You are on page 1of 39

ANALISA ARSITEKTUR

Analisa Persiapan
Ars - 01 1 M2 Pembersihan Lahan 5%
(PERMEN PU 11/PRT/M/2013)
Tenaga
0.10 Hr Pekerja @ Rp 100,000.00 = Rp 10,000.00
0.05 Hr Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 875.00 = Rp 875.00
Jumlah pekerjaan = Rp 18,375.00
Ars - 02 1 M3 Timbunan Tanah Kembali
(PERMEN PU 11/PRT/M/2013)
0.500 OH Pekerja @ Rp 100,000.00 = Rp 50,000.00
0.050 OH Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 2,875.00 = Rp 2,875.00
Jumlah Rp 60,375.00

Ars - 03 1 Mengurug tanah biasa sedalam 1 meter


(PERMEN PU 11/PRT/M/2013)
Tenaga kerja
0.250 OH Pekerja @ Rp 100,000.00 = Rp 25,000.00
0.008 OH Mandor @ Rp 150,000.00 = Rp 1,250.00
Bahan
1.20 M3 Tanah Urugan @ Rp 95,000.00 = Rp 114,000.00
(Over head + profit ) 5% @ Rp 7,012.50 = Rp 7,012.50
Jumlah = Rp 147,262.50

Analisa Dinding
Ars - 04 1 M2 Memasang dinding bata merah cm tebal ½ bata, campuran spesi 1 PC : 3 PP
(PERMEN PU 11/PRT/M/2013)
Bahan
70.00 Buah Bata merah @ Rp 600.00 = Rp 42,000.00
14.37 kg PC @ Rp 1,610.00 = Rp 23,135.70
0.04 m3 PP @ Rp 115,308.00 = Rp 4,612.32
Tenaga kerja
0.30 OH Pekerja @ Rp 100,000.00 = Rp 30,000.00
0.10 OH Tukang batu @ Rp 135,000.00 = Rp 13,500.00
0.01 OH Kepala tukang @ Rp 135,000.00 = Rp 1,350.00
0.02 OH Mandor @ Rp 150,000.00 = Rp 2,250.00
(Over head + profit ) 5% @ Rp 5,842.40 = Rp 5,842.40
Jumlah total Rp 122,690.42

Ars - 05 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’)
(PERMEN PU 11/PRT/M/2013)
Bahan
3.11 kg Portland Cement @ Rp 1,610.00 = Rp 5,003.88
Tenaga kerja
0.15 OH Pekerja @ Rp 100,000.00 = Rp 15,000.00
0.08 OH Tukang batu @ Rp 135,000.00 = Rp 10,125.00
0.01 OH Kepala tukang @ Rp 135,000.00 = Rp 1,080.00
0.01 OH Mandor @ Rp 150,000.00 = Rp 1,200.00
(Over head + profit ) 5% @ Rp 1,620.44 = Rp 1,620.44
Jumlah total Rp 34,029.32

Ars - 06 1 M2 Memasang dinding bata merah tebal ½ bata, campuran spesi 1 PC : 5 PP


(PERMEN PU 11/PRT/M/2013)
Bahan
70.00 Buah Bata merah @ Rp 600.00 = Rp 42,000.00
9.68 kg PC @ Rp 1,610.00 = Rp 15,584.80
0.045 m3 PP @ Rp 115,308.00 = Rp 5,188.86
Tenaga kerja
0.30 OH Pekerja @ Rp 100,000.00 = Rp 30,000.00
0.10 OH Tukang batu @ Rp 135,000.00 = Rp 13,500.00
0.01 OH Kepala tukang @ Rp 135,000.00 = Rp 1,350.00
0.02 OH Mandor @ Rp 150,000.00 = Rp 2,250.00
(Over head + profit ) 5% @ Rp 5,493.68 = Rp 5,493.68
Jumlah total Rp 115,367.34

Ars - 07 1 M2 Memasang plesteran 1 PC : 5 PP, tebal 15 mm


(PERMEN PU 11/PRT/M/2013)
Bahan
5.184 Kg PC @ Rp 1,610.00 = Rp 8,346.24
0.026 M3 PP @ Rp 115,308.00 = Rp 2,998.01
Tenaga kerja
0.300 OH Pekerja @ Rp 100,000.00 = Rp 30,000.00
0.100 OH Tukang batu @ Rp 135,000.00 = Rp 13,500.00
0.010 OH Kepala tukang @ Rp 135,000.00 = Rp 1,350.00
0.015 OH Mandor @ Rp 150,000.00 = Rp 2,250.00
(Over head + profit ) 5% @ Rp 2,922.21 = Rp 2,922.21
Jumlah total Rp 61,366.46

Ars - 08 1 m2 Screed 1 : 3 tebal


(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m3 Pasir @ Rp 115,308.00 = Rp 4,035.78
0.02 zak Semen (50 kg) @ Rp 80,500.00 = Rp 1,771.00
Tenaga
0.20 Oh Tukang batu @ Rp 135,000.00 = Rp 27,000.00
0.30 Oh Pekerja @ Rp 100,000.00 = Rp 30,000.00
0.02 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,700.00
0.01 Oh Mandor @ Rp 150,000.00 = Rp 1,950.00
(Over head + profit ) 5% @ Rp 3,372.84 = Rp 3,372.84
Jumlah total = Rp 70,829.62
Ars - 09 Memasang 1 m2 acian
(PERMEN PU 11/PRT/M/2013)
Bahan
3.250 Kg Portland Cement @ Rp 1,610.00 = Rp 5,232.50
Tenaga kerja
0.200 OH Pekerja @ Rp 100,000.00 = Rp 20,000.00
0.100 OH Tukang batu @ Rp 135,000.00 = Rp 13,500.00
0.010 OH Kepala tukang @ Rp 135,000.00 = Rp 1,350.00
0.010 OH Mandor @ Rp 150,000.00 = Rp 1,500.00
(Over head + profit ) 5% @ Rp 2,079.13 = Rp 2,079.13
Jumlah total Rp 43,661.63

Ars - 10 1 M2 Memasang plesteran 1 PC : 3 PP, tebal 15 mm


(PERMEN PU 11/PRT/M/2013)
Bahan
7.776 Kg PC @ Rp 1,610.00 = Rp 12,519.36
0.023 M3 PP @ Rp 115,308.00 = Rp 2,652.08
Tenaga kerja
0.300 OH Pekerja @ Rp 100,000.00 = Rp 30,000.00
0.150 OH Tukang batu @ Rp 135,000.00 = Rp 20,250.00
0.015 OH Kepala tukang @ Rp 135,000.00 = Rp 2,025.00
0.015 OH Mandor @ Rp 150,000.00 = Rp 2,250.00
(Over head + profit ) 5% @ Rp 3,484.82 = Rp 3,484.82
Jumlah total Rp 73,181.27

analisa pekerjaan pengecetan


Ars -11 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup) Interior
(PERMEN PU 11/PRT/M/2013)
Bahan
0.10 Kg Plamir @ Rp 49,000.00 = Rp 4,900.00
0.10 Kg Cat dasar @ Rp 96,000.00 = Rp 9,600.00
0.26 Kg Cat penutup 2 x @ Rp 67,600.00 = Rp 17,576.00
0.01 bh Rool Cat Tembok @ Rp 30,000.00 = Rp 300.00
Jumlah I = Rp 32,376.00

Tenaga
0.02 Oh Pekerja @ Rp 100,000.00 = Rp 2,000.00
0.063 Oh Tukang cat @ Rp 135,000.00 = Rp 8,505.00
0.0063 Oh Kepala Tukang @ Rp 135,000.00 = Rp 850.50
0.003 Oh Mandor @ Rp 150,000.00 = Rp 375.00
Jumlah II = Rp 11,730.50
(Over head + profit ) 5% @ Rp 2,205.33 = Rp 2,205.33
Jumlah rekap = Rp 46,311.83

Ars -12 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup) eksterior
(PERMEN PU 11/PRT/M/2013)
Bahan
0.10 Kg Plamir @ Rp 49,000.00 = Rp 4,900.00
0.10 Kg Cat dasar @ Rp 96,000.00 = Rp 9,600.00
0.26 Kg Cat penutup 2 x @ Rp 85,800.00 = Rp 22,308.00
0.01 bh Rool Cat Tembok @ Rp 30,000.00 = Rp 300.00
Jumlah I = Rp 37,108.00
Tenaga
0.02 Oh Pekerja @ Rp 100,000.00 = Rp 2,000.00
0.063 Oh Tukang cat @ Rp 135,000.00 = Rp 8,505.00
0.0063 Oh Kepala Tukang @ Rp 135,000.00 = Rp 850.50
0.003 Oh Mandor @ Rp 150,000.00 = Rp 375.00
Jumlah II = Rp 11,730.50
(Over head + profit ) 5% @ Rp 2,441.93 = Rp 2,441.93
Jumlah rekap = Rp 51,280.43

Ars - 13 1 m2 pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
(PERMEN PU 11/PRT/M/2013)
Bahan
0.12 Kg Cat dasar @ Rp 96,000.00 = Rp 11,520.00
0.18 Kg Cat penutup 2 x @ Rp 67,600.00 = Rp 12,168.00
Tenaga
0.028 Oh Pekerja @ Rp 100,000.00 = Rp 2,800.00
0.042 Oh Tukang cat @ Rp 135,000.00 = Rp 5,670.00
0.0042 Oh Kepala Tukang @ Rp 135,000.00 = Rp 567.00
0.003 Oh Mandor @ Rp 150,000.00 = Rp 375.00
(Over head + profit ) 5% @ Rp 1,655.00 = Rp 1,655.00
Jumlah rekap Rp 34,755.00

analisa pekerjaan Lantai

Ars - 15 Pasang Keramik Lantai 60/60 per m2


(PERMEN PU 11/PRT/M/2013)
Bahan :
3.10 buah Keramik @ Rp 76,666.67 = Rp 237,666.67
9.60 kg Semen @ Rp 1,610.00 = Rp 15,456.00
0.05 m3 Pasir pasang @ Rp 115,308.00 = Rp 5,188.86
1.50 kg semen nat @ Rp 10,000.00 = Rp 15,000.00
Tenaga kerja
0.12 OH Tukang @ Rp 135,000.00 = Rp 16,200.00
0.24 OH Pekerja @ Rp 100,000.00 = Rp 24,000.00
0.012 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,620.00
0.012 OH Mandor @ Rp 150,000.00 = Rp 1,800.00
(Over head + profit ) 5% @ Rp 15,846.58 = Rp 15,846.58
Rp 332,778.10

Ars - 17 Pasang keramik 60/60 per m2 warna


(PERMEN PU 11/PRT/M/2013)
Bahan :
3.10 buah Keramik Warna @ Rp 92,000.00 = Rp 285,200.00
9.60 kg Semen @ Rp 1,610.00 = Rp 15,456.00
0.05 m3 Pasir pasang @ Rp 115,308.00 = Rp 5,188.86
1.50 kg semen nat @ Rp 10,000.00 = Rp 15,000.00
Tenaga kerja
0.12 OH Tukang @ Rp 135,000.00 = Rp 16,200.00
0.24 OH Pekerja @ Rp 100,000.00 = Rp 24,000.00
0.012 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,620.00
0.012 OH Mandor @ Rp 150,000.00 = Rp 1,800.00
(Over head + profit ) 5% @ Rp 18,223.24 = Rp 18,223.24
Rp 382,688.10

Ars - 15 Pasang keramik lantai km/wc 25/25 per m2


(Analisa Lapangan)
Bahan :
17.60 buah Keramik @ Rp 5,312.50 = Rp 93,500.00
10.00 kg Semen @ Rp 1,610.00 = Rp 16,100.00
0.045 m3 Pasir pasang @ Rp 115,308.00 = Rp 5,188.86
1.50 kg semen nat @ Rp 10,000.00 = Rp 15,000.00
Tenaga kerja
0.13 OH Tukang Batu @ Rp 135,000.00 = Rp 17,550.00
0.26 OH Pekerja @ Rp 100,000.00 = Rp 26,000.00
0.013 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,755.00
0.013 OH Mandor @ Rp 150,000.00 = Rp 1,950.00
(Over head + profit ) 5% @ Rp 8,852.19 = Rp 8,852.19
Rp 185,896.05

Ars - 18 Pasang keramik dinding km/wc 25 x 40 per m2


(PERMEN PU 11/PRT/M/2013)
Bahan :
11.00 buah Keramik @ Rp 9,500.00 = Rp 104,500.00
10.00 kg Semen @ Rp 1,610.00 = Rp 16,100.00
0.045 m3 pasir @ Rp 115,308.00 = Rp 5,188.86
1.50 kg Semen warna @ Rp 10,000.00 = Rp 15,000.00
Jumlah I Rp 140,788.86
Tenaga kerja
0.13 OH Tukang Batu @ Rp 100,000.00 = Rp 13,000.00
0.26 OH Pekerja @ Rp 135,000.00 = Rp 35,100.00
0.013 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,755.00
0.013 OH Mandor @ Rp 150,000.00 = Rp 1,950.00
Jumlah II Rp 51,805.00
(Over head + profit ) 5% @ Rp 9,629.69 = Rp 9,629.69
Jumlah I + Jumlah II Rp 202,223.55

Ars - 19 Pasang keramik antislip ujung tangga 10x60 per m'


(analisa lapangan)
Bahan :
1.83 buah Keramik Anti slip @ Rp 41,350.00 = Rp 75,670.50
0.011 zak Semen @ Rp 80,500.00 = Rp 885.50
0.002 m3 Pasir pasang @ Rp 115,308.00 = Rp 230.62
0.075 kg Semen warna @ Rp 10,000.00 = Rp 750.00
Tenaga kerja
0.018 OH Tukang @ Rp 100,000.00 = Rp 1,800.00
0.031 OH Pekerja @ Rp 135,000.00 = Rp 4,185.00
0.002 OH Kepala Tukang @ Rp 135,000.00 = Rp 270.00
0.002 OH Mandor @ Rp 150,000.00 = Rp 300.00
(Over head + profit ) 5% @ Rp 4,204.58 = Rp 4,204.58
Rp 88,296.20

analisa pekerjaan Waterproff


Ars - 20 1m2 Waterproofing / m2
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 kg waterprofing coating @ Rp 180,000.00 = Rp 180,000.00
Tenaga
0.03 Oh Pekerja @ Rp 100,000.00 = Rp 2,800.00
0.004 Oh Kepala Tukang @ Rp 135,000.00 = Rp 540.00
0.003 Oh Mandor @ Rp 150,000.00 = Rp 450.00
(Over head + profit ) 5% @ Rp 9,189.50 = Rp 9,189.50
Jumlah = Rp 192,979.50

analisa pekerjaan plafond

Ars - 21 1 M2 Pasang Rangka Plafond Aluminium Hollow


(PERMEN PU 11/PRT/M/2013)
Bahan :
4.00 m' Besi Hollow 2X4 @ Rp 16,500.00 = Rp 66,000.00
1.00 Ls Aksesoris (perkuat, Las dll) @ Rp 16,500.00 = Rp 16,500.00
Jumlah I = Rp 82,500.00
Upah :
0.35 Oh Pekerja @ Rp 100,000.00 = Rp 35,000.00
0.35 Oh Tukang Aluminium @ Rp 135,000.00 = Rp 47,250.00
0.04 Oh Kepala Tukang @ Rp 135,000.00 = Rp 4,725.00
0.02 Oh Mandor @ Rp 150,000.00 = Rp 2,700.00
Jumlah II = Rp 89,675.00
(Over head + profit ) 5% @ Rp 8,608.75 = Rp 8,608.75
Jumlah = Rp 180,783.75

Ars - 22 1 M2 Langit -Langit GYpsum, Tebal 9mm


(PERMEN PU 11/PRT/M/2013)
Bahan :
0.38 Lbr Gypsum @ Rp 82,500.00 = Rp 30,937.50
0.11 Kg Paku Gypsum @ Rp 20,000.00 = Rp 2,200.00
Jumlah I = Rp 33,137.50
Upah :
0.100 Oh Pekerja @ Rp 100,000.00 = Rp 10,000.00
0.050 Oh Tukang Kayu @ Rp 135,000.00 = Rp 6,750.00
0.005 Oh Kepala Tukang @ Rp 135,000.00 = Rp 675.00
0.005 Oh Mandor @ Rp 150,000.00 = Rp 750.00
Jumlah II = Rp 18,175.00
(Over head + profit ) 5% @ Rp 2,565.63 = Rp 2,565.63
Jumlah = Rp 53,878.13

Ars - 23 1 M2 Langit -Langit Kalsiboard, Tebal 3mm


(PERMEN PU 11/PRT/M/2013)
Bahan :
0.38 Lbr Kalsiboard @ Rp 69,500.00 = Rp 26,062.50
0.03 Kg Paku Kalsiboard @ Rp 45,000.00 = Rp 1,350.00
Jumlah I = Rp 27,412.50
Upah :
0.100 Oh Pekerja @ Rp 100,000.00 = Rp 10,000.00
0.100 Oh Tukang Kayu @ Rp 135,000.00 = Rp 13,500.00
0.010 Oh Kepala Tukang @ Rp 135,000.00 = Rp 1,350.00
0.005 Oh Mandor @ Rp 150,000.00 = Rp 750.00
Jumlah II = Rp 25,600.00
(Over head + profit ) 5% @ Rp 2,650.63 = Rp 2,650.63
Jumlah = Rp 55,663.13

ANALISA PEKERJAAN RELLING, ACP DLL

Ars - 24 1 m' Railing Tangga


(analisa lapangan)
Bahan
1.10 M' Stenless Galvanis @ Rp 250,000.00 = Rp 275,000.00
7.10 M' Besi holow Galvanis @ Rp 30,000.00 = Rp 213,000.00
1.10 M' Plat Baja @ Rp 16,000.00 = Rp 17,600.00
1.00 Ls Alat Bantu @ Rp 35,000.00 = Rp 35,000.00
1.00 m2 Cat besi @ Rp 40,000.00 = Rp 40,000.00
1.00 ls kuas dan alat lainnya @ Rp 50,000.00 = Rp 50,000.00
Kelengkapan dan Aksesoris
@ Rp 75,000.00 = Rp 75,000.00
1.00 Ls Lainnya Lengkap
Tenaga kerja
0.15 Org/Hr Pekerja @ Rp 100,000.00 = Rp 15,000.00
0.30 Org/Hr Tukang Besi @ Rp 135,000.00 = Rp 40,500.00
0.05 Org/Hr Kepala Tukang @ Rp 135,000.00 = Rp 6,750.00
0.01 Org/Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
(Over head + profit ) 5% @ Rp 38,467.50 = Rp 38,467.50
jumlah total = Rp 807,817.50

Ars - 25 1 M2 Pasangan Dinding Batu alam andesit 2/50


(analisa lapangan)
Bahan
1.000 M² Batu Alam Andesit 2/50 @ Rp 200,000.00 = Rp 200,000.00
0.118 Zak Semen PC @ Rp 80,500.00 = Rp 9,458.75
0.800 Kg Semen Warna @ Rp 10,000.00 = Rp 8,000.00
0.029 M³ Pasir Pasang @ Rp 115,308.00 = Rp 3,286.28
Tenaga
0.600 Org/Hr Tukang Batu @ Rp 100,000.00 = Rp 60,000.00
0.025 Org/Hr Kepala Tukang @ Rp 135,000.00 = Rp 3,375.00
0.500 Org/Hr Pekerja @ Rp 135,000.00 = Rp 67,500.00
0.050 Org/Hr Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 17,956.00 = Rp 17,956.00
jumlah total = Rp 377,076.03

Ars - 26 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding partisi
(PERMEN PU 11/PRT/M/2013)
Bahan
4.00 m' Besi Hollow 0.8X40X40 mm @ Rp 18,300.00 = Rp 73,200.00
1.00 LS assesoris (perkuatan, las, dll) @ Rp 18,300.00 = Rp 18,300.00
(100% Rangka Metal)
Tenaga
0.250 Org/Hr Pekerja @ Rp 100,000.00 = Rp 25,000.00
0.250 Org/Hr Tukang besi @ Rp 135,000.00 = Rp 33,750.00
0.025 Org/Hr Kepala tukang Besi @ Rp 135,000.00 = Rp 3,375.00
0.013 Org/Hr Mandor @ Rp 150,000.00 = Rp 1,950.00
(Over head + profit ) 5% @ Rp 7,778.75 = Rp 7,778.75
jumlah total = Rp 163,353.75

analisa pekerjaan Kunci

Ars - 27 1 buah pasang engsel pintu Tanam


(PERMEN PU 11/PRT/M/2013)
Bahan

1.00 Bh Engsel pintu tanam EX DORMA @ Rp 1,200,000.00 = Rp 1,200,000.00

Tenaga
0.02 Oh Pekerja @ Rp 100,000.00 = Rp 1,500.00
0.15 Oh Tukang kayu @ Rp 135,000.00 = Rp 20,250.00
0.02 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,025.00
0.0008 Oh Mandor @ Rp 150,000.00 = Rp 112.50
(Over head + profit ) 5% @ Rp 61,194.38 = Rp 61,194.38
Jumlah = Rp 1,285,081.88
Ars - 28 1 buah pasang engsel pintu biasa
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Engsel pintu @ Rp 142,800.00 = Rp 142,800.00

Tenaga
0.015 Oh Pekerja @ Rp 100,000.00 = Rp 1,500.00
0.15 Oh Tukang kayu @ Rp 135,000.00 = Rp 20,250.00
0.015 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,025.00
0.0008 Oh Mandor @ Rp 150,000.00 = Rp 112.50
(Over head + profit ) 5% @ Rp 8,334.38 = Rp 8,334.38
Jumlah = Rp 175,021.88
Ars - 29 1 buah pasang kunci stenless
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Kunci stenless @ Rp 173,000.00 = Rp 173,000.00

Tenaga
0.01 Oh Pekerja @ Rp 100,000.00 = Rp 1,000.00
0.50 Oh Tukang kayu @ Rp 135,000.00 = Rp 67,500.00
0.05 Oh Kepala Tukang @ Rp 135,000.00 = Rp 6,750.00
0.005 Oh Mandor @ Rp 150,000.00 = Rp 750.00
(Over head + profit ) 5% @ Rp 12,450.00 = Rp 12,450.00
Jumlah = Rp 261,450.00
Ars - 30 1 buah pasang Handle Pintu Utama
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Handle pintu biasa @ Rp 211,200.00 = Rp 211,200.00
Tenaga
0.05 Oh Pekerja @ Rp 100,000.00 = Rp 5,000.00
0.50 Oh Tukang kayu @ Rp 135,000.00 = Rp 67,500.00
0.05 Oh Kepala Tukang @ Rp 135,000.00 = Rp 6,750.00
0.00 Oh Mandor @ Rp 150,000.00 = Rp 375.00
(Over head + profit ) 5% @ Rp 14,541.25 = Rp 14,541.25
Jumlah = Rp 305,366.25
Ars - 31 1 buah pasang Handle Pintu Utama
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Handle pintu P1 @ Rp 3,990.50 = Rp 3,990.50
Tenaga
0.05 Oh Pekerja @ Rp 100,000.00 = Rp 5,000.00
0.50 Oh Tukang kayu @ Rp 135,000.00 = Rp 67,500.00
0.05 Oh Kepala Tukang @ Rp 135,000.00 = Rp 6,750.00
0.00 Oh Mandor @ Rp 150,000.00 = Rp 375.00
(Over head + profit ) 5% @ Rp 4,180.78 = Rp 4,180.78
Jumlah = Rp 87,796.28

Ars - 32 1 buah pasang Grendel jendela


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Grendel jendela @ Rp 13,500.00 = Rp 13,500.00
Tenaga
0.02 Oh Pekerja @ Rp 100,000.00 = Rp 1,500.00
0.15 Oh Tukang kayu @ Rp 135,000.00 = Rp 20,250.00
0.02 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,025.00
0.00 Oh Mandor @ Rp 150,000.00 = Rp 112.50
(Over head + profit ) 5% @ Rp 1,869.38 = Rp 1,869.38
Jumlah = Rp 39,256.88
Ars - 33 1 Unit pasang engsel Casement
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Engsel Jendela Casement @ Rp 118,000.00 = Rp 118,000.00

Tenaga
0.10 Oh Pekerja @ Rp 100,000.00 = Rp 10,000.00
0.20 Oh Tukang kayu @ Rp 135,000.00 = Rp 27,000.00
0.02 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,700.00
0.0005 Oh Mandor @ Rp 150,000.00 = Rp 75.00
(Over head + profit ) 5% @ Rp 7,888.75 = Rp 7,888.75
Jumlah = Rp 165,663.75
Ars - 34 1 Unit pasang door Closer
(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 set door closer ex. ROWELL @ Rp 187,200.00 = Rp 187,200.00

Tenaga
0.05 Oh Pekerja @ Rp 100,000.00 = Rp 5,000.00
0.50 Oh Tukang kayu @ Rp 135,000.00 = Rp 67,500.00
0.05 Oh Kepala Tukang @ Rp 135,000.00 = Rp 6,750.00
0.0030 Oh Mandor @ Rp 150,000.00 = Rp 450.00
(Over head + profit ) 5% @ Rp 13,345.00 = Rp 13,345.00
Jumlah = Rp 280,245.00

analisa pekerjaan Jendela, Pintu & Kaca

Ars - 35 1 m2 pasang kaca polos, tebal 6 mm


(PERMEN PU 11/PRT/M/2013)
Bahan
1.10 M2 Kaca polos 6 mm @ Rp 275,000.00 = Rp 302,500.00
0.05 Kg Sealent @ Rp 350.00 = Rp 17.50
Tenaga
0.015 Oh Pekerja @ Rp 100,000.00 = Rp 1,500.00
0.15 Oh Tukang kayu @ Rp 135,000.00 = Rp 20,250.00
0.015 Oh Kepala Tukang @ Rp 135,000.00 = Rp 2,025.00
0.0008 Oh Mandor @ Rp 150,000.00 = Rp 112.50
(Over head + profit ) 5% @ Rp 16,320.25 = Rp 16,320.25
Jumlah = Rp 342,725.25

Ars - 40 Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela, kayu kelas I
(PERMEN PU 11/PRT/M/2013)
Bahan
1.10 m3 Balok kayu @ Rp 13,000,000.00 = Rp 14,300,000.00
1.25 Kg Paku 10 cm @ Rp 20,000.00 = Rp 25,000.00
1.00 Kg Lem Kayu @ Rp 21,000.00 = Rp 21,000.00

Tenaga kerja
7.000 OH Pekerja @ Rp 100,000.00 = Rp 700,000.00
21.000 OH Tukang kayu @ Rp 135,000.00 = Rp 2,835,000.00
2.100 OH Kepala tukang @ Rp 135,000.00 = Rp 283,500.00
0.350 OH Mandor @ Rp 150,000.00 = Rp 52,500.00
(Over head + profit ) 5% @ Rp 910,850.00 = Rp 910,850.00
Jumlah = Rp 19,127,850.00

Ars - 40 Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela, kayu kelas II atau III
(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 m3 Balok kayu @ Rp 8,000,000.00 = Rp 9,600,000.00
1.25 Kg Paku 10 cm @ Rp 20,000.00 = Rp 25,000.00
1.00 Kg Lem Kayu @ Rp 21,000.00 = Rp 21,000.00

Tenaga kerja
6.000 OH Pekerja @ Rp 100,000.00 = Rp 600,000.00
18.000 OH Tukang kayu @ Rp 135,000.00 = Rp 2,430,000.00
1.800 OH Kepala tukang @ Rp 135,000.00 = Rp 243,000.00
0.300 OH Mandor @ Rp 150,000.00 = Rp 45,000.00
(Over head + profit ) 5% @ Rp 648,200.00 = Rp 648,200.00
Jumlah = Rp 13,612,200.00

Ars - 41 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m’ Papan Kayu @ 13,000,000.00 = Rp 520,000.00
0.50 m’ Lem kayu @ 21,000.00 = Rp 10,500.00

Tenaga kerja
1.000 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
3.000 OH Tukang kayu @ Rp 135,000.00 = Rp 405,000.00
0.300 OH Kepala tukang @ Rp 135,000.00 = Rp 40,500.00
0.050 OH Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 54,175.00 = Rp 54,175.00
Jumlah Rp 1,137,675.00

Ars - 41 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
(PERMEN PU 11/PRT/M/2013)
Bahan
0.024 m’ Papan Kayu @ 13,000,000.00 = Rp 312,000.00
0.30 m’ Lem kayu @ 21,000.00 = Rp 6,300.00

Tenaga kerja
0.800 OH Pekerja @ Rp 100,000.00 = Rp 80,000.00
2.400 OH Tukang kayu @ Rp 135,000.00 = Rp 324,000.00
0.240 OH Kepala tukang @ Rp 135,000.00 = Rp 32,400.00
0.040 OH Mandor @ Rp 150,000.00 = Rp 6,000.00
(Over head + profit ) 5% @ Rp 38,035.00 = Rp 38,035.00
Jumlah Rp 798,735.00

ANALISA PINTU & JENDELA

Ars - 45 1 buah Type P1


Ars - 40 0.02 M3 Kusen Kayu @ Rp 19,127,850.00 = Rp 430,376.63
Ars - 41 1.44 M2 Daun pintu Kayu @ Rp 1,137,675.00 = Rp 1,632,563.63
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Jumlah = Rp 3,154,822.13

Ars - 46 1 buah Type P2


Ars - 40 5.20 M Kusen Kayu @ Rp 19,127,850.00 = Rp 99,464,820.00
Ars - 41 1.89 M2 Daun pintu Kayu @ Rp 1,137,675.00 = Rp 2,150,205.75
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
#REF! 3.78 M2 Fin. Melamin @ #REF! = #REF!
Jumlah = #REF!

Ars - 47 1 buah Type P4


Ars - 40 4.90 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 93,726,465.00
Ars - 41 1.26 M2 Daun pintu LAPIS TEAKWOOD @ #REF! = #REF!
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
#REF! 2.52 M2 Fin. Melamin @ #REF! = #REF!
Jumlah = #REF!
Ars - 48 1 buah Type P5
Ars - 40 2.92 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 55,853,322.00
Ars - 41 0.60 M2 Daun pintu LAPIS TEAKWOOD @ #REF! = #REF!
Ars - 28 2.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 350,043.75
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.20 M2 Fin. Melamin @ #REF! = #REF!
Jumlah = #REF!
Ars - 49 1 buah Type P6
Ars - 40 5.10 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 97,552,035.00
Ars - 41 0.31 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 352,679.25
Ars - 35 1.37 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 469,533.59
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 2.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 522,900.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
Jumlah = Rp 100,313,190.97
Ars - 50 1 buah Type P7
Ars - 40 5.01 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 95,830,528.50
Ars - 41 1.68 M2 Daun pintu LAPIS TEAKWOOD @ #REF! = #REF!
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
#REF! 3.36 M2 Fin. Melamin @ #REF! = #REF!
Jumlah = #REF!
Ars - 51 1 buah Type P8
Ars - 40 5.31 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 101,568,883.50
Ars - 41 2.31 M2 Daun pintu LAPIS TEAKWOOD @ #REF! = #REF!
Ars - 28 6.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 1,050,131.25
Ars - 29 2.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 522,900.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Ars - 34 2.00 Bh Door Closer @ Rp 280,245.00 = Rp 560,490.00
#REF! 4.62 M2 Fin. Melamin @ #REF! = #REF!
Jumlah = #REF!
Ars - 52 1 buah Type PJ1
Ars - 40 0.11 M3 Kusen Kayu @ Rp 19,127,850.00 = Rp 2,144,710.18
Ars - 41 3.08 M2 Daun pintu Kayu @ Rp 1,137,675.00 = Rp 3,504,039.00
Ars - 35 2.34 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 801,977.09
Ars - 28 6.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 1,050,131.25
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Jumlah = Rp 8,373,040.02
Ars - 53 1 buah Type Pj2
Ars - 40 27.30 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 522,190,305.00
Ars - 41 0.31 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 352,679.25
Ars - 35 9.39 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 3,218,190.10
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
Jumlah = Rp 527,133,301.22
Ars - 54 1 buah Type Pj3
Ars - 40 30.70 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 587,224,995.00
Ars - 41 0.31 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 352,679.25
Ars - 35 9.82 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 3,365,561.96
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
Jumlah = Rp 592,315,363.08
Ars - 55 1 buah Type Pj4
Ars - 40 32.72 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 625,863,252.00
Ars - 41 0.31 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 352,679.25
Ars - 35 11.24 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 3,852,231.81
Ars - 28 3.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 525,065.63
Ars - 29 1.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 1.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 305,366.25
Ars - 34 1.00 Bh Door Closer @ Rp 280,245.00 = Rp 280,245.00
Jumlah = Rp 631,440,289.94
Ars - 56 1 buah Type Pj5
Ars - 40 33.32 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 637,339,962.00
Ars - 41 0.40 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 455,070.00
Ars - 35 12.19 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 4,177,820.80
Ars - 28 6.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 1,050,131.25
Ars - 29 2.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 522,900.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Ars - 34 2.00 Bh Door Closer @ Rp 280,245.00 = Rp 560,490.00
Jumlah = Rp 644,717,106.55
Ars - 57 1 buah Type Pj6
Ars - 40 33.32 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 637,339,962.00
Ars - 41 0.40 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 455,070.00
Ars - 35 12.19 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 4,177,820.80
Ars - 28 6.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 1,050,131.25
Ars - 29 2.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 522,900.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Ars - 34 2.00 Bh Door Closer @ Rp 280,245.00 = Rp 560,490.00
Jumlah = Rp 644,717,106.55
Ars - 58 1 buah Type Pj7
Ars - 40 24.70 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 472,457,895.00
Ars - 35 12.12 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 4,153,830.03
Ars - 28 4.00 Bh Engsel Pintu tanam @ Rp 1,285,081.88 = Rp 5,140,327.50
Ars - 29 1.00 Bh Kunci Pintu stenless @ Rp 261,450.00 = Rp 261,450.00
Ars - 30 2.00 Bh Handle Pintu almunium @ Rp 305,366.25 = Rp 610,732.50
- 0.25 Ls Aksesoris Lengkap dan lainya @ Rp 482,624,235.03 = Rp 120,656,058.76
Jumlah = Rp 603,280,293.79

Ars - 59 1 buah Type Pj8


Ars - 40 23.68 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 452,947,488.00
Ars - 41 0.40 M2 Daun pintu Almunium 6" @ Rp 1,137,675.00 = Rp 455,070.00
Ars - 35 9.63 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 3,301,129.61
Ars - 28 6.00 Bh Engsel Pintu ex. DEKSON @ Rp 175,021.88 = Rp 1,050,131.25
Ars - 29 2.00 Bh Kunci Pintu Ex. DEKSON @ Rp 261,450.00 = Rp 522,900.00
Ars - 30 2.00 Bh Handle Pintu EX. BREMEN @ Rp 305,366.25 = Rp 610,732.50
Ars - 34 2.00 Bh Door Closer @ Rp 280,245.00 = Rp 560,490.00
Jumlah = Rp 459,447,941.36
Ars - 60 1 buah Type J1
#REF! 4.79 M2 Kaca temper 10 mm @ #REF! = #REF!
- 0.05 Ls Aksesoris dan lainya lengkap @ #REF! = #REF!
Jumlah = #REF!
Ars - 61 1 buah Type J2
#REF! 9.99 M2 Kaca temper 10 mm @ #REF! = #REF!
- 0.05 Ls Aksesoris dan lainya lengkap @ #REF! = #REF!
Jumlah = #REF!

Ars - 62. 1 buah Type J3


Ars - 40 7.80 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 149,197,230.00
#REF! 3.81 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 1.22 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 63 1 buah Type J4
Ars - 40 17.22 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 329,381,577.00
#REF! 6.58 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 2.37 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 64 1 buah Type J5
Ars - 40 31.13 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 595,488,226.20
#REF! 13.40 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 7.39 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 65 1 buah Type J6
Ars - 40 42.04 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 804,150,116.28
#REF! 13.56 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 10.05 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 66 1 buah Type J7
Ars - 40 2.02 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 38,638,257.00
Ars - 35 0.18 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 61,690.55
Jumlah = Rp 38,699,947.55
Ars - 67 1 buah Type J8
Ars - 40 10.45 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 199,886,032.50
Ars - 35 3.11 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 1,065,875.53
Jumlah = Rp 200,951,908.03
Ars - 68 1 buah Type J9
Ars - 40 15.84 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 302,985,144.00
Ars - 35 4.76 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 1,631,372.19
Jumlah = Rp 304,616,516.19
Ars - 69 1 buah Type J10
Ars - 40 26.08 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 498,854,328.00
Ars - 35 9.90 M2 Kaca polos 6 mm @ Rp 342,725.25 = Rp 3,392,979.98
Jumlah = Rp 502,247,307.98
Ars - 70 1 buah Type J12
Ars - 40 37.12 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 710,025,792.00
#REF! 8.04 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 19.17 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 71 1 buah Type J13
Ars - 40 31.51 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 602,670,733.88
#REF! 8.44 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 23.85 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 72 1 buah Type J14
Ars - 40 12.52 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 239,438,600.73
#REF! 3.82 M Bingkai Almunium @ #REF! = #REF!
Ars - 35 6.88 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 73 1 buah Type J15
Ars - 40 33.32 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 637,339,962.00
#REF! 4.28 M Bingkai Almunium @ #REF! = #REF!
#REF! 19.93 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 74 1 buah Type J16
Ars - 40 14.70 M2 Kaca temper 10 mm @ #REF! = #REF!
- 0.05 Ls Aksesoris dan lainya lengkap @ #REF! = #REF!
Jumlah = #REF!
Ars - 75 1 buah Type J17
Ars - 40 42.45 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 811,977,232.50
#REF! 4.28 M Bingkai Almunium @ #REF! = #REF!
#REF! 22.28 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 76 1 buah Type J18
Ars - 40 21.71 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 415,265,623.50
#REF! 8.44 M Bingkai Almunium @ #REF! = #REF!
#REF! 8.54 M2 Kaca panasap 5 mm @ #REF! = #REF!
Jumlah = #REF!
Ars - 77 1 buah Type jalusi
Ars - 40 5.78 M Kusen Almunium 4" @ Rp 19,127,850.00 = Rp 110,463,333.75
ANALISA PEKERJAAN INTERIOR

INT - 01 1M2 Analisa Pekerjaan Dinding HPL


(Analisa Lapangan)
Bahan
1.25 Lbr Multipleks @ Rp 250,000.00 = Rp 312,500.00
0.48 Kg Lem Fox @ Rp 21,000.00 = Rp 10,080.00
0.09 Kg Paku Skrup @ Rp 15,000.00 = Rp 1,350.00
0.5 Lbr HPL @ Rp 420,000.00 = Rp 210,000.00
Tenaga
0.6 OH Pekerja @ Rp 100,000.00 = Rp 60,000.00
1.7 OH Tukang @ Rp 135,000.00 = Rp 229,500.00
0.6 OH Kepala tukang @ Rp 135,000.00 = Rp 81,000.00
0.06 OH Mandor @ Rp 150,000.00 = Rp 9,000.00
(Over head + profit ) 5% @ Rp 45,671.50 = Rp 45,671.50
Jumlah Rp 959,101.50

INT - 02 1M2 Analisa Pekerjaan Dinding HPL kolom


(Analisa Lapangan)
Bahan
1.50 Lbr Multipleks @ Rp 250,000.00 = Rp 375,000.00
0.48 Kg Lem Fox @ Rp 21,000.00 = Rp 10,080.00
0.09 Kg Paku Skrup @ Rp 15,000.00 = Rp 1,350.00
1 Lbr HPL @ Rp 420,000.00 = Rp 420,000.00
Tenaga
0.6 OH Pekerja @ Rp 100,000.00 = Rp 60,000.00
1.7 OH Tukang @ Rp 135,000.00 = Rp 229,500.00
0.6 OH Kepala tukang @ Rp 135,000.00 = Rp 81,000.00
0.06 OH Mandor @ Rp 150,000.00 = Rp 9,000.00
(Over head + profit ) 5% @ Rp 59,296.50 = Rp 59,296.50
Jumlah Rp 1,245,226.50

INT - 03 1M Analisa Pekerjaan Meubel


(Analisa Lapangan)
Bahan
2.95 Lbr Multipleks @ Rp 250,000.00 = Rp 737,500.00
1 Kg Lem Fox @ Rp 21,000.00 = Rp 21,000.00
0.08 Kg Paku Skrup @ Rp 15,000.00 = Rp 1,200.00
3.2 Lbr HPL @ Rp 420,000.00 = Rp 1,344,000.00
Tenaga
0.8 OH Pekerja @ Rp 100,000.00 = Rp 80,000.00
2.5 OH Tukang @ Rp 135,000.00 = Rp 337,500.00
0.5 OH Kepala tukang @ Rp 135,000.00 = Rp 67,500.00
0.07 OH Mandor @ Rp 150,000.00 = Rp 10,500.00
(Over head + profit ) 5% @ Rp 129,960.00 = Rp 129,960.00
Jumlah Rp 2,729,160.00

INT - 04 1M2 Analisa Pekerjaan Back drop


(Analisa Lapangan)
Bahan
1.50 Lbr Multipleks @ Rp 250,000.00 = Rp 375,000.00
0.65 Kg Lem Fox @ Rp 21,000.00 = Rp 13,650.00
0.09 Kg Paku Skrup @ Rp 15,000.00 = Rp 1,350.00
1.5 Lbr HPL @ Rp 420,000.00 = Rp 630,000.00
Tenaga
1 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
2 OH Tukang @ Rp 135,000.00 = Rp 270,000.00
0.68 OH Kepala tukang @ Rp 135,000.00 = Rp 91,800.00
0.08 OH Mandor @ Rp 150,000.00 = Rp 12,000.00
(Over head + profit ) 5% @ Rp 74,690.00 = Rp 74,690.00
Jumlah Rp 1,568,490.00
Pekerjaan Tanah
STR - 01 1m3 Menggali tanah biasa sedalam 1 meter
(PERMEN PU 11/PRT/M/2013)
Tenaga kerja
0.75 OH Pekerja @ Rp 100,000.00 = Rp 75,000.00
0.025 OH Mandor @ Rp 150,000.00 = Rp 3,750.00
(Over head + profit ) 5% @ Rp 3,937.50 = Rp 3,937.50
jumlah tot = Rp 82,687.50

STR - 02 1 m3 Memadatkan tanah (per 20 cm)


(PERMEN PU 11/PRT/M/2013)
Tenaga kerja
0.5 OH Pekerja @ Rp 100,000.00 = Rp 50,000.00
0.05 OH Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 2,875.00 = Rp 2,875.00
jumlah tot = Rp 60,375.00

1 m3 Mengurug sirtu padat untuk peninggian


STR - 03
lantai bangunan
(PERMEN PU 11/PRT/M/2013)
Bahan
1.5 m3 Sirtu @ Rp 150,000.00 = Rp 225,000.00
Tenaga kerja
0.45 OH Pekerja @ Rp 100,000.00 = Rp 45,000.00
0.25 OH Mandor @ Rp 150,000.00 = Rp 37,500.00
(Over head + profit ) 5% @ Rp 15,375.00 = Rp 15,375.00
jumlah tot = Rp 322,875.00

STR - 04 1 m3 pengurugan kembali tanah galian


(PERMEN PU 11/PRT/M/2013)
Tenaga kerja
0.5 OH Pekerja @ Rp 100,000.00 = Rp 50,000.00
0.05 OH Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 5% @ Rp 2,875.00 = Rp 2,875.00
jumlah tot Rp 60,375.00

STR - 05 1 m3 Mengurug pasir urug


(PERMEN PU 11/PRT/M/2013)
Bahan
1.9 m3 Pasir Urug @ Rp 125,000.00 = Rp 237,500.00
Tenaga kerja
0.6 OH Pekerja @ Rp 100,000.00 = Rp 60,000.00
0.1 OH Mandor @ Rp 150,000.00 = Rp 15,000.00
(Over head + profit ) 5% @ Rp 15,625.00 = Rp 15,625.00
jumlah tot Rp 328,125.00

STR - 06 1m3 Mengurug tanah biasa sedalam 1 meter


(PERMEN PU 11/PRT/M/2013)
Bahan
1.100 M3 Tanah Timbunan @ Rp 95,000.00 = Rp 104,500.00
Tenaga kerja
0.250 OH Pekerja @ Rp 100,000.00 = Rp 25,000.00
0.008 OH Mandor @ Rp 150,000.00 = Rp 1,250.00
(Over head + profit ) 5% @ Rp 6,537.50 = Rp 6,537.50
jumlah tot Rp 137,287.50

Pekerjaan pembesian
STR - 07 10.000 Kg Pembesian dengan besi polos atau besi ulir D 14
(PERMEN PU 11/PRT/M/2013)
Bahan
10.5 kg Besi beton Ulir D 14 @ Rp 15,910.00 = Rp 167,055.00
0.15 kg Kawat beton @ Rp 30,000.00 = Rp 4,500.00
Tenaga kerja
0.07 OH Pekerja @ Rp 100,000.00 = Rp 7,000.00
0.07 OH Tukang besi @ Rp 135,000.00 = Rp 9,450.00
0.007 OH Kepala tukang @ Rp 135,000.00 = Rp 945.00
0.004 OH Mandor @ Rp 150,000.00 = Rp 600.00
(Over head + profit ) 5% @ Rp 9,477.50 = Rp 9,477.50
jumlah tot Rp 199,027.50
1 kg pembesian Rp 19,902.75

STR - 09 10.000 Kg Pembesian dengan besi polos atau besi ulir Ø 12

Page 13 analisa struktur


(PERMEN PU 11/PRT/M/2013)
Bahan
10.5 kg Besi Ø 12 @ Rp 15,910.00 = Rp 167,055.00
0.15 kg Kawat beton @ Rp 30,000.00 = Rp 4,500.00
Tenaga kerja
0.07 OH Pekerja @ Rp 100,000.00 = Rp 7,000.00
0.07 OH Tukang Besi @ Rp 135,000.00 = Rp 9,450.00
0.007 OH Kepala Tukang Besi @ Rp 135,000.00 = Rp 945.00
0.004 OH Mandor @ Rp 150,000.00 = Rp 600.00
(Over head + profit ) 5% @ Rp 9,477.50 = Rp 9,477.50
jumlah tot Rp 199,027.50
1 kg pembesian Rp 19,902.75

STR - 10 10.000 Kg Pembesian dengan besi polos atau besi ulir Ø10
(PERMEN PU 11/PRT/M/2013)
Bahan
10.5 kg Besi beton polos Ø10 @ Rp 15,910.00 = Rp 167,055.00
0.15 kg Kawat beton @ Rp 30,000.00 = Rp 4,500.00
Tenaga kerja
0.07 OH Pekerja @ Rp 100,000.00 = Rp 7,000.00
0.07 OH Tukang besi @ Rp 135,000.00 = Rp 9,450.00
0.007 OH Kepala tukang @ Rp 135,000.00 = Rp 945.00
0.004 OH Mandor @ Rp 150,000.00 = Rp 600.00
(Over head + profit ) 5% @ Rp 9,477.50 = Rp 9,477.50
jumlah tot Rp 199,027.50
1 kg pembesian Rp 19,902.75

STR - 11 10.000 Kg Pembesian dengan besi polos atau besi ulir Ø8


(PERMEN PU 11/PRT/M/2013)
Bahan
10.5 kg Besi beton polos Ø8 @ Rp 15,910.00 = Rp 167,055.00
0.15 kg Kawat beton @ Rp 30,000.00 = Rp 4,500.00
Tenaga kerja
0.07 OH Pekerja @ Rp 100,000.00 = Rp 7,000.00
0.07 OH Tukang besi @ Rp 135,000.00 = Rp 9,450.00
0.007 OH Kepala tukang @ Rp 135,000.00 = Rp 945.00
0.004 OH Mandor @ Rp 150,000.00 = Rp 600.00
(Over head + profit ) 5% @ Rp 9,477.50 = Rp 9,477.50
jumlah tot Rp 199,027.50
1 kg pembesian Rp 19,902.75

Pekerjaan Bekisting
STR - 12 1.000 M2 Memasang bekisting untuk pondasi
(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m3 Kayu kelas III bekisting @ Rp 2,250,000.00 = Rp 90,000.00
0.3 kg Paku 5 cm – 10 cm @ Rp 20,000.00 = Rp 6,000.00
0.1 Liter Minyak bekisting @ Rp 5,000.00 = Rp 500.00
= Rp 96,500.00
Bahan 2x pakai = Rp 48,250.00
Tenaga kerja
0.52 OH Pekerja @ Rp 100,000.00 = Rp 52,000.00
0.26 OH Tukang Kayu @ Rp 135,000.00 = Rp 35,100.00
0.026 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 3,510.00
0.026 OH Mandor @ Rp 150,000.00 = Rp 3,900.00
upah = Rp 94,510.00
(Over head + profit ) 5% @ Rp 7,138.00 = Rp 7,138.00
jumlah tot = Rp 149,898.00

STR - 13 1.000 M2 Memasang bekisting untuk sloof


(PERMEN PU 11/PRT/M/2013)
Bahan
0.045 m3 Kayu kelas III @ Rp 2,250,000.00 = Rp 101,250.00
0.3 kg Paku 5 cm – 10 cm @ Rp 20,000.00 = Rp 6,000.00
0.1 Liter Minyak bekisting @ Rp 5,000.00 = Rp 500.00
= Rp 107,750.00
Bahan 2x pakai = Rp 53,875.00
Tenaga kerja
0.52 OH Pekerja @ Rp 100,000.00 = Rp 52,000.00
0.26 OH Tukang Kayu @ Rp 135,000.00 = Rp 35,100.00
0.026 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 3,510.00
0.026 OH Mandor @ Rp 150,000.00 = Rp 3,900.00

Page 14 analisa struktur


upah = Rp 94,510.00
(Over head + profit ) 5% @ Rp 7,419.25 = Rp 7,419.25
jumlah tot = Rp 155,804.25

STR - 14 1.000 M2 Memasang bekisting untuk kolom


(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m3 Kayu kelas III bekisting @ Rp 2,250,000.00 = Rp 90,000.00
0.4 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 8,000.00
0.2 Ltr Minyak bekisting @ Rp 5,000.00 = Rp 1,000.00
0.015 m3 Balok Kayu kelas II @ Rp 8,000,000.00 = Rp 120,000.00
0.35 Lbr Plywood tebal 9 mm @ Rp 90,000.00 = Rp 31,500.00
2.00 Btg Kayu dolken dia 8-10 / 400 cm @ Rp 28,000.00 = Rp 56,000.00
= Rp 306,500.00
Bahan 2x pakai = Rp 153,250.00
Tenaga kerja
0.66 OH Pekerja @ Rp 100,000.00 = Rp 66,000.00
0.33 OH Tukang Kayu @ Rp 135,000.00 = Rp 44,550.00
0.033 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Mandor @ Rp 150,000.00 = Rp 4,950.00
Rp 119,955.00
(Over head + profit ) 5% @ Rp 13,660.25 = Rp 13,660.25
jumlah tot Rp 286,865.25

STR - 15 1.000 M2 Memasang bekisting untuk balok


(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m3 Kayu kelas III @ Rp 2,250,000.00 = Rp 90,000.00
0.4 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 8,000.00
0.2 Ltr Minyak bekisting @ Rp 5,000.00 = Rp 1,000.00
0.018 m3 Balok kayu kelas II @ Rp 8,000,000.00 = Rp 144,000.00
0.35 Lbr Plywood tebal 9 mm @ Rp 90,000.00 = Rp 31,500.00
2 Btg Dolken kayu galam,ö (8-10) cm, p @ Rp 28,000.00 = Rp 56,000.00
= Rp 330,500.00
Bahan 2x pakai = Rp 165,250.00
Tenaga kerja
0.66 OH Pekerja @ Rp 100,000.00 = Rp 66,000.00
0.33 OH Tukang Kayu @ Rp 135,000.00 = Rp 44,550.00
0.033 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Mandor @ Rp 150,000.00 = Rp 4,950.00
= Rp 119,955.00
(Over head + profit ) 5% @ Rp 14,260.25 = Rp 14,260.25
jumlah tot = Rp 299,465.25

STR - 16 1.000 M2 Memasang bekisting untuk plat lantai


(PERMEN PU 11/PRT/M/2013)
Bahan
0.04 m3 Kayu kelas III @ Rp 2,250,000.00 = Rp 90,000.00
0.4 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 8,000.00
0.2 Liter Minyak bekisting @ Rp 5,000.00 = Rp 1,000.00
0.015 m3 Balok kayu kelas II @ Rp 8,000,000.00 = Rp 120,000.00
0.35 Lbr Plywood tebal 9 mm @ Rp 90,000.00 = Rp 31,500.00
6 Batang Dolken kayu galam,ö (8-10) cm, p @ Rp 28,000.00 = Rp 168,000.00
= Rp 418,500.00
Bahan 1x pakai = Rp 418,500.00
Bahan 2x pakai = Rp 209,250.00
Tenaga kerja
0.66 OH Pekerja @ Rp 100,000.00 = Rp 66,000.00
0.33 OH Tukang Kayu @ Rp 135,000.00 = Rp 44,550.00
0.033 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Mandor @ Rp 150,000.00 = Rp 4,950.00
= Rp 119,955.00
STR - 16 (Over head + profit 5% @ Rp 26,922.75 = Rp 26,922.75
STR - 17 (Over head + profit 5% @ Rp 16,460.25 = Rp 16,460.25
jumlah 1x Pakai = Rp 565,377.75
jumlah 2x pakai Rp 345,665.25

STR- 18 1.000 M2 Memasang bekisting untuk tangga


(PERMEN PU 11/PRT/M/2013)
Bahan
0.03 m3 Kayu kelas III @ Rp 2,250,000.00 = Rp 67,500.00
0.4 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 8,000.00

Page 15 analisa struktur


0.15 Liter Minyak bekisting @ Rp 5,000.00 = Rp 750.00
0.015 m3 Balok kayu kelas II @ Rp 8,000,000.00 = Rp 120,000.00
0.35 Lbr Plywood tebal 9 mm @ Rp 90,000.00 = Rp 31,500.00
2 Batang Dolken kayu galam,ö(8-10) cm, pa @ Rp 28,000.00 = Rp 56,000.00

Tenaga kerja
0.66 OH Pekerja @ Rp 100,000.00 = Rp 66,000.00
0.33 OH Tukang Kayu @ Rp 135,000.00 = Rp 44,550.00
0.033 OH Kepala Tukang Kayu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Mandor @ Rp 150,000.00 = Rp 4,950.00
(Over head + profit ) 5% @ Rp 20,185.25 = Rp 20,185.25
jumlah tot = Rp 423,890.25

Pekerjaan beton
STR - 19 1.000 m3 Membuat beton mutu f’c = 26,4 MPa (K 175), slump (12 ± 2) cm, w/c = 0,52
(PERMEN PU 11/PRT/M/2013)
bahan :
326 Kg PC @ Rp 1,610.00 = Rp 524,860.00
760 Kg PB @ Rp 82.36 = Rp 62,595.77
1029 Kg KR (maksimum 30 mm) @ Rp 153.89 = Rp 158,351.67
215 Ltr Air @ Rp 80.00 = Rp 17,200.00

Upah :
1.65 Oh Pekerja @ Rp 100,000.00 = Rp 165,000.00
0.275 Oh Tukang Batu @ Rp 150,000.00 = Rp 41,250.00
0.028 Oh Kepala Tukang Batu @ Rp 135,000.00 = Rp 3,780.00
0.083 Oh Mandor @ Rp 135,000.00 = Rp 11,205.00
(Over head + profit ) 5% @ Rp 49,212.12 = Rp 49,212.12
jumlah tot = Rp 1,033,454.56

STR - 20 1.000 m3 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
(PERMEN PU 11/PRT/M/2013)
bahan :
371 kg Semen Portland (Tonasa 50 Kg) @ Rp 1,610.00 = Rp 597,310.00
698 kg Pasir Pasangan @ Rp 82.36 = Rp 57,489.27
1047 kg Kerikil Rp 153.89 = Rp 161,121.67
215 Liter Air Rp 80.00 = Rp 17,200.00
Upah :
1.65 OH Pekerja @ Rp 100,000.00 = Rp 165,000.00
0.275 OH Tukang Batu @ Rp 135,000.00 = Rp 37,125.00
0.028 OH Kepala Tukang Batu @ Rp 135,000.00 = Rp 3,780.00
0.083 OH Mandor Rp 150,000.00 = Rp 12,450.00
(Over head + profit ) 5% @ Rp 52,573.80 = Rp 52,573.80
jumlah tot Rp 1,104,049.74

analisa pondasi
STR - 22 1.000 M3 Memasang pondasi batu belah, campuran 1 PC : 4 PP
(PERMEN PU 11/PRT/M/2013)
Bahan
1.2 M3 Batu belah 15 cm/20 cm @ Rp 180,000.00 = Rp 216,000.00
163 Kg PC @ Rp 1,610.00 = Rp 262,430.00
0.52 M3 PP @ Rp 115,308.00 = Rp 59,960.16
Tenaga kerja
1.5 OH Pekerja @ Rp 100,000.00 = Rp 150,000.00
0.75 OH Tukang Batu @ Rp 135,000.00 = Rp 101,250.00
0.075 OH Kepala Tukang Batu @ Rp 135,000.00 = Rp 10,125.00
0.075 OH Mandor @ Rp 150,000.00 = Rp 11,250.00
(Over head + profit ) 5% @ Rp 40,550.76 = Rp 40,550.76
jumlah tot Rp 851,565.92

STR - 23 1.000 M3 Memasang batu kosong (anstamping)


(PERMEN PU 11/PRT/M/2013)
Bahan
1.2 m3 Batu belah 15 cm/20 cm @ Rp 180,000.00 = Rp 216,000.00
0.432 m3 Pasir urug @ Rp 125,000.00 = Rp 54,000.00
Tenaga kerja
0.78 OH Pekerja @ Rp 100,000.00 = Rp 78,000.00
0.39 OH Tukang Batu @ Rp 135,000.00 = Rp 52,650.00
0.039 OH Kepala Tukang Batu @ Rp 135,000.00 = Rp 5,265.00
0.039 OH Mandor @ Rp 150,000.00 = Rp 5,850.00
(Over head + profit ) 5% @ Rp 20,588.25 = Rp 20,588.25
jumlah tot Rp 432,353.25

Page 16 analisa struktur


STR - 24 1 M' Membuat kolom praktis beton bertulang (11 x 11) cm
(PERMEN PU 11/PRT/M/2013)
Bahan
0.002 m3 Kayu kelas III @ #REF! = #REF!
0.01 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 200.00
0.2 Liter Minyak bekisting @ Rp 5,000.00 = Rp 1,000.00
3 kg Besi beton polos @ Rp 19,902.75 = Rp 59,708.25
0.45 kg Kawat beton @ Rp 30,000.00 = Rp 13,500.00
4.00 kg PC @ Rp 1,610.00 = Rp 6,440.00
0.006 m3 PB @ Rp 82.36 = Rp 0.49
0.009 m3 KR @ Rp 153.89 = Rp 1.39
Tenaga kerja
0.18 OH Pekerja @ Rp 100,000.00 = Rp 18,000.00
0.02 OH Tukang batu @ Rp 135,000.00 = Rp 2,700.00
0.02 OH Tukang kayu @ Rp 135,000.00 = Rp 2,700.00
0.02 OH Tukang besi @ Rp 135,000.00 = Rp 2,700.00
0.006 OH Kepala tukang @ Rp 135,000.00 = Rp 810.00
0.009 OH Mandor @ Rp 150,000.00 = Rp 1,350.00
(Over head + profit ) 5% @ #REF! = #REF!
jumlah tot #REF!

STR - 25 1 M' Membuat ring balok beton bertulang (10 x 15) cm


(PERMEN PU 11/PRT/M/2013)
Bahan
0.003 m3 Kayu kelas III @ #REF! = #REF!
0.02 kg Paku 5 cm – 12 cm @ Rp 20,000.00 = Rp 400.00
0.200 Liter Minyak bekisting @ Rp 5,000.00 = Rp 1,000.00
3.600 kg Besi beton polos @ Rp 19,902.75 = Rp 71,649.90
0.05 kg Kawat beton @ Rp 30,000.00 = Rp 1,500.00
5.500 Kg PC @ Rp 1,610.00 = Rp 8,855.00
0.009 m3 PB @ Rp 82.36 = Rp 0.74
0.015 m3 KR @ Rp 153.89 = Rp 2.31
Tenaga kerja
0.297 OH Pekerja @ Rp 100,000.00 = Rp 29,700.00
0.033 OH Tukang batu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Tukang kayu @ Rp 135,000.00 = Rp 4,455.00
0.033 OH Tukang besi @ Rp 135,000.00 = Rp 4,455.00
0.01 OH Kepala tukang @ Rp 135,000.00 = Rp 1,350.00
0.015 OH Mandor @ Rp 150,000.00 = Rp 2,250.00
(Over head + profit ) 5% @ #REF! = #REF!
jumlah tot #REF!

Page 17 analisa struktur


ANALISA PEKERJAAN MEP
Analisa pekerjaan Pipa
ME-01 Memasang 1 m' pipa PVC tipe AW Ø 4"
(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M1 Pipa PVC Ø 4" @ Rp 56,500.00 = Rp 67,800.00
0.35Harga pipaPerlengkapan @ Rp 56,500.00 = Rp 19,775.00
Jumlah I = Rp 87,575.00

Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala Tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
. Jumlah II Rp 28,762.50
(Over head + profit ) 10% @ Rp 5,816.88 = Rp 5,816.88
Jumlah I + Jumlah II = Rp 122,154.38

ME - 02 Memasang 1 m' pipa PVC tipe AW Ø 3"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M1 Pipa PVC Ø 3" @ Rp 38,250.00 = Rp 45,900.00
Harga
0.35 pipa Perlengkapan @ Rp 56,500.00 = Rp 19,775.00
Jumlah I = Rp 65,675.00
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala Tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
Jumlah II Rp 28,762.50
(Over head + profit ) 10% @ Rp 4,721.88 = Rp 4,721.88
Jumlah I + Jumlah II = Rp 99,159.38

ME - 03 Memasang 1 m' pipa PVC diameter 1 1/2"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M' Pipa PVC Ø 1 1/2" @ Rp 11,166.67 = Rp 13,400.00
harga
0.25 Perlengkapan
pipa @ Rp 17,750.00 = Rp 4,437.50
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
(Over head + profit ) 10% @ Rp 2,330.00 = Rp 2,330.00
Jumlah total Rp 48,930.00

ME - 04 Memasang 1 m' pipa PVC diameter 1"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M' Pipa PVC Ø 1" @ Rp 17,750.00 = Rp 21,300.00
harga
0.25 Perlengkapan
pipa @ Rp 17,750.00 = Rp 4,437.50
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
(Over head + profit ) 10% @ Rp 2,725.00 = Rp 2,725.00
Jumlah total Rp 57,225.00

ME - 05 Memasang 1 m' pipa PVC diameter 2"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M' Pipa PVC Ø 2" @ Rp 21,500.00 = Rp 25,800.00
harga
0.25 pipa Perlengkapan @ Rp 21,500.00 = Rp 5,375.00
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
(Over head + profit ) 10% @ Rp 2,996.88 = Rp 2,996.88
Jumlah total Rp 62,934.38

ME - 06 Memasang 1 m' pipa PVC diameter 1/2"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M' Pipa PVC 1/2" @ Rp 2,875.00 = Rp 3,450.00
harga
0.35 pipa Perlengkapan @ Rp 2,875.00 = Rp 1,006.25
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.06 Oh Tukang batu @ Rp 135,000.00 = Rp 8,100.00
0.006 Oh Kepala tukang @ Rp 135,000.00 = Rp 810.00
0.002 Oh Mandor @ Rp 150,000.00 = Rp 300.00
(Over head + profit ) 10% @ Rp 1,088.31 = Rp 1,088.31
Jumlah total = Rp 22,854.56

ME - 07 Memasang 1 m' pipa PVC diameter 3/4"


(PERMEN PU 11/PRT/M/2013)
Bahan
1.20 M' Pipa PVC 3/4" @ Rp 4,250.00 = Rp 5,100.00
harga
0.25 pipa Perlengkapan @ Rp 4,250.00 = Rp 1,062.50
Tenaga
0.08 Oh Pekerja @ Rp 100,000.00 = Rp 8,100.00
0.14 Oh Tukang batu @ Rp 135,000.00 = Rp 18,225.00
0.01 Oh Kepala tukang @ Rp 135,000.00 = Rp 1,822.50
0.00 Oh Mandor @ Rp 150,000.00 = Rp 615.00
(Over head + profit ) 10% @ Rp 1,746.25 = Rp 1,746.25
Jumlah total = Rp 36,671.25

ME - 08 1 Bh Pekerjaan Pasangan Closet Duduk


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Kloset Jongkok @ Rp 2,350,000.00 = Rp 2,350,000.00
0.06 Ls Perlengkapan @ Rp 2,350,000.00 = Rp 141,000.00
Tenaga
1.00 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
1.00 OH Tukang Batu @ Rp 135,000.00 = Rp 135,000.00
0.10 OH Kepala Tukang @ Rp 135,000.00 = Rp 13,500.00
0.10 OH Mandor @ Rp 150,000.00 = Rp 15,000.00
(Over head + profit ) 10% @ Rp 137,725.00 = Rp 137,725.00
Jumlah total Rp 2,892,225.00

ME - 09 1 Bh Pekerjaan Closet Jongkok Porselin


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Closet Jongkok @ Rp 3,703,000.00 = Rp 3,703,000.00
6.00 Kg Semen Portland @ Rp 1,610.00 = Rp 9,660.00
0.01 M3 Pasir Pasangan @ Rp 115,308.00 = Rp 1,153.08
Tenaga
1.00 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
1.50 OH Tukang Batu @ Rp 135,000.00 = Rp 202,500.00
0.15 OH Kepala Tukang @ Rp 135,000.00 = Rp 20,250.00
0.16 OH Mandor @ Rp 150,000.00 = Rp 24,000.00
(Over head + profit ) 10% @ Rp 203,028.15 Rp 203,028.15
Jumlah total Rp 4,263,591.23

ME - 10 1 Bh Pekerjaan pasangan Urinoir


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Urinoir @ Rp 2,300,000.00 = Rp 2,300,000.00
0.30 Ls Perlengkapan @ Rp 2,300,000.00 = Rp 690,000.00
6.00 Kg Semen Portland @ Rp 1,610.00 = Rp 9,660.00
0.01 M3 Pasir Pasangan @ Rp 115,308.00 = Rp 1,153.08
Tenaga
1.00 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
1.00 OH Tukang Batu @ Rp 135,000.00 = Rp 135,000.00
0.10 OH Kepala Tukang @ Rp 135,000.00 = Rp 13,500.00
0.05 OH Mandor @ Rp 150,000.00 = Rp 7,500.00
(Over head + profit ) 10% @ Rp 162,840.65 Rp 162,840.65
Jumlah total Rp 3,419,653.73

ME - 11 1 Bh Pekerjaan pasangan Wastafel


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Wastafel @ Rp 850,000.00 = Rp 850,000.00
0.12 Ls Perlengkapan @ Rp 850,000.00 = Rp 102,000.00
6.00 Kg Semen Portland @ Rp 1,610.00 = Rp 9,660.00
0.01 M3 Pasir Pasangan @ Rp 115,308.00 = Rp 1,153.08
Tenaga
1.20 OH Pekerja @ Rp 100,000.00 = Rp 120,000.00
1.45 OH Tukang Batu @ Rp 135,000.00 = Rp 195,750.00
0.15 OH Kepala Tukang @ Rp 135,000.00 = Rp 20,250.00
0.10 OH Mandor @ Rp 150,000.00 = Rp 15,000.00
(Over head + profit ) 10% @ Rp 65,690.65 Rp 65,690.65
Jumlah total Rp 1,379,503.73

ME - 12 1 bh Pasang floor drain /unit


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Floor drain @ Rp 343,000.00 = Rp 343,000.00
Tenaga
0.01 OH Pekerja @ Rp 100,000.00 = Rp 1,000.00
0.10 OH Tukang Batu @ Rp 135,000.00 = Rp 13,500.00
0.01 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,350.00
0.01 OH Mandor @ Rp 150,000.00 = Rp 750.00
(Over head + profit ) 10% @ Rp 17,980.00 = Rp 17,980.00
Jumlah total Rp 377,580.00

ME - 13 1 bh Pasang Roof drain /unit


(PERMEN PU 11/PRT/M/2013)
Bahan
1.00 Bh Roof drain dia 4" @ Rp 143,750.00 = Rp 143,750.00
Tenaga
0.01 OH Pekerja @ Rp 100,000.00 = Rp 1,000.00
0.10 OH Tukang Batu @ Rp 135,000.00 = Rp 13,500.00
0.01 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,350.00
0.01 OH Mandor @ Rp 150,000.00 = Rp 750.00
(Over head + profit ) 10% @ Rp 8,017.50 = Rp 8,017.50
Jumlah total Rp 168,367.50
ME - 14 Memasang Clean Out dia 4"
(Analisa Lapangan)
Bahan
1.00 Bh clean Out 4" @ Rp 308,730.00 = Rp 308,730.00
harga
0.25 CO Perlengkapan & Accesoris lain @ Rp 308,730.00 = Rp 77,182.50
Tenaga
0.20 Mtr Betelan dan Perapian tembok @ Rp 22,500.00 = Rp 4,500.00
8.00 bh Fitser + Sekrup @ #REF! = #REF!
2.00 bh Penggantung/Pengikat/Lem @ Rp 36,018.50 = Rp 72,037.00
0.50 o/hr Pekerja @ Rp 100,000.00 = Rp 50,000.00
0.35 o/hr Tukang Batu @ Rp 135,000.00 = Rp 47,250.00
0.15 o/hr Mandor @ Rp 150,000.00 = Rp 22,500.00
(Over head + profit ) 10% @ #REF! = #REF!
Jumlah total #REF!

ME - 15 1 Bh pekerjaan pasangan Shower


(Analisa Lapangan)
Bahan
1.00 Bh Shower @ Rp 1,850,000.00 = Rp 1,850,000.00
Tenaga
0.01 OH Pekerja @ Rp 100,000.00 = Rp 1,000.00
0.10 OH Tukang Batu @ Rp 135,000.00 = Rp 13,500.00
0.01 OH Kepala Tukang @ Rp 135,000.00 = Rp 1,350.00
0.00 OH Mandor @ Rp 150,000.00 = Rp 75.00
(Over head + profit ) 10% @ Rp 93,296.25 = Rp 93,296.25
Jumlah Rp 1,959,221.25

ME - 16 1 Bh Pekerjaan pasangan Jet Washer


(Analisa Lapangan)
Bahan
Jet Washer Ex TOTO THX 20
1.00 Bh
WHITE @ Rp 200,000.00 = Rp 200,000.00
0.30 Ls Perlengkapan @ Rp 200,000.00 = Rp 60,000.00
Tenaga
1.00 OH Pekerja @ Rp 100,000.00 = Rp 100,000.00
1.00 OH Tukang Batu @ Rp 135,000.00 = Rp 135,000.00
0.10 OH Kepala Tukang @ Rp 135,000.00 = Rp 13,500.00
0.10 OH Mandor @ Rp 150,000.00 = Rp 15,000.00
(Over head + profit ) 10% @ Rp 26,175.00 = Rp 26,175.00
Jumlah Rp 549,675.00

ME - 17 Memasang 1 Buah Kran Ø 3/4" Atau Ø 1/2"


(PERMEN PU 11/PRT/M/2013)
1.00 Bh Kran Air @ Rp 321,100.00 = Rp 321,100.00
0.03 Bh Seal Tape @ Rp 2,100.00 = Rp 52.50
0.01 Oh Pekerja @ Rp 100,000.00 = Rp 1,000.00
0.40 Oh Tukang Batu @ Rp 135,000.00 = Rp 54,000.00
0.04 Oh Kepala Tukang @ Rp 135,000.00 = Rp 5,400.00
0.01 Oh Mandor @ Rp 150,000.00 = Rp 750.00
(Over head + profit ) 10% @ Rp 19,115.13 = Rp 19,115.13
Jumlah total = Rp 401,417.63

ME - 18 1 Unit Septic tank dan peresapan


(Analisa Lapangan)
10.17 M3 Galian Tanah @ Rp 82,687.50 = Rp 841,236.17
18.72 M2 Pas. Trasram 1 : 2 @ Rp 122,690.42 = Rp 2,296,460.41
0.90 M3 Pasir Urug @ Rp 328,125.00 = Rp 295,312.50
23.80 M Kolom, Sloef dan Balok @ #REF! = #REF!
18.72 M2 Plesteran Trasram @ Rp 73,181.27 = Rp 1,369,771.81
3.00 M2 Ijuk @ Rp 1,200.00 = Rp 3,600.00
0.43 M3 Plat Beton @ Rp 1,033,454.56 = Rp 442,731.93
25.70 Kg Besi Plat Beton @ Rp 19,902.75 = Rp 511,580.29
0.40 M' Pipa Penghawaan @ Rp 57,225.00 = Rp 22,890.00
1.35 M3 Kerikil @ Rp 322,875.00 = Rp 435,881.25
1.75 M' PVC dia. 4" (D) @ Rp 122,154.38 = Rp 213,770.16
Jumlah total = #REF!
ANLISA ME
Analisa intalasi ME (Panel)

ME - 19 1 Unit Panel Utama - LVMDP


(Analisa Lapangan)
1.00 Bh MCCB 100 A/3 Phasa @ Rp 2,500,000.00 = Rp 2,500,000.00
4.00 Bh MCCB 25 A/3 Phasa @ Rp 780,000.00 = Rp 3,120,000.00
3.00 Bh MCCB 40 A/3 Phasa @ Rp 1,200,000.00 = Rp 3,600,000.00
1.00 Bh Mechanic Motor Interlock @ Rp 250,000.00 = Rp 250,000.00
1.00 Bh Volt Meter @ Rp 225,000.00 = Rp 225,000.00
1.00 Bh Ampere meter @ Rp 225,000.00 = Rp 225,000.00
2.00 Bh Fuse & Indicator @ Rp 225,000.00 = Rp 450,000.00
2.00 Bh Pilot Lamp @ Rp 45,000.00 = Rp 90,000.00
1.00 Unit Box Panel & Accessories @ Rp 362,500.00 = Rp 362,500.00
1.00 Ls Grounding @ Rp 500,000.00 = Rp 500,000.00
2.00 Hr Mandor @ Rp 150,000.00 = Rp 300,000.00
2.00 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 270,000.00
2.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 270,000.00
(Over head + profit ) 10% Rp 608,125.00 = Rp 608,125.00
Jumlah total = Rp 12,770,625.00

ME - 20 1 Unit Panel - PP LP satu


(Analisa Lapangan)
21.00 Bh MCB 10 A/1 Phasa @ Rp 99,000.00 = Rp 2,079,000.00
2.00 Bh Pilot Lamp @ Rp 45,000.00 = Rp 90,000.00
1.00 Bh Fuse & Indicator @ Rp 225,000.00 = Rp 225,000.00
1.00 Bh Box Panel & Accessories @ Rp 362,500.00 = Rp 362,500.00
1.00 Ls Grounding B @ Rp 375,000.00 = Rp 375,000.00
1.00 Ls Material Bant @ Rp 250,000.00 = Rp 250,000.00
1.00 Hr Mandor @ Rp 150,000.00 = Rp 150,000.00
1.00 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% Rp 190,075.00 = Rp 190,075.00
Jumlah total = Rp 3,991,575.00

ME - 21 1 Unit Panel - PP LP Lantai 2


(Analisa Lapangan)
21.00 Bh MCB 10 A/1 Phasa @ Rp 99,000.00 = Rp 2,079,000.00
2.00 Bh Pilot Lamp @ Rp 45,000.00 = Rp 90,000.00
1.00 Bh Fuse & Indicator @ Rp 225,000.00 = Rp 225,000.00
1.00 Bh Box Panel & Accessories @ Rp 362,500.00 = Rp 362,500.00
1.00 Ls Grounding B @ Rp 375,000.00 = Rp 375,000.00
1.00 Ls Material Bant @ Rp 250,000.00 = Rp 250,000.00
1.00 Hr Mandor @ Rp 150,000.00 = Rp 150,000.00
1.00 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% Rp 190,075.00 = Rp 190,075.00
Jumlah total = Rp 3,991,575.00
ME - 22 1 Unit Panel - AC LT satu
(Analisa Lapangan)
12.00 Bh MCB 16 A/1 Phasa @ Rp 125,000.00 = Rp 1,500,000.00
2.00 Bh Pilot Lamp @ Rp 45,000.00 = Rp 90,000.00
1.00 Bh Fuse & Indicator @ Rp 225,000.00 = Rp 225,000.00
1.00 Bh Box Panel & Accessories @ Rp 362,500.00 = Rp 362,500.00
1.00 Ls Grounding B @ Rp 375,000.00 = Rp 375,000.00
1.00 Ls Material Bant @ Rp 250,000.00 = Rp 250,000.00
1.00 Hr Mandor @ Rp 150,000.00 = Rp 150,000.00
1.00 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% Rp 161,125.00 = Rp 161,125.00
Jumlah total = Rp 3,383,625.00
ME - 23 1 Unit Panel - AC LT dua
(Analisa Lapangan)
12.00 Bh MCB 6 A/1 Phasa @ Rp 125,000.00 = Rp 1,500,000.00
2.00 Bh Pilot Lamp @ Rp 45,000.00 = Rp 90,000.00
1.00 Bh Fuse & Indicator @ Rp 225,000.00 = Rp 225,000.00
1.00 Bh Box Panel & Accessories @ Rp 362,500.00 = Rp 362,500.00
1.00 Ls Grounding B @ Rp 375,000.00 = Rp 375,000.00
1.00 Ls Material Bant @ Rp 250,000.00 = Rp 250,000.00
1.00 Hr Mandor @ Rp 150,000.00 = Rp 150,000.00
1.00 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% Rp 161,125.00 = Rp 161,125.00
Jumlah total = Rp 3,383,625.00

Analisa intalasi Kabel


ME - 24 1 m' Kabel Tr NYFGBY 4 x 70 mm
(Analisa Lapangan)
Bahan
1.15 M' Kabel NYFGBY 4 x 70 mm2 @ Rp 465,000.00 = Rp 534,750.00
1.00 M' gali, urugan dan pelindung @ Rp 125,000.00 = Rp 125,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% Rp 33,887.50 = Rp 33,887.50
Jumlah total = Rp 711,637.50

ME - 25 1 m' Kabel Tr NYY 4 x35 mm


(Analisa Lapangan)
Bahan
1.00 M' Kabel NYY 4 x 35 mm @ Rp 239,850.00 = Rp 239,850.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) Rp 12,337.50 = Rp 12,337.50
Jumlah total = Rp 259,087.50
ME - 26 1 m' Kabel Tr NYY 4 x 16 mm
(Analisa Lapangan)
Bahan
1.00 M' Kabel NYY 4 x 16 mm @ Rp 91,000.00 = Rp 91,000.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) Rp 4,895.00 = Rp 4,895.00
Jumlah total = Rp 102,795.00

ME - 27 1 m' Kabel Tr NYY 4 x 10 mm


(Analisa Lapangan)
Bahan
1.00 M' Kabel NYY 4 x 10 mm @ Rp 55,000.00 = Rp 55,000.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) Rp 3,095.00 = Rp 3,095.00
Jumlah total = Rp 64,995.00
ME - 28 1 m' Kabel Tr NYMHY 3 x 2.5mm
(Analisa Lapangan)
Bahan
1.00 M' Kabel Tr NYMHY 3 x 2.5mm @ Rp 6,000.00 = Rp 6,000.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 645.00 = Rp 645.00
Jumlah total = Rp 13,545.00

ME - 29 1 m' kabel ITC 10 pairs x 0,2x0,6mm2


(Analisa Lapangan)
Bahan
1.00 M' Kabel Coaxial Rg8 (0.6mm) @ Rp 7,000.00 = Rp 7,000.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 695.00 = Rp 695.00
Jumlah total = Rp 14,595.00

ME - 30 1 m' kabel ITC 20 pairs x 0,2x0,6mm2


(Analisa Lapangan)
Bahan
1.00 M' Kabel Coaxial Rg8 (0.6mm) @ Rp 12,000.00 = Rp 12,000.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 945.00 = Rp 945.00
Jumlah total = Rp 19,845.00

ME - 31 1 m' Kabel Coaxial RG-11 ( 7 C /2V )


(Analisa Lapangan)
Bahan
Kabel Coaxial RG-11 ( 7 C
1.00 M' @ Rp 8,684.43 = Rp 8,684.43
/2V )
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 779.22 = Rp 779.22
Jumlah total = Rp 16,363.65

ME - 32 1 m' Kabel Tray Lebar 200 x 100


(Analisa Lapangan)
Bahan
1.00 M' Kabel Tray Lebar 200 x 100 @ Rp 83,854.17 = Rp 83,854.17
Kelengkapan
1.00 Lot ( Elbow,Tee,Cross,redd,dll) @ Rp 20,963.54 = Rp 20,963.54
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 5,585.89 = Rp 5,585.89
Jumlah total = Rp 117,303.59

ME - 33 1 m' Kabel Ladder Lebar 400 x 100


(Analisa Lapangan)
Bahan
1.00 M' Kabel Ladder Lebar 400 x 100 @ Rp 307,050.00 = Rp 307,050.00
Kelengkapan
1.00 Lot ( Elbow,Tee,Cross,redd,dll) @ Rp 76,762.50 = Rp 76,762.50
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 19,535.63 = Rp 19,535.63
Jumlah total = Rp 410,248.13

ME - 34 1 m' Kabel Tray Lebar 400 x 200


(Analisa Lapangan)
Bahan
1.00 M' Kabel Tray Lebar 400 x 200 @ Rp 162,500.00 = Rp 162,500.00
Kelengkapan
1.00 Lot ( Elbow,Tee,Cross,redd,dll) @ Rp 40,625.00 = Rp 40,625.00
Tenaga
0.01 Hr Mandor @ Rp 150,000.00 = Rp 1,500.00
0.02 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 2,700.00
0.02 Hr Tukang @ Rp 135,000.00 = Rp 2,700.00
(Over head + profit ) 10% Rp 10,501.25 = Rp 10,501.25
Jumlah total = Rp 220,526.25

Analisa intalasi ME
ME - 35 1 titik instalasi Penerangan
(Analisa Lapangan)
Bahan
4.20 M' Kabel NYM 3x2,5 mm2 @ Rp 15,500.00 = Rp 65,100.00
4.20 M' Pipa Conduit @ Rp 4,166.67 = Rp 17,500.00
1.00 Bh Socket Pipa @ Rp 3,000.00 = Rp 3,000.00
1.00 Bh Tee Doos @ Rp 1,500.00 = Rp 1,500.00
2.00 Bh Klem Pipa @ Rp 4,000.00 = Rp 8,000.00
4.00 Bh Fhiser @ Rp 321.59 = Rp 1,286.38
1.00 Bh Las Doop @ Rp 6,000.00 = Rp 6,000.00
0.25 Bh Isolasi ban @ Rp 2,500.00 = Rp 625.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 10,475.57 = Rp 10,475.57
Jumlah total = Rp 219,986.94

ME - 36 1 titik instalasi Telephone / Data


(Analisa Lapangan)
Bahan
5.00 M' Kabel Coaxial Rg8 (0.6mm) @ Rp 7,000.00 = Rp 35,000.00
5.00 M' Pipa Conduit @ Rp 4,166.67 = Rp 20,833.33
1.00 Bh Socket Pipa @ Rp 3,000.00 = Rp 3,000.00
2.00 Bh Tee Doos @ Rp 1,500.00 = Rp 3,000.00
3.00 Bh Klem Pipa @ Rp 4,000.00 = Rp 12,000.00
6.00 Bh Fhiser @ Rp 321.59 = Rp 1,929.56
2.00 Bh Las Doop @ Rp 6,000.00 = Rp 12,000.00
0.25 Bh Isolasi ban @ Rp 2,500.00 = Rp 625.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 9,744.39 = Rp 9,744.39
Jumlah total = Rp 204,632.29

ME - 37 1 titik instalasi Stop Kontak


(Analisa Lapangan)
Bahan
4.50 M' Kabel NYM 3x2,5 mm2 @ Rp 15,500.00 = Rp 69,750.00
4.50 M' Pipa Conduit @ Rp 4,166.67 = Rp 18,750.00
1.00 Bh Socket Pipa @ Rp 3,000.00 = Rp 3,000.00
2.00 Bh Tee Doos @ Rp 1,500.00 = Rp 3,000.00
3.00 Bh Klem Pipa @ Rp 4,000.00 = Rp 12,000.00
6.00 Bh Fhiser @ Rp 321.59 = Rp 1,929.56
2.00 Bh Las Doop @ Rp 6,000.00 = Rp 12,000.00
0.25 Bh Isolasi ban @ Rp 2,500.00 = Rp 625.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 11,377.73 = Rp 11,377.73
Jumlah total = Rp 238,932.29

ME - 38 1 titik instalasi speaker


(Analisa Lapangan)
Bahan
4.50 M' Kabel NYMHY 3x1,5 mm2 @ Rp 17,500.00 = Rp 78,750.00
4.50 M' Pipa Conduit @ Rp 4,166.67 = Rp 18,750.00
1.00 Bh Socket Pipa @ Rp 3,000.00 = Rp 3,000.00
2.00 Bh Tee Doos @ Rp 1,500.00 = Rp 3,000.00
3.00 Bh Klem Pipa @ Rp 4,000.00 = Rp 12,000.00
6.00 Bh Fhiser @ Rp 321.59 = Rp 1,929.56
2.00 Bh Las Doop @ Rp 6,000.00 = Rp 12,000.00
0.25 Bh Isolasi ban @ Rp 2,500.00 = Rp 625.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 11,827.73 = Rp 11,827.73
Jumlah total = Rp 248,382.29

ME - 39 1 titik instalasi AC/FAN 1 PHASE


(Analisa Lapangan)
Bahan
6.00 M' Kabel NYM 3x4 mm2 @ Rp 20,800.00 = Rp 124,800.00
1.00 Bh Isolasi ban @ Rp 2,500.00 = Rp 2,500.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 11,690.00 = Rp 11,690.00
Jumlah total = Rp 245,490.00

ME - 40 1 titik instalasi MATV


(Analisa Lapangan)
Bahan
25.00 M' Kabel Coaxial 5C-2v @ Rp 5,000.00 = Rp 125,000.00
25.00 M' Pipa Conduit @ Rp 4,166.67 = Rp 104,166.67
1.00 Bh Socket Pipa @ Rp 3,000.00 = Rp 3,000.00
2.00 Bh Tee Doos @ Rp 1,500.00 = Rp 3,000.00
3.00 Bh Klem Pipa @ Rp 4,000.00 = Rp 12,000.00
6.00 Bh Fhiser @ Rp 321.59 = Rp 1,929.56
2.00 Bh Las Doop @ Rp 6,000.00 = Rp 12,000.00
0.25 Bh Isolasi ban @ Rp 2,500.00 = Rp 625.00
Tenaga
0.17 Hr Mandor @ Rp 150,000.00 = Rp 25,500.00
0.30 Hr Kepala Tukang listrik @ Rp 135,000.00 = Rp 40,500.00
0.30 Hr Tukang @ Rp 135,000.00 = Rp 40,500.00
(Over head + profit ) 10% Rp 18,411.06 = Rp 18,411.06
Jumlah total = Rp 386,632.29
ME - 41 1 TITIK PEMASANGAN INSTALASI CCTV
(Analisa Lapangan)
(Dari Terminal Box TV ke Boster Kemudian Ke Titik Outlet TV)
Bahan
1.00 bh L.Bow Sekrup @ Rp 1,698.02 = Rp 1,698.02
6.00 m' Kabel RG 59 @ Rp 5,402.78 = Rp 32,416.65
12.00 bh Sadel @ Rp 360.19 = Rp 4,322.22
6.00 bh Penggantung TYPE A @ Rp 1,479.33 = Rp 8,875.99
1.00 bh Inbow Dos @ Rp 6,689.15 = Rp 6,689.15
2.00 bh T-Dos @ Rp 1,500.00 = Rp 3,000.00
24.00 bh Fizzer + Sekrup @ Rp 321.59 = Rp 7,718.25
6.00 bh Kabel Teets @ Rp 231.55 = Rp 1,389.29
2.00 Mtr Pipa Spiral @ Rp 1,286.38 = Rp 2,572.75
5.00 bh L-Bow @ Rp 1,286.38 = Rp 6,431.88
2.50 btg Pipa Clipsal @ Rp 4,166.67 = Rp 10,416.67
0.20 bh Isolasi @ Rp 2,500.00 = Rp 500.00
Tenaga
0.80 o/hr Pekerja @ Rp 100,000.00 = Rp 80,000.00
0.50 o/hr Tukang listrik @ Rp 135,000.00 = Rp 67,500.00
0.08 o/hr Mandor @ Rp 150,000.00 = Rp 12,000.00
(Over head + profit ) 10% Rp 12,276.54 = Rp 12,276.54
Jumlah total Rp 257,807.39

Analisa Armature ME ( Saklar dan Stop Kontak)


ME - 42 1 Bh Saklar Tunggal
(Analisa Lapangan)
Bahan
1.00 Bh Saklar Tunggal 10 A @ Rp 23,000.00 = Rp 23,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 2,050.00 = Rp 2,050.00
Jumlah total = Rp 43,050.00

ME - 43 1 Bh Saklar Ganda
(Analisa Lapangan)
Bahan
1.00 Bh Saklar Ganda 10 A @ Rp 26,000.00 = Rp 26,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 2,200.00 = Rp 2,200.00
Jumlah total = Rp 46,200.00

ME - 44 1 Bh saklar 12 Gang
(Analisa Lapangan)
Bahan
1.00 Bh Grid Switch 12 GANG @ Rp 128,000.00 = Rp 128,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 7,300.00 = Rp 7,300.00
Jumlah total = Rp 153,300.00
ME - 45 1 Bh Stop Kontak 200 VA
(Analisa Lapangan)
Bahan
1.00 Bh Stop Kontak 200 VA @ Rp 26,703.00 = Rp 26,703.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 2,235.15 = Rp 2,235.15
Jumlah total = Rp 46,938.15

ME - 46 1 Bh Stop Kontak 200 VA water proof


(Analisa Lapangan)
Bahan
Stop Kontak 200 VA + Cover
1.00 Bh @ Rp 53,958.00 = Rp 53,958.00
Water proof
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 3,597.90 = Rp 3,597.90
Jumlah total = Rp 75,555.90

ME - 47 1 Bh socket telepon
` (Analisa Lapangan)
Bahan
1.00 Bh socket Telepon @ Rp 65,000.00 = Rp 65,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.05 Hr Kepala tukang @ Rp 135,000.00 = Rp 6,750.00
0.05 Hr Tukang Listrik @ Rp 135,000.00 = Rp 6,750.00
(Over head + profit ) 10% @ Rp 4,150.00 = Rp 4,150.00
Jumlah total = Rp 87,150.00

ME - 48 1 Bh socket Data
(Analisa Lapangan)
Bahan
1.00 Bh Socket Data RG-45 @ Rp 50,000.00 = Rp 50,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.06 Hr Kepala tukang @ Rp 135,000.00 = Rp 8,100.00
0.06 Hr Tukang Listrik @ Rp 135,000.00 = Rp 8,100.00
(Over head + profit ) 10% @ Rp 3,535.00 = Rp 3,535.00
Jumlah total = Rp 74,235.00
ME - 49 1 Bh socket MATV
(Analisa Lapangan)
Bahan
1.00 Bh Socket Data MATV @ Rp 65,000.00 = Rp 65,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.06 Hr Kepala tukang @ Rp 135,000.00 = Rp 8,100.00
0.06 Hr Tukang Listrik @ Rp 135,000.00 = Rp 8,100.00
(Over head + profit ) 10% @ Rp 4,285.00 = Rp 4,285.00
Jumlah total = Rp 89,985.00
ME - 50 1 Bh Stop kontak AC
(Analisa Lapangan)
Bahan
1.00 Bh Stop Kontak @ Rp 65,435.00 = Rp 65,435.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,500.00
0.06 Hr Kepala tukang @ Rp 135,000.00 = Rp 8,100.00
0.06 Hr Tukang Listrik @ Rp 135,000.00 = Rp 8,100.00
(Over head + profit ) 10% @ Rp 4,306.75 = Rp 4,306.75
Jumlah total = Rp 90,441.75

ME - 51 1 Bh Terminal Box
(Analisa Lapangan)
Bahan
1.00 Bh Terminal Box @ Rp 125,000.00 = Rp 125,000.00
Tenaga
0.25 Hr Mandor @ Rp 150,000.00 = Rp 37,500.00
0.50 Hr Kepala tukang @ Rp 135,000.00 = Rp 67,500.00
0.50 Hr Tukang Listrik @ Rp 135,000.00 = Rp 67,500.00
(Over head + profit ) 10% @ Rp 14,875.00 = Rp 14,875.00
Jumlah total = Rp 312,375.00
ME - 52 1 Bh dome camera interior
(Analisa Lapangan)
Bahan
1.00 Bh dome camera @ Rp 1,300,000.00 = Rp 1,300,000.00
Tenaga
0.50 Hr Mandor @ Rp 150,000.00 = Rp 75,000.00
1.00 Hr Kepala tukang @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% @ Rp 82,250.00 = Rp 82,250.00
Jumlah total = Rp 1,727,250.00

ME - 53 1 Bh dome camera exterior


(Analisa Lapangan)
Bahan
1.00 Bh fixed camera @ Rp 1,700,000.00 = Rp 1,700,000.00
Tenaga
0.50 Hr Mandor @ Rp 150,000.00 = Rp 75,000.00
1.00 Hr Kepala tukang @ Rp 135,000.00 = Rp 135,000.00
1.00 Hr Tukang Listrik @ Rp 135,000.00 = Rp 135,000.00
(Over head + profit ) 10% @ Rp 102,250.00 = Rp 102,250.00
Jumlah total = Rp 2,147,250.00

Analisa Armature ME ( lampu)

ME - 54 1 Bh pekerjaan Lampu TlD 2 x 36 watt Surface Mounted


(Analisa Lapangan)
Bahan
TlD 2 x 36 watt Surface
1.00 Bh @ Rp 244,950.00 = Rp 244,950.00
Mounted
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 13,399.50 = Rp 13,399.50
Jumlah total = Rp 281,389.50

ME - 55 1 Bh pekerjaan Lampu TL PLC 1 x 14 watt


(Analisa Lapangan)
Bahan
1.00 Bh Lampu TL 1 x 14 watt @ Rp 24,050.00 = Rp 24,050.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 2,354.50 = Rp 2,354.50
Jumlah total = Rp 49,444.50

ME - 56 Lampu TLP 2 x 10 watt Exit


(Analisa Lapangan)
Bahan
1.00 Bh LP 2 x 10 watt Exit @ Rp 65,000.00 = Rp 65,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 4,402.00 = Rp 4,402.00
Jumlah total = Rp 92,442.00

ME - 57 Lampu LED 80 Watt


(Analisa Lapangan)
Bahan
1.00 Bh LED 80 Watt @ Rp 1,495,000.00 = Rp 1,495,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 75,902.00 = Rp 75,902.00
Jumlah total = Rp 1,593,942.00

ME - 58 Lampu Lp lampu baret 20 watt


(Analisa Lapangan)
Bahan
1.00 Bh lampu baret 20 watt @ Rp 224,250.00 = Rp 224,250.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 12,364.50 = Rp 12,364.50
Jumlah total = Rp 259,654.50

ME - 59 Lampu Lp lampu baret 40 watt


(Analisa Lapangan)
Bahan
1.00 Bh Lampu baret 40 watt @ Rp 448,500.00 = Rp 448,500.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 23,577.00 = Rp 23,577.00
Jumlah total = Rp 495,117.00

ME - 60 Lampu lampu TLD 2 x 18 watt


(Analisa Lapangan)
Bahan
1.00 Bh lampu TLD 2 x 18 watt @ Rp 125,000.00 = Rp 125,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 7,402.00 = Rp 7,402.00
Jumlah total = Rp 155,442.00

ME - 61 Lampu lampu RM TLD 2 x 18 watt


(Analisa Lapangan)
Bahan

1.00 Bh lampu RM TLD 3 x 18 watt @ Rp 371,800.00 = Rp 371,800.00


Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 19,742.00 = Rp 19,742.00
Jumlah total = Rp 414,582.00

ME - 62 Lampu Down light 2 x 18 watt


(Analisa Lapangan)
Bahan
1.00 Bh Down light 2 x 18 watt @ Rp 130,000.00 = Rp 130,000.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 7,652.00 = Rp 7,652.00
Jumlah total = Rp 160,692.00

ME - 63 Lampu spot light 40 watt


(Analisa Lapangan)
Bahan
1.00 Bh Lampu spot light 80 watt @ Rp 141,974.40 = Rp 141,974.40
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 8,250.72 = Rp 8,250.72
Jumlah total = Rp 173,265.12

ME - 64 Lampu DL 1 x 18 Watt
(Analisa Lapangan)
Bahan
1.00 Bh Lampu DL 1 x 18 @ Rp 79,200.00 = Rp 79,200.00
Tenaga
0.03 Hr Mandor @ Rp 150,000.00 = Rp 4,950.00
0.07 Hr Kepala tukang @ Rp 135,000.00 = Rp 9,045.00
0.07 Hr Tukang Listrik @ Rp 135,000.00 = Rp 9,045.00
(Over head + profit ) 10% @ Rp 5,112.00 = Rp 5,112.00
Jumlah total = Rp 107,352.00
Analisa Armature ME ( Exhause Fan)

ME - 65 1 bh EXHAUST FAN
(Analisa Lapangan)
1.00 Bh Exhaust Fan Inline @ Rp 380,650.00 = Rp 380,650.00
1.00 set Alat bantu @ Rp 35,000.00 = Rp 35,000.00
0.33 Hr Mandor @ Rp 150,000.00 = Rp 49,500.00
0.33 Hr Kepala Tukang AC @ Rp 135,000.00 = Rp 44,550.00
0.33 Hr Tukang @ Rp 135,000.00 = Rp 44,550.00
(Over head + profit ) 10% @ Rp 27,712.50 = Rp 27,712.50
@ Jumlah total = Rp 581,962.50

Analisa Armature ME Tata Suara


ME - 66 1 bh Ceiling Speaker
(Analisa Lapangan)
1.00 Bh Ceiling Speker @ Rp 150,000.00 = Rp 150,000.00
0.07 Hr Mandor @ Rp 150,000.00 = Rp 10,500.00
0.15 Hr Kepala Tukang Listrik @ Rp 135,000.00 = Rp 20,250.00
0.15 Hr Tukang @ Rp 135,000.00 = Rp 20,250.00
(Over head + profit ) 10% @ Rp 10,050.00 = Rp 10,050.00
@ Jumlah total = Rp 211,050.00
GATE VALVE
ME - 67 1 BH Balvalve 2"
(Analisa Lapangan)
1.00 Bh Gate Valve 2" @ Rp 55,900.00 Rp 55,900.00
0.15 o/hr Pekerja @ Rp 100,000.00 Rp 15,000.00
0.15 o/hr Tukang listrik @ Rp 135,000.00 Rp 20,250.00
0.07 o/hr Mandor @ Rp 150,000.00 Rp 10,500.00
(Over head + profit ) 10% @ Rp 5,082.50 = Rp 5,082.50
@ Jumlah total = Rp 106,732.50
Rekap Analisa harga satuan Kerja Struktur
Kode Nama Analisa Jumlah harga Acuan Analisa
(PERMEN PU
STR - 01 1m3 Menggali tanah biasa sedalam 1 meter Rp 82,687.50
11/PRT/M/2013)
(PERMEN PU
STR - 02 1 m3 Memadatkan tanah (per 20 cm) Rp 60,375.00 11/PRT/M/2013)
(PERMEN PU
STR - 03 1 m3 Mengurug sirtu padat untuk peninggian lantai bangunan Rp 322,875.00 11/PRT/M/2013)
(PERMEN PU
STR - 04 1 m3 pengurugan kembali tanah galian Rp 60,375.00 11/PRT/M/2013)
(PERMEN PU
STR - 05 1 m3 Mengurug pasir urug Rp 328,125.00 11/PRT/M/2013)
(PERMEN PU
STR - 06 1m3 Mengurug tanah biasa sedalam 1 meter Rp 137,287.50 11/PRT/M/2013)
(PERMEN PU
STR - 07 Pembesian dengan besi polos atau besi ulir D 14 Rp 19,902.75 11/PRT/M/2013)
(PERMEN PU
STR - 09 Pembesian dengan besi polos atau besi ulir Ø 12 Rp 19,902.75 11/PRT/M/2013)
(PERMEN PU
STR - 10 Pembesian dengan besi polos atau besi ulir Ø10 Rp 19,902.75 11/PRT/M/2013)
(PERMEN PU
STR - 11 Pembesian dengan besi polos atau besi ulir Ø8 Rp 19,902.75 11/PRT/M/2013)
(PERMEN PU
STR - 12 Memasang bekisting untuk pondasi Rp 149,898.00 11/PRT/M/2013)
(PERMEN PU
STR - 13 Memasang bekisting untuk sloof Rp 155,804.25 11/PRT/M/2013)
(PERMEN PU
STR - 14 Memasang bekisting untuk kolom Rp 286,865.25 11/PRT/M/2013)
(PERMEN PU
STR - 15 Memasang bekisting untuk balok Rp 299,465.25 11/PRT/M/2013)
(PERMEN PU
STR - 16 Memasang bekisting untuk plat lantai Rp 565,377.75 11/PRT/M/2013)
(PERMEN PU
STR - 17 Memasang bekisting untuk plat lantai Rp 345,665.25 11/PRT/M/2013)
(PERMEN PU
STR- 18 Memasang bekisting untuk tangga Rp 423,890.25 11/PRT/M/2013)
(PERMEN PU
STR - 19 Membuat beton mutu f’c = 26,4 MPa (K 175), slump (12 ± 2) cm, w/c = 0,52 Rp 1,033,454.56 11/PRT/M/2013)
(PERMEN PU
STR - 20 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 Rp 1,104,049.74 11/PRT/M/2013)
(PERMEN PU
STR - 22 Memasang pondasi batu belah, campuran 1 PC : 4 PP Rp 851,565.92 11/PRT/M/2013)
(PERMEN PU
STR - 23 Memasang batu kosong (anstamping) Rp 432,353.25 11/PRT/M/2013)
(PERMEN PU
STR - 24 Membuat kolom praktis beton bertulang (11 x 11) cm #REF! 11/PRT/M/2013)
(PERMEN PU
STR - 25 Membuat ring balok beton bertulang (10 x 15) cm #REF! 11/PRT/M/2013)
Rekap Analisa harga satuan Kerja Arsitektur
(PERMEN PU
Ars - 01 1 M2 Pembersihan Lahan Rp 18,375.00 11/PRT/M/2013)
(PERMEN PU
Ars - 02 1 M3 Timbunan Tanah Kembali Rp 60,375.00 11/PRT/M/2013)
(PERMEN PU
Ars - 03 1 Mengurug tanah biasa sedalam 1 meter Rp 147,262.50 11/PRT/M/2013)
(PERMEN PU
Ars - 04 1 M2 Memasang dinding bata merah cm tebal ½ bata, campuran spesi 1 PC : 3 PP Rp 122,690.42 11/PRT/M/2013)
(PERMEN PU
Ars - 05 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’) Rp 34,029.32 11/PRT/M/2013)
(PERMEN PU
Ars - 06 1 M2 Memasang dinding bata merah tebal ½ bata, campuran spesi 1 PC : 5 PP Rp 115,367.34 11/PRT/M/2013)
(PERMEN PU
Ars - 07 1 M2 Memasang plesteran 1 PC : 5 PP, tebal 15 mm Rp 61,366.46 11/PRT/M/2013)
(PERMEN PU
Ars - 08 1 m2 Screed 1 : 3 tebal Rp 70,829.62 11/PRT/M/2013)
(PERMEN PU
Ars - 09 Memasang 1 m2 acian Rp 43,661.63 11/PRT/M/2013)
(PERMEN PU
Ars - 10 1 M2 Memasang plesteran 1 PC : 3 PP, tebal 15 mm Rp 73,181.27 11/PRT/M/2013)
(PERMEN PU
Ars -11 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, Rp 46,311.83 11/PRT/M/2013)
(PERMEN PU
Ars -12 1 m2 pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, Rp 51,280.43 11/PRT/M/2013)
(PERMEN PU
Ars - 13 1 m2 pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Rp 34,755.00 11/PRT/M/2013)
(PERMEN PU
Ars - 15 Pasang Keramik Lantai 60/60 per m2 Rp 332,778.10 11/PRT/M/2013)
(PERMEN PU
Ars - 17 Pasang keramik 60/60 per m2 warna Rp 382,688.10 11/PRT/M/2013)

Pasang keramik lantai km/wc 25/25 per m2 Rp 185,896.05


(PERMEN PU
Ars - 18 Pasang keramik dinding km/wc 25 x 40 per m2 Rp 202,223.55 11/PRT/M/2013)
(analisa
Ars - 19 Pasang keramik antislip ujung tangga 10x60 per m' Rp 88,296.20 lapangan)
(PERMEN PU
Ars - 20 1m2 Waterproofing / m2 Rp 192,979.50 11/PRT/M/2013)
(PERMEN PU
Ars - 21 1 M2 Pasang Rangka Plafond Aluminium Hollow Rp 180,783.75 11/PRT/M/2013)
(PERMEN PU
Ars - 22 1 M2 Langit -Langit GYpsum, Tebal 9mm Rp 53,878.13 11/PRT/M/2013)
(PERMEN PU
Ars - 23 1 M2 Langit -Langit Kalsiboard, Tebal 3mm Rp 55,663.13 11/PRT/M/2013)
(PERMEN PU
Ars - 24 1 m' Railing Tangga Rp 807,817.50 11/PRT/M/2013)
(analisa
Ars - 25 1 M2 Pasangan Dinding Batu alam andesit 2/50 Rp 377,076.03 lapangan)
Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding (PERMEN PU
Ars - 26
partisi Rp 163,353.75 11/PRT/M/2013)
Ars - 45 1 buah Type P1 Rp 3,154,822.13
Ars - 46 1 buah Type P2 #REF!
Ars - 47 1 buah Type P4 #REF!
Ars - 48 1 buah Type P5 #REF!
Ars - 49 1 buah Type P6 Rp 100,313,190.97
Ars - 50 1 buah Type P7 #REF!
Ars - 51 1 buah Type P8 #REF!
Ars - 52 1 buah Type PJ1 Rp 8,373,040.02
Ars - 53 1 buah Type Pj2 Rp 527,133,301.22
Ars - 54 1 buah Type Pj3 Rp 592,315,363.08
Ars - 55 1 buah Type Pj4 Rp 631,440,289.94
Ars - 56 1 buah Type Pj5 Rp 644,717,106.55
Ars - 57 1 buah Type Pj6 Rp 644,717,106.55
Ars - 58 1 buah Type Pj7 Rp 603,280,293.79
Ars - 59 1 buah Type Pj8 Rp 459,447,941.36
Ars - 60 1 buah Type J1 #REF!
Ars - 61 1 buah Type J2 #REF!
Ars - 62. 1 buah Type J3 #REF!
Ars - 63 1 buah Type J4 #REF!
Ars - 64 1 buah Type J5 #REF!
Ars - 65 1 buah Type J6 #REF!
Ars - 66 1 buah Type J7 Rp 38,699,947.55
Ars - 67 1 buah Type J8 Rp 200,951,908.03
Ars - 68 1 buah Type J9 Rp 304,616,516.19
Ars - 69 1 buah Type J10 Rp 502,247,307.98
Ars - 70 1 buah Type J12 #REF!
Ars - 71 1 buah Type J13 #REF!
Ars - 72 1 buah Type J14 #REF!
Ars - 73 1 buah Type J15 #REF!
Ars - 74 1 buah Type J16 #REF!
Ars - 75 1 buah Type J17 #REF!
Ars - 76 1 buah Type J18 #REF!
Ars - 77 1 buah Type jalusi Rp 110,463,333.75
REKAP ANALISA PEKERJAAN INTERIOR
(Analisa
INT - 01 1M2 Analisa Pekerjaan Dinding HPL Rp 959,101.50 Lapangan)
(Analisa
INT - 02 1M2 Analisa Pekerjaan Dinding HPL kolom Rp 1,245,226.50 Lapangan)
(Analisa
INT - 03 1M Analisa Pekerjaan Meubel Rp 2,729,160.00 Lapangan)
(Analisa
INT - 04 1M2 Analisa Pekerjaan Back drop Rp 1,568,490.00 Lapangan)
Rekap Analisa harga satuan Kerja ME
(PERMEN PU
ME-01 Memasang 1 m' pipa PVC tipe AW Ø 4" Rp 122,154.38
11/PRT/M/2013)
(PERMEN PU
ME - 02 Memasang 1 m' pipa PVC tipe AW Ø 3" Rp 99,159.38 11/PRT/M/2013)
(PERMEN PU
ME - 03 Memasang 1 m' pipa PVC diameter 1 1/2" Rp 48,930.00 11/PRT/M/2013)
(PERMEN PU
ME - 04 Memasang 1 m' pipa PVC diameter 1" Rp 57,225.00 11/PRT/M/2013)
(PERMEN PU
ME - 05 Memasang 1 m' pipa PVC diameter 2" Rp 62,934.38 11/PRT/M/2013)
(PERMEN PU
ME - 06 Memasang 1 m' pipa PVC diameter 1/2" Rp 22,854.56 11/PRT/M/2013)
(PERMEN PU
ME - 07 Memasang 1 m' pipa PVC diameter 3/4" Rp 36,671.25 11/PRT/M/2013)
(PERMEN PU
ME - 08 1 Bh Pekerjaan Pasangan Closet Duduk Rp 2,892,225.00 11/PRT/M/2013)
(PERMEN PU
ME - 09 1 Bh Pekerjaan Closet Jongkok Porselin Rp 4,263,591.23 11/PRT/M/2013)
(PERMEN PU
ME - 10 1 Bh Pekerjaan pasangan Urinoir Rp 3,419,653.73 11/PRT/M/2013)
(PERMEN PU
ME - 11 1 Bh Pekerjaan pasangan Wastafel Rp 1,379,503.73 11/PRT/M/2013)
(PERMEN PU
ME - 12 1 bh Pasang floor drain /unit Rp 377,580.00 11/PRT/M/2013)
(PERMEN PU
ME - 13 1 bh Pasang Roof drain /unit Rp 168,367.50 11/PRT/M/2013)
(Analisa
ME - 14 Memasang Clean Out dia 4" #REF! Lapangan)
(Analisa
ME - 15 1 Bh pekerjaan pasangan Shower Rp 1,959,221.25 Lapangan)
(Analisa
ME - 16 1 Bh Pekerjaan pasangan Jet Washer Rp 549,675.00 Lapangan)
(PERMEN PU
ME - 17 Memasang 1 Buah Kran Ø 3/4" Atau Ø 1/2" Rp 401,417.63 11/PRT/M/2013)
(Analisa
ME - 18 1 Unit Septic tank dan peresapan #REF! Lapangan)
(Analisa
ME - 19 1 Unit Panel Utama - LVMDP Rp 12,770,625.00 Lapangan)
(Analisa
ME - 20 1 Unit Panel - PP LP satu Rp 3,991,575.00 Lapangan)
(Analisa
ME - 21 1 Unit Panel - PP LP Lantai 2 Rp 3,991,575.00 Lapangan)
(Analisa
ME - 22 1 Unit Panel - AC LT satu Rp 3,383,625.00 Lapangan)
(Analisa
ME - 23 1 Unit Panel - AC LT dua Rp 3,383,625.00 Lapangan)
(Analisa
ME - 24 1 m' Kabel Tr NYFGBY 4 x 70 mm Rp 711,637.50 Lapangan)
(Analisa
ME - 25 1 m' Kabel Tr NYY 4 x35 mm Rp 259,087.50 Lapangan)
(Analisa
ME - 26 1 m' Kabel Tr NYY 4 x 16 mm Rp 102,795.00 Lapangan)
(Analisa
ME - 27 1 m' Kabel Tr NYY 4 x 10 mm Rp 64,995.00 Lapangan)
(Analisa
ME - 28 1 m' Kabel Tr NYMHY 3 x 2.5mm Rp 13,545.00 Lapangan)
(Analisa
ME - 29 1 m' kabel ITC 10 pairs x 0,2x0,6mm2 Rp 14,595.00 Lapangan)
(Analisa
ME - 30 1 m' kabel ITC 20 pairs x 0,2x0,6mm2 Rp 19,845.00 Lapangan)
(Analisa
ME - 31 1 m' Kabel Coaxial RG-11 ( 7 C /2V ) Rp 16,363.65 Lapangan)
(Analisa
ME - 32 1 m' Kabel Tray Lebar 200 x 100 Rp 117,303.59 Lapangan)
(Analisa
ME - 33 1 m' Kabel Ladder Lebar 400 x 100 Rp 410,248.13 Lapangan)
(Analisa
ME - 34 1 m' Kabel Tray Lebar 400 x 200 Rp 220,526.25 Lapangan)
(Analisa
ME - 35 1 titik instalasi Penerangan Rp 219,986.94 Lapangan)
(Analisa
ME - 36 1 titik instalasi Telephone / Data Rp 204,632.29 Lapangan)
(Analisa
ME - 37 1 titik instalasi Stop Kontak Rp 238,932.29 Lapangan)
(Analisa
ME - 38 1 titik instalasi speaker Rp 248,382.29 Lapangan)
(Analisa
ME - 39 1 titik instalasi AC/FAN 1 PHASE Rp 245,490.00 Lapangan)
(Analisa
ME - 40 1 titik instalasi MATV Rp 386,632.29 Lapangan)
(Analisa
ME - 41 1 TITIK PEMASANGAN INSTALASI CCTV Rp 257,807.39 Lapangan)
(Analisa
ME - 42 1 Bh Saklar Tunggal Rp 43,050.00 Lapangan)
(Analisa
ME - 43 1 Bh Saklar Ganda Rp 46,200.00 Lapangan)
(Analisa
ME - 44 1 Bh saklar 12 Gang Rp 153,300.00 Lapangan)
(Analisa
ME - 45 1 Bh Stop Kontak 200 VA Rp 46,938.15 Lapangan)
(Analisa
ME - 46 1 Bh Stop Kontak 200 VA water proof Rp 75,555.90 Lapangan)
(Analisa
ME - 47 1 Bh socket telepon Rp 87,150.00 Lapangan)
(Analisa
ME - 48 1 Bh socket Data Rp 74,235.00 Lapangan)
(Analisa
ME - 49 1 Bh socket MATV Rp 89,985.00 Lapangan)
(Analisa
ME - 50 1 Bh Stop kontak AC Rp 90,441.75 Lapangan)
(Analisa
ME - 51 1 Bh Terminal Box Rp 312,375.00 Lapangan)
(Analisa
ME - 52 1 Bh dome camera interior Rp 1,727,250.00 Lapangan)
(Analisa
ME - 53 1 Bh dome camera exterior Rp 2,147,250.00 Lapangan)
(Analisa
ME - 54 1 Bh pekerjaan Lampu TlD 2 x 36 watt Surface Mounted Rp 281,389.50 Lapangan)
(Analisa
ME - 55 1 Bh pekerjaan Lampu TL PLC 1 x 14 watt Rp 49,444.50 Lapangan)
(Analisa
ME - 56 Lampu TLP 2 x 10 watt Exit Rp 92,442.00 Lapangan)
(Analisa
ME - 57 Lampu LED 80 Watt Rp 1,593,942.00 Lapangan)
(Analisa
ME - 58 Lampu Lp lampu baret 20 watt Rp 259,654.50 Lapangan)
(Analisa
ME - 59 Lampu Lp lampu baret 40 watt Rp 495,117.00 Lapangan)
(Analisa
ME - 60 Lampu lampu TLD 2 x 18 watt Rp 155,442.00 Lapangan)
(Analisa
ME - 61 Lampu lampu RM TLD 2 x 18 watt Rp 414,582.00 Lapangan)
(Analisa
ME - 62 Lampu Down light 2 x 18 watt Rp 160,692.00 Lapangan)
(Analisa
ME - 63 Lampu spot light 40 watt Rp 173,265.12 Lapangan)
(Analisa
ME - 64 Lampu DL 1 x 18 Watt Rp 107,352.00 Lapangan)
(Analisa
ME - 65 1 bh EXHAUST FAN Rp 581,962.50 Lapangan)
(Analisa
ME - 66 1 bh Ceiling Speaker Rp 211,050.00 Lapangan)
(Analisa
ME - 67 1 BH Balvalve 2" Rp 106,732.50 Lapangan)
DAFTAR HARGA BAHAN BANGUNAN DAN UPAH KERJA
TAHUN ANGGARAN 2015

NO JENIS BAHAN/ TENAGA SATUAN HARGA KET KET. HARGA


1 2 3 4 5 6
1 Batu kali Utuh/Bulat M3 Rp 180,000.00
2 Batu Gunung M3 Rp 180,000.00
3 Pasir Timbunan/Gunung M3 Rp 125,000.00
4 Tanah Timbunan M3 Rp 95,000.00
5 Pasir Pasangan M3 Rp 115,308.00 Rp 82.36
6 Kerikil M3 Rp 277,000.00 Rp 153.89
7 Sirtu M3 Rp 150,000.00
8 Air Ltr Rp 80.00
9 besi D 14 Kg Rp 15,910.00
13 Besi Ø 12 Kg Rp 15,910.00
14 Besi Ø 10 Kg Rp 15,910.00
15 Besi Ø 8 Kg Rp 15,910.00
16 Semen Portland (Tonasa 50 Kg) Kg Rp 1,610.00 Rp 80,500.00
17 Semen Nat/warna Kg Rp 10,000.00 1140
18 Batu Merah Bh Rp 600.00
19 Kawat beton Kg Rp 30,000.00
20 tekwood 3 mm Lbr Rp 90,000.00
21 Minyak bekisting Lt Rp 5,000.00
22 Kayu dolken dia 8-10 / 400 cm btg Rp 28,000.00
Balok Kayu kelas I Rp 13,000,000.00
23 Balok Kayu kelas II M3 Rp 8,000,000.00
Papan Kayu kelas I Rp 13,000,000.00
24 Papan Kayu kelas II M3 Rp 8,000,000.00
26 Kayu kelas III bekisting M3 Rp 2,250,000.00
27 Batu Alam Andesit M2 Rp 200,000.00
31 Pek. Besi Hollow atas GRC 4 x 6 fin duco M2 Rp 550,000.00
32 Multipleks 15 mm Lbr Rp 250,000.00
33 Paku Campur Kg Rp 20,000.00
34 Paku Sekrup Dos Rp 15,000.00 120,000.00
35 Paku Mur Bh Rp 450.00
36 Cat dasar Undercoat Tembok Kg Rp 96,000.00
37 Cat Penutup EX Mowilex interior 2,5 kg Rp 67,600.00
Cat Penutup EX Mowilex exterior
38 2,5 kg Rp 85,800.00
watercoating
39 Roll Cat Tembok bh Rp 30,000.00
40 Amplas Lbr Rp 5,500.00
41 Cat kayu & besi warna standar kg Rp 40,000.00
42 Keramik 60 x60 M2 Rp 76,666.67 2.78
43 Keramik 60 x 60 warna M2 Rp 92,000.00
44 Keramik 25 x 25 M2 Rp 5,312.50 212,962.96
45 Keramik 25 x 40 M2 Rp 9,500.00
46 Keramik Anti slip tangga Bh Rp 41,350.00
47 Stainless Galvanis + aksesoris M Rp 250,000.00
48 Pipa Galvanis M Rp 30,000.00
49 Rangka Hollow 2x4 M Rp 16,500.00
50 Rangka Hollow 4x4 M Rp 18,300.00
51 Gypsum board Lbr Rp 82,500.00 238000
52 Kalsiboard Lbr Rp 69,500.00
53 Paku Kalsiboard Kg Rp 45,000.00
54 Seal Tape Roll Rp 2,100.00
55 Plat Baja M' Rp 16,000.00
56 Paku sekrup Bh Rp 490.00
57 Sealent Kg Rp 350.00 40000
58 Meni besi Kg Rp 42,000.00
59 Plamur Kg Rp 49,000.00
penangkal Petir lengkap Instalasi dan
60 set Rp 1,650,000.00
aksesoris Lengkap
61 Kabel NYY (4 x 10") M Rp 55,000.00
62 Kabel NYY (4 x 16"") M Rp 91,000.00
63 Kabel NYY (4 x 35") M Rp 239,850.00
64 Kabel NYM 3 x 2,5 mm2 M' Rp 15,500.00
65 Kabel NYM 3 x 4 mm2 M' Rp 20,800.00
66 Kabel NYMHY 3 x1,5 mm2 M' Rp 17,500.00
67 Kabel NYMHY 3 x2,5 mm3 M' Rp 6,000.00
68 Kabel Tray Lebar 100 x 200 M' Rp 83,854.17
69 Kabel Tray Lebar 400 x 200 M' Rp 162,500.00
70 Kabel Ladder Lebar 400 x 100 M' Rp 307,050.00
71 Kabel Coaxial ITC 2 x 6 mm M' Rp 7,000.00
72 Kabel Coaxial Rg 8 (0.6mm) 20 pairs M' Rp 12,000.00
NO JENIS BAHAN/ TENAGA SATUAN HARGA KET KET. HARGA
73 Kabel Coaxial 5C-2v M' Rp 5,000.00
74 Kabel Coaxial Rg 11 (0.6mm) M' Rp 8,684.43
75 Pipa Listrik Ø1/2 M' Rp 4,166.67
76 Socket Pipa Bh Rp 3,000.00
77 Tee Doos Bh Rp 1,500.00
78 Inbow Dos bH Rp 6,689.15
79 Klem Pipa Bh Rp 4,000.00
80 Fhiser Bh Rp 321.59
81 Las Doop Bh Rp 6,000.00
82 Isolasi ban Bh Rp 2,500.00
83 L.Bow Sekrup Bh Rp 1,698.02
84 Kabel RG 59 Bh Rp 5,402.78
85 Sadel Bh Rp 360.19
86 Kabel Teets Bh Rp 231.55
87 Pipa Spiral Bh Rp 1,286.38
88 L-Bow Bh Rp 1,286.38
89 Saklar Tunggal Bh Rp 23,000.00
90 Saklar Ganda Bh Rp 26,000.00
91 Saklar 12 gang Bh Rp 128,000.00
92 Stop kontak grounding CP Bh Rp 26,703.00
93 Stop Kontak AC Bh Rp 65,435.00
94 Stop Kontak waterproof Bh Rp 53,958.00
95 Socket Data RG-45 Bh Rp 50,000.00
96 Socket Telepon Bh Rp 65,000.00
97 Socket MATV Bh Rp 65,000.00
98 Terminal Box Telephone Bh Rp 125,000.00
99 TlD 2 x 18 watt Surface Mounted Bh Rp 244,950.00
100 Lampu TL PLC 1 x 14 watt Bh Rp 24,050.00
101 Lampu TL 1 x 14 Watt Bh Rp 65,000.00
102 lampu Baret 20 watt Bh Rp 224,250.00
103 Lampu baret 40 watt Bh Rp 448,500.00
104 lampu TLD 2 x 18 watt Bh Rp 125,000.00
105 lampu RM TLD 3 x 18 watt Bh Rp 371,800.00
106 Down light 2 x 18 watt Bh Rp 130,000.00
107 Spot Light LED 40 Watt Bh Rp 141,974.40
108 LED 80 Watt Bh Rp 1,495,000.00
109 Lampu DL 1 x 18 Bh Rp 79,200.00
110 Exhaust Fan Inline Type Kap. 400 CFM Bh Rp 380,650.00
111 fixed dome camera interior Bh Rp 1,300,000.00
112 fixed dome camera exterior Bh Rp 1,700,000.00
113 Ceiling Speker (Zs-646R) Bh Rp 150,000.00 211050.00
Modem Speedy Linksys WAG120N Modem
114 ADSL2+ Wireless Router Bh Rp 812,500.00

115 ACB 1250 A Bh Rp 25,000.00


116 MCCB 40 A/3 Phasa Bh Rp 1,200,000.00
117 ACB 1000 A Bh Bh Rp 80,000.00
118 MCB 20 A/3 Phasa Bh Rp 65,000.00
119 MCCB 80-100 A/3 Phasa Bh Rp 125,000.00
120 MCCB 100-125 A/3 Phasa Bh Rp 2,500,000.00
121 MCCB 25 A/3 Phasa Bh Rp 780,000.00
122 Mechanic Motor Interlock Bh Rp 250,000.00
123 Volt Meter Bh Rp 225,000.00
124 Ampere meter Bh Rp 225,000.00
125 Fuse & Indicator Bh Rp 225,000.00
126 Pilot Lamp Bh Rp 45,000.00
127 Box Panel & Accessories Unit Rp 362,500.00
128 Grounding A Ls Rp 500,000.00
129 Grounding B ls Rp 375,000.00
130 Material Bant ls Rp 250,000.00
131 MCB 16 A/3 Phasa Rp 250,000.00
132 MCB 16 A/1 Phasa Bh Rp 125,000.00
133 MCB 10 A/1 Phasa Bh Rp 99,000.00
134 Kabel NYFGBY 4 x 70 mm2 M Rp 465,000.00
135 gali, urugan dan pelindung M Rp 125,000.00
136 Pipa pvc 3/4' M Rp 4,250.00
137 Pipa pvc 1/2' M Rp 2,875.00
138 Pipa pvc 1' M Rp 17,750.00
139 Pipa pvc 1,5' M Rp 11,166.67
140 Pipa pvc 2" m Rp 21,500.00
141 Pipa PVC 4" m Rp 56,500.00
142 Pipa PVC 3" btng Rp 38,250.00
143 CO dia 4" Bh Rp 308,730.00
144 Westafel Ex toto LW 526J Bh Rp 850,000.00
145 Kloset Duduk Ex Toto SW660G Bh Rp 2,350,000.00
146 Kloset Jongkok Ex TOTO Bh Rp 3,703,000.00
147 Urinoir EX toto U 57M Bh Rp 2,300,000.00
NO JENIS BAHAN/ TENAGA SATUAN HARGA KET KET. HARGA
148 Floor Drain Ex TOTO TX 1 BN Bh Rp 343,000.00
149 Roof Drain dia 4" Bh Rp 143,750.00
150 Kran air Ex TOTO T23 B13 Bh Rp 321,100.00
151 Shower EX TOTO TX 471 SRR Bh Rp 1,850,000.00
152 Jet Washer Ex TOTO THX 20 WHITE Bh Rp 200,000.00
153 Cermin 6mm + bingkai Bh Rp 185,000.00
154 Pas Tabung Air + Rangka dudukan Bh Rp 2,550,000.00
155 Water Profing Kg Rp 180,000.00
156 Kunci stenless Bh Rp 173,000.00
157 Engsel pintu Bh Rp 142,800.00
158 Engsel pintu tanam Bh Rp 1,200,000.00
159 Engsel jendela Bh Rp 26,000.00
160 Handle Pintu Bh Rp 211,200.00
161 Handle Pintu P1 Bh Rp 3,990.50
162 Grendel jendela Bh Rp 13,500.00
163 Engsel Casement Unit Rp 118,000.00
164 Door Closer Bh Rp 187,200.00
165 Kaca polos 8 mm M2 Rp 275,000.00
169 Lem kayu Kg Rp 21,000.00
171 HPL Lbr Rp 420,000.00
175 ACP , Rangka + instalasi M2 Rp 750,000.00
176 ijuk ikat Rp 1,200.00
177 bale Valve 2" Bh Rp 55,900.00
178 Betelan dan Perapian tembok M Rp 22,500.00
180 Penggantung/Pengikat Bh Rp 36,018.50
181 Penggantung Type A Bh Rp 1,479.33
183 Digital Recorder ( DVR ) Unit Rp 1,950,000.00
184 Peralatan bantu + Accessories Unit Rp 750,000.00
185 Phenolic M Rp 1,920,000.00
186 kuas dan alat lainnya Ls Rp 50,000.00
188 Alat Bantu Ls Rp 35,000.00

NO. UPAH KERJA SAT. HARGA SATUAN KET. KET. HARGA


1 Pekerja Org/Hari Rp 100,000.00
2 Tukang Kayu Org/Hari Rp 135,000.00
3 Tukang Batu Org/Hari Rp 135,000.00
4 Tukang Cat Org/Hari Rp 135,000.00
5 Tukang Listrik Org/Hari Rp 135,000.00
6 Tukang Pipa Org/Hari Rp 135,000.00
7 Tukang Besi Org/Hari Rp 135,000.00
8 Kepala Tukang Kayu Org/Hari Rp 135,000.00
9 Kepala Tukang Batu Org/Hari Rp 135,000.00
10 Kepala Tukang Listrik Org/Hari Rp 135,000.00
11 Kepala Tukang Cat Org/Hari Rp 135,000.00
12 Kepala Tukang Pipa Org/Hari Rp 135,000.00
13 Kepala Tukang Besi Org/Hari Rp 135,000.00
14 Mandor Org/Hari Rp 150,000.00
RENCANA ANGGARAN BIAYA
PEKERJAAN : RENOVASI RUMAH JL. ROSEMARY STROLL NO 39
LOKASI : GREEN RIVER VIEW CLUSTER ROSEMARY
HARGA JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL SAT.
SATUAN (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Pembongkaran 1.00 Ls Rp 500,000 Rp 500,000
2 Pembersihan Akhir 1.00 Ls Rp 500,000 Rp 500,000
Rp 1,000,000
II Pekerjaan Beton
1 Pondasi Rolag 7 M' Rp 145,000 Rp 1,015,000
2 Sloof & Ringbalk K225 (15/25) 0.4 M3 Rp 2,500,000 Rp 1,000,000
3 Kolom K225 Praktis 0.36 M3 Rp 2,500,000 Rp 900,000
4 Talang Beton 0.35 M3 Rp 2,500,000 Rp 875,000
5 Bekisting 4.5 M3 Rp 120,000 Rp 540,000
Rp 4,330,000
III Pekerjaan Dinding
1 Bata 28.8 M2 Rp 120,000 Rp 3,456,000
2 Plester 28.8 M2 Rp 25,000 Rp 720,000
3 A Plus MU-200 28.8 M2 Rp 35,000 Rp 1,008,000
4 Cat Dinding (Jotun) Jotashield 1453 Interior 35 M2 Rp 25,000 Rp 875,000
Rp 6,059,000
IV Pekerjaan Lantai & Plafond
1 Lantai kerja /Urugan Pasir t =5 cm 0.78 M3 Rp 850,000 Rp 663,000
2 Lantai Keramik Dalam/ Asia Tile Nirwana Cream 40x40 9.00 M2 Rp 225,000 Rp 2,025,000
3 Lantai Keramik Teras/ Asia Tile Orcar Grey 30x30 6.00 M2 Rp 195,000 Rp 1,170,000
4 Pekerjaan Rangka Plafond (Hollow 4x2) 9.00 M2 Rp 65,000 Rp 585,000
5 Pekerjaan Plafond (KalsiBoard T 9mm) 9.00 M2 Rp 105,000 Rp 945,000
SUB TOTAL Rp 5,388,000
V Pekerjaan Atap
1 Rangka Bajaringan 0.75 (Canal C) 9.00 M2 Rp 125,000 Rp 1,125,000
2 Reng Baja ringan 9.00 M2 Rp 65,000 Rp 585,000
3 Spandek Zinc 0.30 mm (Silver) 9.00 M2 Rp 135,000 Rp 1,860,806
4 Serbuk Atap & Sika 1.00 ls Rp 350,000 Rp 350,000
5 Karet Talang 9.00 M' Rp 20,000 Rp 180,000
6 No Drop 2.00 bh Rp 180,000 Rp 360,000
SUB TOTAL Rp 4,460,806
VI Pekerjaan Dapur & Pembatas Teras
1 Dapur 120 x 65 Cm 1.00 ls Rp 1,850,000 Rp 1,850,000
2 Pembatas Teras Samping 5.00 M2 Rp 145,000 Rp 725,000
3 Plesteran & Pengecatan 1.00 ls Rp 750,000 Rp 750,000
SUB TOTAL Rp 3,325,000
VII Intalasi Listrik & Buangan Air
1 Pipa 1/2 Rucika 6.00 M' Rp 45,000 Rp 270,000
2 Pipa 2.5 Inci Rucika 8.00 M' Rp 85,000 Rp 680,000
3 Kabel NYY 2x1.5 20.00 M' Rp 20,000 Rp 400,000
4 Saklar & Fitting onw Light 1.00 ls Rp 250,000 Rp 250,000
SUB TOTAL Rp 1,600,000
VIII Penambahan kanopi & Teralis Jendela & Pintu
1 Penambahan Kanopi Teras 7.50 M' Rp 420,000 Rp 3,150,000
2 Partisi Dapur 1.00 ls Rp 1,200,000 Rp 1,200,000
3 Teralis Jendela 3.00 bh Rp 750,000 Rp 2,250,000
SUB TOTAL Rp 6,600,000
SUB TOTAL Rp 32,762,806
Pembulatan Rp 32,000,000
REKAPITULASI RENCANA ANGGARAN BIAYA S
T
A
PEKERJAAN : CARESTER & CALL CENTER
N
LOKASI : Metro Tanjung Bunga D
A
R
NO. URAIAN PEKERJAAN JUMLAH HARGA
P
I. PEKERJAAN PERSIAPAN Rp 1,000,000.00 E
R
II. PEKERJAAN STRUKTUR Rp 9,848,805.50###
M
E
A. PONDASI Rp - N

B. LANTAI SATU Rp 5,388,000.00

C. LANTAI DUA

D. LANTAI ATAP Rp 4,460,805.50

III #REF! #REF!

1 PEKERJAAN PASANGAN & PELESTERAN

A. LANTAI SATU Rp 32,000,000.00

B. LANTAI DUA #REF!

C. LANTAI ATAP #REF!

2 #REF!

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

3 PEKERJAAN ATAP #REF!

3 PEKERJAAN LANTAI

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

4 PEKERJAAN KOSEN PINTU & JENDELA + ASESORIS

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

C. LANTAI ATAP #REF!

5 PEKERJAAN PENGECATAN

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

C. LANTAI ATAP #REF!

IV PEKERJAAN ME #REF!

1 #REF!

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

2 #REF!

A. LANTAI SATU #REF!

B. LANTAI DUA #REF!

REAL COST #REF!

TOTAL BIAYA #REF!

DIBULATKAN #REF!

Makassar , 2017
DIBUAT OLEH
S
T
A
N
D
A
R
NO. URAIAN PEKERJAAN JUMLAH HARGA
P
E
R
M
E
N

You might also like