1 m3 Galian Untuk Tanah Biasa sedalam 1 m
Upah An. SNI ( Revisi ) 6.1.1
0.750 Oh Pekerja @ Rp. 90,000.00 = Rp 67,500.00
0.025 Oh Mandor @ Rp. 125,000.00 = Rp 3,125.00
= Rp 70,625.00
Total Upah = Rp 70,625.00
9. 1 m3 Urugan kembali
Upah An. SNI ( Revisi ) 6.9.1
0.192 Oh Pekerja @ Rp. 90,000.00 = Rp 17,280.00
0.019 Oh Mandor @ Rp. 125,000.00 = Rp 2,375.00
Sub total : = Rp 19,655.00
Total Upah = Rp 19,655.00
9. 1 m3 Pemindahan Tanah
Upah An. SNI ( Revisi ) 6.9.1
0.380 Oh Pekerja @ Rp. 90,000.00 = Rp 34,200.00
0.025 Oh Mandor @ Rp. 125,000.00 = Rp 3,125.00
Sub total : = Rp 37,325.00
Total Upah = Rp 37,325.00
10. 1 m3 Pemadatan tanah konvensional.
Upah An. SNI ( Revisi ) 6.10.1
0.500 Oh Pekerja @ Rp. 90,000.00 = Rp 45,000.00
0.050 Oh Mandor @ Rp. 125,000.00 = Rp 6,250.00
Sub total : = Rp 51,250.00
Total Upah = Rp 51,250.00
16 1 m3 Urugan sirtu
Bahan An. SNI ( Revisi ) 6.15.1
1.200 m3 Sirtu @ Rp. 85,600.00 = Rp 102,720.00
Sub total : = Rp 102,720.00
Pekerjaan Pondasi
6. 1 m3 Pasang pondasi batu kali 1 Pc : 4 Ps
Bahan evisi ) 6.5.1
1.100 m3 Batu belah ( 15/20 ) @ Rp. 121,000.00 = Rp 133,100.00
163.000 Kg Semen porland @ Rp. 1,400.00 = Rp 228,200.00
0.520 m3 Pasir pasang @ Rp. 170,000.00 = Rp 88,400.00
Sub total : = Rp 449,700.00
Upah evisi ) 6.5.2
1.500 Oh Pekerja @ Rp. 90,000.00 = Rp 135,000.00
0.600 Oh Tukang batu @ Rp. 100,000.00 = Rp 60,000.00
0.060 Oh Kepala tukang @ Rp. 110,000.00 = Rp 6,600.00
0.075 Oh Mandor @ Rp. 125,000.00 = Rp 9,375.00
Sub total : = Rp 210,975.00
Total upah+bahan : = Rp 660,675.00
Ket : Pekerjaan Batu Kumbung Pengerjaannya Lebih Murah Dari Pada Bata Roolag
26 1 m3 Membuat Pile Cap 1 ( 80X80X20 )
Bahan An. SNI ( Revisi ) 6.38.1
Err:509 m3 Kayu terentang/Meranti (MC) @ Rp. Err:509 = Rp Err:509
Err:509 btg Usuk Kayu Meranti 4 x 6 cm @ Rp. Err:509 = Rp Err:509
1.000 Kg Paku biasa 2" - 5" @ Rp. 34,000.00 = Rp 34,000.00
0.400 Ltr Minyak bekisting @ Rp. 40,000.00 = Rp 16,000.00
19.643 lnjr Besi beton polos Ø10 @ Rp. 61,250.00 = Rp 1,203,125.00
2.866 Kg Kawat beton @ Rp. 16,000.00 = Rp 45,857.14
186.000 Kg Semen portland @ Rp. 1,400.00 = Rp 260,400.00
0.500 m3 Pasir beton @ Rp. 120,000.00 = Rp 60,000.00
#REF! m3 Koral beton @ Rp. #NAME? = Rp #NAME?
Sub total : = Rp Err:509
Upah An. SNI ( Revisi ) 6.38.2
4.300 Oh Pekerja @ Rp. 90,000.00 = Rp 387,000.00
0.275 Oh Tukang batu @ Rp. 100,000.00 = Rp 27,500.00
1.150 Oh Tukang kayu @ Rp. 100,000.00 = Rp 115,000.00
1.020 Oh Tukang besi @ Rp. 100,000.00 = Rp 102,000.00
0.262 Oh Kepala tukang @ Rp. 110,000.00 = Rp 28,820.00
0.265 Oh Mandor @ Rp. 125,000.00 = Rp 33,125.00
Sub total : = Rp 693,445.00
Total upah+bahan : = Rp Err:509
Pekerjaan Beton
5. 1 m2 Membuat Rabatan Beton, 1 Pc : 3 Ps
Bahan An. SNI ( Revisi ) 6.5.1
186.000 Kg Semen portland @ Rp. 1,400.00 = Rp 260,400.00
0.500 m3 Pasir beton @ Rp. 120,000.00 = Rp 60,000.00
Sub total : = Rp 320,400.00
Upah An. SNI ( Revisi ) 6.5.2
2.100 Oh Pekerja @ Rp. 90,000.00 = Rp 189,000.00
0.280 Oh Tukang batu @ Rp. 100,000.00 = Rp 28,000.00
0.040 Oh Kepala tukang @ Rp. 110,000.00 = Rp 4,400.00
0.050 Oh Mandor @ Rp. 125,000.00 = Rp 6,250.00
Sub total : = Rp 227,650.00
Total upah+bahan : = Rp 548,050.00
Pekerjaan Pasangan
4. 1 m2 Pasangan bata ringan (Hebel) tebal 7,5cm + space PM 110
Bahan An. SNI ( Revisi ) 6.4.1
12.000 Bh Bata hebel 60 x 20 x 7,5 cm @ Rp. 5,225.23 = Rp 62,702.70
0.065 Zak Thin Bed @ Rp. 110,000.00 = Rp 7,150.00
0.100 Lot Peralatan @ Rp. 3,500.00 = Rp 350.00
Sub total : = Rp 69,852.70
Upah An. SNI ( Revisi ) 6.4.2
0.280 Oh Pekerja @ Rp. 90,000.00 = Rp 25,200.00
0.065 Oh Tukang batu @ Rp. 100,000.00 = Rp 6,500.00
0.009 Oh Kepala tukang @ Rp. 110,000.00 = Rp 990.00
0.008 Oh Mandor @ Rp. 125,000.00 = Rp 1,000.00
Sub total : = Rp 33,690.00
Total upah+bahan : = Rp 103,542.70
1 m2 Acian
Bahan 4.250 Kg Semen portland @ Rp. 1,400.00 = Rp 5,950.00
Sub total : = Rp 5,950.00
36 1 m' Benangan
Bahan 0.900 Kg Semen portland @ Rp. 1,400.00 = Rp 1,260.00
Sub total : = Rp 1,260.00
Pekerjaan Plafond
44 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu MERANTI 4/6 panjang 4 m.
Bahan An. SNI ( Revisi ) 6.39.1
1.050 m1 Kayu meranti 5/7 - 4 mtr. @ Rp. 57,500.00 = Rp 60,375.00
0.100 Kg Paku biasa 2" - 5" @ Rp. 15,000.00 = Rp 1,500.00
Sub total : = Rp 61,875.00
Upah An. SNI ( Revisi ) 6.39.2
0.070 Oh Pekerja @ Rp. 90,000.00 = Rp 6,300.00
0.120 Oh Tukang kayu @ Rp. 100,000.00 = Rp 12,000.00
0.012 Oh Kepala tukang @ Rp. 110,000.00 = Rp 1,320.00
0.014 Oh Mandor @ Rp. 125,000.00 = Rp 1,750.00
Sub total : = Rp 21,370.00
Total upah+bahan : = Rp 83,245.00
Pekerjaan Pengecatan
15 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Cat Paragon
Bahan An. SNI ( Revisi ) 6.14.1
0.112 Kg Semen Putih/ Kalsium (Untuk Plamir) @ Rp. 55,000.00 = Rp 6,160.00
0.480 Pcs Lem Rajawali (Untuk Plamir) @ Rp. 12,000.00 = Rp 5,760.00
0.200 Lbr Ampelas @ Rp. 8,500.00 = Rp 1,700.00
0.020 Bh Kuwas / roll @ Rp. 20,000.00 = Rp 400.00
0.100 Kg Cat dasar @ Rp. 48,000.00 = Rp 4,800.00
0.140 Kg Cat penutup 2x @ Rp. 48,000.00 = Rp 6,720.00
Sub total : = Rp 25,540.00
Upah An. SNI ( Revisi ) 6.14.2
0.024 Oh Pekerja @ Rp. 90,000.00 = Rp 2,160.00
0.076 Oh Tukang cat @ Rp. 100,000.00 = Rp 7,560.00
0.007 Oh Kepala tukang @ Rp. 110,000.00 = Rp 762.30
0.003 Oh Mandor @ Rp. 125,000.00 = Rp 343.75
. Sub total : = Rp 10,826.05
Total upah+bahan : = Rp 36,366.05
Pekerjaan Keramik
8 1 m2 Pasang lantai marmer akuran 60 x 60 cm
Bahan visi ) 6.13.1
2.940 Bh Ubin teralux marmer 60 x 60 cm @ Rp. 29,000.00 = Rp 85,260.00
3.262 Kg Semen portland @ Rp. 1,400.00 = Rp 4,566.80
0.200 Kg Kapur bubuk/ Nat @ Rp. 7,000.00 = Rp 1,400.00
0.038 m3 Pasir pasang @ Rp. 170,000.00 = Rp 6,460.00
Sub total : = Rp 97,686.80
Upah visi ) 6.13.2
0.250 Oh Pekerja @ Rp. 90,000.00 = Rp 22,500.00
0.120 Oh Tukang batu @ Rp. 100,000.00 = Rp 12,000.00
0.012 Oh Kepala tukang @ Rp. 110,000.00 = Rp 1,320.00
0.013 Oh Mandor @ Rp. 125,000.00 = Rp 1,562.50
Biaya poles. @ Rp. = Rp 2,500.00
Sub total : = Rp 39,882.50
Total upah+bahan : = Rp 137,569.30
11. 1 m2 Pasang Daun Pintu Aluminium Silver 4" (Uk. 90cm x 200cm)
Bahan An. SNI ( Revisi ) 6.11.1
7.300 m1 Bingkai Daun Pintu @ Rp. 75,000.00 = Rp 547,500.00
0.408 Bh List Silent @ Rp. 58,500.00 = Rp 23,868.00
0.840 Kg Paku Sekrup 7cm @ Rp. 19,170.00 = Rp 16,102.80
6.000 Bh Plat Siku Aluminium @ Rp. 1,800.00 = Rp 10,800.00
1.000 Bh Kunci Pintu @ Rp. 32,000.00 = Rp 32,000.00
2.000 Bh Engsel Pintu @ Rp. 18,000.00 = Rp 36,000.00
2.000 m2 Kaca Polos tb. 5mm @ Rp. 87,500.00 = Rp 175,000.00
Sub total : = Rp 841,270.80
Alat An. SNI ( Revisi ) 6.3.1
0.273 Bh Peralatan @ Rp. 168,254.16 = Rp 45,933.39
Sub total : = Rp 45,933.39
11. 1 m2 Pasang Daun Pintu Aluminium Putih 4" (Uk. 85cm x 200cm)
Bahan An. SNI ( Revisi ) 6.11.1
7.300 m1 Bingkai Daun Pintu @ Rp. 115,000.00 = Rp 839,500.00
0.408 Bh List Silent @ Rp. 58,500.00 = Rp 23,868.00
0.840 Kg Paku Sekrup 7cm @ Rp. 19,170.00 = Rp 16,102.80
6.000 Bh Plat Siku Aluminium @ Rp. 1,800.00 = Rp 10,800.00
1.000 Bh Kunci Pintu @ Rp. 32,000.00 = Rp 32,000.00
2.000 Bh Engsel Pintu @ Rp. 18,000.00 = Rp 36,000.00
2.000 m2 Kaca Polos tb. 5mm @ Rp. 87,500.00 = Rp 175,000.00
Sub total : = Rp 1,133,270.80
Alat An. SNI ( Revisi ) 6.3.1
0.273 Bh Peralatan @ Rp. 226,654.16 = Rp 61,876.59
Sub total : = Rp 61,876.59
11. 1 m2 Pasang Daun Jendela Aluminium Silver 4" (Uk. 70cm x 160cm)
Bahan An. SNI ( Revisi ) 6.11.1
4.600 m1 Bingkai Daun Pintu Aluminium Biasa @ Rp. 75,000.00 = Rp 345,000.00
0.361 Bh List Silent @ Rp. 58,500.00 = Rp 21,106.80
0.740 Kg Paku Sekrup 7cm @ Rp. 19,170.00 = Rp 14,185.80
4.000 Bh Plat Siku Aluminium @ Rp. 1,800.00 = Rp 7,200.00
1.000 Bh Kunci Pintu @ Rp. 32,000.00 = Rp 32,000.00
2.000 Bh Engsel Jendela @ Rp. 9,000.00 = Rp 18,000.00
2.000 Bh Sikutan Angin Jendela @ Rp. 18,353.00 = Rp 36,706.00
1.260 m2 Kaca Polos tb. 5mm @ Rp. 87,500.00 = Rp 110,250.00
Sub total : = Rp 584,448.60
Alat An. SNI ( Revisi ) 6.3.1
0.273 Bh Peralatan @ Rp. 116,889.72 = Rp 31,910.89
Sub total : = Rp 31,910.89
11. 1 Unit Pasang Daun Jendela Aluminium Putih 4" (Uk. 70cm x 160cm)
Bahan An. SNI ( Revisi ) 6.11.1
4.600 m1 Bingkai Daun Pintu Aluminium Warna @ Rp. 115,000.00 = Rp 529,000.00
0.361 Bh List Silent @ Rp. 58,500.00 = Rp 21,106.80
0.740 Kg Paku Sekrup 7cm @ Rp. 19,170.00 = Rp 14,185.80
4.000 Bh Plat Siku Aluminium @ Rp. 1,800.00 = Rp 7,200.00
1.000 Bh Kunci Pintu @ Rp. 32,000.00 = Rp 32,000.00
2.000 Bh Engsel Jendela @ Rp. 9,000.00 = Rp 18,000.00
2.000 Bh Sikutan Angin Jendela @ Rp. 18,353.00 = Rp 36,706.00
1.260 m2 Kaca Polos tb. 5mm @ Rp. 87,500.00 = Rp 110,250.00
Sub total : = Rp 768,448.60
Alat An. SNI ( Revisi ) 6.3.1
0.273 Bh Peralatan @ Rp. 153,689.72 = Rp 41,957.29
Sub total : = Rp 41,957.29
11. 1 m2 Pasang Daun Jendela Casment Aluminium Putih 4" (Uk. 100cm x 50cm)
Bahan An. SNI ( Revisi ) 6.11.1
2.800 m1 Bingkai Daun Pintu Aluminium Warna @ Rp. 115,000.00 = Rp 322,000.00
0.361 Bh List Silent @ Rp. 58,500.00 = Rp 21,106.80
0.740 Kg Paku Sekrup 7cm @ Rp. 19,170.00 = Rp 14,185.80
4.000 Bh Plat Siku Aluminium @ Rp. 1,800.00 = Rp 7,200.00
1.000 Bh Kunci Pintu @ Rp. 32,000.00 = Rp 32,000.00
2.000 Bh Engsel Jendela @ Rp. 19,373.00 = Rp 38,746.00
2.000 Bh Sikutan Angin Jendela @ Rp. 62,800.00 = Rp 125,600.00
0.500 m2 Kaca Polos tb. 5mm @ Rp. 87,500.00 = Rp 43,750.00
Sub total : = Rp 604,588.60
Alat An. SNI ( Revisi ) 6.3.1
0.273 Bh Peralatan @ Rp. 75,573.58 = Rp 20,631.59
Sub total : = Rp 20,631.59
8. Pasang 1 Set bak mandi FIber Batu Bata Uk.60 x 60 t. 75cm vol 0.3 m3
Bahan An. SNI ( Revisi ) 6.8.1
74.000 Bh Batu bata @ Rp. 560.00 = Rp 41,440.00
120.000 Kg Semen portland @ Rp. 1,078.79 = Rp 129,455.04
0.300 m3 Pasir pasang @ Rp. 117,889.72 = Rp 35,366.92
6.000 Kg Semen nat @ Rp. 10,000.00 = Rp 60,000.00
1.000 Set Bak Fiber + Aksesories @ Rp. 171,100.00 = Rp 171,100.00
2.200 m2 Dinding Keramik 20x25cm @ Rp. 82,000.00 = Rp 180,400.00
5.217 Kg Kapur Bubuk @ Rp. 7,000.00 = Rp 36,521.10
Sub total : = Rp 654,283.06
Upah An. SNI ( Revisi ) 6.8.2
2.600 Oh Pekerja @ Rp. 90,000.00 = Rp 234,000.00
0.850 Oh Tukang batu @ Rp. 100,000.00 = Rp 85,000.00
0.850 Oh Tukang Keramik @ Rp. 100,000.00 = Rp 85,000.00
0.080 Oh Kepala tukang @ Rp. 110,000.00 = Rp 8,800.00
0.030 Oh Mandor @ Rp. 125,000.00 = Rp 3,750.00
Sub total : = Rp 416,550.00
Total upah+bahan : = Rp 1,070,833.06
16. Memasang 1 buah bak kontrol pas. batu bata ( 30x30 ) cm, tinggi 35 cm
Bahan visi ) 6.16.1
50.000 Bh Batu bata @ Rp. 560.00 = Rp 28,000.00
44.000 Kg Semen portland @ Rp. 1,400.00 = Rp 61,600.00
0.070 m3 Pasir pasang @ Rp. 170,000.00 = Rp 11,900.00
0.070 m3 Batu kerikil @ Rp. 179,000.00 = Rp 12,530.00
1.600 Kg Besi beton @ Rp. 12,000.00 = Rp 19,200.00
0.060 m3 Pasir beton @ Rp. 122,000.00 = Rp 7,320.00
Sub total : = Rp 140,550.00
Upah visi ) 6.16.2
0.167 Oh Pekerja @ Rp. 90,000.00 = Rp 15,000.00
1.015 Oh Tukang batu @ Rp. 100,000.00 = Rp 101,500.00
0.002 Oh Kepala tukang @ Rp. 110,000.00 = Rp 165.00
0.016 Oh Mandor @ Rp. 125,000.00 = Rp 2,000.00
Sub total : = Rp 118,665.00
Total upah+bahan : = Rp 259,215.00
16. Memasang 1 buah bak kontrol pas. batu bata ( 20x20 ) cm, tinggi 25 cm
Bahan An. SNI ( Revisi ) 6.16.1
Bahan Pembuatan Bak Kontrol
45.000 Bh Batu bata @ Rp. 560.00 = Rp 25,200.00
20.000 Kg Semen portland @ Rp. 1,400.00 = Rp 28,000.00
0.045 m3 Pasir pasang @ Rp. 170,000.00 = Rp 7,650.00
16. Memasang 1 buah bak kontrol pas. batu bata ( 50x50 ) cm, tinggi 1.00 cm
Bahan An. SNI ( Revisi ) 6.16.1
Bahan Pembuatan Bak Kontrol
106.000 Bh Batu bata @ Rp. 560.00 = Rp 59,360.00
76.000 Kg Semen portland @ Rp. 1,400.00 = Rp 106,400.00
0.171 m3 Pasir pasang @ Rp. 170,000.00 = Rp 29,070.00