1 Analisa SNI-2013 1 m3 Galian tanah biasa sedalam 2 m

TENAGA
0.9000 Oh Pekerja @ Rp 85,000.00 Rp 76,500.00
0.0450 Oh Mandor @ Rp 100,000.00 Rp 4,500.00
Total A+B Rp 81,000.00
Overhead + profit 15 % Rp 12,150.00
Total Rp 93,150.00

2 Analisa SNI-2013 1 m3 Galian tanah biasa sedalam 1 m


TENAGA
0.7500 Oh Pekerja @ Rp 85,000.00 Rp 63,750.00
0.0250 Oh Mandor @ Rp 100,000.00 Rp 2,500.00
Total A+B Rp 66,250.00
Overhead + profit 15 % Rp 9,937.50
Total Rp 76,187.50

3 Analisa SNI-2013 1 m3 Urugan kembali


TENAGA
0.5000 Oh Pekerja @ Rp 85,000.00 Rp 42,500.00
0.0500 Oh Mandor @ Rp 100,000.00 Rp 5,000.00
Total A+B Rp 47,500.00
Overhead + profit 15 % Rp 7,125.00
Total Rp 54,625.00

4 Analisa SNI-2013 1 m3 Urugan Pasir


BAHAN
1.2000 M3 Pasir urug @ Rp 135,000.00 Rp 162,000.00
TENAGA
0.3000 Oh Pekerja @ Rp 85,000.00 Rp 25,500.00
0.0100 Oh Mandor @ Rp 100,000.00 Rp 1,000.00
Total A+B Rp 188,500.00
Overhead + profit 15 % Rp 28,275.00
Total Rp 216,775.00

5 Analisa SNI-2013 1 m3 Urugan tanah lantai/pemadatan tanah (didatangkan)


BAHAN
1.2000 M3 Tanah urug @ Rp 84,000.00 Rp 100,800.00
TENAGA
0.5000 Oh Pekerja @ Rp 85,000.00 Rp 42,500.00
0.0500 Oh Mandor @ Rp 100,000.00 Rp 5,000.00
Total A+B Rp 148,300.00
Overhead + profit 15 % Rp 22,245.00
Total Rp 170,545.00