
475,000.00
10,183,380.15

1,725,000.00
896,083.67
3,136,292.84
5,757,376.51

1,365,000.00
29,500.00
112,000.00
102,000.00
440,000.00
60,000.00
175,000.00
225,000.00
2,508,500.00

16,452,684.99
3,114,070.19
1,616,990.94
1,798,675.31
1,046,502.00
8,643,620.74
1,308,127.50
893,887.13
817,579.69
35,692,138.48
Halaman : 16

Km/Wc)

JUMLAH HARGA
(Rp)
416,357,222.28
416,357,225.28
41,635,722.53
457,992,947.81
457,993,000.00
27,479,580.00
485,472,580.00
19,418,903.20
504,891,483.20
6,563,589.28
511,455,072.48
511,455,000.00

2,427,696.69
1,976,301.06

3,447,914.22
70.41

117,836,950.55

sebaikmya diambil
115,251,457.44
Halaman : 20

R M2
NG
SAR
KANTOR.

JUMLAH
HARGA
( Rp )
6

1,181,250.00 397.58
789,750.00 397.58
500,000.00 ###
1,225,000.00 158.00
750,000.00 233.75
4,446,000.00

2,461,945.31 7.86
206,239.78 3.54
8,526,225.75 62.92
1,955,661.75 13.05
13,150,072.59

647,259.67 1.18
668,482.01 2.70
8,943,327.25 16.36
5,585,146.88
909,581.06
1,631,217.50 1.42
5,531,955.00 ###
21,314,067.00 1,553,999.00
750,000.00 2.36
3,078,101.25 158.00
4,784,248.80 35.06
2,789,606.25 170.20
2,156,990.63 28.80
4,542,637.50 318.32
63,332,620.80

475,550.78 0.45
5,810,134.60 0.31
11,245,421.81 1.83
9,926,822.47
6,700,397.16 0.92
3,344,406.00 0.48
1,672,203.00 0.30
6,452,765.12 0.80
14,047,390.29 3.40
59,675,091.24
### #VALUE!
57,375,000.00 1,553,999.00
1,851,727.50 29.50
10,948,918.75 85.60
2,391,812.50 27.00
25,339,500.00 397.58
3,085,492.50 29.50
30,368,471.88 315.75
9,906,538.25
2,457,000.00 305.20
143,724,461.38 ###
1,553,999.00

Halaman : 21
6

26,241,510.75 2.40

6,470,509.50 0.63 144 22


5,560,899.75 8.93 1
13,302,354.20 7.62
1,797,124.61 5.10
5,663,207.81 17.50
1,795,800.00 5.01
684,000.00 57.00
352,800.00 34.00
691,200.00 8.00
1,701,000.00 7.62
199,500.00 15.25
289,800.00 7.62
64,749,706.63

28,375,982.84 242.00
2,700,198.79
739,745.65
8,963,754.69 1.00
40,779,681.97
###
1,365,000.00 1,553,999.00
29,500.00 4.00
112,000.00 2.00
102,000.00 5.00
275,000.00 14.00
60,000.00 6.00
175,000.00
225,000.00
4,310,000.00 1.00
6,653,500.00

17,673,294.82 523.60
3,114,070.19 101.00
1,616,990.94 45.42
1,798,675.31 58.03
1,046,502.00 13.30
8,359,757.99 315.75
1,308,127.50 305.20
893,887.13 42.75
817,579.69 1,553,999.00
36,628,885.55 ###

Halaman : 19

JUMLAH HARGA
(Rp)

433,140,020.16
433,140,023.16
43,314,002.32
476,454,025.47
476,454,000.00
28,587,240.00
505,041,240.00
20,201,649.60
525,242,889.60
6,828,157.56
532,071,047.16
532,071,000.00

/M2 1,800,337.00

65 % 1,170,219.05

2,525,553.58 73
2,055,963.09

3,447,914.22
73.25

122,586,799.01

Halaman : 23

R M2
NG

SAR
KANTOR.

JUMLAH
HARGA
( Rp )
6

1,181,250.00 397.58
789,750.00 397.58
500,000.00 ###
1,225,000.00 158.00
750,000.00 233.75
4,446,000.00

2,461,945.31 7.86
206,239.78 3.54
8,526,225.75 62.92
1,955,661.75 ###
13,150,072.59

647,259.67 1.18
668,482.01 2.70
8,943,327.25 16.36
5,585,146.88
909,581.06
1,631,217.50 1.42
5,531,955.00 ###
21,314,067.00 1,553,999.00
750,000.00 2.36
3,078,101.25 158.00
4,784,248.80 35.06
2,789,606.25 170.20
2,156,990.63 28.80
4,542,637.50 318.32
63,332,620.80

475,550.78 0.45
5,810,134.60 0.31
11,245,421.81 1.83
9,926,822.47
6,700,397.16 0.92
3,344,406.00 0.48
1,672,203.00 0.30
6,452,765.12 0.80
14,047,390.29 3.40
59,675,091.24
###
38,045,130.77 1,553,999.00
7,725,372.70
9,154,100.69
1,504,009.35
5,344,159.98
1,540,000.00
4,156,568.87
4,275,833.71

Halaman : 24
6

23,249,041.20
28,644,215.63
1,851,727.50 29.50
10,948,918.75 85.60
2,391,812.50 27.00
25,339,500.00 397.58
3,085,492.50 29.50
30,368,471.88 315.75
9,906,538.25
2,457,000.00 305.20
209,987,894.27 ###
1,553,999.00

26,241,510.75 2.40
6,470,509.50 0.63
5,560,899.75 8.93
13,302,354.20 7.62
1,797,124.61 5.10
5,663,207.81 17.50
1,795,800.00 5.01
684,000.00 57.00
352,800.00 34.00
691,200.00 8.00
1,701,000.00 7.62
199,500.00 15.25
289,800.00 7.62
64,749,706.63

28,375,982.84 242.00
2,700,198.79
739,745.65
8,963,754.69 1.00
40,779,681.97

###
1,365,000.00 1,553,999.00
29,500.00 4.00
112,000.00 2.00
102,000.00 5.00
275,000.00 14.00
60,000.00 6.00
175,000.00
225,000.00
4,310,000.00 1.00
6,653,500.00

17,673,294.82 523.60
3,114,070.19 101.00
1,616,990.94 45.42
1,798,675.31 58.03
1,046,502.00 13.30
8,359,757.99 315.75
1,308,127.50 305.20
893,887.13 42.75
817,579.69 1,553,999.00
36,628,885.55 ###

Halaman : 22

.
JUMLAH HARGA
(Rp)

1,800,337.00
1,170,219.05

499,403,453.06
499,403,456.06
49,940,345.61
549,343,801.66
549,344,000.00
32,960,640.00
582,304,640.00
23,292,185.60
605,596,825.60
7,872,758.73
613,469,584.33
613,470,000.00

/M2

65 %

3,067,350.00 89
2,497,017.28

3,447,914.22
88.96

148,884,655.34
Halaman : 26

R M2
NG

SAR
KANTOR.

JUMLAH
HARGA
( Rp )
6

1,181,250.00 397.58
789,750.00 397.58
500,000.00 ###
1,225,000.00 158.00
750,000.00 233.75
4,446,000.00

2,461,945.31 7.86
206,239.78 3.54
8,526,225.75 62.92
1,955,661.75 ###
13,150,072.59

647,259.67 1.18
668,482.01 2.70
8,943,327.25 16.36
5,585,146.88
909,581.06
1,631,217.50 1.42
5,531,955.00 ###
21,314,067.00 1,553,999.00
750,000.00 2.36
3,078,101.25 158.00
4,784,248.80 35.06
2,789,606.25 170.20
2,156,990.63 28.80
4,542,637.50 318.32
63,332,620.80

475,550.78 0.45
5,810,134.60 0.31
14,759,616.13 1.83
9,926,822.47
6,700,397.16 0.92
3,344,406.00 0.48
1,672,203.00 0.30
6,452,765.12 0.80
14,047,390.29 3.40
63,189,285.56
###
38,741,791.65 1,553,999.00
7,725,372.70
3,020,853.23
1,504,009.35
4,961,520.50
1,540,000.00
3,858,960.39

Halaman : 27
6

3,088,864.28
12,855,533.79
36,422,794.13

1,851,727.50 29.50
10,948,918.75 85.60

2,391,812.50 27.00
25,339,500.00 397.58
3,085,492.50 29.50
30,368,471.88 315.75
9,906,538.25
2,457,000.00 305.20
200,069,161.38 ###

26,241,510.75 2.40
6,470,509.50 0.63
5,560,899.75 8.93
13,302,354.20 7.62
1,797,124.61 5.10
5,663,207.81 17.50
1,795,800.00 5.01
684,000.00 57.00
352,800.00 34.00
691,200.00 8.00
1,701,000.00 7.62
199,500.00 15.25
289,800.00 7.62
64,749,706.63

28,375,982.84 242.00
2,700,198.79
739,745.65
8,963,754.69 1.00
40,779,681.97
###
1,365,000.00 1,553,999.00
29,500.00 4.00
112,000.00 2.00
102,000.00 5.00
275,000.00 14.00
60,000.00 6.00
175,000.00
225,000.00
4,310,000.00 1.00
6,653,500.00

17,673,294.82 523.60
3,114,070.19 101.00
1,616,990.94 45.42
1,798,675.31 58.03
1,046,502.00 13.30
8,359,757.99 315.75
1,308,127.50 305.20
893,887.13 42.75
817,579.69 1,553,999.00
36,628,885.55 ###

Halaman : 25

JUMLAH HARGA
(Rp)

492,998,914.48
492,998,917.48
49,299,891.75
542,298,809.23
542,299,000.00
32,537,940.00
574,836,940.00
22,993,477.60
597,830,417.60
7,771,795.43
605,602,213.03
605,602,000.00

/M2

65 %

3,067,350.00 89
2,464,994.59

3,447,914.22
88.96

146,975,302.27

Halaman : 33

KUDA
008

112,665,964.32 3067350
1,889,575.92 89

122,586,799.01
2,055,963.09

148,884,655.34
2,497,017.28

146,975,302.27 3067350
2,464,994.59 89

#VALUE!

126,543,396.23
2,122,321.11

98,103,073.31
1,751,840.59

Dihitung oleh:
si Perencanaan Teknis
Subdin Tata Bangunan

i Utomo, ST. MM.


NIP. 110 022 647
ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNANBIAYA
RENCANA ANGGARAN GEDUNG
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP ASBES GELOMBANG EX. INPRES.
ADA PENINGGIAN LANTAI 40 CM.
DILOKASI KABUPATEN SIDOARJO.
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00 1,181,250.00
2 Pek. Pembongkaran kap dan plafond 235.85 m2 3,000.00 707,550.00
3 Pek. Pembongkaran kusen lama. 1.00 Ls 500,000.00 500,000.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00 750,000.00
Jumlah : 3,138,800.00
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat / Teras. 2.59 M3 58,968.75 152,729.06
2 Pek. Urug tanah kembali 0.78 M3 16,466.25 12,794.28
3 Pek. Urugan sirtu bawah lantai / peninggian 40 Cm 94.34 M3 143,587.50 13,546,044.75
4 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 143,587.50 107,690.63
Jumlah : 13,819,258.71

III PEK. PASANGAN, PLESTERAN & BENANGAN


1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75 256,764.17
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25 412,128.36
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6). 120 Cm 6.36 M3 709,225.00 4,510,671.00
4 Pek. Pas bt. bata atas kusen ( 1 : 6). 65 Cm 5.17 M3 709,225.00 3,664,920.19
5 Pek. Pas bt. bata peninggian gewel ( 1 : 6) 70 Cm 5.78 M3 709,225.00 4,095,774.38
6 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00 909,581.06
7 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00 1,631,217.50
8 Pek. Plesteran (1 : 6 ) 230.85 M2 39,691.00 9,162,799.65
9 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00 750,000.00
10 Pembongkaran plesteran dinding 1 mtr. luar + dlm. 176.00 M2 6,500.00 1,144,000.00
11 Pek. Plesteran dinding 1m luar dlm trasram (1 : 3) 176.00 M2 58,630.50 10,318,968.00
12 Pek. Plesteran beton (1 : 3) 57.60 M2 58,630.50 3,377,116.80
13 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75 2,789,606.25
14 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75 2,156,990.63
15 Pek. Tali air kusen 298.00 M' 15,243.75 4,542,637.50
Jumlah : 49,723,175.48

IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 0.91 M3 4,685,592.42 4,273,260.29
2 Pek. Cor Kolom utama 15/25 K 175 1.79 M3 4,685,592.42 8,363,782.47
3 Pek. Cor Kolom 15/15 peninggian bewel. K 175 0 M3 4,685,592.42 1,054,258.30
4 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50 3,344,406.00
5 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50 1,672,203.00
6 Pek. Cor Kolom sisi partisi 15/25 K 175 0.38 M3 3,625,148.94 1,359,430.85
7 Pek. Cor Ring balk gewel 15/20 K 175 1.95 M3 6,243,284.58 12,174,404.92
8 Pek. Cor Ring balk gedung 15/20 K 175 2.64 M3 6,243,284.58 16,482,271.28
Jumlah : 48,724,017.11

1 2 3 4 5 6
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kruwing 8/12 2 M3 8,154,125.00 19,406,817.50
2 Pasang gording kayu kruwing.8 / 12. 3 M3 8,154,125.00 23,239,256.25
3 Pasang usuk meranti 5/7 reng kamper 2/3 338 M2 107,919.39 36,422,794.13
4 Konsol meranti 2x6/12 + tiang teras. 1 M3 6,614,125.00 4,166,898.75
5 Pek. Papan reuter 2/20 meranti 28.50 M' 68,582.50 1,954,601.25
6 Pek. Lisplank 3/30 kamper 83.50 M' 142,193.75 11,873,178.13
7 Pek. Papan kompres 2/15 kamper 26.00 M' 95,672.50 2,487,485.00
8 Pek. Atap genteng Ex. Karangpilang 337.50 M2 75,080.00 25,339,500.00
9 Pek. Atap Bumbungan Ex. Karangpilang 28.50 M' 114,277.50 3,256,908.75
10 Pek. Rangka plafond kayu meranti. 304.50 M2 103,118.75 31,399,659.38
11 Pek. eternit Ex. Kerang Spesial 337.50 M2 33,638.50 11,352,993.75
12 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00 2,457,000.00
Jumlah : 173,357,092.88

VI PEK. KUSEN DAN PENGGANTUNG


1 Pek. Kusen kayu kamper 6/12 1.75 M3 11,982,425.00 20,993,208.60
2 Pek. jalusi kayu kamper 2.5/15 0.54 M3 11,982,425.00 6,470,509.50
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50 5,560,899.75
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00 13,302,354.20
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25 1,797,124.61
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 265,000.00 2,981,250.00
7 Pek. Kaca 5 mm 20.50 M2 87,600.00 1,795,800.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00 684,000.00
9 Pek. Engsel jendela 21.00 Set 16,800.00 352,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00 691,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00 1,701,000.00
12 Pas. Hak angin 21.00 Set 9,500.00 199,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00 289,800.00
Jumlah : 56,819,446.66

VII PEKERJAAN KERAMIK LANTAI


1 Pek. Keramik lantai 30/30 (putih polos) 235.85 m2 119,477.82 28,178,844.44
2 Rabatan bawah keramic 6 Cm. 14.15 m3 754,842.50 10,681,776.22
Jumlah : 38,860,620.65
34,600.00
VIII PEKERJAAN INSTALASI LISTRIK .
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00 1,365,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00 112,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00 102,000.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 8.00 bh 55,000.00 440,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00 60,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00 225,000.00
Jumlah : 2,508,500.00

IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 519.31 M2 28,386.28 14,741,181.85
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88 3,114,070.19
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88 1,616,990.94
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88 1,798,675.31
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88 1,046,502.00
6 Pek. Pengecatan plafond 304.50 M2 28,386.28 8,643,620.74
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98 1,308,127.50
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88 893,887.13
9 Pek. Cat Partisi 22.50 M2 36,336.88 817,579.69
Jumlah : 33,980,635.34
RANGKA ATAP DARI BESI.C. KE KUDA2 KAYU. ( 1 ) Asbes PENINGGIAN LANTAI.
REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP ASBES GELOMBANG EX. INPRES.
ADA PENINGGIAN LANTAI 40 CM.
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,138,800.00
II PEKERJAAN TANAH Rp. 13,819,258.71
III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 49,723,175.48
IV PEKERJAAN BETON Rp. 48,724,017.11
V PEKERJAAN ATAP DAN PLAFOND Rp. 173,357,092.88
VI PEK. KUSEN DAN PENGGANTUNG Rp. 56,819,446.66
VII PEKERJAAN KERAMIK LANTAI Rp. 38,860,620.65
VIII PEKERJAAN INSTALASI LISTRIK . Rp. 2,508,500.00
IX PEKERJAAN PENGECATAN Rp. 33,980,635.34
Jumlah. 420,931,546.84
Jumlah. Rp. 420,931,549.84
PPn 10 %. Rp. 42,093,154.98
Jumlah. Rp. 463,024,704.82
Dibulatkan. Rp. 463,025,000.00
Biaya perencanaan 6 %. Rp. 27,781,500.00
Jumlah. Rp. 490,806,500.00
Biaya pengawasan.4 %. Rp. 19,632,260.00
Jumlah. Rp. 510,438,760.00
Biaya PTP.1,3 %. Rp. 6,635,703.88
Jumlah total. Rp. 517,074,463.88
Dibulatkan. Rp. 517,074,000.00

Luas lantai gedung 26,5 X 7 = 186 M2


luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp. 2,454,368.10
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .) 1,998,013.76

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2. 3,447,914.22
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar % 71.18
Harga per
3 ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 1,998,013.76 119,131,570.71

Sidoarjo, Pebruari 2007.


Dihitung oleh:
Kasi Perencanaan Teknis
Subdin Tata Bangunan

Budi Utomo, ST. MM.


NIP. 110 022 647
ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP ASBES GELOMBANG EX. INPRES.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap asbes gelombang. 337.50 m2 3,500.00 1,181,250.00
2 Pek. Pembongkaran kap dan plafond 235.85 m2 3,000.00 707,550.00
3 Pek. Pembongkaran kusen lama. 1.00 Ls 500,000.00 500,000.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00 750,000.00
Jumlah : 3,138,800.00
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat / Teras. 2.59 M3 58,968.75 152,729.06
2 Pek. Urug tanah kembali 0.78 M3 16,466.25 12,794.28
3 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 148,912.50 111,684.38
Jumlah : 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75 256,764.17
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25 412,128.36
3 Pek. Pas bt. bata peninggian dinding ( 1 : 6). 80 Cm 6.36 M3 709,225.00 4,510,671.00
4 Pek. Pas bt. bata atas kusen ( 1 : 6). 65 Cm 5.17 M3 709,225.00 3,664,920.19
5 Pek. Pas bt. bata peninggian gewel ( 1 : 6) 70 Cm 5.78 M3 709,225.00 4,095,774.38
6 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00 909,581.06
7 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00 1,631,217.50
8 Pek. Plesteran (1 : 3 : 5 ) 144.19 M2 39,691.00 5,722,912.99
9 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00 750,000.00
10 Pembongkaran plesteran dinding 1 mtr. luar + dlm. 176.00 M2 6,500.00 1,144,000.00
11 Pek. Plesteran dinding 1m luar dlm trasram (1 : 3) 176.00 M2 58,630.50 10,318,968.00
12 Pek. Plesteran beton (1 : 3) 57.60 M2 58,630.50 3,377,116.80
13 Pek. Benangan kolom dan konsol 183.00 M' 15,243.75 2,789,606.25
14 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75 2,156,990.63
15 Pek. Tali air kusen 298.00 M' 15,243.75 4,542,637.50
Jumlah : 46,283,288.81
IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 0.91 M3 4,685,592.42 4,273,260.29
2 Pek. Cor Kolom utama 15/25 K 175 1.79 M3 4,685,592.42 8,363,782.47
3 Pek. Cor Kolom 15/15 peninggian bewel. K 175 0 M3 4,685,592.42 1,054,258.30
4 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50 3,344,406.00
5 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50 1,672,203.00
6 Pek. Cor Kolom sisi partisi 15/25 K 175 0.38 M3 3,625,148.94 1,359,430.85
7 Pek. Cor Ring balk gewel 15/20 K 175 1.95 M3 6,243,284.58 12,174,404.92
8 Pek. Cor Ring balk gedung 15/20 K 175 2.64 M3 6,243,284.58 16,482,271.28
Jumlah : 48,724,017.11
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kruwing 8/12 2 M3 8,154,125.00 19,406,817.50
2 Pasang gording kayu kruwing.8 / 12. 3 M3 8,154,125.00 23,239,256.25
3 Pasang usuk meranti 5/7 reng kamper 2/3 338 M2 107,919.39 36,422,794.13
4 Konsol meranti 2x6/12 + tiang teras. 1 M3 6,614,125.00 4,166,898.75

1 2 3 4 5 6

5 Pek. Papan reuter 2/20 meranti 28.50 M' 68,582.50 1,954,601.25


6 Pek. Lisplank 3/30 kamper 83.50 M' 142,193.75 11,873,178.13
7 Pek. Papan kompres 2/15 kamper 26.00 M' 95,672.50 2,487,485.00
8 Pek. Atap genteng Ex. Karangpilang 370.50 M2 75,080.00 27,817,140.00
9 Pek. Atap Bumbungan Ex. Karangpilang 28.50 M' 114,277.50 3,256,908.75
10 Pek. Rangka plafond kayu meranti. 337.50 M2 103,118.75 34,802,578.13
11 Pek. eternit Ex. Kerang Spesial 337.50 M2 33,638.50 11,352,993.75
12 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00 2,457,000.00
Jumlah : 179,237,651.63
VI PEK. KUSEN DAN PENGGANTUNG
1 Pek. Kusen kayu kamper 6/12 1.75 M3 11,982,425.00 20,993,208.60
2 Pek. jalusi kayu kamper 2.5/15 0.54 M3 11,982,425.00 6,470,509.50
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50 5,560,899.75
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00 13,302,354.20
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25 1,797,124.61
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 265,000.00 2,981,250.00
7 Pek. Kaca 5 mm 20.50 M2 87,600.00 1,795,800.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00 684,000.00
9 Pek. Engsel jendela 21.00 Set 16,800.00 352,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00 691,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00 1,701,000.00
12 Pas. Hak angin 21.00 Set 9,500.00 199,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00 289,800.00
Jumlah : 56,819,446.66
VII PEKERJAAN KERAMIK LANTAI
1 Pek. Keramik lantai 30/30 (putih polos) 235.85 m2 119,477.82 28,178,844.44
2 Rabatan bawah keramic 6 Cm. 14.15 m3 754,842.50 10,681,021.38
Jumlah : 38,859,865.81
VIII PEKERJAAN INSTALASI LISTRIK .
1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00 1,365,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00 112,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00 102,000.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 8.00 bh 55,000.00 440,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00 60,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00 225,000.00
Jumlah : 2,508,500.00
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 377.79 M2 28,386.28 10,723,956.21
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88 3,114,070.19
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88 1,616,990.94
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88 1,798,675.31
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88 1,046,502.00
6 Pek. Pengecatan plafond 337.50 M2 28,386.28 9,580,367.81
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98 1,308,127.50
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88 893,887.13
9 Pek. Cat Partisi 22.50 M2 36,336.88 817,579.69
Jumlah : 30,900,156.77
RANGKA ATAP DARI BESI.C. KE KUDA2 KAYU. ( 2 ) Asbes TANPA PENINGGIAN
REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP ASBES GELOMBANG EX. INPRES.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,138,800.00
II PEKERJAAN TANAH Rp. 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 46,283,288.81
IV PEKERJAAN BETON Rp. 48,724,017.11
V PEKERJAAN ATAP DAN PLAFOND Rp. 179,237,651.63
VI PEK. KUSEN DAN PENGGANTUNG Rp. 56,819,446.66
VII PEKERJAAN KERAMIK LANTAI Rp. 38,859,865.81
VIII PEKERJAAN INSTALASI LISTRIK . Rp. 2,508,500.00
IX PEKERJAAN PENGECATAN Rp. 30,900,156.77
Jumlah. 406,748,934.51
Jumlah. Rp. 406,748,937.51
PPn 10 %. Rp. 40,674,893.75
Jumlah. Rp. 447,423,831.26
Dibulatkan. Rp. 447,424,000.00
Biaya perencanaan 6 %. Rp. 26,845,440.00
Jumlah. Rp. 474,269,440.00
Biaya pengawasan.4 %. Rp. 18,970,777.60
Jumlah. Rp. 493,240,217.60
Biaya PTP.1,3 %. Rp. 6,412,122.83
Jumlah total. Rp. 499,652,340.43
Dibulatkan. Rp. 499,652,000.00

Luas lantai gedung 26,5 X 7 = 186 M2


luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp. 2,371,672.01
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .) 1,930,693.90
Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2. 3,447,914.22
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar % 68.79
Harga per
3 ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 1,930,693.90 115,117,623.82

Sidoarjo, Pebruari 2007.


Dihitung oleh:
Kasi Perencanaan Teknis
Subdin Tata Bangunan

Budi Utomo, ST. MM.


NIP. 110 022 647

Halaman : 28
RANGKA ATAP LAMA DIPAKAI KEMBALI (Jati). MODEL ATAP PERISAI DAN TANPA PENINGGIAN.
ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS UKURAN KLAS 6 X 8 M
BANGUNAN ATAP GENTENG VLAMS / JAMAN BELANDA.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.

HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap GENTENG FLAMS. 337.50 m2 3,500.00 1,181,250.00
2 Pek. Pembongkaran kap dan plafond 293.00 m2 5,250.00 1,538,250.00
3 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00 750,000.00
Jumlah : 3,469,500.00
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat / Teras. 2.59 M3 58,968.75 152,729.06
2 Pek. Urug tanah kembali 0.78 M3 16,466.25 12,794.28
3 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 148,912.50 111,684.38
Jumlah : 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75 256,764.17
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25 412,128.36
2 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 709,225.00 909,581.06
3 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 709,225.00 1,631,217.50
4 Pek. Plesteran (1 : 3 : 5 ) 46.00 M2 39,691.00 1,825,786.00
5 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00 750,000.00
6 Pembongkaran plesteran dinding 1 mtr. luar + dlm. 176.00 M2 6,500.00 1,144,000.00
7 Pek. Plesteran trasram (1 : 3) 176.00 M2 58,630.50 10,318,968.00
8 Pek. Plesteran beton (1 : 3) 57.60 M2 58,630.50 3,377,116.80
9 Pek. Benangan kolom dan konsol 115.00 M' 15,243.75 1,753,031.25
10 Pek. Benangan ban - banan tepi lantai. 84.00 M' 15,243.75 1,280,475.00
Jumlah : 23,659,068.14
IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 1.20 M3 4,685,592.42 5,622,710.91
2 Pek. Cor Kolom 15/25 pembungkus tiang kayu K 175 1.79 M3 4,685,592.42 8,363,782.47
3 Pek. Cor Ring balk gedung 15/20 + konsol K 175 3.18 M3 6,243,284.58 19,853,644.95
Jumlah : 33,840,138.33
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kayu lama 35% 1 M3 1,450,000.00 1,131,000.00
2 Pasang kuda kuda kayu kruwing 8/12 (baru) 2 M3 8,154,125.00 13,454,306.25
3 Pasang gording jurai dan konsol.8 / 12. 1 M3 8,154,125.00 8,561,831.25
4 Pasang gording kayu kruwing.8 / 12. 3 M3 8,154,125.00 23,239,256.25
5 Pasang usuk meranti 5/7 reng kamper 2/3 (baru) 303.00 M2 107,919.39 32,699,575.17
6 Konsol meranti 2x6/12 + tiang teras. (baru) 1 M3 6,614,125.00 4,166,898.75
7 Pek. Papan reuter 2/20 meranti 50.00 M' 68,582.50 3,429,125.00
8 Pek. Lisplank 3/30 kamper 74.00 M' 142,193.75 10,522,337.50
9 Pek. Atap genteng Ex. Karangpilang 303.00 M2 75,080.00 22,749,240.00
10 Pek. Atap Bumbungan Ex. Karangpilang 50.00 M' 114,277.50 5,713,875.00
11 Pek. Rangka plafond kayu meranti. 251.75 M2 103,118.75 25,960,145.31
12 Pek. eternit Ex. Kerang Spesial 251.75 M2 33,638.50 8,468,492.38
13 Pek. List plafond kayu kamper 1/5 165.00 M' 9,750.00 1,608,750.00
Jumlah : 161,704,832.86

Halaman : 29
1 2 3 4 5 6

VI PEK. KUSEN DAN PENGGANTUNG


1 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50 5,560,899.75
2 Pek. Penggantian kawat harmonica. 52.00 M2 27,500.00 1,430,000.00
3 Pek. Daun pintu doubel triplek (penghubung) 4.20 M2 503,396.25 2,114,264.25
4 Pek. Engsel pintu 18.00 Set 22,800.00 410,400.00
5 Pek. Kunci daun pintu Yale 2 x Putar 5.00 Set 115,200.00 576,000.00
Jumlah : 10,091,564.00

VII PEKERJAAN KERAMIK LANTAI


1 Pek. Keramik lantai 30/30 (putih polos) 180.00 m2 119,477.82 21,506,008.05
2 Rabatan bawah keramic 6 Cm. 10.80 m3 754,842.50 8,152,299.00
Jumlah : 29,658,307.05

VIII PEKERJAAN INSTALASI LISTRIK .


1 Pek. Titik Instalasi listrik 17.00 Ttk 65,000.00 1,105,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00 112,000.00
4 Pas. Stop kontak 3.00 bh 25,500.00 76,500.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 6.00 bh 55,000.00 330,000.00
6 Pas. Lampu pijar 25 Wt 3.00 bh 15,000.00 45,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00 225,000.00
Jumlah : 2,098,000.00

IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 452.00 M2 28,386.28 12,830,596.30
2 Pek. Pengecatan kayu kusen 115.00 M2 36,336.88 4,178,740.63
3 Pek. Pengecatan daun pintu dan jendela 68.50 M2 36,336.88 2,489,075.94
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88 1,046,502.00
6 Pek. Pengecatan plafond 251.75 M2 28,386.28 7,146,244.73
7 Pek. Pengecatan list plafond 165.00 M' 5,190.98 856,512.05
8 Pek. Pengecatan papan lisplank 26.50 M2 36,336.88 962,927.19
Jumlah : 29,510,598.83
Halaman : 27
RANGKA ATAP LAMA DIPAKAI KEMBALI (Jati). MODEL ATAP PERISAI DAN TANPA PENINGGIAN.

REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS UKURAN KLAS 6 X 8 M
BANGUNAN ATAP GENTENG VLAMS / JAMAN BELANDA.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,469,500.00
II PEKERJAAN TANAH Rp. 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 23,659,068.14
IV PEKERJAAN BETON Rp. 33,840,138.33
V PEKERJAAN ATAP DAN PLAFOND Rp. 161,704,832.86
VI PEK. KUSEN DAN PENGGANTUNG Rp. 10,091,564.00
VII PEKERJAAN KERAMIK LANTAI Rp. 29,658,307.05
VIII PEKERJAAN INSTALASI LISTRIK . Rp. 2,098,000.00
IX PEKERJAAN PENGECATAN Rp. 29,510,598.83
Jumlah. 294,309,216.93
Jumlah. Rp. 294,309,219.93
PPn 10 %. Rp. 29,430,921.99
Jumlah. Rp. 323,740,141.92
Dibulatkan. Rp. 323,740,000.00
Biaya perencanaan 6 %. Rp. 19,424,400.00
Jumlah. Rp. 343,164,400.00
Biaya pengawasan.4 %. Rp. 13,726,576.00
Jumlah. Rp. 356,890,976.00
Biaya PTP.1,3 %. Rp. 4,639,582.69
Jumlah total. Rp. 361,530,558.69
Dibulatkan. Rp. 361,531,000.00
Luas lantai gedung 24 X 6 = 144 M2
luas lantai teras separuh luas lantai gedung. 24 M2
jumlah luas lantai. 168 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp. 2,151,970.24
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .) 1,751,840.59

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2. 3,447,914.22
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar % 62.41
Harga per
3 ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
56 X 1,751,840.59 98,103,073.31

Halaman : 31
RANGKA ATAP LAMA KUDA2 KAYU DIPAKAI LAGI SEBAGIAN.
ANALISA PERHITUNGAN HARGA PER M2
REHABILITASI BANGUNAN GEDUNG
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP GENTENG FLAMS EX. INPRES.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.

HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran atap. 337.50 m2 3,500.00 1,181,250.00
2 Pek. Pembongkaran kap dan plafond 235.85 m2 3,000.00 707,550.00
3 Pek. Pembongkaran kusen lama. 1.00 Ls 500,000.00 500,000.00
5 Pek. Pembersihan Lokasi 1.00 Ls 750,000.00 750,000.00
Jumlah : 3,138,800.00
II. PEKERJAAN TANAH
1 Pek. Galian pondasi setempat / Teras. 2.59 M3 58,968.75 152,729.06
2 Pek. Urug tanah kembali 0.78 M3 16,466.25 12,794.28
3 Pek. Urug sirtu bawah pondasi 10 Cm 0.75 M3 148,912.50 111,684.38
Jumlah : 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN
1 Pek. Pasangan Aanstampeng 0.86 M3 297,180.75 256,764.17
2 Pek. Pasangan batu kali setempat (1pc : 6ps) 0.67 M3 613,286.25 412,128.36
3 Pek. Pasangan batu bata peninggian 30 Cm. 2.39 M3 613,286.25 1,462,687.71
4 Pek. Plesteran (1 : 3 : 5 ) 31.80 M2 39,691.00 1,262,173.80
5 Pek. Pasangan batu bata stage dekat papan tulis 1.28 M3 613,286.25 786,539.62
6 Pek. Pasangan batu bata tepi selasar 30 Cm. 2.30 M3 613,286.25 1,410,558.38
7 Pek. Plesteran (1 : 3 : 5 ) 144.19 M2 39,691.00 5,722,912.99
8 Pek. Perbaikan / pemasangan dinding retak 1.00 Ls 750,000.00 750,000.00
9 Pembongkaran plesteran dinding 1 mtr. luar + dlm. 176.00 M2 6,500.00 1,144,000.00
10 Pek. Plesteran trasram (1 : 3) 176.00 M2 58,630.50 10,318,968.00
11 Pek. Benangan ban - banan tepi lantai. 141.50 M' 15,243.75 2,156,990.63
12 Pek. perbaikan benangnan 85.00 M' 15,243.75 1,295,718.75
Jumlah : 26,979,442.39
IV PEKERJAAN BETON
1 Pek. Cor kolom 20/20 selasar K 175 0.91 M3 6,967,512.50 6,354,371.40
2 Pek. Cor Konsol 15/20 K 175 0.48 M3 6,967,512.50 3,344,406.00
3 Pek. Cor balok gantung 15/30 K 175 0.24 M3 6,967,512.50 1,672,203.00
4 Pek. Cor Ring balk gewel 15/20 K 175 1.95 M3 6,243,284.58 12,174,404.92
5 Pek. Cor Kolom sisi partisi 15/25 K 175 0.45 M3 3,625,148.94 1,631,317.02
6 Pek. Cor Ring balk gedung 15/20 K 175 2.64 M3 6,243,284.58 16,482,271.28
Jumlah : 41,658,973.62
V PEKERJAAN ATAP DAN PLAFOND
1 Pasang kuda kuda kayu kruwing 8/12 lama 35 % 1 M3 1,450,000.00 1,203,500.00
2 Pasang kuda kuda kayu kruwing 8/12 baru 2 M3 8,154,125.00 12,638,893.75
3 Pasang gording kayu kruwing.8 / 12.lama 25 % 1 M3 1,450,000.00 1,029,500.00
4 Pasang gording kayu kruwing.8 / 12. baru. 2 M3 8,154,125.00 17,449,827.50
5 Pasang usuk meranti 5/7 reng kamper 2/3 338 M2 107,919.39 36,422,794.13
6 Konsol meranti 2x6/12 + tiang teras. 1 M3 6,614,125.00 4,166,898.75
7 Pek. Lisplank 3/30 kamper 83.50 M' 142,193.75 11,873,178.13
8 Pek. Papan kompres 2/15 kamper 26.00 M' 95,672.50 2,487,485.00
9 Pek. Atap genteng Ex. Karangpilang 337.50 M2 75,080.00 25,339,500.00
10 Pek. Atap Bumbungan Ex. Karangpilang 28.50 M' 114,277.50 3,256,908.75
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\SHEET Rb SD2 \2007..

Halaman : 32
1 2 3 4 5 6

11 Pek. Rangka plafond kayu meranti. 304.50 M2 103,118.75 31,399,659.38


12 Pek. eternit Ex. Kerang Spesial 304.50 M2 33,638.50 10,242,923.25
13 Pek. List plafond kayu kamper 1/5 252.00 M' 9,750.00 2,457,000.00
Jumlah : 159,968,068.63

VI PEK. KUSEN DAN PENGGANTUNG


1 Pek. Kusen kayu kamper 6/12 1.75 M3 11,982,425.00 20,993,208.60
2 Pek. jalusi kayu kamper 2.5/15 0.54 M3 11,982,425.00 6,470,509.50
3 Pek. Daun pintu panil kamper isi Multiplek 9 mm 7.14 M2 778,837.50 5,560,899.75
4 Pek. Daun jendela kaca kayu kamper 20.66 M2 643,870.00 13,302,354.20
5 Pek. Daun pintu doubel triplek (penghubung) 3.57 M2 503,396.25 1,797,124.61
6 Pek. Daun Partisi doubel triplek rangka kamper 11.25 M2 265,000.00 2,981,250.00
7 Pek. Kaca 5 mm 20.50 M2 87,600.00 1,795,800.00
8 Pek. Engsel pintu & partisi 30.00 Set 22,800.00 684,000.00
9 Pek. Engsel jendela 21.00 Set 16,800.00 352,800.00
10 Pek. Kunci daun pintu Yale 2 x Putar 6.00 Set 115,200.00 691,200.00
11 Pas. Grendel Jendela 21.00 Set 81,000.00 1,701,000.00
12 Pas. Hak angin 21.00 Set 9,500.00 199,500.00
13 Pas. Handel jendela 21.00 Set 13,800.00 289,800.00
Jumlah : 56,819,446.66

VII PEKERJAAN KERAMIK LANTAI


1 Pek. Keramik lantai 30/30 (putih polos) 235.85 m2 119,477.82 28,178,844.44
2 Rabatan bawah keramic 6 Cm. 14.15 m3 754,842.50 10,681,776.22
Jumlah : 38,860,620.65

VIII PEKERJAAN INSTALASI LISTRIK .


1 Pek. Titik Instalasi listrik 21.00 Ttk 65,000.00 1,365,000.00
2 Pas. Skakelar ganda 1.00 bh 29,500.00 29,500.00
3 Pas. Skakelar tunggal 4.00 bh 28,000.00 112,000.00
4 Pas. Stop kontak 4.00 bh 25,500.00 102,000.00
5 Pas. Lampu TL 1 x 20 Wt dan reflektor 8.00 bh 55,000.00 440,000.00
6 Pas. Lampu pijar 25 Wt 4.00 bh 15,000.00 60,000.00
7 Pas. Panel MCB 1.00 Unit 175,000.00 175,000.00
8 Penyambunmgan over spaneeng. 1.00 Unit 225,000.00 225,000.00
Jumlah : 2,508,500.00

IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 512.00 M2 28,386.28 14,533,772.80
2 Pek. Pengecatan kayu kusen 85.70 M2 36,336.88 3,114,070.19
3 Pek. Pengecatan daun pintu dan jendela 44.50 M2 36,336.88 1,616,990.94
4 Pek. Pengecatan papan jalusi 49.50 M2 36,336.88 1,798,675.31
5 Pek. Pengecatan tiang selasar dan konsol kayu 28.80 M2 36,336.88 1,046,502.00
6 Pek. Pengecatan plafond 304.50 M2 28,386.28 8,643,620.74
7 Pek. Pengecatan list plafond 252.00 M' 5,190.98 1,308,127.50
8 Pek. Pengecatan papan lisplank 24.60 M2 36,336.88 893,887.13
9 Pek. Cat Partisi 22.50 M2 36,336.88 817,579.69
Jumlah : 33,773,226.29

D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\SHEET Rb SD2 \2007..

Halaman : 30
Dari genteng flams TANPA PENINGGIAN
LAMA KUDA2 KAYU DIPAKAI LAGI SEBAGIAN.
REKAPITULASI
RENCANA ANGGARAN BIAYA
UTUK REHABILITASI GEDUNG SEKOLAH DASAR
1 UNIT TERDIRI DARI : 3 RUANG KLAS DAN SATU BUAH KANTOR.
BANGUNAN ATAP GENTENG FLAMS EX. INPRES.
TIDAK ADA PENINGGIAN LANTAI
DILOKASI KABUPATEN SIDOARJO.

NO. URAIAN PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 3,138,800.00
II PEKERJAAN TANAH Rp. 277,207.71
III PEK. PASANGAN, PLESTERAN & BENANGAN Rp. 26,979,442.39
IV PEKERJAAN BETON Rp. 41,658,973.62
V PEKERJAAN ATAP DAN PLAFOND Rp. 159,968,068.63
VI PEK. KUSEN DAN PENGGANTUNG Rp. 56,819,446.66
VII PEKERJAAN KERAMIK LANTAI Rp. 38,860,620.65
VIII PEKERJAAN INSTALASI LISTRIK . Rp. 2,508,500.00
IX PEKERJAAN PENGECATAN Rp. 33,773,226.29
Jumlah. 363,984,285.95
Jumlah. Rp. 363,984,288.95
PPn 10 %. Rp. 36,398,428.90
Jumlah. Rp. 400,382,717.85
Dibulatkan. Rp. 400,383,000.00
Biaya perencanaan 6 %. Rp. 24,022,980.00
Jumlah. Rp. 424,405,980.00
Biaya pengawasan.4 %. Rp. 16,976,239.20
Jumlah. Rp. 441,382,219.20
Biaya PTP.1,3 %. Rp. 5,737,968.85
Jumlah total. Rp. 447,120,188.05
Dibulatkan. Rp. 447,120,000.00
Luas lantai gedung 26,5 X 7 = 186 M2
luas lantai teras separuh luas lantai gedung. 25 M2
jumlah luas lantai. 211 M2

Jadi harga Rehab per M2 bangunan gedung (+DC + DV+ PTP) tsb. Rp. 2,122,321.11
Harga per M2 rehabilitasi bangunan gedung SD ( BKF saja .) 2,122,321.11

Catatan:
1 HARGA BANGUNAN TYPE ( C ) Per M2. 3,447,914.22
2 Prosentase kerusakan untuk SD dengan atap genteng kuda2 kayu sebesar % 61.55
Harga per
3 ruang klas untuk direhabilitasi 1 unit 3 Rg.Klas + Km /WC. =
60 X 2,122,321.11 126,543,396.23
D:\Budi\DataBudi\ANALISA-07A\SNI.07-A.wk4\SHEET Rb SD2 \2007..

Sidoarjo, Pebruari 2007.


Dihitung oleh:
Kasi Perencanaan Teknis
Subdin Tata Bangunan

Budi Utomo, ST. MM.


NIP. 110 022 647
517,074,000.00
71.18

517,074,000.00
71.18

71.18

517,074,000.00
71.18
517,074,000.00
71.18

517,074,000.00
71.18

517,074,000.00
71.18

517,074,000.00
71.18
62.41

62.41
144
36
180

62.41

62.41
DAFTAR HARGA SATUAN PER M2 BANGUNAN GEDUNG BERTINGKAT,
GEDUNG TAK BERTINGKAT, RUMAH DINAS DAN PAGAR
DIWILAYAH KABUPATEN SIDOARJO UNTUK TAHUN ANGGARAN 2009

HARGA DARI ANALISA


No. STATUS / JENIS P.U.CK dan P - Th 2009
BANGUNAN Harga satuan Gedung PerM2
(Terhitung mulai 1 Januari 2009)
SEMESTER - 1.

A GEDUNG BERTINGKAT
1 KLAS - A Rp. 5,454,191.83
2 KLAS - B Rp. 4,877,537.19
3 KLAS - C. Rp. 3,652,146.07

B GEDUNG TAK BERTINGKAT


1 KLAS - A Rp. 5,021,700.85
2 KLAS - B Rp. 4,469,073.48
3 KLAS - C. Rp. 3,363,818.75

C RUMAH DINAS.
1 TYPE - 250. Rp. 3,291,736.92
2 TYPE - 120. Rp. 3,051,464.15
3 TYPE - 70 / 50 / 36. Rp. 2,787,164.11

D PAGAR KANTOR / PAGAR RUMAH DINAS.


1 PAGAR DEPAN ( Besi+tembok) Rp. 1,855,600.00
2 PAGAR SAMPING / BELAKANG. Rp. 1,452,000.00

CATATAN:
1 Dari type "C" gedung tak bertingkat lantai memakai keramic, dinding batu bata rangka beton
praktis, rangka atap kayu kruwing + meranti, penutup atap genteng karangpilang klas I. kusen
memakai kayu kamper, dinding dan kusen dicat, penerangan listrik penyambungan setempat,
air sumur.
2 Harga satuan per M2 tersebut diatas terdiri dari : a: BKF = 87,7 %
b : D.C = 7 %
c : D.V = 4 %
d : PTP = 1,3 %
3 Perbandingan prosentase kenaikan berdasarkan hasil rata2 harga dari 8 Kabupaten di Jatim antara
lain Kab. Sidoarjo, Kodya Surabaya, Kab.Gresik, Kab. Lamongan, Kab. Mojokerto, Kab Pasu-
ruan, Kab. Sampang, Kab. Mojokerto.
4 Sebagai acuan harga tersebut diambil dari harga satuan tertinggi yang dikeluarkan Dinas Per-
mukiman Propinsi Jawa Timur tahun 2002 triwulan ke IV. (terlampir).

Sidoarjo, Januari 2009

Kepala Dinas PU Cipta Karya


dan Tata Ruang
Kabupaten Sidoarjo.

Ir. SULAKSONO
Pembina Utama muda
Nip. 510 111 129
DAFTAR HARGA BAHAN BANGUNAN
YANG MENGALAMI KENAIKAN HARGA
DIWILAYAH KABUPATEN SIDOARJO

Ke
lom NO. NAMA / JENIS BAHAN SATUAN HARGA BAHAN HARGA BAHAN SESUAI
pok SESUIA SK BUPATI KONDISI LAPANGAN
1 2 3 4 5 6

A. BAHAN PASIR
1 Pasir Urug / Tanah katel. M3 Rp. 57,631.00 Tetap
2 Pasir Pasang M3 Rp. 90,207.00 98,570.00
3 Pasir Cor M3 Rp. 84,754.00 128,000.00
4 Sirtu urug M3 Rp. 42,500.00 Tetap
5 Tanah Urug M3 Rp. 39,050.00 45,000.00
6 Tanah grosok M3 Rp. 81,675.00 Tetap
7 Tanah taman M3 Rp. 65,000.00 Tetap
B. BAHAN BATU
M2 Rp. 63,718.00 Tetap
1 Batu bata tebal 5,5 cm. Bakaran kay Bh Rp. 297.00 415,000.00
2 Batu bata tebal 5,5 cm. Bakaran sek Bh Rp. 270.00 395,000.00
C BAHAN PAVING STONE. 0.00 Tetap
1 Paving stone abu-2 tb. 6 cm (3 berli Bj Rp. 787.00 900.00
2 Paving stone abu-2 tb. 6 cm (4 perseg Bj Rp. 780.00 875.00
3 Paving stone abu-2 tb. 6 cm (type-DT Bj Rp. 677.00 800.00
4 Paving stone abu-2 tb. 6 cm (type-D Bj Rp. 806.00 1,100.00
5 Paving stone abu-2 tb. 6 cm (type-D Bj Rp. 861.00 1,200.00
6 Paving stone abu-2 tb. 8 cm (3 berli Bj Rp. 990.00 1,350.00
7 Paving stone abu-2 tb. 8 cm (4 perseg Bj Rp. 875.00 1,350.00
8 Paving stone abu-2 tb. 8 cm (type-DT Bj Rp. 1,045.00 1,700.00
9 Paving stone abu-2 tb. 8 cm (type-D Bj Rp. 1,210.00 1,650.00
10 Paving stone abu-2 tb. 8 cm (type-D Bj Rp. 1,518.00 1,650.00
11 Paving stone merah tb. 6 cm (3 berl Bj Rp. 1,342.00 1,350.00
12 Paving stone merah tb. 6 cm (type-DT Bj Rp. 1,227.00 1,350.00
13 Paving stone merah tb. 6 cm (type-s Bj Rp. 1,245.00 1,350.00
14 Paving stone merah tb. 8 cm (3 berl Bj Rp. 1,419.00 1,700.00
15 Paving stone mrh tb. 8 cm (4 persegi Bj Rp. 1,078.00 1,750.00
16 Paving stone merah tb. 8 cm (type-D Bj Rp. 1,100.00 1,200.00
17 Paving stone merah tb. 8 cm (type-s Bj Rp. 1,419.00 1,530.00

G BAHAN KAYU.
1 Kayu jati balok 6,15, 8/12. panjang 3 M3 Rp. 15,750,000.00 19,500,000.00
2 Kayu reng jati 2/3, panjang 4 mtr. M3 Rp. 8,500,000.00 14,750,000.00
3 Kayu jat usuk 3/5; 4/6 ; 5/7 panjang M3 Rp. 11,750,000.00 17,500,000.00
4 Papan jati papan 2/20 ; panjang 2 mt M3 Rp. 10,615,000.00 21,500,000.00
5 Kayu Kamfer balok 8/12, 6/15 M3 Rp. 4,774,733.00 6,100,000.00
6 Kayu kamfer usuk 5/7 M3 Rp. 4,317,500.00 5,150,000.00
7 Kayu kamfer papan 3/30 , 3/20, 2/20. M3 Rp. 5,766,820.00 7,000,000.00
8 Kayu Kamfer reng 2/3 M3 Rp. 4,736,600.00 4,250,000.00
9 Kayu kruing / bengkirai / kempas pa M3 Rp. 3,547,500.00 4,750,000.00
10 Kayu kruing /bengkirai/kempas blk 8/ M3 Rp. 3,465,000.00 4,300,000.00
11 Kayu kruing / bengkirai/kempas usuk M3 Rp. 2,557,500.00 4,200,000.00
12 Kayu kruing / bengkirai/kempas usuk M3 Rp. 2,557,500.00 4,200,000.00
13 Kayu kruing reng 2/3 M3 Rp. 2,557,500.00 3,900,000.00
14 Kayu meranti balok 8/12, 6/15 M3 Rp. 3,025,000.00 3,950,000.00
15 Keyu meranti usuk 5/7 M3 Rp. 2,213,200.00 3,900,000.00
16 Kayu meranti papan 3/25/400 M3 Rp. 3,190,000.00 4,300,000.00
17 Kayu glugu usuk 5/7 4meter 1 Btg Rp. 48,583.00 62,500.00
18 Papan begesting (MC) M3 Rp. 1,922,877.00 2,950,000.00
19 Rangka plavon kamper potongan M3 Rp. 2,248,480.00 2,750,000.00
20 Rangka plavon meranti potongan M3 Rp. 1,978,000.00 2,350,000.00
21 Kayu gelagar jembatan meranti.8/15 M3 Rp. 2,145,000.00 3,950,000.00
22 Kayu dolken kayu jati. Btg Rp. 49,500.00 85,000.00
23 Kayu Sirap M2 Rp. 106,920.00 Tetap
24 Kayu Sirap Lbr/ 1m' Rp. 1,782.00 Tetap
25 Kayu bakar. M3 Rp. 183,553.00 Tetap
26 I j u k KG Rp. 5,143.00 Tetap
26 Gedek M2 Rp. 10,252.00 Tetap
15 List plafond 1/5 m' Rp. 2,915.00 Tetap
I BAHAN BESI..
1 Besi beton polos. Kg Rp. 8,715.00 9,230.00
2 Besi beton Ulir. Kg Rp. 11,083.00 11,650.00
3 Besi konstruksi ( WF ; H ; INP ; SIKU Kg Rp. 10,533.00 10,850.00

Sidoarjo, 10 April 2008.

Menyetujui: Disurvey dan disusun oleh :


Plt. Kasubdin Tata Bangunan Staf Perencanaan Teknik Ta- Ba.
Dinas PU Cipta Karya dan Permukiman Dinas PU Cipta Karya & Permukiman
Kabupaten Sidoarjo. Kabupaten Sidoarjo.

BUDI UTOMO, ST.MM. KUSDI

Penata
Nip. 110 022 647.

You might also like